JPH09256379A - Manufacturing of steel shell caisson - Google Patents
Manufacturing of steel shell caissonInfo
- Publication number
- JPH09256379A JPH09256379A JP9198196A JP9198196A JPH09256379A JP H09256379 A JPH09256379 A JP H09256379A JP 9198196 A JP9198196 A JP 9198196A JP 9198196 A JP9198196 A JP 9198196A JP H09256379 A JPH09256379 A JP H09256379A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- caisson
- bottom slab
- placing
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Revetment (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、鋼殻ケーソンの製
造技術、特に、人工島などの施工に用いる巨体な鋼殻ケ
ーソン内に底版コンクリートを打設する技術に関するも
のである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technique for manufacturing a steel shell caisson, and more particularly to a technique for placing bottom slab concrete in a huge steel shell caisson used for construction of artificial islands.
【0002】[0002]
【従来の技術】例えば、人工島のような巨体な海洋構造
物の施工においては、岸壁や護岸などの施工に用いる一
般的なコンクリート製ケーソンに代えて、巨体な鋼殻ケ
ーソンを用いることがある。この鋼殻ケーソン自体は、
上面が開口した内部中空な箱形に形成されるのが普通で
あるが、その内部には必要に応じて底版コンクリートを
打設する場合もある。2. Description of the Related Art For example, in the construction of a huge marine structure such as an artificial island, a giant steel shell caisson may be used in place of a general concrete caisson used for construction of a quay or a seawall. . This steel shell caisson itself,
It is usually formed in the shape of a hollow box with an open upper surface, but bottom slab concrete may be placed inside the box if necessary.
【0003】この底版コンクリートを打設するには、鋼
殻ケーソンの沈設現場よりも製造場所が望ましい。なぜ
なら、例えば、鋼殻ケーソンの海上曳航時や沈設時など
において風の影響を受けにくくするため、その鋼殻ケー
ソンの喫水を深くしておくのに大変有効となるからであ
る。さらに、沈設後における鋼殻ケーソンの底部部分の
補強やその底部部分と基礎杭頭部との結合部の補強、あ
るいは杭頭結合作業の向上などを図る目的からも重要な
構造要素となるからである。もちろん、こうした底版コ
ンクリートは沈設現場でも施工することは可能である。
しかし、そこでは水中不分離性のコンクリートを打設す
る作業となってしまうため、施工性や施工費の点からも
好ましくない。In order to drive this bottom slab concrete, it is preferable to use a manufacturing place rather than a steel shell caisson digging site. This is because, for example, when the steel shell caisson is towed or submerged, the steel shell caisson is less susceptible to the influence of the wind, which is very effective in deepening the draft of the steel shell caisson. Furthermore, it is an important structural element for the purpose of reinforcing the bottom portion of the steel shell caisson after sunk, reinforcing the joint portion between the bottom portion and the foundation pile head, and improving the pile head joint work. is there. Of course, such bottom slab concrete can also be constructed at the site of sunk.
However, this is a work of placing concrete that is inseparable in water, which is not preferable in terms of workability and construction cost.
【0004】ところで、このような巨体な鋼殻ケーソン
を製作する場合、通常、造船設備として知られている、
近くのドライドックを利用することが多い。それは、巨
体で大重量の鋼殻ケーソンを容易に進水させることがで
き、しかも、その沈設位置までの海上輸送も大変便利に
なるからである。By the way, when manufacturing such a huge steel shell caisson, it is generally known as shipbuilding equipment,
I often use a dry dock nearby. This is because it is possible to easily launch a large and heavy steel shell caisson, and it is also very convenient to transport it by sea to its sunk position.
【0005】[0005]
【発明が解決しようとする課題】ところが、このように
鋼殻ケーソンの製作にドライドックを利用した場合、以
下のような点で解決すべき課題がある。However, when the dry dock is used for manufacturing the steel shell caisson as described above, there are problems to be solved in the following points.
【0006】すなわち、鋼殻ケーソン内に底版コンクリ
ートを打設する時期や場所について考慮してみると、ま
ず、その時期については、鋼殻ケーソンを沈設する前に
打設する必要がある。そこで、ドライドック内で予め打
設しておく方法が考えられるが、これには問題が多い。That is, considering the time and place for placing the bottom slab concrete in the steel shell caisson, first, at that time, it is necessary to place the steel shell caisson before it is sunk. Therefore, a method of placing it in the dry dock in advance can be considered, but this has many problems.
【0007】第1に、造船所では大規模なコンクリート
の打設設備を備えていないことに加え、深くて広大なド
ライドック内では既存のコンクリートポンプ車などを有
効に利用することができないことである。First, in addition to the fact that the shipyard is not equipped with large-scale concrete pouring equipment, it is not possible to effectively use the existing concrete pump truck etc. in the deep and vast dry dock. is there.
【0008】第2に、底版コンクリートの打設およびそ
の養生に要する期間については、次の鋼殻ケーソンの製
作が不可能になり、設備の有効利用を図ることができな
いことである。Secondly, as for the period required for placing the bottom slab concrete and curing it, it is impossible to manufacture the next steel shell caisson and it is impossible to effectively utilize the equipment.
【0009】第3に、底版コンクリートは、その打設リ
フトが5m前後にも及ぶために相当な重量となり、その
ため、本来沈設すべき構造物として設計してある鋼殻ケ
ーソンの構造要素のうち、鋼製のケーソン本体部分に及
ぼす強度的な影響、あるいはドライドック自体に作用す
る重量なども無視できなくなることである。Thirdly, the bottom slab concrete has a considerable weight due to the pouring lift reaching about 5 m, and therefore, among the structural elements of the steel shell caisson originally designed as a structure to be laid, The strength of the caisson body made of steel and the weight of the dry dock itself cannot be ignored.
【0010】第4に、上記第3の問題点の解決策とし
て、鋼殻ケーソン自体をドック内で浮かせた状態で底版
コンクリートの打設作業を行う方法も考えられるが、こ
れにはドック自体の水深の問題があり、やはり適切な方
法とは言えない。Fourth, as a solution to the third problem, a method of placing bottom slab concrete with the steel shell caisson itself floating in the dock can be considered. There is a problem of water depth, which is still not an appropriate method.
【0011】本発明は、以上のような点を考慮してなさ
れたもので、鋼殻ケーソンの主体をなす鋼製のケーソン
本体部分の施工と、その内部に打設する底版コンクリー
トの施工とをそれぞれ別の場所で行うことによって、既
存の設備を有効利用して製作製の向上を図ることがで
き、しかも、自重による強度的な影響を及ぼすことなく
施工することができるようにした技術を提供することを
目的とする。The present invention has been made in consideration of the above points. The construction of a steel caisson main body, which is the main constituent of a steel shell caisson, and the construction of bottom slab concrete to be placed inside thereof. Providing technology that enables existing facilities to be effectively used to improve manufacturing and production by performing them in different locations, and in which construction can be carried out without affecting the strength due to its own weight. The purpose is to do.
【0012】[0012]
【課題を解決するための手段】前記課題を解決するた
め、本発明では、上面が開口した内部中空な鋼製のケー
ソン本体を製造し、その内部に底版コンクリートを打設
するに際し、以下のA、BおよびCの各工程を行うこと
を特徴としている。 A 前記鋼製のケーソン本体を、ドライドック等の進水
設備をもつ場所で製造する第1工程。 B 第1工程において製造したケーソン本体を進水させ
て浮かせ、そのケーソン本体を曳航して、底版コンクリ
ートを打設するための岸壁に係留する第2工程。 C 岸壁上にコンクリートポンプ車を複数台配置し、そ
れら各コンクリートポンプ車を利用してケーソン本体内
に底版コンクリートを打設する第3工程。 ここで、底版コンクリートの打設に際し、予め、各コン
クリートポンプ車による底版コンクリートの打設領域を
区画しておき、それら各コンクリートポンプ車によるコ
ンクリートの打設数量を管理することによって、ケーソ
ン本体の重心位置の制御を行うようにすることもでき
る。また、第3工程においては、ケーソン本体の重心位
置の測定値に基づいて各コンクリートポンプ車によるコ
ンクリートの打設数量制御を行うようにすることもでき
る。また、コンクリートポンプ車のブーム先端から延び
るコンクリート圧送用の高圧ホースをケーソン本体の天
端に位置決めし、ケーソン本体内に、前記高圧ホースか
ら底版コンクリートの打設領域に向かって延びるコンク
リート圧送管を配置することにより、コンクリートの打
設に伴うケーソン本体の自沈の変位に対応できるように
設定することもできる。In order to solve the above-mentioned problems, according to the present invention, when a caisson main body made of steel having an open upper surface and made of hollow steel is manufactured and bottom slab concrete is placed therein, the following A , B and C are performed. A First step of manufacturing the above-mentioned steel caisson body at a place having a launch facility such as a dry dock. B The second step in which the caisson body manufactured in the first step is launched and floated, and the caisson body is towed and moored to the quay for placing bottom slab concrete. C The third step of placing multiple concrete pump cars on the quay and using the concrete pump cars to place bottom slab concrete in the caisson body. Here, when placing the bottom slab concrete, the area for placing the bottom slab concrete by each concrete pump truck is defined in advance, and the center of gravity of the caisson body is controlled by controlling the amount of concrete placed by each concrete pump truck. It is also possible to control the position. Further, in the third step, it is possible to control the quantity of concrete to be placed by each concrete pump car based on the measured value of the center of gravity of the caisson body. In addition, a high-pressure hose for concrete pressure feed extending from the boom tip of the concrete pump car is positioned at the top end of the caisson body, and a concrete pressure feed pipe extending from the high-pressure hose toward the placement area of the bottom slab concrete is arranged in the caisson body. By doing so, the caisson body can be set so as to be able to cope with the displacement of the self-sinking caused by the pouring of concrete.
【0013】[0013]
【発明の実施の形態】以下、本発明の好適な実施の形態
について、添付の図1〜図10を参照して説明する。BEST MODE FOR CARRYING OUT THE INVENTION Preferred embodiments of the present invention will be described below with reference to the accompanying FIGS.
【0014】図1は、本発明に係る鋼殻ケーソンのケー
ソン本体に対する底版コンクリートの打設要領を示す斜
視図であり、図2はその概略平面図、図3はその概略縦
断面図、図4は底版コンクリートの打設に至る施工フロ
ー図である。FIG. 1 is a perspective view showing a manner of placing bottom slab concrete on a caisson body of a steel shell caisson according to the present invention, FIG. 2 is a schematic plan view thereof, FIG. 3 is a schematic vertical sectional view thereof, and FIG. [Fig. 3] is a construction flow diagram for placing bottom slab concrete.
【0015】これらの図から理解できるように、ケーソ
ン本体1は、骨組みに大小の多数のH鋼、側板に鋼板等
を用いた、いわゆる鋼殻ケーソンの主体を構成するもの
で、内部中空な箱形に形成される。このケーソン本体1
は、上面が開口し、その内部は、互いに並行する二つの
隔壁2によって三つの室に区画されている。隔壁2の下
部は、後述する底版コンクリートを打設する部分には設
けられていない。つまり、隔壁2は底版コンクリート上
から立ち上がる構造とされる。このケーソン本体1の大
きさは、縦、横、高さがそれぞれ数十メートルあるいは
それ以上にも及ぶ。As can be understood from these figures, the caisson body 1 constitutes the main body of a so-called steel shell caisson in which a large number of large and small H steels are used for the skeleton and steel plates are used for the side plates. Formed into a shape. This caisson body 1
Has an upper surface opened, and the inside thereof is divided into three chambers by two partition walls 2 which are parallel to each other. The lower part of the partition wall 2 is not provided in a portion where a slab concrete to be described later is poured. That is, the partition 2 has a structure rising from the bottom slab concrete. The size of the caisson body 1 may be several tens of meters or more in length, width, and height.
【0016】このような構造および大きさのケーソン本
体1を製作する場合には、例えば造船所のドライドック
を利用して製作する。そこでは、ケーソン本体1を進水
させる前に、図4の施工フロー図で示すように、杭頭型
枠組立、底版コンクリートの打設足場組立、コンクリー
ト打設配管設置、打設機材・照明設備配置などの施工を
予め行う。When the caisson body 1 having such a structure and size is manufactured, it is manufactured, for example, using a dry dock of a shipyard. Before launching the caisson body 1, as shown in the construction flow diagram of FIG. 4, pile head formwork assembly, bottom slab concrete placement scaffolding assembly, concrete placement piping installation, placement equipment and lighting equipment. Perform construction such as placement in advance.
【0017】一方、打設岸壁側では、ケーソン本体1を
曳航して係留する前に、あるいは係留後において、コン
クリートの流動化剤投入足場の組立、岸壁養生、照明・
保安設備等設置、コンクリートポンプ車配置などの各作
業を行い、底版コンクリートを打設する準備を行う。On the other hand, on the pier side, the assembling of the fluidizing agent injection scaffold for concrete, the quay curing, the lighting, before the mooring and mooring of the caisson body 1 are carried out.
Preparations for placing bottom slab concrete will be made by carrying out various operations such as installation of safety equipment and placement of concrete pump trucks.
【0018】こうした準備の後に、前記ケーソン本体1
内に底版コンクリートCが打設されるが、ここで、まず
底版コンクリートCの構造および機能などについて、図
5の断面図を参照しながらもう少し具体的に説明する。
すなわち、ケーソン本体1は、底版コンクリートCの打
設後において、目的とする沈設場所まで曳航され、そこ
で沈設される。この沈設に際しては、予め施工しておい
た多数の基礎杭3の頭部部分でテンプレート4を支持さ
せ、そのテンプレート4上にケーソン本体1を設置して
固定する。テンプレート4は基礎杭3に固定され、しか
も各基礎杭3の頭部はテンプレート4を貫通してケーソ
ン本体1内に臨む構造とされる。After such preparation, the caisson body 1
The bottom slab concrete C is placed therein, and the structure and function of the bottom slab concrete C will be described more concretely with reference to the sectional view of FIG.
That is, the caisson main body 1 is towed to a target setting place after the bottom slab concrete C is set, and is set there. At the time of this sinking, the template 4 is supported by the head portions of a large number of foundation piles 3 that have been constructed in advance, and the caisson body 1 is installed and fixed on the template 4. The template 4 is fixed to the foundation pile 3, and the head of each foundation pile 3 penetrates the template 4 and faces the caisson body 1.
【0019】したがって、底版コンクリートCの部分に
は、各基礎杭3の頭部をそれぞれ引き込むための多数の
空所5が形成される。これらの空所5は、底版コンクリ
ートCの打設前に、その空所5を形成するのに必要な型
枠(図示せず)を組むことによって形成される。また、
空所5内に基礎杭3の頭部を導くために設けてある、ケ
ーソン本体1の底面側の穴には、水密性のある仮蓋fが
着脱可能に取り付けられる。図5において符号6は杭頭
結合コンクリートを打設する部分、7はガスケット、8
a、8bは側壁、9は上床梁を示している。Therefore, in the portion of the bottom slab concrete C, a large number of voids 5 for drawing in the heads of the respective foundation piles 3 are formed. These cavities 5 are formed by assembling the formwork (not shown) necessary for forming the cavities 5 before placing the bottom slab concrete C. Also,
A watertight temporary lid f is detachably attached to a hole on the bottom surface side of the caisson body 1 provided for guiding the head of the foundation pile 3 into the void 5. In FIG. 5, reference numeral 6 is a portion for placing pile head connection concrete, 7 is a gasket, and 8 is a gasket.
a and 8b are side walls, and 9 is an upper floor beam.
【0020】図6はコンクリート打設足場10の側面図
を示すもので、ケーソン本体1を構成する内部部材(例
えば切梁一段目)を支持部材として利用し、単管パイプ
11により吊り足場として組み立てたものである。すな
わち、単管パイプ11を用いてケーソン本体1の最下段
の切梁12に架け渡し、クランプ等で固定し、足場板1
3を敷設している。足場板13の高さは、打設すべき底
版コンクリートCの天端上1m程度にしている。ここ
で、Kは杭頭型枠、14はスリーブ管を示している。FIG. 6 is a side view of the concrete pouring scaffold 10, which uses an internal member (for example, the first step of a beam) of the caisson body 1 as a supporting member and assembles it as a hanging scaffold by a single pipe 11. It is a thing. That is, the single pipe 11 is used to bridge the bottom beam 12 of the caisson body 1 and fixed by a clamp or the like to fix the scaffolding plate 1
3 is laid. The height of the scaffolding plate 13 is about 1 m above the top of the bottom slab concrete C to be cast. Here, K is a pile head formwork and 14 is a sleeve pipe.
【0021】こうした構造のコンクリート打設足場10
は、図7に示すように、ケーソン本体1内の底部近くに
縦横に配置される。この配置関係については、ここで
は、図8に示すように、底版コンクリートCを打設すべ
き領域の合理的な区画に基づいて行われている。すなわ
ち、底版コンクリートCの打設領域は、図中破線で示す
ように、左右に6等分、前後に2等分、合計12等分に
区画している。したがって、打設足場10は、これを上
から見た位置が、各区画のちょうど中央にそれぞれ位置
するように配置している。なお、連絡用の打設足場10
aについては、区画の境界付近に配置している。これに
より、コンクリート打設足場10は、全体として平面格
子状となっている。Concrete pouring scaffold 10 having such a structure
Are vertically and horizontally arranged near the bottom of the caisson body 1, as shown in FIG. This arrangement relationship is performed here based on the rational division of the area where the bottom slab concrete C should be placed, as shown in FIG. That is, the casting area of the bottom slab concrete C is divided into 6 equal parts on the left and right sides and 2 equal parts on the front and rear sides, for a total of 12 equal parts, as indicated by the broken line in the figure. Therefore, the placement scaffolding 10 is arranged so that the position viewed from above is exactly in the center of each section. In addition, the setting scaffolding 10 for communication
About a, it is arranged near the boundary of the section. As a result, the concrete pouring scaffold 10 has a planar lattice shape as a whole.
【0022】コンクリート打設配管20については、ケ
ーソン本体1の内部部材の最上段に受け架台21を取り
付け、コンクリート打設足場10まで縦配管22によっ
て垂直配管し、そこから横配管23によって足場板13
上を水平配管している。Regarding the concrete pouring pipe 20, a receiving stand 21 is attached to the uppermost stage of the internal member of the caisson body 1, vertical pipes 22 are vertically piped up to the concrete pouring scaffold 10, and from there, horizontal pipes 23 are used for the scaffolding plate 13.
The top is horizontally piped.
【0023】さて、ドライドックにおけるケーソン本体
1の製作作業を終えたら、これを進水させて打設岸壁3
0まで曳航(一次曳航)し、そこへ係留する。そして、
図1〜図3に示すように、打設岸壁30上の海寄りの位
置に、複数台のコンクリートポンプ車(図示例ではA1
〜A4、B1〜B4、C1〜C4の合計12台)を横一
列に配置し、その後ろにコンクリートミキサー車40を
配置する。コンクリートミキサー車40は、コンクリー
トの円滑な供給を図るため、コンクリートポンプ車1台
につき、少なくとも2台準備しておく。Now, when the manufacturing work of the caisson main body 1 in the dry dock is finished, it is launched and the casting quay 3
Tow to 0 (primary tow) and moored there. And
As shown in FIGS. 1 to 3, a plurality of concrete pump cars (A1 in the illustrated example) are provided at a position near the sea on the casting quay 30.
-A4, B1-B4, C1-C4) (12 units in total) are arranged in a horizontal row, and the concrete mixer truck 40 is arranged behind it. At least two concrete mixer trucks 40 are prepared for each concrete pump truck in order to ensure smooth supply of concrete.
【0024】また、各コンクリートポンプ車A1〜C4
の各ブーム50の先端を持ち上げて、図3に示すように
弓形に曲げ、そのブーム50の先端から延びるコンクリ
ート圧送用の高圧ホース51をケーソン本体1の天端部
分に位置決めする。そして、受け架台21に支持されて
いる、コンクリート打設配管20の縦配管22に接続す
る。この作業を全てのコンクリートポンプ車について行
い、底版コンクリートCの打設準備を完了する。In addition, each concrete pump car A1 to C4
The upper end of each boom 50 is lifted and bent into an arc shape as shown in FIG. 3, and a high-pressure hose 51 for concrete pumping extending from the end of the boom 50 is positioned at the top end portion of the caisson body 1. Then, it is connected to the vertical pipe 22 of the concrete pouring pipe 20, which is supported by the receiving stand 21. This work is performed for all concrete pump cars, and the preparation for placing the bottom slab concrete C is completed.
【0025】こうして打設準備を完了したら、各コンク
リートポンプ車A1〜C4の全てから一斉にコンクリー
トを圧送し、底版コンクリートCの打設作業を行う。こ
の打設作業に際しては、区画した打設領域の打設数量を
管理することによって、すなわち、コンクリートポンプ
車によるコンクリートの打設数量を管理することによっ
て、ケーソン本体1の重心位置の制御を行うようにす
る。When the preparation for placing is completed in this way, the concrete is pumped from all of the concrete pump cars A1 to C4 all at once, and the work for placing the bottom slab concrete C is performed. At the time of this placing work, the center of gravity position of the caisson body 1 is controlled by controlling the placing amount of the divided placing regions, that is, by controlling the placing amount of concrete by the concrete pump truck. To
【0026】その場合、各コンクリートポンプ車による
コンクリートの打設数量制御に際しては、ケーソン本体
1の重心位置の測定値に基づいて行うようにするのが好
適である。測定方法としては、例えば船舶に装備するト
リム計、傾斜計などを利用し行うことができる。さら
に、高精度に行う場合、3次元自動測量システムを用い
たケーソンの沈設管理方法を採用することができる。In this case, it is preferable that the concrete pouring quantity control by each concrete pump car is performed based on the measured value of the position of the center of gravity of the caisson body 1. As a measuring method, for example, a trim meter, an inclinometer, or the like equipped on a ship can be used. Furthermore, when performing with high accuracy, a caisson sinking management method using a three-dimensional automatic surveying system can be adopted.
【0027】この方法は、例えばケーソン本体1の3次
元座標を光学的に測定し、さらにジャイロコンパス、加
速度計等を用いてケーソン本体の3軸回りの姿勢角を検
出し、それらの検出値に基づいて、例えばコンピュータ
で演算処理して、その結果をディスプレイ上に表示しな
がら制御する方法である。こうすることにより、ケーソ
ン本体1が傾かないようにして底版コンクリートCの打
設作業を実施することができる。In this method, for example, the three-dimensional coordinates of the caisson body 1 are optically measured, the attitude angles of the caisson body around the three axes are detected using a gyrocompass, an accelerometer, and the like, and the detected values are obtained. Based on this, for example, a computer performs arithmetic processing, and the result is controlled while being displayed on a display. By doing so, it is possible to perform the work of placing the bottom slab concrete C without tilting the caisson body 1.
【0028】ケーソン本体1に傾きが生じないようにす
るのは大変重要である。なぜなら、例えばケーソン本体
1が岸壁側に傾いた場合、そのケーソン本体1は、水圧
や風等の影響によって岸壁側に近づく動きを強め、逆に
反対側に傾いた場合、岸壁から遠ざかる方向の動きを強
め、いずれにしてもケーソン本体1が安定しないという
現象を招くからである。It is very important to prevent the caisson body 1 from tilting. This is because, for example, when the caisson body 1 leans toward the quay side, the caisson body 1 strengthens the movement toward the quay side due to the influence of water pressure, wind, etc. On the contrary, when the caisson body 1 leans toward the opposite side, it moves away from the quay. This is because the caisson body 1 is instable in any case.
【0029】底版コンクリートCの打設作業中において
は、ブーム50が弓なりになっているので、このブーム
50の先端部の高さ調整を行うことにより、ケーソン本
体1の上下移動を許容することができる状態となる。し
たがって、コンクリートポンプ車によるコンクリートの
打設に伴うケーソン本体1の自沈の変化に対応すること
ができる。さらに、潮の干満に伴うケーソン本体1の上
下移動に対しても対応することができる。During the operation of placing the bottom slab concrete C, since the boom 50 is arched, it is possible to allow the caisson body 1 to move up and down by adjusting the height of the tip of the boom 50. It will be ready. Therefore, it is possible to cope with the change in the self-sink of the caisson body 1 due to the pouring of concrete by the concrete pump car. Furthermore, it is possible to cope with the vertical movement of the caisson body 1 due to the ebb and flow of the tide.
【0030】底版コンクリートCの打設作業を終え、必
要に応じて養生期間を経た後、このケーソン本体1は目
的とする沈設場所に二次曳航される。After the work of placing the bottom slab concrete C is completed and, if necessary, a curing period is passed, the caisson body 1 is secondarily towed to a desired settling place.
【0031】図9および図10は、コンクリートの流動
化剤投入設備60の平面図および背面図を示している。
打設するコンクリートには、レディーミクストコンクリ
ートを現場まで運搬し、軽量・添加を行い、運搬車の攪
拌により流動化した。現場で流動化を行う場合、流動化
はコンクリートの打ち込み場所にできるだけ近いところ
で流動化させ、ただちに打ち込みができるようにするた
め、図示のような流動化剤投入設備を設置した。流動化
剤の軽量は、ポンプ式自動計量装置(ポンプ61とタイ
マー盤62の組合せ)を使用し、事前に計量精度を検定
・調整した。9 and 10 show a plan view and a rear view of the concrete fluidizing agent charging facility 60.
For the concrete to be placed, ready-mixed concrete was transported to the site, lightened and added, and fluidized by stirring the transport vehicle. In the case of fluidization at the site, fluidization was carried out as close as possible to the concrete driving place, and in order to enable immediate driving, the fluidizing agent charging equipment as shown in the figure was installed. As for the weight of the fluidizing agent, a pump type automatic weighing device (a combination of the pump 61 and the timer board 62) was used, and the weighing accuracy was verified and adjusted in advance.
【0032】この流動化剤投入設備60は、横方向に4
つに区画され、同時に4台のトラックミキサー車40が
進入して流動化剤の供給を受けることができるように構
成されている。この図9および図10において、63は
流動化剤収容タンク、64は発電機、65は鋼製の足場
板、66はアイランプ、67はビティ枠、68は階段で
ある。This fluidizing agent charging equipment 60 has a horizontal 4
The truck mixer trucks 40 are divided into two sections and are configured so that four truck mixer trucks 40 can enter at the same time and receive the supply of the fluidizing agent. 9 and 10, 63 is a fluidizer storage tank, 64 is a generator, 65 is a steel scaffolding plate, 66 is an eye lamp, 67 is a bite frame, and 68 is stairs.
【0033】[0033]
【発明の効果】以上のように、本発明によれば、上面が
開口した内部中空な鋼製のケーソン本体を製造し、その
内部に底版コンクリートを打設するに際し、鋼製のケー
ソン本体を、ドライドック等の進水設備をもつ場所で製
造する第1工程と、第1工程において製造したケーソン
本体を進水させて浮かせ、そのケーソン本体を曳航し
て、底版コンクリートを打設するための岸壁に係留する
第2工程と、岸壁上にコンクリートポンプ車を複数台配
置し、それら各コンクリートポンプ車を利用してケーソ
ン本体内に底版コンクリートを打設する第3工程とを行
うようにしたから、鋼殻ケーソンの主体をなす鋼製のケ
ーソン本体部分の施工と、その内部に打設する底版コン
クリートの施工とをそれぞれ別の場所で行うことによっ
て、既存の設備を有効利用して製作性の向上を図ること
ができ、しかも、自重による強度的な影響を及ぼすこと
なく施工することができる。また、ケーソン本体を沈設
場所に曳航する前に底版コンクリートを打設すること
で、ケーソン本体の喫水を深く、しかも一定にすること
ができ、これにより、その後の構造強度の問題等を回避
して種々の作業を円滑に行うことができる。As described above, according to the present invention, when manufacturing an internal hollow steel caisson main body with an open upper surface and placing bottom slab concrete inside the caisson main body, the steel caisson main body is The first step of manufacturing at a place with a launch facility such as a dry dock, and the caisson body manufactured in the first step is launched and floated, and the caisson body is towed to pour bottom slab concrete Since the second step of mooring the pier and the third step of placing a plurality of concrete pump cars on the quay and using each of these concrete pump cars to place bottom slab concrete in the caisson body, The existing equipment can be installed by performing the construction of the steel caisson main body, which is the main component of the steel shell caisson, and the construction of the bottom slab concrete that is placed inside the caisson body at different locations. It is possible to improve the productivity of using, moreover, it may be applied without strength influence by its own weight. Also, by pouring the bottom slab concrete before towing the caisson body to the place where it was sunk, the draft of the caisson body can be made deep and constant, thereby avoiding problems such as the subsequent structural strength. Various operations can be performed smoothly.
【0034】また、底版コンクリートの打設に際し、予
め、各コンクリートポンプ車による底版コンクリートの
打設領域を区画しておき、それら各コンクリートポンプ
車によるコンクリートの打設数量を管理することによっ
て、ケーソン本体の重心位置の制御を行うようにするこ
とができる。これにより、ケーソン本体の重心が偏らな
いようにして安全に施工することができる。Further, when the bottom slab concrete is poured, the areas for placing the bottom slab concrete by the concrete pump cars are defined in advance, and the quantity of concrete poured by the respective concrete pump cars is controlled to control the caisson body. It is possible to control the position of the center of gravity of the. As a result, the caisson body can be installed safely without being biased in the center of gravity.
【0035】また、第3工程においては、ケーソン本体
の重心位置の測定値に基づいて各コンクリートポンプ車
によるコンクリートの打設数量制御を行うようにするこ
とによって、より安全にしかも正確に管理しながらコン
クリートの打設作業を実施することができる。Further, in the third step, the quantity of concrete placed by each concrete pump car is controlled based on the measured value of the center of gravity of the caisson body, so that it can be managed more safely and accurately. It is possible to perform concrete pouring work.
【0036】さらに、コンクリートポンプ車のブーム先
端から延びるコンクリート圧送用の高圧ホースをケーソ
ン本体の天端に位置決めし、ケーソン本体内に、前記高
圧ホースから底版コンクリートの打設領域に向かって延
びるコンクリート圧送管を配置することにより、コンク
リートの打設に伴うケーソン本体の自沈の変位に対応で
きるように設定することができる。したがって、浮上し
ているケーソン本体に対して岸壁側からコンクリートを
打設する作業を、何等支障なく容易に行うことができ
る。Further, a high-pressure hose for pumping concrete, which extends from the boom tip of the concrete pump car, is positioned at the top end of the caisson body, and concrete pumping that extends from the high-pressure hose toward the placing area of the bottom slab concrete is placed inside the caisson body. By arranging the pipes, the caisson body can be set to cope with the self-sinking displacement of the caisson body caused by the pouring of concrete. Therefore, the operation of placing concrete from the quay side to the floating caisson body can be easily performed without any trouble.
【図1】 ケーソン本体に対する底版コンクリートの打
設要領を示す斜視図である。FIG. 1 is a perspective view showing a procedure for placing bottom slab concrete on a caisson body.
【図2】 図1の概略平面図である。FIG. 2 is a schematic plan view of FIG.
【図3】 図1の概略縦断面図である。FIG. 3 is a schematic vertical sectional view of FIG.
【図4】 底版コンクリートの打設に至る施工フロー図
である。[Fig. 4] Fig. 4 is a construction flow diagram for placing bottom slab concrete.
【図5】 基礎杭上にケーソン本体を設置した状況を示
す断面図である。FIG. 5 is a cross-sectional view showing a state in which a caisson body is installed on a foundation pile.
【図6】 コンクリート打設足場の部分側面図である。FIG. 6 is a partial side view of a concrete pouring scaffold.
【図7】 コンクリート打設足場の配置形態を示す平面
図である。FIG. 7 is a plan view showing an arrangement of concrete pouring scaffolds.
【図8】 底版コンクリートの打設区画割りを示す平面
図である。[Fig. 8] Fig. 8 is a plan view showing a placement section division of bottom slab concrete.
【図9】 コンクリートの流動化剤投入設備の平面図で
ある。FIG. 9 is a plan view of a concrete fluidizing agent charging facility.
【図10】 コンクリートの流動化剤投入設備の背面図
である。FIG. 10 is a rear view of a concrete fluidizing agent charging facility.
1 ケーソン本体 2 隔壁 3 基礎杭 4 テンプレート 5 空所 6 杭頭結合コンクリート 7 ガスケット 8a、8b 側壁 f 仮蓋 10 コンクリート打設足場 10a 連絡用の打設足場 11 単管パイプ 12 切梁 13 足場板 14 スリーブ管 K 杭頭型枠 A1〜C4 コンクリートポンプ車 20 コンクリート打設配管 21 受け架台 30 岸壁 40 コンクリートミキサー車 50 ブーム 51 高圧ホース 60 流動化剤投入設備 1 caisson main body 2 partition wall 3 foundation pile 4 template 5 void space 6 pile head connection concrete 7 gasket 8a, 8b side wall f temporary lid 10 concrete placing scaffolding 10a connecting placing scaffolding 11 single pipe pipe 12 cutting beam 13 scaffolding plate 14 Sleeve pipe K Pile head formwork A1 to C4 Concrete pump car 20 Concrete placing pipe 21 Receiving stand 30 Quay 40 Concrete mixer truck 50 Boom 51 High pressure hose 60 Fluidizer injection equipment
Claims (4)
ン本体を製造し、その内部に底版コンクリートを打設す
るに際し、以下のA、BおよびCの各工程を行うことを
特徴とする鋼殻ケーソンの製造方法。 A 前記鋼製のケーソン本体を、ドライドック等の進水
設備をもつ場所で製造する第1工程。 B 第1工程において製造したケーソン本体を進水させ
て浮かせ、そのケーソン本体を曳航して、前記底版コン
クリートを打設するための岸壁に係留する第2工程。 C 前記岸壁上にコンクリートポンプ車を複数台配置
し、それら各コンクリートポンプ車を利用してケーソン
本体内に底版コンクリートを打設する第3工程。1. A steel which is characterized by performing the following steps A, B and C when a caisson body made of steel having an open upper surface is made and a bottom slab concrete is placed therein. Manufacturing method of shell caisson. A First step of manufacturing the above-mentioned steel caisson body at a place having a launch facility such as a dry dock. B A second step in which the caisson body manufactured in the first step is launched and floated, and the caisson body is towed and moored to the quay wall for placing the bottom slab concrete. C A third step of arranging a plurality of concrete pump cars on the quay and using the respective concrete pump cars to pour bottom slab concrete into the caisson body.
め、各コンクリートポンプ車による底版コンクリートの
打設領域を区画しておき、それら各コンクリートポンプ
車によるコンクリートの打設数量を管理することによっ
て、ケーソン本体の重心位置の制御を行うことを特徴と
する請求項1に記載の鋼殻ケーソンの製造方法。2. A caisson is prepared by preliminarily demarcating an area for placing concrete slabs by each concrete pump car when placing the slab concrete, and managing the quantity of concrete laid by each concrete pump car. The method for manufacturing a steel shell caisson according to claim 1, wherein the position of the center of gravity of the main body is controlled.
の重心位置の測定値に基づいて各コンクリートポンプ車
によるコンクリートの打設数量制御を行うことを特徴と
する、請求項1あるいは2に記載の鋼殻ケーソンの製造
方法。3. The method according to claim 1, wherein in the third step, the quantity of concrete placed by each concrete pump car is controlled based on the measured value of the center of gravity of the caisson body. Steel shell caisson manufacturing method.
から延びるコンクリート圧送用の高圧ホースをケーソン
本体の天端に位置決めし、ケーソン本体内に、前記高圧
ホースから底版コンクリートの打設領域に向かって延び
るコンクリート圧送管を配置することにより、コンクリ
ートの打設に伴うケーソン本体の自沈の変位に対応でき
るように設定したことを特徴とする、請求項1〜3の何
れかに記載の鋼殻ケーソンの製造方法。4. A concrete high-pressure hose extending from the boom end of the concrete pump car for concrete pumping is positioned at the top end of the caisson main body, and concrete extending from the high-pressure hose toward the casting area of the bottom slab concrete is placed inside the caisson main body. The method for producing a steel shell caisson according to any one of claims 1 to 3, characterized in that the pressure feeding pipe is arranged so as to be capable of coping with the displacement of the self-sinking of the caisson body due to the placing of concrete. .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9198196A JPH09256379A (en) | 1996-03-20 | 1996-03-20 | Manufacturing of steel shell caisson |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9198196A JPH09256379A (en) | 1996-03-20 | 1996-03-20 | Manufacturing of steel shell caisson |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH09256379A true JPH09256379A (en) | 1997-09-30 |
Family
ID=14041677
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP9198196A Pending JPH09256379A (en) | 1996-03-20 | 1996-03-20 | Manufacturing of steel shell caisson |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH09256379A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021110187A (en) * | 2020-01-14 | 2021-08-02 | オリエンタル白石株式会社 | Method of placing concrete in pneumatic caisson method |
| CN114622598A (en) * | 2022-03-02 | 2022-06-14 | 上海市隧道工程轨道交通设计研究院 | A steel shell concrete immersed tunnel suspension point structure connection structure and its construction method |
| CN115680023A (en) * | 2022-10-31 | 2023-02-03 | 中交第四航务工程局有限公司 | A construction method and design method for steel shell concrete immersed tube pouring |
-
1996
- 1996-03-20 JP JP9198196A patent/JPH09256379A/en active Pending
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021110187A (en) * | 2020-01-14 | 2021-08-02 | オリエンタル白石株式会社 | Method of placing concrete in pneumatic caisson method |
| CN114622598A (en) * | 2022-03-02 | 2022-06-14 | 上海市隧道工程轨道交通设计研究院 | A steel shell concrete immersed tunnel suspension point structure connection structure and its construction method |
| CN114622598B (en) * | 2022-03-02 | 2024-04-02 | 上海市隧道工程轨道交通设计研究院 | A steel shell concrete immersed tube tunnel lifting point structure connection structure and its construction method |
| CN115680023A (en) * | 2022-10-31 | 2023-02-03 | 中交第四航务工程局有限公司 | A construction method and design method for steel shell concrete immersed tube pouring |
| CN115680023B (en) * | 2022-10-31 | 2024-02-06 | 中交第四航务工程局有限公司 | Construction method and design method for pouring steel shell concrete immersed tube |
| WO2024093623A1 (en) * | 2022-10-31 | 2024-05-10 | 中交第四航务工程局有限公司 | Construction method and design method for pouring of steel-shelled concrete immersed tube |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4440527A (en) | Marine structure | |
| CN100579862C (en) | Method and apparatus for launching a ship transversely built on the ground | |
| CN102251530A (en) | Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River | |
| CN110939148A (en) | A construction method of double-walled steel suspended box cofferdam that doubles as a drilling platform | |
| CN113668610A (en) | Semi-floating pouring method for steel shell concrete immersed tube | |
| CN109707002B (en) | Device and method for accurately positioning, sinking and installing large water intake head | |
| JP3663693B2 (en) | Large structure manufacturing and repair work methods as well as barges used to implement these methods | |
| CN110055984B (en) | Lowering construction method for double-wall deformed steel cofferdam | |
| JPH1046597A (en) | Execution work method of steel shell caisson | |
| JPH11140893A (en) | Manufacture and launching method for sinking box | |
| JPH09256379A (en) | Manufacturing of steel shell caisson | |
| EP0029044B1 (en) | A method of carrying out slip form casting of concrete structures under water and apparatus for carrying out the method | |
| JP3463604B2 (en) | Dolphin construction method | |
| CN201685988U (en) | 1600-ton crane ship main hull closing height positioning device on water | |
| KR101052834B1 (en) | Dredging and driving barges and how to use them | |
| CN111005396A (en) | A steel cofferdam installation process | |
| JP2868725B2 (en) | Seawall repair method | |
| JPH06193391A (en) | How to launch a submerged box | |
| CN222456107U (en) | Construction device for weir first and pile later in deep water without covering layer in reservoir area | |
| CN116378041A (en) | Construction Method of Temporary Steel Pipe Pile in Shallow Water Area | |
| JP3926027B2 (en) | Caisson construction method | |
| JPH10237875A (en) | Caisson installation method | |
| JP2652026B2 (en) | Quay construction method | |
| CN120350680A (en) | A cofferdam hoisting and lowering construction device and construction method | |
| CN120443676A (en) | A construction method for offshore pile-free expanded foundation |