JPH0345179B2 - - Google Patents
Info
- Publication number
- JPH0345179B2 JPH0345179B2 JP26063284A JP26063284A JPH0345179B2 JP H0345179 B2 JPH0345179 B2 JP H0345179B2 JP 26063284 A JP26063284 A JP 26063284A JP 26063284 A JP26063284 A JP 26063284A JP H0345179 B2 JPH0345179 B2 JP H0345179B2
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- construction
- offshore
- seabed
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Revetment (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は沖合に建設する堤体や護岸などを短期
内に完成させる工法及び装置に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a construction method and apparatus for completing an embankment, seawall, etc. constructed offshore within a short period of time.
沖合海域に護岸、防波堤などを建設する場合、
従来は主としてケーソン工法、セル工法が用いら
れている。
When constructing seawalls, breakwaters, etc. in offshore waters,
Conventionally, caisson construction method and cell construction method are mainly used.
ケーソン工法はドライドツクでケーソン函を製
作し、浮上させて建設位置まで曳航運搬し、建設
地に沈設、内部に砂を充填して仕上げる。ケーソ
ン函はドライドツクで製作されるので製作精度も
高く、大規模なものも製作可能である。 In the caisson construction method, a caisson box is manufactured in a dry dock, floated to the surface, towed to the construction site, then sunk at the construction site, and finished by filling the inside with sand. Since caisson boxes are manufactured using dry docks, the manufacturing precision is high, and large-scale items can also be manufactured.
又セル工法は鋼矢板セル工法と鋼板セル工法の
2種類が知られているが、いずれも陸上基地にお
いてセル殻を組立て、台船に載せて曳航するか、
フローテイングクレーンで吊つて建設位置まで運
搬した後、フローテイングクレーンに吊つたバイ
ブロハンマで海底に打設し、その後内部に砂を充
填する工法である。 Two types of cell construction methods are known: steel sheet pile cell construction method and steel plate cell construction method, both of which involve assembling the cell shell at a land base, placing it on a barge and towing it, or
This construction method involves hoisting it using a floating crane and transporting it to the construction location, then driving it into the seabed using a vibro hammer suspended from the floating crane, and then filling the interior with sand.
ところで、最近沖合に建設する堤体や護岸工事
の工期短縮が要望されている。これに対し、従来
のケーソン工法においては、ケーソン函の規模が
大きくなるとドライドツクによる製作費が高価と
なる上、ケーソン函の製作に時間がかかり急速施
工の点で問題がある。
Incidentally, there has recently been a demand for shortening the construction period for offshore embankment and seawall construction. On the other hand, in the conventional caisson construction method, as the scale of the caisson box increases, the cost of producing it using dry docks increases, and it takes time to manufacture the caisson box, which poses a problem in terms of rapid construction.
又セル工法は最近急速工法の開発も進み、建設
地点が陸上基地に近接している場合は工期も比較
的短期ですむが、建設地点が遠くなると曳航時間
が長くなり急速施工というわけにはいかない。又
鋼材の引張強度から考えて実用的な水深はせいぜ
い20mという制約がある。 In addition, rapid cell construction has recently been developed, and if the construction site is close to a land base, the construction period is relatively short, but if the construction site is far away, the towing time becomes longer and rapid construction is not possible. . Also, considering the tensile strength of the steel material, the practical water depth is limited to 20 meters at most.
本発明は、こうした従来工法の問題点を解消し
た堤体、護岸の急速施工法及びその装置を提供し
ようとするものである。 The present invention aims to provide a rapid construction method for embankments and seawalls that solves the problems of the conventional construction methods, and an apparatus therefor.
コの字形を呈し、両側部にそれぞれ複数個のバ
ラストタンクを具備し、開口部に型枠形成部を備
えるとともに、甲板上に材料貯槽、モルタル混合
プラント、ポンプ、門形クレーン、指令室及び居
住室等を配設した大型作業船を、堤体あるいは護
岸の建設地点に運搬し、海底に着座せしめる。続
いて該作業船により堤体又は護岸に型枠を形成
し、その内部に先づ粗骨材を次いで該作業船上で
混合したモルタルを注入するいわゆるプレパクト
コンクリート工法によつて堤体又は護岸のコンク
リート打設を行ない、その養生、コンクリート固
化を俟つて作業船を浮上移動せしめ、同一作業を
繰返して堤体又は護岸を建設する。
It has a U-shape, and is equipped with multiple ballast tanks on each side, a formwork forming section at the opening, and a material storage tank, mortar mixing plant, pump, portal crane, control room, and residence on the deck. A large work boat equipped with rooms, etc. is transported to the construction site of the embankment body or seawall and is seated on the seabed. Next, a formwork is formed on the embankment body or revetment using the work boat, and the levee body or revetment is constructed using the so-called pre-pact concrete construction method, in which coarse aggregate is first poured into the formwork and then mortar mixed on the work boat is poured into the formwork. Concrete is poured, the work boat is floated after the concrete is cured, and the concrete hardens, and the same work is repeated to construct the embankment body or revetment.
以上述べたように大型作業船を利用し、該作業
船上で建設地点に堤体や護岸の型枠を作り、その
内部にプレパクトコンクリートを打設するという
工法を繰返して堤体、護岸の建設を行なうので、
工事期間が非常に短縮される。
As mentioned above, the construction of the embankment body and revetment is carried out by repeatedly using a large work boat to create the formwork for the embankment body and revetment at the construction site, and then pouring pre-pact concrete inside it. Since we will do
The construction period will be greatly shortened.
陸地より2〜5Km程度離れた沖合海域に高さ20
m、幅30m程度の台形の護岸を建設する例を考え
る。
A height of 20 km in the offshore area about 2 to 5 km from the land.
Consider an example of constructing a trapezoidal seawall with a width of approximately 30 m.
第1図、第2図はその護岸建設に使用する大型
作業船の斜視図および断面図である。図中1は作
業船、2は型枠形成部、3はバラストタンク、4
は型枠、5は型枠操作アーム、6は粗骨材、7は
モルタル、8はトレミー管、9はモルタル混合プ
ラント、10は粗骨材タンク、11は門形クレー
ン、12は指令室及び居住室、13はセメントタ
ンク、14はポンプ、15は油圧シリンダ、16
は支承、17は吹付け砂、18は既設護岸、19
は新設護岸、20は海底地盤である。 Figures 1 and 2 are a perspective view and a sectional view of a large working boat used for the construction of the seawall. In the figure, 1 is a work boat, 2 is a formwork forming part, 3 is a ballast tank, and 4
is a formwork, 5 is a formwork operation arm, 6 is coarse aggregate, 7 is mortar, 8 is a tremie pipe, 9 is a mortar mixing plant, 10 is a coarse aggregate tank, 11 is a portal crane, 12 is a control room and Living room, 13 is a cement tank, 14 is a pump, 15 is a hydraulic cylinder, 16
is bearing, 17 is sprayed sand, 18 is existing seawall, 19 is
20 is a newly constructed seawall, and 20 is a seabed.
図に示すように、作業船1はコの字形を呈して
おり、その開口部に型枠形成部を備え、甲板上に
モルタル混合プラント9、粗骨材タンク10、門
形クレーン11、司令室及び居住室12、セメン
トタンク13、ポンプ14などを配設している。
又両側面には複数個のバラストタンク3を具備し
ており、型枠形成部2には油圧駆動の型枠操作ア
ーム5が多数並設されている。 As shown in the figure, the work boat 1 has a U-shape, and is equipped with a formwork forming section at its opening, and has a mortar mixing plant 9, a coarse aggregate tank 10, a portal crane 11, and a control room on the deck. A living room 12, a cement tank 13, a pump 14, etc. are provided.
Also, a plurality of ballast tanks 3 are provided on both sides, and a large number of hydraulically driven formwork operating arms 5 are arranged in parallel on the formwork forming section 2.
作業船1が自航又は曳航により護岸建設地点に
達すると、バラストタンク3に注入し船体を海底
地盤20に着底せしめる。この際船体に装備され
た複数個の油圧シリンダ15を、予め海底に沈設
された支承16上に、船体と海底面とが接触しな
い程度の隙間を残して仮セツトし、その隙間に土
砂19を吹き込み不陸の影響をなくした後、前記
油圧シリンダー15を船体に収めて船体を海底に
着床させ、さらに施工時の作用力も考慮の上バラ
スト量を調整して船体の安定を図る。 When the work boat 1 reaches the seawall construction site by self-propulsion or towing, the ballast is injected into the ballast tank 3 and the hull is brought to the bottom of the seabed 20. At this time, a plurality of hydraulic cylinders 15 installed on the ship's hull are temporarily set on a support 16 that has been sunk on the seabed in advance, leaving a gap that is large enough to prevent the ship's hull from coming into contact with the seabed surface, and earth and sand 19 are poured into the gap. After eliminating the effects of blowing and unevenness, the hydraulic cylinder 15 is housed in the hull, the hull is placed on the seabed, and the amount of ballast is adjusted in consideration of the working force during construction to stabilize the hull.
次に型枠形成部2において型枠操作アーム5を
操作し、護岸の所定形状に合わせて型枠4を形成
する。型枠の形状は平面あるいは縦方向にある程
度の曲率をもつ曲面である。型枠は全体として2
枚の対向する型板となるが、大型であるため縦方
向に数個に分割してもよい。 Next, the formwork operation arm 5 is operated in the formwork forming section 2 to form the formwork 4 in accordance with the predetermined shape of the seawall. The shape of the formwork is a flat surface or a curved surface with a certain degree of curvature in the vertical direction. The formwork as a whole is 2
There will be two opposing templates, but since they are large, they may be divided into several pieces in the vertical direction.
型枠4が形成されると、作業船1よりプレパク
トコンクリート用粗骨材6を型枠内に投入し、ト
レミー管8を作業船1の門形クレーン11を用い
てセツトする。トレミー管8の個数は作業時間、
モルタル混合プラント9の能力などによつて決定
される。ついでモルタル混合プラント9で配合調
整されたモルタル7はトレミー管8で型枠4内に
圧送され、すでに充填されている粗骨材6の間に
充填される。該モルタル7に使用する細骨材は陸
地より作業船1に運搬する他、良好な海底砂が現
地で得られる場合はそれを洗浄して使用してもよ
い。 Once the formwork 4 is formed, coarse aggregate 6 for prepact concrete is put into the formwork from the workboat 1, and the tremie pipe 8 is set using the portal crane 11 of the workboat 1. The number of tremie tubes 8 is the working time,
It is determined by the capacity of the mortar mixing plant 9, etc. Next, the mortar 7 blended in the mortar mixing plant 9 is pumped into the formwork 4 through the tremie tube 8, and is filled between the coarse aggregates 6 that have already been filled. The fine aggregate used for the mortar 7 may be transported from land to the work boat 1, or if good seabed sand is available locally, it may be washed and used.
モルタル7の注入を終り、所謂プレパクトコン
クリートの打設が完了した後は、トレミー管8を
引き上げ、作業船1は海底に着座したままで上記
コンクリートを養生し、その固体化が進み必要な
強度に達したら、型枠操作アーム8を操作して型
枠4をコンクリートから剥離すれば護岸が完成す
る。次にバラストタンク3の水を排水して、作業
船1を浮上前進させ、既設護岸18に続けて、護
岸を新設させていけばよい。 After pouring the mortar 7 and placing the so-called pre-pact concrete, the tremie pipe 8 is pulled up, and the work boat 1 remains seated on the seabed to cure the concrete, allowing it to solidify and reach the required strength. When this is reached, the formwork operation arm 8 is operated to separate the formwork 4 from the concrete, and the seawall is completed. Next, the water in the ballast tank 3 is drained, the work boat 1 is floated forward, and a new seawall is installed following the existing seawall 18.
セメントの硬化材および骨材の補給は、コンク
リートの養生中に済ませることが望ましく、又セ
メントや骨材の消費に伴なう重量の減少はバラス
ト水の注入等で調整すればよい。 It is desirable to replenish cement hardening material and aggregate during concrete curing, and weight loss due to consumption of cement and aggregate can be adjusted by injecting ballast water.
本発明は以上述べたように沖合海域における堤
体や護岸の建設に大型作業船を利用したので、従
来のケーソン工法やセル工法に比べ工期が大きく
短縮される。特に延長の長い同一断面の護岸、防
波堤などの建設には極めて有効である。
As described above, the present invention utilizes a large work boat for constructing embankments and seawalls in offshore waters, so the construction period is greatly shortened compared to the conventional caisson construction method or cell construction method. It is particularly effective for constructing sea walls and breakwaters with the same cross section over a long period of time.
第1図は本発明の一実施例を示す大型作業船に
よる護岸建設工事の斜視図、第2図は該作業船の
断面図である。
図中1は作業船、2は型枠形成部、3はバラス
トタンク、4は型枠、5は型枠操作アーム、6は
粗骨材、7はモルタル、8はトレミー管、9はモ
ルタル混合プラント、10は粗骨材貯槽、11は
門形クレーン、12は指令室および居住区、13
はセメント貯槽、14はポンプである。
FIG. 1 is a perspective view of a seawall construction work performed by a large work boat showing an embodiment of the present invention, and FIG. 2 is a sectional view of the work boat. In the figure, 1 is a work boat, 2 is a formwork forming section, 3 is a ballast tank, 4 is a formwork, 5 is a formwork operation arm, 6 is coarse aggregate, 7 is mortar, 8 is a tremie tube, and 9 is a mortar mixing Plant, 10 is a coarse aggregate storage tank, 11 is a portal crane, 12 is a control room and living area, 13
is a cement storage tank, and 14 is a pump.
Claims (1)
て、建設地点に大型作業船を海底に着座せしめ、
該作業船に装備された型枠支持装置を操作して、
上記堤体、護岸を所要の形状に造成するために型
枠を形成し、該型枠内部にプレパクトコンクリー
トを打設し、養正固化せしめた後型枠をコンクリ
ートより剥離し、作業船を浮上移動せしめ再び同
一作業を繰返すことによつて、前記堤体、護岸を
建設することを特徴とする沖合における堤体、護
岸の急速施工方法。 2 沖合における堤体、護岸の建設工事におい
て、建設地点の海底に着座し、堤体、護岸の型枠
を形成し、かつ該型枠内にプレパクトコンクリー
トを打設する大型作業船が、コの字形を呈し、両
側部にそれぞれ複数個のバラストタンクを具備
し、開口部に型枠形成部を備えるとともに、甲板
上に材料貯槽、モルタル混合プラント、ポンプ、
門形クレーン、指令室および居住室等を配設し、
前記バラストタンク内に注排水することにより、
海底に着座又は浮上しうるように構成されている
ことを特徴とする沖合における堤体、護岸の急速
施工装置。[Claims] 1. In the construction work of an embankment body and seawall offshore, a large work boat is seated on the seabed at the construction site,
Operate the formwork support device installed on the work boat,
A formwork is formed to create the above-mentioned embankment body and revetment in the required shape, and prepact concrete is placed inside the formwork, and after being cured and hardened, the formwork is peeled from the concrete and the work boat is installed. 1. A rapid construction method for offshore embankments and revetments, characterized in that the embankments and revetments are constructed by floating and moving and repeating the same operation. 2. During construction work for offshore embankments and seawalls, large work vessels sit on the seabed at the construction site, form the formwork for the embankment and seawall, and place pre-pact concrete into the formwork. It has a square shape, and is equipped with multiple ballast tanks on each side, a formwork forming part at the opening, and a material storage tank, mortar mixing plant, pump,
A portal crane, control room, living room, etc. will be installed.
By pouring water into the ballast tank,
A rapid construction device for offshore embankment bodies and seawalls, characterized by being configured to be able to sit on or float on the seabed.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26063284A JPS61142255A (en) | 1984-12-12 | 1984-12-12 | Bank body in offshore, rapid construction method and apparatus of shore protection |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26063284A JPS61142255A (en) | 1984-12-12 | 1984-12-12 | Bank body in offshore, rapid construction method and apparatus of shore protection |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61142255A JPS61142255A (en) | 1986-06-30 |
| JPH0345179B2 true JPH0345179B2 (en) | 1991-07-10 |
Family
ID=17350614
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP26063284A Granted JPS61142255A (en) | 1984-12-12 | 1984-12-12 | Bank body in offshore, rapid construction method and apparatus of shore protection |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61142255A (en) |
-
1984
- 1984-12-12 JP JP26063284A patent/JPS61142255A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS61142255A (en) | 1986-06-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3640075A (en) | Method of installing breakwater caissons | |
| Smith | Types of marine concrete structures | |
| WO2023020356A1 (en) | Caisson quay and construction method therefor | |
| CN109024525B (en) | An artificial island structure considering the development and utilization of underground space and its construction method | |
| CN118774027A (en) | A semi-prefabricated construction method for a large deep-water caisson shallow dock | |
| CN201649036U (en) | Pipe pile platform for pier construction | |
| CN1233903C (en) | Construction method for structure of reinforced concrete underwater | |
| JP2001040630A (en) | Caisson offshore structure | |
| CN119083365A (en) | A water-permeable breakwater structure with self-contained wave-breaking function | |
| JP2012180669A (en) | Breakwater reinforcing method and reinforced breakwater | |
| JPH0345179B2 (en) | ||
| CN87103253A (en) | On-site Suspension Construction Method of Caisson and Caisson Engineering | |
| CN216809744U (en) | Modular breakwater based on lightweight concrete | |
| JP2815492B2 (en) | How to build an underwater foundation | |
| CN115897479B (en) | Novel assembled wharf revetment structure based on barrel type foundation and construction method | |
| CN115897640B (en) | Construction method of permeable breakwater | |
| CN202208905U (en) | Integral groove counterfort type revetment and causeway | |
| JPS5934331A (en) | How to build a sewage treatment facility | |
| JP2546110B2 (en) | Levee structure using excavated sludge and its construction method | |
| JP2676779B2 (en) | Cylindrical caisson | |
| CN111335313B (en) | Pile sinking process for wharf pile | |
| JPH06257163A (en) | Drought barge for shallow water foundation work | |
| CN201962645U (en) | Caisson-type open-pier seawall | |
| JPH0323689B2 (en) | ||
| JPS61142219A (en) | Construction of cell at great deep of water |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |