WO2009095884A2 - Procedimiento e instalación para la fabricación de elementos modulares prismáticos huecos de hormigón armado y elemento obtenido mediante estos - Google Patents
Procedimiento e instalación para la fabricación de elementos modulares prismáticos huecos de hormigón armado y elemento obtenido mediante estos Download PDFInfo
- Publication number
- WO2009095884A2 WO2009095884A2 PCT/IB2009/050376 IB2009050376W WO2009095884A2 WO 2009095884 A2 WO2009095884 A2 WO 2009095884A2 IB 2009050376 W IB2009050376 W IB 2009050376W WO 2009095884 A2 WO2009095884 A2 WO 2009095884A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- formwork
- concreting
- slab
- side walls
- modular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/22—Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/002—Producing shaped prefabricated articles from the material assembled from preformed elements
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/0091—Transformable moulds allowing the change of shape of an initial moulded preform by preform deformation or the change of its size by moulding on the preform
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/02—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/32—Tiltable forms or tilting tables for making walls as a whole or in parts in situ
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/0088—Moulds in which at least one surface of the moulded article serves as mould surface, e.g. moulding articles on or against a previously shaped article, between previously shaped articles
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49616—Structural member making
- Y10T29/49623—Static structure, e.g., a building component
Definitions
- the present invention relates to a process for the manufacture of monolithic construction elements and to an installation for carrying out said process, which allow mass production, with optimal control of tolerances, lightweight and large modular building elements. structural resistance, optimizing manufacturing times and costs.
- a monolithic construction element means a homogeneous element from the point of view of the material that composes it. In this sense, several degrees of monolithism can be conceived, which will be greater the more homogeneity obtained in the element.
- This monolithism will be associated with greater structural resistance since the higher this is, the less unions the element will have and, in general, less weak points.
- each panel is homogeneous and can have a high resistance
- the product obtained is not monolithic, since all the joints in the edges are made when the panels have already been obtained.
- the stabilization and union by means of these frames although it has given satisfactory results, implies unions after the setting of the different panels, and therefore, is not optimal from the point of view of global monolithism, since the rigidity of the whole is It mainly concentrates on the frames.
- Another drawback of the fixed formwork is the difficulty of removing, when setting allows, the molds that form the formwork, and especially the interiors.
- the device is complex, since a large structure capable of rotating a large mass is needed. Therefore, it is a clear limitation with respect to the maximum dimensions of the element obtained. -Only items with a single dimension can be obtained, and therefore not versatile from the point of view of the product, unless additional molds or fillings are used. -Although it allows the mass production of elements, the total manufacturing time of an element is around four times the minimum setting time required for each of the four walls of the element. -It presents decoupling problems when the element requires ribs, a necessary condition in any modular stackable system, for lightening issues. In this sense, it has been proposed to use added molds that are removed once the drum part has been removed. But this solution has an added cost of auxiliary elements, process time, and tolerances, since the introduction of new stages and auxiliary elements inevitably introduces positioning errors.
- the process for the manufacture of hollow prismatic monolithic modular elements of reinforced concrete of rectangular section of the invention is characterized by the fact that it comprises the steps of: a) concreting the side walls of the modular element into two horizontally arranged formwork, b) after a sufficient setting of the side walls, make a rotation of said formwork so that they are arranged vertically on both sides of a third formwork, said third formwork being horizontal and, c) performing the concreting of the floor slab slab element in said third formwork, d) arranging a formwork between the side walls held at the appropriate height for the concreting of the roof slab of the element, e) carrying out the concreting of the ceiling slab of the element and, f) removing the element Modulate the third formwork when setting allows.
- the proposed objectives are achieved, namely:
- the control in the measures of the elements is another essential characteristic to achieve a great structural resistance, since it helps to avoid mismatches in the relative disposition of the elements, therefore avoiding the accumulation of mismatches as more plants are made .
- the concreting of the roof slab is carried out immediately after the concreting of the slab slab is finished, so that the upper and lower joints set thereto time, allowing a great homogeneity of the product.
- step b) the formwork of the side walls is horizontally arranged again to start the manufacture of another element, so that these are already available to start the manufacture of another element. This allows to optimize the use of the installation and reduce manufacturing times.
- the invention relates to an installation that makes it possible to carry out the described procedure, and more specifically to an installation for the manufacture of hollow prismatic monolithic modular elements of reinforced concrete of rectangular section, comprising two formwork for the concreting of the walls lateral, a formwork for the concreting of the slab slab and another formwork for the concreting of the ceiling slab, and characterized by the fact that each formwork for the concreting of the side walls are articulated along an axis horizontal so that they can rotate from a horizontal concrete position to a vertical position thus forming the slab formwork of the modular element.
- This installation allows a precise control of the manufacturing tolerances, since there are only three moving parts during the manufacturing process, which are the rotation of the side formwork and the insertion in translation of the formwork of the roof slab.
- the side wall formwork comprises a bottom platform limited by side flanges, and is characterized by the fact that the proximal side flange of said axis is articulated with said platform, so that the side formwork can be removed by rotation.
- These tabs, during formwork, are part of this, becoming also, after the rotation of the element, the vertical supports of the element. Therefore, in order to be able to remove the lateral formwork, it is necessary that these lateral flanges can be de-axialized in rotation of the main surface of the lateral formwork.
- this articulation allows the placement of a second lateral flange arranged perpendicular to said flange, so that the formwork of the lateral walls of the next element can be made.
- the horizontal articulation axes are horizontally movable, so that the installation allows obtaining elements of different widths. Similarly, the length of the elements obtained can be regulated.
- the invention relates to the hollow reinforced concrete prismatic monolithic modular element of rectangular section obtained by the method and The installation described.
- Figure 1 shows the relative arrangement of the formwork of the side walls and the formwork of the floor slab at the initial moment.
- Figure l.c shows an instant of the stage of vertical setting of the side walls, once they have set enough to prevent their deformation above the maximum allowable tolerances in the final product.
- Figure l.g shows the installation once the side formwork is again in a horizontal position and once the formwork of the roof slab has been arranged.
- Figure l.h shows the installation once the roof slab of the element has been formed and the side walls of the next element have been formed.
- Figure 1 shows an installation once the formwork has been removed and, after a sufficient setting of the element, it has been removed from the installation.
- the process for manufacturing hollow prismatic monolithic modular elements of reinforced concrete of rectangular section 1 object of the invention comprises the following stages: In a first phase, the beginning and end of which are shown in Figures 1.a and lb respectively, the concreting (formwork) of the side walls 2 of said element is carried out in two horizontally arranged formworks 3, which allows to ensure optimum concreting from the point of view of the homogeneity of the material.
- the horizontal concreting allows to obtain walls of great mechanical resistance of up to about 50 mm, which gives them a great slenderness and a minimum weight, characteristic that will allow to achieve stacking of many floors with the modular elements obtained.
- the rotation shafts 18 of the installation are horizontally movable, so that they allow to prepare the installation for the manufacture of modules of different sizes, especially of different widths.
- the placement of additional formwork elements is provided to vary the width of the formwork of the floor slab 5.
- a rotation 4 of the formwork of the formwork is carried out. side walls until these are taken to the vertical position shown in figure ld Obviously, sufficient setting is understood as a setting that allows the aforementioned rotation to be performed without the element becoming deformed.
- the formwork of the side walls can be brought to its horizontal position, figure lf, so that the element is stripped by its sides, and these are being prepared for the formwork of the side walls of another element.
- this formwork rotation is only possible if the side walls 11, also called tabs, of the side formworks 2 are previously de-rotated in rotation.
- the solidarity and de-consolidation of these tabs can be carried out by a system of pins that are introduced or removed respectively, for example, by the axis of articulation between the side formwork 2 and said tabs 11.
- the side tabs have a double function. On the one hand they form part of the perimeter surfaces of the formwork of the side walls, and, when the formwork (the wall) is arranged vertically, it serves as support for said wall.
- the formwork 7 of the roof slab is introduced in the longitudinal direction, that is perpendicular to the plane of the sheet, supported by a movable structure 8 and then is raised to its proper position for concreting 9 of the ceiling slab 10 , as seen in figure lh It should be noted that one of the advantages of the invention is that it allows optimizing the use of all formwork.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Moulds, Cores, Or Mandrels (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Panels For Use In Building Construction (AREA)
- Catalysts (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
Claims
Priority Applications (10)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP09706854A EP2248644B1 (en) | 2008-02-01 | 2009-01-30 | Method and installation for manufacturing hollow, prismatic, modular reinforced-concrete elements, and element obtained therefrom |
| AT09706854T ATE523305T1 (de) | 2008-02-01 | 2009-01-30 | Verfahren und anlage zur herstellung von hohlen, prismatischen, modularen stahlbetonelementen und daraus erhaltenes element |
| PL09706854T PL2248644T3 (pl) | 2008-02-01 | 2009-01-30 | Sposób i instalacja do wytwarzania pustych, graniastych, modułowych elementów żelbetowych i otrzymany z tego element |
| BRPI0905842-7A BRPI0905842A2 (pt) | 2008-02-01 | 2009-01-30 | Método e instalação de fabricação de elementos de concreto reforçado modulares prismáticos ocos e elemento obtido com eles. |
| CN2009801069016A CN101965254B (zh) | 2008-02-01 | 2009-01-30 | 生产中空、棱柱形、模块化的钢筋混凝土构件的方法和装置以及由此获得的构件 |
| CA2713826A CA2713826C (en) | 2008-02-01 | 2009-01-30 | Method and installation for manufacturing hollow, prismatic, modular reinforced-concrete elements, and element obtained therefrom |
| MX2010008424A MX2010008424A (es) | 2008-02-01 | 2009-01-30 | Procedimiento e instalacion para la fabricacion de elementos modulares prismaticos huecos de hormigon armado y elemento obtenido mediante estos. |
| US12/865,547 US8652379B2 (en) | 2008-02-01 | 2009-01-30 | Method and system for manufacturing hollow reinforced concrete modular elements and element obtained therefrom |
| RU2010134565/03A RU2471620C2 (ru) | 2008-02-01 | 2009-01-30 | Способ изготовления полых призматических модульных железобетонных элементов и установка для изготовления таких элементов |
| MA33116A MA32103B1 (fr) | 2008-02-01 | 2010-08-26 | Procédé et installation de fabrication d'éléments modulaires prismatiques creux de béton armé et élément obtenu |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ES200800263A ES2330911B1 (es) | 2008-02-01 | 2008-02-01 | Procedimiento e instalacion para la fabricacion de elementos modulares prismaticos huecos de hormigon armado y elemento obtenido mediante estos. |
| ESP200800263 | 2008-02-01 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| WO2009095884A2 true WO2009095884A2 (es) | 2009-08-06 |
| WO2009095884A3 WO2009095884A3 (es) | 2009-12-03 |
Family
ID=40913358
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/IB2009/050376 Ceased WO2009095884A2 (es) | 2008-02-01 | 2009-01-30 | Procedimiento e instalación para la fabricación de elementos modulares prismáticos huecos de hormigón armado y elemento obtenido mediante estos |
Country Status (12)
| Country | Link |
|---|---|
| US (1) | US8652379B2 (es) |
| EP (1) | EP2248644B1 (es) |
| CN (1) | CN101965254B (es) |
| AT (1) | ATE523305T1 (es) |
| BR (1) | BRPI0905842A2 (es) |
| CA (1) | CA2713826C (es) |
| ES (2) | ES2330911B1 (es) |
| MA (1) | MA32103B1 (es) |
| MX (1) | MX2010008424A (es) |
| PL (1) | PL2248644T3 (es) |
| RU (1) | RU2471620C2 (es) |
| WO (1) | WO2009095884A2 (es) |
Families Citing this family (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013175027A1 (es) | 2012-05-23 | 2013-11-28 | Anton Arquitectos, S.L.U. | Módulo habitable y sistema de construcción modular de espacios para habitar |
| CN103029199B (zh) * | 2013-01-09 | 2014-12-31 | 上海高诚艺术包装有限公司 | 一种方形陶瓷制品的生产方法 |
| RU2549977C2 (ru) * | 2013-06-19 | 2015-05-10 | Открытое акционерное общество "Первоуральский завод горного оборудования" (ОАО "ПЗГО") | Металлокаменное полое изделие |
| CN103434010B (zh) * | 2013-08-10 | 2015-10-28 | 杨福聚 | 一种烟道模具及使用该烟道模具制作烟道的方法 |
| CN105178196B (zh) * | 2015-09-28 | 2017-03-29 | 中铁上海工程局集团有限公司 | 一种多节点连动式环湿接段整体模板及方法 |
| CN107627443B (zh) * | 2017-10-31 | 2023-07-25 | 中冶建工集团有限公司 | 一种便于收叠的混凝土试块模具 |
| CN111231076B (zh) * | 2020-01-20 | 2024-05-17 | 中交一公局集团有限公司 | 垫石模板装置 |
| CN114750262B (zh) * | 2022-05-30 | 2023-08-18 | 中国天楹股份有限公司 | 一种利用固废制作大型配重块的全自动生产工艺方法 |
| CN115107147B (zh) * | 2022-05-31 | 2023-11-21 | 青岛青建理工建筑工业化研究院有限公司 | 一种ppvc空间模块构建方法 |
| CN115262968A (zh) * | 2022-09-01 | 2022-11-01 | 天津瑞孚特科技有限公司 | 一种高精度模板卡具 |
| CN116749326B (zh) * | 2023-07-18 | 2026-01-02 | 承德绿建建筑节能科技有限公司 | 侧面无封闭套子钢筋的预制构件侧模、组合结构、立模设备和方法 |
| CN119502091B (zh) * | 2024-10-22 | 2025-07-25 | 湖北金颖建筑材料有限公司 | 一种快装式桩承台钢模板 |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ES2285877A1 (es) | 2004-08-12 | 2007-11-16 | Compact-Habit, S.L. | Sistema estructural para edificaciones. |
Family Cites Families (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US1276624A (en) | 1918-05-20 | 1918-08-20 | Robert A Cummings | Method of constructing reinforced-concrete hulls for boats, &c. |
| US1581797A (en) * | 1925-10-06 | 1926-04-20 | Fey George | Concrete block making |
| US3676536A (en) * | 1969-01-10 | 1972-07-11 | Shelley Systems Inc | System for producing modular building blocks |
| AT301428B (de) * | 1969-07-03 | 1972-09-11 | Hugo Mischek Dipl Ing | Form zur Herstellung einer Raumzelle |
| US3932082A (en) * | 1974-01-21 | 1976-01-13 | Beaman Samuel W | Means for forming a reinforced concrete module |
| US4207042A (en) * | 1979-01-29 | 1980-06-10 | Mikhail Linetsky | Casting and erecting machine |
| DE3203107A1 (de) * | 1982-01-30 | 1983-08-11 | Riplinger, Michael, 6638 Dillingen | Vorrichtung und verfahren zum herstellen von winkelelementen aus beton |
| NL8502696A (nl) * | 1985-10-03 | 1987-05-04 | Jacob Penseel | Werkwijze voor het ter plaatse produceren van monteerbare scheidingswanden alsmede daarvoor toegepaste produktie-eenheid. |
| US4799982A (en) * | 1986-03-20 | 1989-01-24 | Charmasson & Holz | Method of molding monolithic building structure |
| SU1722843A1 (ru) * | 1989-05-03 | 1992-03-30 | Проектный Институт N2 Госстроя Ссср | Установка дл изготовлени объемных железобетонных блоков |
| SU1717368A1 (ru) * | 1990-06-27 | 1992-03-07 | В.В.Пушкарев, В.Я.Фофанов, ААДульзон и Ю.В.Максимов | Установка дл изготовлени сборно-монолитных объемных изделий |
| SU1735011A1 (ru) * | 1990-08-08 | 1992-05-23 | Научно-Исследовательский Институт Строительных Конструкций | Установка дл изготовлени сборно-монолитных объемных элементов |
| AU658179B2 (en) * | 1992-05-08 | 1995-04-06 | Quickcell Technology Pty Ltd | Method of manufacturing precast concrete units |
| CN1106725A (zh) * | 1993-11-10 | 1995-08-16 | 奎克塞尔技术有限公司 | 预制混凝土构件的生产方法 |
-
2008
- 2008-02-01 ES ES200800263A patent/ES2330911B1/es not_active Expired - Fee Related
-
2009
- 2009-01-30 US US12/865,547 patent/US8652379B2/en not_active Expired - Fee Related
- 2009-01-30 PL PL09706854T patent/PL2248644T3/pl unknown
- 2009-01-30 AT AT09706854T patent/ATE523305T1/de not_active IP Right Cessation
- 2009-01-30 MX MX2010008424A patent/MX2010008424A/es active IP Right Grant
- 2009-01-30 CN CN2009801069016A patent/CN101965254B/zh not_active Expired - Fee Related
- 2009-01-30 WO PCT/IB2009/050376 patent/WO2009095884A2/es not_active Ceased
- 2009-01-30 BR BRPI0905842-7A patent/BRPI0905842A2/pt not_active IP Right Cessation
- 2009-01-30 EP EP09706854A patent/EP2248644B1/en active Active
- 2009-01-30 RU RU2010134565/03A patent/RU2471620C2/ru active
- 2009-01-30 CA CA2713826A patent/CA2713826C/en not_active Expired - Fee Related
- 2009-01-30 ES ES09706854T patent/ES2372667T3/es active Active
-
2010
- 2010-08-26 MA MA33116A patent/MA32103B1/fr unknown
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ES2285877A1 (es) | 2004-08-12 | 2007-11-16 | Compact-Habit, S.L. | Sistema estructural para edificaciones. |
Also Published As
| Publication number | Publication date |
|---|---|
| RU2471620C2 (ru) | 2013-01-10 |
| ES2330911B1 (es) | 2010-09-22 |
| WO2009095884A3 (es) | 2009-12-03 |
| ES2372667T3 (es) | 2012-01-25 |
| MA32103B1 (fr) | 2011-02-01 |
| RU2010134565A (ru) | 2012-03-10 |
| CA2713826A1 (en) | 2009-08-06 |
| EP2248644B1 (en) | 2011-09-07 |
| CN101965254B (zh) | 2012-09-05 |
| ATE523305T1 (de) | 2011-09-15 |
| CN101965254A (zh) | 2011-02-02 |
| BRPI0905842A2 (pt) | 2015-06-30 |
| PL2248644T3 (pl) | 2012-01-31 |
| US20110000088A1 (en) | 2011-01-06 |
| EP2248644A2 (en) | 2010-11-10 |
| ES2330911A1 (es) | 2009-12-16 |
| US8652379B2 (en) | 2014-02-18 |
| CA2713826C (en) | 2016-08-30 |
| MX2010008424A (es) | 2010-11-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| ES2372667T3 (es) | Procedimiento e instalación para la fabricación de elementos modulares prismáticos huecos de hormigón armado y elemento obtenido mediante estos. | |
| ES2326010B2 (es) | Estructura y procedimiento de montaje de torres de hormigon para turbinas eolicas. | |
| ES2533339T3 (es) | Módulos de encofrar, ensamblables y desechables, para construir encofrados modulares para hacer cimientos de hormigón | |
| ES2350336B2 (es) | Procedimiento de fabricacion de modulos compactos para la construccion. | |
| ES2624991T3 (es) | Placa prefabricada de hormigón para la construcción de un piso de edificio | |
| US4207042A (en) | Casting and erecting machine | |
| ES2367540T3 (es) | Encofrado en bateria para la fabricación vertical de piezas planas prefabricadas en hormigón. | |
| KR101748781B1 (ko) | 프리캐스트 벽체 구조체의 시공방법 | |
| ITVR20100206A1 (it) | Struttura di fondazione particolarmente per edifici prefabbricati | |
| CN113944483A (zh) | 异形结构、台架结构及联络洞室拱顶二次衬砌施工方法 | |
| CN111512004A (zh) | 简易房 | |
| CN113482405A (zh) | 集成房屋及其搭建方法 | |
| ES3037590T3 (en) | Structural element, layout and wall for architectural construction, especially frame houses | |
| US1560320A (en) | Knockdown building | |
| RU80867U1 (ru) | Крестовый свод | |
| CN110107083B (zh) | 一种跃层式住宅楼层施工方法 | |
| AU2017100711A4 (en) | Modular columbarium | |
| JP2002174025A (ja) | 管路内スライド足場とその施工方法 | |
| ES3055557A1 (es) | Sistema para la construccion de forjados y cubiertas | |
| KR100733715B1 (ko) | 하프 프리캐스트 콘크리트 슬라브 패널용 성형장치 | |
| ES2389812B1 (es) | Conjunto de dispositivos para encofrar rebosaderos en piscinas de desbordamiento y proceso de construcción de bordes de piscinas | |
| SU70243A1 (ru) | Блок ступенчатой формы дл безопалубочного возведени цилиндрических сводов | |
| KR200433870Y1 (ko) | 하프 프리캐스트 콘크리트 슬라브 패널용 성형장치 | |
| JP2023075097A (ja) | 構造体の構築方法 | |
| Santosa et al. | Investigations on earthquake damages of Trajumas Hall in the Sultan's Palace Yogyakarta |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| WWE | Wipo information: entry into national phase |
Ref document number: 200980106901.6 Country of ref document: CN |
|
| DPE1 | Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101) | ||
| WWE | Wipo information: entry into national phase |
Ref document number: 2713826 Country of ref document: CA |
|
| WWE | Wipo information: entry into national phase |
Ref document number: MX/A/2010/008424 Country of ref document: MX |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 5693/DELNP/2010 Country of ref document: IN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: DZP2010000530 Country of ref document: DZ |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2009706854 Country of ref document: EP |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2010134565 Country of ref document: RU |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 12865547 Country of ref document: US |
|
| ENP | Entry into the national phase |
Ref document number: PI0905842 Country of ref document: BR Kind code of ref document: A2 Effective date: 20100730 |