JPS63233196A - Method of executing gallery - Google Patents

Method of executing gallery

Info

Publication number
JPS63233196A
JPS63233196A JP62062640A JP6264087A JPS63233196A JP S63233196 A JPS63233196 A JP S63233196A JP 62062640 A JP62062640 A JP 62062640A JP 6264087 A JP6264087 A JP 6264087A JP S63233196 A JPS63233196 A JP S63233196A
Authority
JP
Japan
Prior art keywords
lining
reaction force
shield machine
concrete
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP62062640A
Other languages
Japanese (ja)
Inventor
康夫 佐藤
邦登 酒井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP62062640A priority Critical patent/JPS63233196A/en
Publication of JPS63233196A publication Critical patent/JPS63233196A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は硬化した既設置・ンネルの内壁からシールドマ
シンの掘進反力を得て掘進しながら、プレストレスを与
えたトンネル躯体を構築する、坑道の施工技術に関する
ものである。
[Detailed Description of the Invention] <Industrial Application Field> The present invention constructs a prestressed tunnel frame while excavating by obtaining the excavation reaction force of a shield machine from the hardened inner wall of an already installed tunnel. This is related to tunnel construction technology.

〈従来の技術〉 シールドマシンで掘削した掘削直後の坑道内に型枠を使
ってコンクリートを現場打ちしてトンネルを構築する技
術は広く知られている。
<Conventional technology> The technology of constructing a tunnel by using formwork to pour concrete on-site in a tunnel immediately after excavation using a shield machine is widely known.

ところで、コンクリートを現場打ちによって構築する場
合、シールドマシンの掘進反力をどこから得るかが問題
となる。
By the way, when constructing concrete by pouring it on-site, the problem is where to obtain the digging reaction force of the shield machine.

現在、シールドマシンの掘進反力を型枠から得る方法が
提案されている。
Currently, a method has been proposed in which the digging reaction force of a shield machine is obtained from the formwork.

また一方、孔壁の崩壊を防止するためには、フレッシュ
コンクリ−1への圧力を孔壁の崩壊力に抗しない圧力を
かけてコンクリートが硬化するまで維持してやる必要が
ある。
On the other hand, in order to prevent the collapse of the hole walls, it is necessary to apply pressure to the fresh concrete 1 that does not resist the collapse force of the hole walls and maintain it until the concrete hardens.

このようなコンクリートに圧力をかけて維持する手段と
しては、ジヤツキ圧やコンクリートポンプによる圧送圧
を利用して施工する方法が知られている。
As a means for applying and maintaining pressure on concrete, methods of construction using jack pressure or pumping pressure using a concrete pump are known.

〈本発明が解決しようとする問題点〉 上記したトンネルの施工技術にはつぎのような問題点が
ある。
<Problems to be Solved by the Present Invention> The tunnel construction techniques described above have the following problems.

(イ)弱材令のコンクリートから反力をとると、覆工構
造物の品質に悪影響を及ぼす。
(b) Taking reaction force from weak concrete will have a negative impact on the quality of the lining structure.

(ロ)覆工コンクリートが硬化するまでの間は脱型でき
ない。
(b) It cannot be removed from the mold until the lining concrete has hardened.

(ハ)覆工コンクリートが硬化するのを待って、硬化構
造物からシールドマシンの掘進反力を得ることも考えら
れるが、コンクリートが硬化するまでの期間作業が中断
するため工期が長期化する。
(c) It is possible to wait for the lining concrete to harden and obtain the digging reaction force of the shield machine from the hardened structure, but this will lengthen the construction period as work will be interrupted until the concrete hardens.

(ニ)コンクリートの硬化時間を縮めるために、超早強
性の材料が使用されるので、施工コストが高くつく。
(d) In order to shorten the hardening time of concrete, materials with ultra-early strength are used, resulting in high construction costs.

(ホ)打設したコンクリートがある程度硬化するまでジ
ヤツキ圧や圧送圧を維持しなければならない関係から、
ジヤツキ装置や圧送管などが邪魔になって、覆工構造物
内に鉄筋や鉄骨などの補強部材を配置できない。
(e) Since the jacking pressure and pumping pressure must be maintained until the poured concrete has hardened to a certain extent,
Reinforcing members such as reinforcing bars and steel frames cannot be placed inside the lining structure because jacking devices and pressure pipes get in the way.

(へ)坑道が小断面なほど、脱型した後の施工が困難と
なる。
(f) The smaller the cross-section of the tunnel, the more difficult it will be to construct it after demolding.

く本発明の目的〉 本発明はこのような問題点を解決するために成されたも
ので、覆工構造物に悪影響を与えずにシールドマシンの
掘進反力が得られ、しかも施工性および経済性に優れ、
そのうえ強度や品質がともに良好に施工できる、坑道の
施工技術を提供することを目的とする。
OBJECT OF THE INVENTION The present invention was made to solve these problems, and it is possible to obtain the digging reaction force of the shield machine without adversely affecting the lining structure, and also to improve workability and economy. excellent in sex,
Furthermore, the purpose is to provide a construction technology for tunnels that can be constructed with good strength and quality.

〈本発明の構成〉 以下、図面を参照しながら本発明の一実施例について説
明する。
<Configuration of the Present Invention> An embodiment of the present invention will be described below with reference to the drawings.

まず、施工に使用する主要な機材について説明する。First, we will explain the main equipment used for construction.

〈イ〉シールドマシン 第1図にシールドマシン1の一例を示す。<A> Shield machine An example of a shield machine 1 is shown in FIG.

このシールドマシン1は、本体11の後部に本体11の
テール部から突出したテールプレート12を有する。
This shield machine 1 has a tail plate 12 protruding from the tail portion of the main body 11 at the rear of the main body 11.

テールプレート12は、本体11に固定したスライドジ
ヤツキ13に接続してスライド自在に構成しである。
The tail plate 12 is connected to a slide jack 13 fixed to the main body 11 so as to be slidable.

また、シールドマシン1には、型枠移動ジヤツキ14と
掘進ジヤツキ15とプレスジヤツキ16とを備えている
The shield machine 1 also includes a formwork moving jack 14, an excavation jack 15, and a press jack 16.

これらのすべてのジャツギ13〜16は、本体11内に
円周方向に複数配列しである。
All of these jatsugi 13 to 16 are arranged in plurality in the circumferential direction inside the main body 11.

〈口〉反力装置 掘進ジヤツキ15の先端は、シールドマシン1の掘進反
力を得るための反力装置2に接続している。
<Port> Reaction force device The tip of the digging jack 15 is connected to the reaction force device 2 for obtaining the digging reaction force of the shield machine 1.

反力装置2は第1.2図に示すように、複数の拡縮筒2
1と、これらの拡縮筒21間を連結する伸縮機能を持っ
た連結ロット22と、走行輪23とからなる。
As shown in Fig. 1.2, the reaction force device 2 includes a plurality of expansion/contraction tubes 2.
1, a connecting rod 22 having a telescopic function that connects these expandable tubes 21, and a running wheel 23.

各円筒状の拡縮筒21は、円弧形をした二枚の分割リン
グ24と、両分割リング24間に介在した複数のジヤツ
キ25とからなり、ジヤツキ25の伸縮操作により各拡
縮筒21の径を拡縮するよう構成しである。
Each cylindrical expansion/contraction tube 21 is made up of two arc-shaped split rings 24 and a plurality of jacks 25 interposed between the two split rings 24, and the diameter of each expansion/contraction tube 21 is adjusted by the expansion/contraction operation of the jacks 25. It is configured to scale.

シールドマシン1の掘進反力を反力装置2から得るため
には、第1図に示ずように反力装置2の前端部にブラケ
ット26を設け、このブラケット26に、掘進ジヤツキ
15から延びる延長用のロッド17の一端を接続する。
In order to obtain the digging reaction force of the shield machine 1 from the reaction force device 2, a bracket 26 is provided at the front end of the reaction device 2 as shown in FIG. Connect one end of the rod 17 for use.

また、掘進ジャツギ15の0ツド17の座屈防止を図る
ため、ロット17の途−1−の複数箇所を支持してやる
In addition, in order to prevent buckling of the bolt 17 of the digging jack 15, a plurality of locations in the middle -1- of the lot 17 are supported.

具体的には、例えば移動型枠装置3の内周面の途上にロ
ッド17の挿通可能な寸法の開設孔を有する支持板18
を複数設け、この各支持板18にロッド17を貫通して
配置する。
Specifically, for example, a support plate 18 having a hole sized to allow insertion of the rod 17 in the middle of the inner circumferential surface of the movable formwork device 3 is used.
A plurality of rods 17 are provided, and the rods 17 are disposed so as to pass through each support plate 18.

〈ハ〉移動型枠装置(第1図) 移動型枠装置3は、型枠移動ジヤツキ14と、型枠移動
ジヤツキ14に接続した移動型枠3]とからなる。
<C> Movable formwork device (FIG. 1) The movable formwork device 3 consists of a formwork moving jack 14 and a movable formwork 3 connected to the formwork moving jack 14.

移動型枠31はライナープレートと円周方向のリブから
なる。
The movable formwork 31 consists of a liner plate and circumferential ribs.

移動型枠31にトンネルの縦断方向のリブを設けないの
は、l−ンネルの縦断方向の剛性を落としてトンネルの
成形曲線に対応するためである。
The reason why the movable formwork 31 is not provided with ribs in the longitudinal direction of the tunnel is to reduce the rigidity of the tunnel in the longitudinal direction to accommodate the forming curve of the tunnel.

移動型枠31は型枠移動ジヤツキ14の伸縮操作によっ
て前進する。
The movable formwork 31 moves forward by the expansion and contraction operations of the formwork movement jack 14.

〈二〉移動支保工装置 移動支保工装置4は覆工直後の構造物の崩落を防止する
だめの走行手段を有する公知の支保装置である。
<2> Movable shoring device The movable shoring device 4 is a known shoring device having a traveling means to prevent the structure from collapsing immediately after lining.

打設直後の覆工ライニングを移動型枠31て支保てきる
場合には、移動型枠装置3で兼用して移動支保装置を省
略できる。
When the movable formwork 31 is used to support the lining immediately after being cast, the movable formwork device 3 can also be used to omit the movable support device.

〈ホ〉プレスリング(第3.4図) プレスリング5は、前記移動型枠31と協動じて型枠を
構成する円環状の板体であり、円弧形の分割体を円環状
に組み立て使用する。
<E> Press ring (Fig. 3.4) The press ring 5 is an annular plate that cooperates with the movable form 31 to form a form, and the arc-shaped divided bodies are assembled into an annular shape. use.

プレスリング5は断面がH形を有し、内環51と外環5
2および内環51.52を連絡する遮板53とからなる
The press ring 5 has an H-shaped cross section, and includes an inner ring 51 and an outer ring 5.
2 and a shielding plate 53 connecting the inner rings 51 and 52.

プレスリング5の遮板53の板面には、複数の孔54を
有する。
The plate surface of the shielding plate 53 of the press ring 5 has a plurality of holes 54.

この孔54は、覆工構造物内に埋設した緊張材6の端を
貫通して型枠外へ案内するための案内用の孔である。
This hole 54 is a guide hole for penetrating the end of the tendon material 6 buried in the lining structure and guiding it out of the formwork.

また、他のプレスリング5として、第5図に示すような
内環51の内周面と外環52の外周面に連続したコンク
リート層55を接着したタイプを使用することも考えら
れる。
Further, as another press ring 5, it is also possible to use a type in which a continuous concrete layer 55 is adhered to the inner circumferential surface of an inner ring 51 and the outer circumferential surface of an outer ring 52 as shown in FIG.

次に施工方法について説明する。Next, the construction method will be explained.

くイ〉掘進反力を得るための工程(第1.6図)反力装
置2を既に硬化した覆工ライニング7内に配置し、つぎ
に各拡縮筒21−を拡径して硬化した覆工ライニング7
に圧着させる。
Kui> Process for obtaining excavation reaction force (Fig. 1.6) The reaction force device 2 is placed inside the already hardened lining 7, and then each expansion/contraction tube 21- is expanded in diameter to remove the hardened lining. Engineering lining 7
Crimp it.

本発明ては特に、前回の工程で打設してまだ硬化しない
覆工ライニング7から反力を得るのではなく、前回の工
程で打設した覆工ライニング7から数スパン分程度離れ
た位置てあって、十分に強度が発現した覆工ライニング
7からシールドマシン1の掘進のための反力を(qるこ
とを特徴の一つとする。
In particular, in the present invention, instead of obtaining reaction force from the lining 7 that was cast in the previous process and has not yet hardened, the reaction force is obtained from a position several spans away from the lining 7 that was cast in the previous process. One of the features is that the reaction force for the digging of the shield machine 1 is generated from the lining 7 which has developed sufficient strength.

〈口〉掘進工程 硬化した覆工ライニング7に圧接する反力装置2から反
力を得て、掘進ジヤツキ15を伸長してシールドマシン
1の本体11を切羽側へ前進させる。
<Excavation> Excavation process A reaction force is obtained from the reaction force device 2 that presses against the hardened lining 7, and the excavation jack 15 is extended to advance the main body 11 of the shield machine 1 toward the face side.

くハ〉プレスリングを組み立てる工程 シールドマシン1の前進を終えたら、掘進ジヤツキ15
を収縮する。
Kuha〉The process of assembling the press ring After the shield machine 1 has finished moving forward, the excavation jack 15
to contract.

掘進ジヤツキ15が収縮すると、掘進ジヤツキ15の自
由端部がロッド17から離隔し、テールプレート12内
にプレスリング5を組み立てるための空間が形成される
When the digging jack 15 is retracted, the free end of the digging jack 15 separates from the rod 17, creating a space in the tail plate 12 for assembling the press ring 5.

つぎに分割されたプレスリング5を搬入し、移動型枠3
1とテールプレート12との間に組み立てる。
Next, the divided press ring 5 is carried in, and the movable formwork 3
1 and the tail plate 12.

プレスリング5を組み立てる際、第7図に示すように前
工程で構築した覆工ライニング7から突出する各緊張材
6aに接続具61aを介して別途の緊張材6bを接続し
、この緊張材6bの自由端をプレスリング5の孔54に
貫通して絹み立てる。
When assembling the press ring 5, as shown in FIG. 7, a separate tendon 6b is connected to each tendon 6a protruding from the lining 7 constructed in the previous step via a connecting tool 61a, and this tendon 6b The free end of the press ring 5 is passed through the hole 54 to create silk.

く二〉コンクリートを打設する工程(第1.7図)最外
端に位置するプレスリング5にプレスジヤツキ16をセ
ットする。
2> Process of pouring concrete (Fig. 1.7) Set the press jack 16 on the press ring 5 located at the outermost end.

つぎに、シールドマシン1から反力を得て、移動型枠3
1を切羽側へ前進させる。
Next, the reaction force is obtained from the shield machine 1, and the movable formwork 3
1 to the face side.

その結果、テールプレー1・12と移動型枠31との間
に遮蔽空間が形成される。
As a result, a shielded space is formed between the tail plays 1 and 12 and the movable formwork 31.

そして、コンクリート打設のための配管を行い、テール
プレート12と移動型枠31との間に形成された遮蔽空
間内にコンクリートを圧入する。
Then, piping for concrete pouring is performed, and concrete is press-fitted into the shielded space formed between the tail plate 12 and the movable formwork 31.

前記遮蔽空間の全域にコンクリートを充填したら、プレ
スジヤツキ16を伸長して、所定のプレス圧力で加圧す
る。
Once the entire area of the shielded space is filled with concrete, the press jack 16 is extended and pressurized with a predetermined press pressure.

くホ〉覆工ライニングにプレストレスを与える工程(第
8図) プレスジヤツキ16を伸長するするとプレスリング5は
前記遮蔽空間の体債を減少する方向に後退する。
Step of applying prestress to the lining (Fig. 8) When the press jack 16 is extended, the press ring 5 retreats in a direction that reduces the body weight of the shielded space.

その結果、遮蔽空間内のコンクリートは加圧されて余剰
水の大部分が排出される。
As a result, the concrete within the shielded space is pressurized and most of the excess water is drained away.

さらに、コンクリートに加圧を続けながらテールプレー
ト12を切羽側に前進させると、コンクリートが地山に
密着する。
Furthermore, when the tail plate 12 is advanced toward the face side while continuing to pressurize the concrete, the concrete comes into close contact with the ground.

打設直後の覆工ライニング7の加圧状態を保持するため
に、プレスリング5から突出する緊張材6に模式または
ナツト式の固定具62を取り付けて定着した後、プレス
ジヤツキ16を収縮する。
In order to maintain the pressurized state of the lining 7 immediately after casting, a model or nut-type fixture 62 is attached to the tension material 6 protruding from the press ring 5 and fixed, and then the press jack 16 is contracted.

このように本発明では、前行程で施工した覆工ライニン
グ7に与えたプレストレスをプレスリン容易に配設する
ことができる。
As described above, in the present invention, the prestress applied to the lining 7 constructed in the previous step can be easily applied to the prestress.

くべ〉施工装置を移動する工程(第9図)つぎに、反力
装置2の各拡縮筒21を゛縮径して、走行輪23を出す
Step of moving the construction device (FIG. 9) Next, the diameter of each expansion/contraction tube 21 of the reaction force device 2 is reduced to expose the running wheels 23.

つづいて、掘進ジヤツキ15を収縮操作しなから反力装
置2を1スパン分だけ切羽側−\前進させる。
Next, the digging jack 15 is retracted and the reaction device 2 is moved forward by one span toward the face.

以上の各工程を繰り返しながら、掘進上交互にあるいは
並行して覆工ライニング7を順次延長して構築する。
While repeating each of the above steps, the lining 7 is successively extended and constructed alternately or in parallel during excavation.

なお、移動支保工装置4は、lスパン分の覆工ライニン
グ7の施工毎に切羽側に移動する。
Note that the movable shoring device 4 moves to the face side every time one span of lining 7 is constructed.

く本発明の効果〉 本発明は以上説明したようになるからっぎの効果が得ら
れる。
Effects of the Present Invention> The present invention provides the effects described above.

(イ)本発明はシールドマシンの掘進反力を硬化した覆
工構造物から得る方式である。
(a) The present invention is a system in which the digging reaction force of a shield machine is obtained from a hardened lining structure.

そのため、覆工構造物に不要な圧力が作用して悪影響を
及ぼす心配がない。
Therefore, there is no need to worry about unnecessary pressure acting on the lining structure and adversely affecting it.

(ロ)覆工構造物にトンネル方向のプレストレスを与え
て施工する。
(b) Perform construction by applying prestress to the lining structure in the direction of the tunnel.

したがって、トンネル軸方向に圧縮力が残り、トンネル
軸方向に堅固な構造物を施工できる。
Therefore, compressive force remains in the axial direction of the tunnel, and a strong structure can be constructed in the axial direction of the tunnel.

(ハ)覆工構造物の円周方向にもプレストレスが与えら
れ、曲げモーメントよりも軸力が卓越する。
(c) Prestress is also applied to the lining structure in the circumferential direction, and the axial force is more dominant than the bending moment.

その結果、覆工構造物の引張応力の発生が抑制される。As a result, generation of tensile stress in the lining structure is suppressed.

(ニ)コンクリートを加圧するので、コンクリート中の
余剰水が排出されて水セメント比が良好になる。
(d) Since the concrete is pressurized, excess water in the concrete is discharged and the water-cement ratio is improved.

そのため、覆工構造物を高品質に施工できる。Therefore, the lining structure can be constructed with high quality.

(ホ〉テールプレー1・と移動型枠間でコンクリートを
加圧してから他山に押し付けるため、コンクリートの品
質が地山の性状に左右されない。
(E) Since the concrete is pressurized between the tail play 1 and the movable formwork and then pressed onto another pile, the quality of the concrete is not affected by the properties of the ground.

(へ)シールドマシンの前進と、テールプレートの前進
とを別々に独立して行える。
(f) The forward movement of the shield machine and the forward movement of the tail plate can be performed separately and independently.

したがって、コンクリートの打設時期とシールドマシン
の掘進時期のタイミングを合わぜないで施工でき、施工
上有利である。
Therefore, construction can be carried out without matching the timing of concrete placement and the timing of excavation of the shield machine, which is advantageous in terms of construction.

(ト)組立式のプレスリングを用いてコンクリートが硬
化ずのを待たずに、次の行程を進行できる。
(g) By using a prefabricated press ring, the next process can proceed without waiting for the concrete to harden.

したがって、施工期間が短くなる。Therefore, the construction period is shortened.

(チ)型枠や支保工および反力カ装置を機械的にスライ
ド移動できるから省力化が図れる。
(h) Labor can be saved because the formwork, shoring, and reaction force device can be mechanically slid.

また自動化も容易に可能である。Automation is also easily possible.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明に係る一実施例の説明同第2因二反力装
置の斜視図 第3図ニブレスリングの説明図 第4図ニブレスリングの横断面図 第5図:他のプレスリングの横断面図 第6N:反力装置の縮径時の説明図 第7図・覆工ライニングの終端部の部分断面図第8図;
覆工ライニングの加圧時の説明図第9図・反力装置の移
動時の説明図 第3図 第4図   第5図 第6図
Fig. 1: Explanation of one embodiment of the present invention A perspective view of the second factor-two reaction force device Fig. 3 An explanatory view of the nib ring Fig. 4 A cross-sectional view of the nib ring Fig. 5: Another press ring Cross-sectional view No. 6N: Explanatory view of the reaction device when the diameter is reduced. FIG. 7. Partial cross-sectional view of the terminal end of the lining. FIG. 8;
Explanatory diagram when pressurizing the lining Figure 9 Explanatory diagram when moving the reaction force device Figure 3 Figure 4 Figure 5 Figure 6

Claims (1)

【特許請求の範囲】 シールドマシンで掘削して形成された地山と移動型枠間
にコンクリートを現場打ちしてライニングを覆工して坑
道を施工する方法において、硬化した覆工ライニング内
に拡縮自在の筒体からなる反力装置を位置させ、 前記シールドマシンと反力装置との間に伸縮自在なジャ
ッキを介在し、 シールドマシンと反力装置との間に移動型枠と支保工装
置とを配置し、 硬化した覆工ライニングから反力を得てシールドマシン
を掘進させ、 つぎに既設の覆工ライニングの終端の延長上であって、
この覆工ライニングの終端から突出する緊張材に貫通さ
せて分割形のリング板を組み立て、前記リング板と移動
型枠とで閉塞した空間内にコンクリートを打設し、 つぎに、リング板を加圧状態で緊張材に固定して覆工ラ
イニングにプレストレスを与え、 シールドマシンの掘進工程と、ライニングの覆工工程と
をそれぞれ独立して繰り返して行う、坑道の施工方法。
[Claims of Claims] In a method of constructing a tunnel by pouring concrete on-site between the ground formed by excavating with a shield machine and a movable formwork and lining the tunnel, expansion and contraction within the hardened lining is performed. A reaction force device consisting of a flexible cylindrical body is positioned, a telescopic jack is interposed between the shield machine and the reaction force device, and a movable formwork and a shoring device are interposed between the shield machine and the reaction force device. The shield machine is then excavated by obtaining a reaction force from the hardened lining, and then it is located on the extension of the end of the existing lining,
A split ring plate is assembled by passing through the tendons protruding from the end of the lining, concrete is poured into the space closed by the ring plate and the movable formwork, and then the ring plate is processed. A method of constructing tunnels in which the tunnel lining is fixed under pressure to tension members to apply prestress, and the excavation process with a shield machine and the process of lining the lining are repeated independently.
JP62062640A 1987-03-19 1987-03-19 Method of executing gallery Pending JPS63233196A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62062640A JPS63233196A (en) 1987-03-19 1987-03-19 Method of executing gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62062640A JPS63233196A (en) 1987-03-19 1987-03-19 Method of executing gallery

Publications (1)

Publication Number Publication Date
JPS63233196A true JPS63233196A (en) 1988-09-28

Family

ID=13206130

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62062640A Pending JPS63233196A (en) 1987-03-19 1987-03-19 Method of executing gallery

Country Status (1)

Country Link
JP (1) JPS63233196A (en)

Similar Documents

Publication Publication Date Title
JPS62202199A (en) Method of lining shield tunnel
JPS63233196A (en) Method of executing gallery
JPS63233198A (en) Method of executing pc tunnel
JPS5991298A (en) Shield drilling apparatus
JPH0237480B2 (en)
JPH0325600B2 (en)
JPS63233197A (en) Reaction device for shielding machine
JPH0464398B2 (en)
JP2691472B2 (en) Tunnel lining concrete continuous pouring equipment
JPS63289198A (en) Method of executing gateway
JPH01192998A (en) Tunnel refilling method and device therefor
JPH0351499A (en) Cast-in-place lining shield excavator
JPS6278399A (en) Method for lining shield tunnel and mold frame apparatus used therein
JPH011894A (en) In-situ lining method for shield tunnels
JP2501072Y2 (en) Shield pressure machine for shield machine
JPH0784834B2 (en) Road construction method
JPH04174196A (en) In-situ lining work
SU1182173A2 (en) Tunneling sliding forms
JPH01322100A (en) Shield work method with cast-in-place concrete lining
JPH0361000B2 (en)
JPH0464400B2 (en)
JPH0367192B2 (en)
JPS624518B2 (en)
JPH01299998A (en) Shielded propulsion and shielding construction method in lining on-site lining
JPH09303094A (en) Concrete pipe constructing device