PL145373B1 - Movable face-type filling dam operating in association with advancing roof support - Google Patents

Movable face-type filling dam operating in association with advancing roof support Download PDF

Info

Publication number
PL145373B1
PL145373B1 PL24836784A PL24836784A PL145373B1 PL 145373 B1 PL145373 B1 PL 145373B1 PL 24836784 A PL24836784 A PL 24836784A PL 24836784 A PL24836784 A PL 24836784A PL 145373 B1 PL145373 B1 PL 145373B1
Authority
PL
Poland
Prior art keywords
support
dam
sections
upper beam
association
Prior art date
Application number
PL24836784A
Other languages
Polish (pl)
Other versions
PL248367A1 (en
Inventor
Wojciech Skoczynski
Wincenty Pretor
Marceli Gabka
Andrzej Kedziora
Kornel Olender
Original Assignee
Ct Kt Maszyn Gorniczych Komag
Kloeckner Becorit Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ct Kt Maszyn Gorniczych Komag, Kloeckner Becorit Gmbh filed Critical Ct Kt Maszyn Gorniczych Komag
Priority to PL24836784A priority Critical patent/PL145373B1/en
Publication of PL248367A1 publication Critical patent/PL248367A1/en
Publication of PL145373B1 publication Critical patent/PL145373B1/en

Links

Landscapes

  • Tents Or Canopies (AREA)

Description

Przedmiotem wynalazku jest przesuwna czolowa tama podsadzkowa wspólpracujaca z obudo¬ wa zmechanizowana, która to tama odgradza przestrzen robocza przodka scianowego od prze¬ strzeni podsadzanej* Z polskiego opisu patentowego nr 143 133 znana jest górnicza obudowa kroczaca zwia¬ zana z tama podsadzkowa* Konstrukcje nosna tamy tworzy belka górna, belka dolna, oraz pio¬ nowe, rozsuwne laoznlkl laczace belke górna z belka dolna* Konstrukcja nosna tamy podwie¬ szona jest do stropnicy obudowy za pomoca zawiesia przesuwnego wzdluz stropnicy* Celem wynalazku jest czolowa tama podsadzkowa której górna nosna belka ma mozliwosc zginania sie stosownie do zmian wysokosci polozenia poszczególnych stropnic obudowy, z któ¬ ra wspólpracuje tama oraz ma mozliwosc zginania sie wzdluz frontu sciany* Cel ten osiag¬ nieto przez podzielenie górnej nosnej belki tamy na odcinki odpowiadajace podzialce sek¬ cji obudowy, do której przyporzadkowana jest tama* Poszczególne odcinki górnej belki tamy polaczone sa przegubami o osiach poziomych, a kazdy z tych odcinków podwieszony Jest za pomoca przegubu o osi poziomej do zawiesia przesuwnego wzdluz stropnicy obudowy* W wyniku takiej konstrukcji górna belka tamy podsadzkowej moze zginac sie dowolnie w plaszczyznie pionowej, zas w plaszczyznie poziomej moze zginac sie o pewien ograniczony kat* Umozli¬ wia to dostosowanie wysokosci tamy do wysokosci polozenia poszczególnych stropnic zesta¬ wu obudowy, która to wysokosc z kolei uzalezniona jest od zmieniajacej sie wysokosci podsadzanego wyrobiska* Przedmiot wynalazku w przykladowym wykonaniu przedstawiony jesi na rysunku, na któ¬ rym fig* 1 przedstawia przesuwna czolowa tame podsadzkowa w czesciowym widoku z przodu 1 czesciowym przekroju 1-1 przez obudowe, a fig* 2 - tame w czesciowym widoku i czesciowym przekroju* Konstrukcje nosna tamy tworzy górna belka 1, dolna belka 4, oraz laczace te belki laczniki 2, 3a, 3b* Górna belka 1 tamy podwieszona jest do stropnicy 5 obudowy, a dolna 145 3732 145 373 belka 4 wspiera sie na plozach 6 lezacych na spagu* Górna belka 1 sklada sie z odcinków polaczonych przegubami 8 o osiach poziomych* Poszczególne odcinki tej górnej belki 1 ta¬ my polaczone sa ze stropnicami 5 obudowy za posrednictwem zawiesi 9 1 poprzez przeguby 12 o osiach poziomych* Zawiesia 9 dla górnej belki 1 sa przesuwne w korytkach wzdluz pod¬ luznych osi stropnic 5* Dolna belka 4 tamy sklada sie z odcinków polaczonych przegubami 7* Tama utworzona z kilku ' zespolów nosnych pokryta jest przepona skladajaca sie z warst¬ wy przedziny 10 1 warstwy siatki 11* Tama taka przesuwa sie w calosci* a jej poszczegól¬ ne odcinki moga zginac sie wzdluz frontu sciany pod katami ustalonymi konstrukcyjnie* Górna belka 1 w razie potrzeby moze zginac sie w przegubach 8 w plaszczyznie poziomej o kat wartosci do 5°, zas w plaszczyznie pionowej o dowolny kat* Stropnica 5 moze skrecac sie wzgledem górnej belki 1 i przesuwac sie poprzecznie do przodka* Tama Jest równoczes¬ nie ciagnieta po spagu wyrobiska 1 pod stropem za pomoca urzadzenia 24 do przesuwania, które to urzadzenie zapewnia równiez korygowanie dosuwanla ciagu górnych belek 1 i ciagu dolnych belek 4 tamy do sekcji obudowy* Podczas podsadzania górna belke 1 podtrzymuje silownik 25 urzadzenia 24, a dolna belka 4 opiera sie o spagnice 26 sekcji obudowy* Zastrzezenia patentowe 1* Przesuwna czolowa tama podsadzkowa wspólpracujaca z obudowa zmechanizowana, ma¬ jaca górna belke nosna i dolna belke nosna które to belki polaczone sa pionowymi rozsuw- nynii lacznikami, przy czym górna nosna belka jest podwieszona na zawiesiu przesuwnym wzdluz stropnicy obudowy, znamienna t y m, ze górna belka /i/ nosna sklada sie z odcinków polaczonych przegubami /&/ o osi poziomej, zas poszczególne odcinki górnej belki /i/ podwieszone sa do przesuwnych zawiesi /9/ za pomoca przegubów /12/ o osi po¬ ziomej* 2* Przesuwna czolowa tama podsadzkowa wedlug zastrz* 19 znamienna tym, ze odcinki górnej belki /!/ maja dlugosc równa podzialce sekcji obudowy*145 373 Ol145 373 Pracownia PotigrafKzna UP PRL. Naklad 100 egz.Cena 220 zl PLThe subject of the invention is a sliding front support dam cooperating with a powered support, which separates the working space of the longwall face from the backfilling space * From the Polish patent description No. 143 133 a mining treading support is known related to the support dam * Support structure of the dam it consists of an upper beam, a lower beam, and a vertical, extensible laoznlkl, connecting the upper beam with the lower beam * The supporting structure of the dam is suspended to the roof canopy by means of a sling that is sliding along the canopy * The purpose of the invention is a front support dam with an upper bearing beam bending according to changes in the height of the position of individual canopies of the support, with which the dam works, and has the possibility of bending along the front of the wall * This goal was achieved by dividing the upper supporting beam of the dam into sections corresponding to the division of the section of the support to which it is assigned dam * The individual sections of the upper dam beam are connected by hinges with horizontal axes, and each of these sections is suspended by a joint with a horizontal axis for a sling that slides along the roof of the support structure * As a result of this structure, the top beam of the loading dam can bend freely in the vertical plane, and in the horizontal plane it can bend a certain amount limited angle * This makes it possible to adjust the height of the dam to the height of the position of individual canopies of the support set, which in turn depends on the changing height of the excavated excavation * The subject of the invention in an exemplary embodiment is shown in the drawing, in which fig * 1 shows the sliding frontal support in a partial front view, 1 partial cross-section 1-1 through the casing, and fig * 2 - the same in a partial view and a partial cross-section * The supporting structure of the dam consists of the upper beam 1, the lower beam 4, and connecting the beams between these beams 2, 3a, 3b * The upper beam 1 of the dam is suspended from the canopy 5 of the housing, and the lower one 145 3732 145 373 b Elka 4 is supported on skids 6 lying on the spag * The upper beam 1 consists of sections connected by articulated joints 8 with horizontal axes * The individual sections of this upper beam 1 are connected with the canopies 5 of the casing by means of slings 9 1 through joints 12 with axes horizontal * The slings 9 for the upper beam 1 are movable in the troughs along the longitudinal axes of the canopy 5 * The lower beam 4 of the dam consists of sections connected by articulations 7 * The dam made of several 'carriers is covered with a diaphragm consisting of a layer of a compartment 10 1 mesh layer 11 * Such a dam moves as a whole * and its individual sections can bend along the front of the wall at structurally determined angles * The upper beam 1, if necessary, can bend at joints 8 in the horizontal plane with an angle of up to 5 ° , while in the vertical plane by any angle * Stropnica 5 may turn relative to the upper beam 1 and move transversely to the face * The dam is simultaneously pulled along the spag spark 1 under the ceiling by means of the shifting device 24, which also ensures correcting the advancement of the upper beam 1 and the lower beam 4 of the dam against the casing section * During the back-up, the upper beam 1 supports the cylinder 25 of the device 24, and the lower beam 4 rests against cuff 26 sections of support * Patent Claims 1 * Sliding front support dam interfacing with a powered support, having an upper beam and a lower beam which are connected by vertical extensions and couplings, the upper beam is suspended on a sling that slides along canopy of the casing, characterized by the fact that the upper beam / and / of the carrier consists of sections connected by articulated joints / & / with a horizontal axis, and individual sections of the upper beam / and / are suspended from sliding slings / 9 / by means of joints / 12 / with an axis horizontal * 2 * Sliding front loading dam according to claim 19, characterized in that the sections of the upper beam /! / have a length equal to the division of the housing sections y * 145 373 Ol145 373 Potigraphy studio of the People's Republic of Poland. Mintage 100 copies Price PLN 220 PL

Claims (2)

Zastrzezenia patentowe 1. * Przesuwna czolowa tama podsadzkowa wspólpracujaca z obudowa zmechanizowana, ma¬ jaca górna belke nosna i dolna belke nosna które to belki polaczone sa pionowymi rozsuw- nynii lacznikami, przy czym górna nosna belka jest podwieszona na zawiesiu przesuwnym wzdluz stropnicy obudowy, znamienna t y m, ze górna belka /i/ nosna sklada sie z odcinków polaczonych przegubami /&/ o osi poziomej, zas poszczególne odcinki górnej belki /i/ podwieszone sa do przesuwnych zawiesi /9/ za pomoca przegubów /12/ o osi po¬ ziomej*Claims 1. * Sliding front support dam interfacing with a powered support, having an upper support beam and a lower support beam, which beams are connected by vertical extensions and couplings, the upper support beam being suspended on a sling that slides along the roof of the support, characterized by the fact that the upper beam / and / carrier consists of sections connected by articulated joints / & / by the horizontal axis, and the individual sections of the upper beam / and / are suspended from sliding slings / 9 / by means of joints / 12 / with a horizontal axis * 2. * Przesuwna czolowa tama podsadzkowa wedlug zastrz* 19 znamienna tym, ze odcinki górnej belki /!/ maja dlugosc równa podzialce sekcji obudowy*145 373 Ol145 373 Pracownia PotigrafKzna UP PRL. Naklad 100 egz. Cena 220 zl PL2. * Sliding front loading dam according to claim * 19, characterized in that the sections of the upper beam /! / Have a length equal to the division of the support section * 145 373 Ol145 373 Pracownia PotigrafKzna UP PRL. Mintage 100 copies. Price PLN 220 PL
PL24836784A 1984-06-19 1984-06-19 Movable face-type filling dam operating in association with advancing roof support PL145373B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL24836784A PL145373B1 (en) 1984-06-19 1984-06-19 Movable face-type filling dam operating in association with advancing roof support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL24836784A PL145373B1 (en) 1984-06-19 1984-06-19 Movable face-type filling dam operating in association with advancing roof support

Publications (2)

Publication Number Publication Date
PL248367A1 PL248367A1 (en) 1986-05-06
PL145373B1 true PL145373B1 (en) 1988-09-30

Family

ID=20022361

Family Applications (1)

Application Number Title Priority Date Filing Date
PL24836784A PL145373B1 (en) 1984-06-19 1984-06-19 Movable face-type filling dam operating in association with advancing roof support

Country Status (1)

Country Link
PL (1) PL145373B1 (en)

Also Published As

Publication number Publication date
PL248367A1 (en) 1986-05-06

Similar Documents

Publication Publication Date Title
PL145373B1 (en) Movable face-type filling dam operating in association with advancing roof support
US4186969A (en) Apparatus for controlling the position of a mining machine
SU1758240A1 (en) Unit of unitized-aggregated powered support
SU1375820A1 (en) Tunneling set
SU777233A1 (en) Power roof support section
SU742594A1 (en) Conjugation roof support
RU2065971C1 (en) Mechanized support section
RU2065970C1 (en) Mechanized support section
SU732528A1 (en) Temporary mining roof support frame
SU831998A1 (en) Mechanized mining set for inclined beds
RU1770583C (en) Temporary advancing support
SU1025785A1 (en) Tubular crossing on chute canal on sagging soil
SU994758A1 (en) Transverse stability system of units of power support for steep seams
SU900014A1 (en) Arrangement for supporting the stoping face and roof
SU599088A1 (en) Section of powered mine roof support
SU876524A1 (en) Flight of flight bending conveyer
SU1278463A1 (en) Machine set for working steep seams
SU878949A1 (en) Temporary safety roof support of preparatory face
SU450889A1 (en) Support mate
RU2003809C1 (en) Arched shield
SU832003A1 (en) Power roof support unit
SU840383A1 (en) Flexible shield
SU846745A1 (en) Power roof support for steep beds
SU569720A1 (en) Neumatic prop section