WO2010003724A3 - System and method for implementing a power control application in a distributed control system using iec61850 - Google Patents
System and method for implementing a power control application in a distributed control system using iec61850 Download PDFInfo
- Publication number
- WO2010003724A3 WO2010003724A3 PCT/EP2009/055982 EP2009055982W WO2010003724A3 WO 2010003724 A3 WO2010003724 A3 WO 2010003724A3 EP 2009055982 W EP2009055982 W EP 2009055982W WO 2010003724 A3 WO2010003724 A3 WO 2010003724A3
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- automation system
- implementing
- plant
- power control
- industrial automation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Program-control systems
- G05B19/02—Program-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/4185—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by the network communication
- G05B19/4186—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by the network communication by protocol, e.g. MAP, TOP
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/02—Standardisation; Integration
- H04L41/0226—Mapping or translating multiple network management protocols
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/22—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks comprising specially adapted graphical user interfaces [GUI]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S40/00—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Automation & Control Theory (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Programmable Controllers (AREA)
Abstract
A system and a method for implementing an electrical process control in a Distributed Control System (DCS) is provided. The system is based on integrating Industrial Substation Automation system and the DCS by having a combined control bus (135) conveying process control messages and station bus conveying power control messages. The integrated industrial automation system utilizes a process controller capable of communication using IEC 61850 communication standard and interacts with one or more Intelligent Electronic Devices (IEDs) configured for one or more substations in an industrial plant. The method of configuring the process controller of the integrated industrial automation system uses electrical process and plant process engineering tools. The plant process engineering tool has at least one module, present as an integral part of externally for engineering IEC 61850 based application or function for configuring one or more process controllers of the integrated industrial automation system.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP09779500.9A EP2283403B1 (en) | 2008-05-16 | 2009-05-18 | System and method for implementing a power control application in a distributed control system using iec61850 |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US7178208P | 2008-05-16 | 2008-05-16 | |
| US61/071,782 | 2008-05-16 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| WO2010003724A2 WO2010003724A2 (en) | 2010-01-14 |
| WO2010003724A3 true WO2010003724A3 (en) | 2010-07-15 |
Family
ID=41334890
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/EP2009/055982 Ceased WO2010003724A2 (en) | 2008-05-16 | 2009-05-18 | System and method for implementing a power control application in a distributed control system using iec61850 |
Country Status (2)
| Country | Link |
|---|---|
| EP (1) | EP2283403B1 (en) |
| WO (1) | WO2010003724A2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104240143A (en) * | 2014-07-31 | 2014-12-24 | 山东网聪信息科技有限公司 | Method for generating transformer substation service circuits intelligently |
Families Citing this family (30)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2537296B1 (en) * | 2010-02-16 | 2015-04-01 | ABB Technology AG | Electricity system configuration method and computer program performing the method |
| CN101944770B (en) * | 2010-08-04 | 2013-01-16 | 浙江省电力公司 | Communication implementation method of virtual station grade IED mode between primary station and substation in fault information system 61850 |
| US8682495B2 (en) * | 2010-10-21 | 2014-03-25 | The Boeing Company | Microgrid control system |
| WO2012131074A1 (en) * | 2011-03-31 | 2012-10-04 | Alstom Technology Ltd | Method for managing process automation control and associated system |
| CN102243482B (en) * | 2011-04-12 | 2013-11-06 | 株洲变流技术国家工程研究中心有限公司 | Control method and master controller for cascaded high-voltage frequency converters |
| CN102495313B (en) * | 2011-12-05 | 2013-08-07 | 山东电力研究院 | IEC 61850-based digital measurement and control device synchronization performance test method |
| CN102495608B (en) * | 2011-12-21 | 2014-07-02 | 河北省电力勘测设计研究院 | DCS (Distributed Control System) based integrated-control system of coal-fired power plant |
| CN103186135B (en) * | 2011-12-27 | 2016-01-27 | 五冶集团上海有限公司 | The adjustment method of rise residential fire-fighting linkage control system |
| CN102571787B (en) * | 2011-12-30 | 2015-04-29 | 浙江大华系统工程有限公司 | IEC (international electrotechnical commission) 61850-based protocol conversion method and device |
| CN102541014B (en) * | 2012-01-11 | 2013-07-17 | 北京四方继保自动化股份有限公司 | Thermotechnical electrical integrated control system for thermal power plant |
| CN102749902A (en) * | 2012-07-04 | 2012-10-24 | 江苏省电力公司扬州供电公司 | Integrated intelligent information monitoring platform of power distribution system in residential district |
| EP2687925B1 (en) * | 2012-07-16 | 2018-10-17 | ABB Schweiz AG | Master intelligent electronic device for high level application |
| CN102801213B (en) * | 2012-08-10 | 2014-12-10 | 广东省电力调度中心 | Integrated method and integrated device of SCD (System Configuration Document) of transformer station |
| CN102999367B (en) * | 2012-12-14 | 2016-03-30 | 北京四方继保自动化股份有限公司 | A kind of method of fast initialization IEC61850 intelligent apparatus user client communication |
| CN103338262B (en) * | 2013-07-05 | 2016-05-04 | 南京国电南自电网自动化有限公司 | Based on the fast initializing method of IEC61850 and MMS client |
| CN103412507A (en) * | 2013-08-19 | 2013-11-27 | 扬州市职业大学 | Automatic controller designed based on MCU |
| CN103683502B (en) * | 2013-11-30 | 2015-07-29 | 许继电气股份有限公司 | A kind of transformer station process bed device switching circuitry drived control method and device |
| CN103744402B (en) * | 2014-01-17 | 2016-02-24 | 华东理工大学 | Gasoline pipeline blending dispatching lot automatic switching method |
| CN104092311A (en) * | 2014-07-31 | 2014-10-08 | 山东网聪信息科技有限公司 | Intelligent substation service state monitoring system and method |
| CN104809932B (en) * | 2015-04-22 | 2017-09-01 | 北京广利核系统工程有限公司 | A kind of nuclear power plant's digital safety level Control system simulation device |
| CN104967217A (en) * | 2015-06-28 | 2015-10-07 | 许继集团有限公司 | Intelligent transformer station secondary virtual loop monitoring method |
| CN108139741B (en) * | 2015-10-12 | 2021-10-08 | 费希尔-罗斯蒙特系统公司 | A system and method for commissioning a process plant |
| CN105354253A (en) * | 2015-10-20 | 2016-02-24 | 许继集团有限公司 | SCD file decoupling method |
| GB2601081B (en) * | 2016-10-24 | 2022-09-28 | Fisher Rosemount Systems Inc | Systems and methods for merging modular control systems into a process plant |
| CN106300684A (en) * | 2016-10-26 | 2017-01-04 | 电子科技大学 | A kind of intelligent integral towards transformer station's standby power system monitors method |
| CN109283897A (en) * | 2018-08-23 | 2019-01-29 | 中国电力工程顾问集团西南电力设计院有限公司 | A kind of wisdom power plant comprehensively monitoring center intelligent monitoring implementation method |
| CN110611312B (en) * | 2019-09-29 | 2022-12-30 | 深圳供电局有限公司 | On-line simulation system and method for panoramic data of substation bay level |
| CN110896363B (en) * | 2019-11-25 | 2022-07-29 | 东方电子股份有限公司 | Plug-and-play access configuration method for IEC61850 intelligent device |
| EP3985465B1 (en) * | 2020-10-14 | 2024-03-13 | ABB Schweiz AG | Mixed operation of production units in hybrid plants |
| AU2025201963A1 (en) * | 2024-05-20 | 2025-12-04 | Schneider Electric Systems Usa, Inc. | Unified dynamic controller for power and process applications |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20070185591A1 (en) * | 2004-08-16 | 2007-08-09 | Abb Research Ltd | Method and system for bi-directional data conversion between IEC 61970 and IEC 61850 |
-
2009
- 2009-05-18 WO PCT/EP2009/055982 patent/WO2010003724A2/en not_active Ceased
- 2009-05-18 EP EP09779500.9A patent/EP2283403B1/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20070185591A1 (en) * | 2004-08-16 | 2007-08-09 | Abb Research Ltd | Method and system for bi-directional data conversion between IEC 61970 and IEC 61850 |
Non-Patent Citations (7)
| Title |
|---|
| ANONYMOUS: "Substation Configuration Language - Summary", August 2006 (2006-08-01), pages 1 - 13, XP002578382, Retrieved from the Internet <URL:http://cimug.ucaiug.org/Harmonization%20Documents/EPRI%20Harmonization%20Project%20Notes%20and%20Minutes/IEC%20TC57%20Substation%20Configuration%20Language%20Summary.pdf> [retrieved on 20091130] * |
| CHRISTOPH BRUNNER: "IEC 61850 Object Model and Configuration Language", 10 March 2003 (2003-03-10), pages 1 - 23, XP002578383, Retrieved from the Internet <URL:http://www.pes-psrc.org/h/H5/H5-Brunner_61850-intro.pdf> [retrieved on 20091130] * |
| JONAS LIDEN: "Design and Implementation of an IEC 61850 gateway for PLC Systems", 2006, KTH Electrical Engineering, pages 1 - 84, XP002558217, Retrieved from the Internet <URL:http://www.ee.kth.se/php/modules/publications/reports/2006/XR-EE-ICS_2006_021.pdf> [retrieved on 20091130] * |
| KEZUNOVI M ET AL: "Automated Monitoring and Control Using New Data Integration Paradigm", 20050103; 20050103 - 20050106, 3 January 2005 (2005-01-03), pages 66A - 66A, XP010762451 * |
| KLAUS-PETER BRAND: "IEC 61850 Short Tutorial", March 2005 (2005-03-01), pages 1 - 34, XP002558218, Retrieved from the Internet <URL:http://www.ceb5.cepel.br/arquivos/eventos_setor/iec61850_tutoria.pdf> [retrieved on 20091130] * |
| KOSTIC T ET AL: "TOWARDS THE FORMAL INTEGRATION OF TWO UPCOMING STANDARDS: IEC61970 AND IEC61850", LESCOPE. LARGE ENGINEERING SYSTEMS CONFERENCE ON POWERENGINEERING CONFERENCE PROCEEDINGS. ENERGY FOR THE FUTURE, XX, XX, 7 May 2003 (2003-05-07), pages 24 - 29, XP008050807 * |
| RICHARD BIALA: "Aktueller Stand der Elektro-und Leittechnik für Kraftwerke", 2007, TechnikTreffBerlin 2007, pages 1 - 13, XP002558216, Retrieved from the Internet <URL:http://www02.abb.com/global/deabb/deabb207.nsf/0/0bee5d0145e24cbfc125730e004f6745/$file/ABB+Elektro-+und+Leittechnik+f%C3%BCr+Kraftwerke.pdf> [retrieved on 20091130] * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104240143A (en) * | 2014-07-31 | 2014-12-24 | 山东网聪信息科技有限公司 | Method for generating transformer substation service circuits intelligently |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2010003724A2 (en) | 2010-01-14 |
| EP2283403A2 (en) | 2011-02-16 |
| EP2283403B1 (en) | 2015-08-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2010003724A3 (en) | System and method for implementing a power control application in a distributed control system using iec61850 | |
| WO2012154921A3 (en) | Control system for photovoltaic power plant | |
| EP2472698A3 (en) | On-board power supply system and protection method | |
| WO2013020916A3 (en) | Configuration of an iec 61850 teleprotection ied for inter-substation communication | |
| WO2011082856A3 (en) | Energy storage system and method for the operation thereof | |
| WO2009052121A3 (en) | Electrical energy usage monitoring system | |
| WO2012041902A3 (en) | Charging system for electric vehicles | |
| WO2006094128A3 (en) | Methods and systems for intentionally isolating distributed power generation sources | |
| WO2010120952A3 (en) | Automated shore power system | |
| WO2014173695A3 (en) | Method for feeding electrical power into an electrical supply network | |
| CN103795233A (en) | Modularized inverter power supply control method for intelligent start and stop polling mechanism | |
| WO2012019785A3 (en) | Arrangement for generating a control signal for controlling a power output of a power generation system | |
| WO2012051042A3 (en) | Centralized power conditioning | |
| WO2009111478A3 (en) | Machine battery packs and controls | |
| WO2011083967A3 (en) | Network system | |
| CN105554012A (en) | Communication unit for converting EtherCAT slave station into Canopen master station on basis of DSP (Digital Signal Processor) | |
| WO2002037638A3 (en) | Distributed energy network control system and method | |
| WO2007126480A3 (en) | Power transfer field device | |
| SG10201407577UA (en) | Controls interface solution for energy savings | |
| US20130030594A1 (en) | Electric vehicle charging station remote disconnect system | |
| WO2010089077A3 (en) | Dynamic rechargeable battery management | |
| AU2001228729A1 (en) | System with web/wap-interface, for supervision of electrical power generation | |
| CN202956979U (en) | Electric power automation engineering education platform | |
| CN203054172U (en) | Automatic withstanding voltage test platform for low-voltage electrical appliance | |
| CN105429587B (en) | A kind of solar power station group tandem power optimization device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 09779500 Country of ref document: EP Kind code of ref document: A2 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2009779500 Country of ref document: EP |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |