ATE315687T1 - METHOD FOR PRODUCING STUFFING COLUMNS FOR SUBSTANCE IMPROVEMENT - Google Patents

METHOD FOR PRODUCING STUFFING COLUMNS FOR SUBSTANCE IMPROVEMENT

Info

Publication number
ATE315687T1
ATE315687T1 AT02014508T AT02014508T ATE315687T1 AT E315687 T1 ATE315687 T1 AT E315687T1 AT 02014508 T AT02014508 T AT 02014508T AT 02014508 T AT02014508 T AT 02014508T AT E315687 T1 ATE315687 T1 AT E315687T1
Authority
AT
Austria
Prior art keywords
fibers
subsoil
esp
pile
similar
Prior art date
Application number
AT02014508T
Other languages
German (de)
Inventor
Heinz Dipl-Ing Priebe
Original Assignee
Keller Grundbau Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Keller Grundbau Gmbh filed Critical Keller Grundbau Gmbh
Application granted granted Critical
Publication of ATE315687T1 publication Critical patent/ATE315687T1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Revetment (AREA)

Abstract

For construction, a depth vibrator is driven into the subsoil, and the pile is constructed in an upward direction in a vibration packing process. For subsoil with low support, the pile is constructed of loose material, e.g. sand, gravel, etc. containing added fiber material. For supportive subsoil, the material does not contain fibers. The pile has a wider foot, and ends in a supporting soil layer. For subsoil with low support, the pile is constructed floating. The fibers used are steel, glass, or synthetic fibers, esp. with a length of approx. 50mm, esp. 25-75mm. Fibers are added in an amount of 05 - 5kg, esp. 2-3kg fibers for m SIMILAR 3. The loose material with fibers has a cohesion value of 5-50kN/m SIMILAR 2, esp. 10-30kN/m SIMILAR 2.
AT02014508T 2001-07-07 2002-07-01 METHOD FOR PRODUCING STUFFING COLUMNS FOR SUBSTANCE IMPROVEMENT ATE315687T1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE10133122A DE10133122A1 (en) 2001-07-07 2001-07-07 Process for the manufacture of darning pillars for soil improvement

Publications (1)

Publication Number Publication Date
ATE315687T1 true ATE315687T1 (en) 2006-02-15

Family

ID=7691055

Family Applications (1)

Application Number Title Priority Date Filing Date
AT02014508T ATE315687T1 (en) 2001-07-07 2002-07-01 METHOD FOR PRODUCING STUFFING COLUMNS FOR SUBSTANCE IMPROVEMENT

Country Status (3)

Country Link
EP (1) EP1273713B1 (en)
AT (1) ATE315687T1 (en)
DE (2) DE10133122A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10333613B4 (en) * 2003-07-24 2011-06-30 Keller Grundbau GmbH, 63067 Improvement of a soft layer
CN101392527B (en) * 2008-10-21 2010-10-06 冯守中 Method of treating soft foundation with geotextile bulk pile
CN102168420B (en) * 2011-03-15 2012-12-19 冯守中 Method for processing soft soil base by geotextile light active material piles
CN104652407B (en) * 2015-01-05 2016-08-24 同济大学 A kind of band stirrup collapsible geosynthetics abnormity granular pile and construction method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4013801C2 (en) * 1990-04-28 1994-12-22 Keller Grundbau Gmbh Method of manufacturing a support and / or sealing body
DE4130339C2 (en) * 1991-09-12 2000-12-14 Keller Grundbau Gmbh Process for improving a building site
DE19707687C1 (en) * 1997-02-26 1998-10-15 Wilhelm Dr Degen Device for producing columns of material in the floor
DE19814021A1 (en) * 1998-03-30 1999-10-14 Degen Wilhelm Device for introducing a foreign substance into soils or for compacting the soil
DE19822290C2 (en) * 1998-05-18 2003-01-02 Bul Sachsen Gmbh Process and device for compacting vibratory pressure and vibrating plugging of binding and non-binding compaction material

Also Published As

Publication number Publication date
DE50205555D1 (en) 2006-04-06
DE10133122A1 (en) 2003-01-23
EP1273713A2 (en) 2003-01-08
EP1273713A3 (en) 2003-07-23
EP1273713B1 (en) 2006-01-11

Similar Documents

Publication Publication Date Title
DE50206850D1 (en) Method for producing columns
DE3860572D1 (en) METHOD FOR DRIVING Piles.
ATE250170T1 (en) METHOD FOR INCREASING THE LOADING CAPACITY OF THE STRUCTURAL SOIL
DE69623241D1 (en) Process for the introduction of micro-organisms in soils for the remediation thereof
KR960016698A (en) Plant growth method and plant growth support
DE69216203D1 (en) Device and method for the production of compacted stone or ballast columns in earth masses
HUP9802411A2 (en) Procedures and materials for conferring disease resistance in plants
DE69405881D1 (en) SOUND ABSORBING ROAD COVERING AND METHOD FOR THE PRODUCTION THEREOF
ATE315687T1 (en) METHOD FOR PRODUCING STUFFING COLUMNS FOR SUBSTANCE IMPROVEMENT
ATE239143T1 (en) DEVICE AND METHOD FOR SOIL CONSOLIDATION
ATE207168T1 (en) METHOD FOR INSTALLING TAPERED PILES, ASSOCIATED PILES, AND FOUNDATIONS AND FOUNDATION FORMATIONS MADE THEREFROM
DE59801707D1 (en) METHOD AND ENVIRONMENT FOR THE PRODUCTION OF A PILLAR FOR THE REMOVAL OF CONSTRUCTION OR TRAFFIC LOADS
DE3880497D1 (en) METHOD AND ARRANGEMENT FOR INFLUENCING THE INTERACTION BETWEEN A SOIL LAYER AND A CONSTRUCTION THEREOF.
DE69701730D1 (en) METHOD FOR PRODUCING MORTAR
US5192168A (en) Method and apparatus for stabilizing friction soil and adjacent cohesion soil layers
DE60235600D1 (en) Process for the production of self-compacting filler material
ATE115103T1 (en) INJECTION FOR SEALING AND/OR CONSOLIDATING SOIL AND BUILDING MATERIALS AND METHODS OF IMPLEMENTATION.
HUP9701528A2 (en) Method and apparatus for making floor
ATE309413T1 (en) STABILIZED SOIL AND METHOD FOR PRODUCING SAME
ATE147714T1 (en) MIXTURE FOR COVERING AND/OR RECULTIVATION OF WASTE LANDFILLS, SOIL SIGNIFICATIONS OR SIMILAR
FI935009A7 (en) Photoluminescent calcium silicate material, concrete and gravel material containing the same, and method for producing photoluminescent calcium silicate material
FR2718771B1 (en) Method of consolidating concrete structures.
DE60215106D1 (en) Process for the production of road surface
DE59502198D1 (en) Process for obtaining landfill space for flowable waste materials
ATE96606T1 (en) METHODS OF CONSOLIDATION OF LAND AREA.

Legal Events

Date Code Title Description
REN Ceased due to non-payment of the annual fee