WO2011006526A1 - Telescopic tower assembly and method - Google Patents
Telescopic tower assembly and method Download PDFInfo
- Publication number
- WO2011006526A1 WO2011006526A1 PCT/EP2009/058896 EP2009058896W WO2011006526A1 WO 2011006526 A1 WO2011006526 A1 WO 2011006526A1 EP 2009058896 W EP2009058896 W EP 2009058896W WO 2011006526 A1 WO2011006526 A1 WO 2011006526A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- section
- sections
- tower
- jacking
- segments
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/18—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic
- E04H12/182—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic telescopic
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/30—Water-towers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/10—Assembly of wind motors; Arrangements for erecting wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/22—Foundations specially adapted for wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2240/00—Components
- F05B2240/90—Mounting on supporting structures or systems
- F05B2240/91—Mounting on supporting structures or systems on a stationary structure
- F05B2240/915—Mounting on supporting structures or systems on a stationary structure which is vertically adjustable
- F05B2240/9151—Mounting on supporting structures or systems on a stationary structure which is vertically adjustable telescopically
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
Definitions
- the present invention relates to the field of construction of tower-like structures and particularly, but not exclusively, to the assembly of pre-fabhcated concrete towers for wind turbines and the like.
- Tall tower structures such as are commonly used for wind turbines, are often constructed of pre-cast segments of reinforced and/or pre-stressed concrete, which are then transported to the erection site, usually by road, and assembled by lifting the segments into position by crane.
- each vertical section will be assembled from several arcuate segments.
- the bottom tower section will be assembled and erected first, after which the second, third and successive sections will be lifted into position using a crane.
- Each section is usually pre- assembled at ground level and then lifted whole into position on top of the previous section. Alternatively, the segments of a particular section may be lifted into position separately and then assembled on top of the previous section. Finally, the top section is lifted into position, followed by the generator assembly and the turbine rotor.
- Towers for wind turbines may be as tall as 100m, and plans for towers as tall as 160m are envisaged, bearing generator units capable of producing many megawatts.
- the prior art construction techniques require the parts of the tower to be lifted using huge cranes, which must be at least as tall as the tower structure itself.
- the generator unit which may weigh as much as 130 tonnes, must be lifted into position at the top of the structure.
- Generator units weighing up to 300 tonnes may eventually be required.
- Cranes which can safely lift such weights to such heights are extremely large and expensive, and the process of transporting such a crane to the site and assembling it is a huge task requiring specialist staff, heavy machinery and often the construction of roads much bigger than would be required for transporting the pre-fabhcated tower pieces.
- a similarly giant crane is also required for any major maintenance work to the generator or the rotor, or if the tower needs to be dismantled.
- a crane capable of lifting a 130 tonne generator on to the top of one of the envisaged 160m towers would be orders of magnitude larger and more expensive than those currently being used for 100m towers.
- the height to which a tower can be built is therefore limited by the size of crane which will be required for its construction, and the erection of 160m pre-fabricated towers has still to be realized.
- UK patent application GB2451191 describes a telescopic tower erection method in which several pre-fabricated telescopic sections of a tower are fitted together horizontally at low level.
- each vertical section is alternately supported and jacked up on its next outer section, so that the wall members form an extra supporting wall lining the inner surface of the next outer section.
- a supporting structure is fixed to the side walls of the outer section to support the underside of the inner section.
- the tower erection method disclosed in GB2451191 suffers from the following disadvantages, however. Firstly, the disclosed jacking method relies on supporting a flange at the bottom of each section on a ledge at the bottom of the previous section. This means that the sections must be raised in a particular order, since each successive inner section rests on its outer neighbour.
- the interim supporting method of GB2451191 is exceedingly labour intensive, involving the construction and subsequent dismantling of an entire inner wall structure almost as large as the tower itself, something which may have a severe impact on the speed of construction and therefore on the overall programme of works.
- the jacking and supporting techniques are only suitable for structures in which all the walls of all the sections are substantially parallel.
- the present invention aims to solve these and other problems inherent in the prior art.
- the invention aims to provide a construction method and assembly which permits the tower sections to be assembled without a crane, or using a small crane just slightly taller than one section. Further objects of the invention are also to enable a much faster and more efficient raising of the tower sections, and to enable the use of tower sections having non-parallel walls.
- a further object of the invention is to provide a method and assembly which permit the raising of the tower sections in any order.
- a method is provided of erecting a structure on a site using a plurality of substantially coaxial telescopic sections, the method comprising the following steps: a first step of placing or constructing an innermost one of said plurality of sections in position on the site, a second step of placing or constructing, in position on site, one or more substantially coaxial sections around said innermost section, so as to form two or more substantially coaxial telescopic sections, each of said coaxial telescopic sections having an inner and/or an outer coaxially adjacent section, a third step of fitting a plurality of jacking tendons between lower jacking points of a first one of said telescopic sections, and upper jacking points of a second one of said telescopic sections, said first and second telescopic sections being coaxially adjacent, a fourth step of attaching a tendon jack to one or more of said
- the method of the invention may also comprise a seventh step of securing a lower part of the first section to an upper part of the second section.
- the second step is performed so as to form three or more substantially coaxial telescopic sections comprising two or more pairs of coaxially adjacent sections, and the third to sixth or seventh steps are performed for each of the two or more pairs of coaxially adjacent sections.
- the method of the invention may be used for the erection of a tower for supporting a top-mounted element such as a wind- turbine generator unit or a water tank on an uppermost one of the telescopic sections, the method may also comprise an eighth step, performed before the sixth step, of placing the top-mounted element into position on a predetermined one of the telescopic sections.
- a top-mounted element such as a wind- turbine generator unit or a water tank on an uppermost one of the telescopic sections
- the method may also comprise an eighth step, performed before the sixth step, of placing the top-mounted element into position on a predetermined one of the telescopic sections.
- the eighth step may comprise fitting the wind turbine generator unit to the top of the predetermined telescopic section and fitting turbine blades such that the rotation plane of turbine blades is maintained at an angle from the operational rotation plane of the blades during the lifting subsequently performed in the sixth step, and wherein the method further comprises a ninth step of moving the rotation plane of the turbine blades to their operational rotation plane during or after the execution of sixth step once the predetermined telescopic section has been raised above a height at which the turbine blades, when in their operational rotation plane, are clear of
- the second step of constructing may comprise assembling the or each coaxial section from a plurality of pre-fabricated segments, and the second step may further comprise fastening the pre-fabricated segments together using tensionable lateral connecting elements.
- the sections may be made of any suitable material. However, in a preferred embodiment of the method of the invention, the sections are made of concrete, or a steel -reinforced concrete, or a combination or steel and concrete. In a further embodiment of the invention, the method further comprising a sequence of dismantling steps including performing some or all of said first to ninth steps in reverse so as to dismantle the structure.
- first and/or second steps of the method of the invention may comprise providing a mould, former or shuttering, and casting the sections.
- the first and second steps may involve a combination of precasting and in situ construction methods.
- the top and bottom flanges of each segment may be precast remote from site, or on a flat surface adjacent to the construction area. Or the entire bottom flange of each section may be cast in situ.
- Segment flange parts may be pre-cast with the necessary starter bars in place, ready to be to be embedded into the cylinder or wall part of the segment.
- the underneath surface of the top flange could be match-cast against the top surface of the bottom flange of the neighbouring segment so as to form a pair of perfectly mating surfaces.
- the bottom flange of the section would be positioned first, then the cylinder of that segment would then be cast in place above the bottom flange, then the top flange would be cast in place, or fitted, adjusted and stitched to the top of the wall section of that section.
- This latter variant eases the construction of the top section, removing the need for a formwork between two sections, which would be difficult to remove after casting.
- This variant also allows the creation of a perfect contact between the two mating concrete surfaces of the top and bottom flanges at a particular joint, thus improving the quality of the structure or possibly avoiding the need to have an epoxy or high strength mortar to be provided at these joints.
- the flanges may also be made in composite concrete and steel to improve further the contact area between the mating surfaces of the flanges.
- the method comprises a preliminary step of constructing a foundation for the structure, the foundation having a recessed access area for permitting access to the underside of at least some of the plurality of telescopic sections placed or constructed in the first or second steps.
- the invention also provides a pre-fabricated tower segment for joining with one or more other similar tower segments to form a section of the height of a tower structure, the section being for joining with other similar sections to form the tower structure, the tower segment being characterised in that it comprises: upper jacking points and/or lower jacking points for attaching jacking tendons, one or more first mating surfaces for fixably engaging with corresponding mating surfaces of the other similar tower segments, segment fastening points for attaching first tensioning means such that the or each first mating surface is tensionably secured to a corresponding mating surface of the other similar tower segments, one or more second mating surfaces for, when the tower segment is fixably engaged with the other similar tower segments to form the section of the height of the tower structure, fixably engaging with corresponding mating surfaces of an adjacent
- the upper jacking points and/or the lower jacking points are implemented as a flange provided at or near an upper and/or lower edge, respectively, of the tower segment, the or each flange comprises openings for tensionably accommodating the jacking tendons.
- the invention also provides a tower structure comprising a plurality of pre-fabricated tower segments as described above.
- Figure 1 of the drawings shows a sectional view of a telescopic tower assembly according to the present invention.
- Figure 2 shows an example distribution of jacking holes and PT-bar holes in one of the section flanges.
- Figure 3 shows an example of a PT bar used to join two sections.
- Figure 4 shows an example of a tendon and anchor used during jacking in the present invention.
- Figure 5 shows an exploded view to illustrate how the successive tower sections are assembled.
- Figure 6 shows an example of a connecting structure for joining neighbouring segments of a tower section.
- Figure 7 shows a cut-away view of the final erection stages of a tower having three sections.
- Figure 8 shows a detail of a possible guiding mechanism for neighbouring sections.
- Figure 9 shows a sectional view of a telescopic tower assembly before the raising process begins, and with the generator already mounted.
- Figure 10 shows an example of a working platform arrangement inside a tower.
- Figure 11 shows a lateral view of a telescopic tower arrangement to which the generator and rotor are added before the tower is raised.
- Figure 12 shows the telescopic tower of figure 10 in its extended state.
- Figures 13 and 14 show lateral views of a rotor and a water reservoir respectively, both mounted on the telescopic tower at low level before extending the tower.
- Figure 15 shows a tower having non-parallel walls, being erected by the method of the invention.
- Figure 16 shows an alternative example of a tower having non- parallel walls, being erected by the method according to the invention.
- the drawings are provided to illustrate example implementations of the present invention, and to aid an understanding of the invention. They do not imply any restriction of the scope of the invention.
- FIG 1 we see in schematic cross-section a tower comprising five coaxial sections: an outer section 2, three mid-sections 3 and an inner section 4.
- the various sections 2, 3 and 4 are each depicted already assembled and in position, ready for erection.
- the outer section 2 is supported on a foundation 1
- the mid and inner sections 3 and 4 are supported in a slightly raised position, resting on support 10. This is to provide space under sections 3 and 4 for attaching jacking tendons 5 and hydraulic stroking jacks 8.
- a suitable space for example by excavation
- the mid- and inner sections 3 and 4 do not need to be raised, and the height requirement for the assembly crane may thereby be still further reduced.
- Figure 1 shows the sections all having the same height, however the sections may be of different heights, dependent on the requirements of the particular structure being erected.
- some or all of the sections to be raised can somewhat shorter than the section which is not raised. This allows for a support 10 underneath the sections, as already mentioned, to allow space which can be used for installing jacks etc, without the need to make such a space in the foundation.
- the tops of all the sections can be more or less level with each other, so as to allow the use of a small crane the height of just one section (or slightly taller).
- the mid and inner sections 3 and 4 are shown ready to be raised by the hydraulic jacks 8 in figure 1.
- the stroking jacks 8 may be of the kind used to stress tendons in post-tensioned (PT) structures or cables for supporting bridge decks.
- the tendons 5 may each be any kind of elongated structure, such as cable or bar, which is sufficiently strong in tension to bear the combined weight of the supported sections 3 and 4, distributed over the number of tendons 5 present, and along which a stroking jack can crawl.
- each tendon is connected from a flange 7 at the bottom of one section to a flange 6 at the top of the neighbouring section.
- the tendons 5 connecting the flange 6 at the top of the outer section 2 to the flange 7 at the bottom of the first mid section 6 will be required to bear the weight of all three mid sections and the inner section, as well as the weight of all the tendons 5 and the jacks 8.
- Anchors can be used to support the structure until the jacks are positioned and tensioned to take the weight, ready for lifting.
- the innermost section is raised to form the uppermost part of the structure, while the outer section forms the lowest part.
- the method of the invention also applies when the order of the sections is reversed, such that the innermost section forms the lowest part of the finished structure, with successive outer sections being raised to form successive upper parts of the structure. This reversed arrangement will be described in more detail with reference to figure 15.
- the sections shown in figure 1 are depicted all having a similar height. The sections may of course be of different heights.
- Figures 2 to 4 show examples of how the jacking tendons 5 and connectors 13 can be distributed around each flange.
- jacking tendons are inserted through holes 12 in each flange, and used to raise one section 3 relative to its outer neighbour 2 (together with any other sections being supported by the section being raised).
- the corresponding flanges 6 and 7 of the pair of sections 3 and 2 are designed such that they marry up in their final raised position, whereupon connectors 13 can be inserted through the alternate holes 5 and secured so that the tension in the jacking tendons 5 can be released.
- the tendons 5 can then, if appropriate, be removed.
- Reciprocating crawler jacks operate in a cyclic way, with a lifting stroke followed by a climbing stroke.
- each jack is supplied with hydraulic fluid under pressure from a hydraulic pump, and under control of a control unit.
- Each jack may be operated individually, or they may be operated in groups, with the jacks in each group being supplied by a common hydraulic source (pump and control unit).
- the jacks in one group may be physically adjacent to each other on the section being lifted, or they may be distributed around the structure.
- twelve jacks may be operated as four groups of three jacks, with each three jacks in each group being separated from each other by approximately 120°. In this way, the control of the lifting may be improved, and the risk of overloading one jack would be reduced.
- the twelve jacks of the example may be divided into three groups of four adjacent jacks, with each group of four jacks being controllable as though it were one jack, but with the load distributed over four tendons. By dividing the lifting control into three sectors, it is possible to improve the control, and therefor the stability, of the section as it is being raised.
- the connectors 13 may for example be lengths of high-tensile steel bar, or they may be lengths of multi-strand cable or any other shape or material suitable for maintaining high tensile force between the mating flanges.
- Figure 3 shows an example of how such a bar might be fitted: mating flanges 6 and 7 are clamped together by tensile bar 13.
- the bar may be threaded, with the tension being achieved by the tightening of nuts on the thread.
- the connecting bar/cable may be fixed using anchors, for example similar to those used in post-tensioning tendons, and tensioned using hydraulic jacks.
- the connector bar 13 in figure 3 is depicted as having a cover or seal. In many environments it is advantageous if the connector is protected from the potentially corrosive effects of damp, for example. A seal may also be provided between the inner surface of one section and the outer surface of its neighbour, so as to prevent water penetration.
- a captive nut or anchor is pre-fitted in the section during manufacture, so that the connector 13 can simply be inserted and, in the case of a threaded bar and a captive nut, threaded into the nut to the desired depth.
- FIG. 4 shows how an anchor 9 can be used at the top of a jacking tendon 5.
- Such anchors are commonly used for holding post-tensioning cables in the stressing of concrete structures.
- the anchor may be fitted to the cable during assembly of the section 2, or it may be pre-fitted during the pre-fabrication of the section 2, so that the on-site procedure involves merely inserting a tendon into the opening 12 and engaging the anchor 9.
- the tendons used for raising the sections may then be tensioned and anchored so as to form the connectors.
- the jacking tendons 5 are arranged such that the crawler jacks 8 are at the lower end of each jacking tendon 5, and the anchors 9 at the top of each jacking tendon 5. This arrangement could be reversed, with the anchors 9 at the bottom of the sections 2, 3, 4 and the jacks 8 at the top, without departing from the invention.
- each section can mean, for example, assembling each section from pre-fabricated segments, or it can mean casting the sections whole in situ.
- the sections are assembled/constructed in an assembly sequence of substantially coaxial sections, from the inner to the outer section, such that each successive section to be constructed (assembled from segments or cast in situ, for example) is constructed around the previously constructed sections. In this way, no section needs to be lifted over any previously constructed sections, and there is ample unobstructed working space for assembling or constructing each successive section.
- the sections thus assembled or constructed are then raised into their destination positions relative to one another using the crawler jacks.
- the order in which the sections are raised is advantageously the reverse of the order in which the sections were assembled or constructed.
- each section to be raised is raised relative to its neighbouring section (its outer neighbour in the case where the sections are arranged inner-to-outer as shown in figures 1 , 7, 8, 14 etc., or its inner neighbour in the case where the sections are arranged outer-to-inner as shown in figure 15), and such that the weight of the section is supported on the neighbouring section.
- Figure 5 shows an exploded view of an example of the method and assembly of the invention.
- Each of the tower sections 2, 3, 4 which together will make up the height of the tower is constructed or assembled from several segments 21 , 22, 23. Each segment is prefabricated having the necessary jacking and fixing points (flanges with holes 12).
- the coaxial sections which make up the tower structure are assembled from the inner section outwards, with each section being made up of several segments.
- the innermost section is shown as being assembled from four segments 23, the next outer section as being assembled from four segments 22, and the outermost section as being assembled from four segments 21.
- each segment can be positioned without needing to be lifted over other, already installed segments.
- the crane required for lifting the segments into position need on be a little taller than the tallest segment to be lifted. Note that it is not necessary for the innermost section to be constructed from several segments, since this section can in any case be lifted into place directly, without obstruction.
- each section can be chosen to suit the shape and load bearing requirements of the tower structure, as well as the constraints on transporting the segments to the assembly site.
- Each of the segments is joined to its adjacent segment(s).
- the segments may be provided with integral hoops or staples 25, as shown in figure 6.
- the hoops of each segment overlap and interlock with hoops of the adjacent segment such that, when a locking bar or frame 26 is driven down through the overlapping and interlocking hoops, the segments are locked and held together in tension.
- the sections may be cast in situ, from concrete for example, instead of being assembled from multiple segments.
- the interlocking hoop
- FIG 7 shows a cut-away view of the assembly of figure 5 in its erected state.
- Each of the sections 2, 3a and 3b is composed of several segments, as in figure 5, and jacking tendons are fitted between the upper and lower fixing points (flanges) of each pair of adjacent sections (2 and 3a, 3a and 3b in this case.
- the outermost section 2 can be made without any lower jacking points
- the innermost section 3b can be made without any upper jacking point.
- the outermost 2 and innermost 3b sections can be made with both upper and lower jacking points (top and bottom flanges).
- the lower flange on the outermost section 2 may then be used for securing it to the foundation 1
- the upper flange on the innermost section may be used to secure an element such as a water-tank or a wind turbine generator unit to the top of the tower.
- the cut-away view of figure 7 also shows how the tendons 5 and the jacks 8 can be positioned for lifting the sections 3a and 3b. In the position shown, the sections are in their lifted state - the connector elements 13 have been at least partially fitted, and some or all of the jacks 8 may be removed. The tendons may also be detached and removed to be used elsewhere.
- Figure 8 shows an example of a vertical stabilising rib 27 and corresponding groove 26 combination implemented between two adjacent sections 2 and 3.
- This arrangement can prevent the sections 2 and 3 from rotating relative to each other about a vertical axis.
- Such a rotational motion may be caused, for example, when raising a tower in windy conditions, with a large wind-turbine generator unit on top, and may give rise to unacceptable additional stress on the structure and/or on the tendons during lifting,
- Figure 9 shows in sectional view a tower assembly according to the invention.
- the example shown has five coaxial sections (labelled 2, 3, 3, 3 and 4), and supports a nacelle (wind-turbine generator unit) 40.
- figure 9 shows the use of a working platform 30 secured to innermost section 4.
- Platform 30 not only provides a convenient working area which rises with the sections as they are lifted, but it also provides a support for jacks when they are being transferred from one set of tendons to the next.
- the platform shown in figure 9 also has the function of stabilising the structure while it is being elevated. Until the sections 2, 3, 4 are all secured to each other with the respective connector elements 13, the tower structure is relatively unstable, since each unfixed section is only supported by the jacking tendons 5.
- the platform By making the platform as wide as the inner dimension of the tower structure, and by equipping it with wheels or guides so that it can be in continuous mechanical contact with the inner surface of the section 2, the platform can be used to give mechanical stability to the tower structure as it is being raised.
- the width of the platform (or at least the distance between the wheels 31 on opposite sides of the platform) can be made adjustable to allow for the varying width of the inside of the tower as the platform progresses up the inside of the tower.
- a ladder 36 is also illustrated on the inside of the tower - sections of ladder 36 may be added to the inside of each section once it is raised into position.
- a pulley arrangement 33 may also be provided for lifting equipment or people up and down inside the tower which it is under construction.
- This pulley arrangement 33, the platform 30 and the ladder 36 are more clearly illustrated in figure 10, which also shows the use of a cage 35 for transporting people and equipment up and down inside the tower.
- the same winch and pulley arrangement can also be used to lower the platform when the erection of the tower is complete. The hook is secured to the top of the platform or cage 30, and the platform can then be released from its location attached to the innermost section, and then be lowered to ground level where it can be dismantled and taken off site.
- An important advantage of the invention is that it permits the erection of a tower of unlimited height with the use of relatively small scale lifting equipment such as a small crane capable of reaching just slightly above the height of one section.
- Figures 11 and 12 show how this advantage can be used in the erection, for example, of a wind turbine.
- the tower is in its un- erected state, and the wind-turbine generator 40 has been lifted into position on top of inner section 4.
- a crane 42 can be used for this purpose.
- the crane 42 is also used for lifting the turbine blades into position and attaching them before the tower is erected to its full height. Thus all work can be carried out at a relatively low level (at about the height of one section).
- the blades can then be rotated to their operating orientation as depicted in Figure 12.
- Figure 11 shows the turbine blade assembly as hinged on the generator unit (nacelle).
- FIG. 13 shows a frontal view of a three-bladed turbine in position on an un-erected telescopic tower, and shows how the blades do not reach the ground.
- Figure 14 shows the application of the principle of assembly at low level to the erection of a water tower. Water tank 44 is mounted and secured to the topmost tower section before the tower is erected. Note that, because the method of the present invention is reversible, the wind-turbine generator 40, water tank 44 etc can be lowered to the low level again in future so that maintenance work can be carried out which would otherwise have to be carried out at the top of the tower.
- Figures 15 and 16 show cut-away views of how the method of the invention can be applied to telescopic sections having significantly non-parallel walls.
- each section can have more or less any shape.
- the tower structure has three sections which are initially assembled such that they are coaxial and nested at ground level, then raised using hydraulic jacks until they are in position, then secured using connector bars or tendons 13.
- it is the innermost section which rests on the foundations 1 , while the outermost section is raised to become the uppermost section.
- the assembly of the sections, and the jacking and the fastening operations are the same as those used in figure 15 and the previous figures.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
Abstract
Description
Claims
Priority Applications (9)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| BR112012000808A BR112012000808A2 (en) | 2009-07-13 | 2009-07-13 | telescopic tower assembly and method |
| AU2009349932A AU2009349932B2 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
| DK09780492.6T DK2454427T3 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower arrangement and method |
| CN200980160435.XA CN102482892B (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
| PCT/EP2009/058896 WO2011006526A1 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
| JP2012519892A JP5629316B2 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
| HK12108544.0A HK1167880B (en) | 2009-07-13 | Telescopic tower assembly and method | |
| US13/382,341 US8919074B2 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
| EP09780492.6A EP2454427B1 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/EP2009/058896 WO2011006526A1 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2011006526A1 true WO2011006526A1 (en) | 2011-01-20 |
Family
ID=42045355
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/EP2009/058896 Ceased WO2011006526A1 (en) | 2009-07-13 | 2009-07-13 | Telescopic tower assembly and method |
Country Status (8)
| Country | Link |
|---|---|
| US (1) | US8919074B2 (en) |
| EP (1) | EP2454427B1 (en) |
| JP (1) | JP5629316B2 (en) |
| CN (1) | CN102482892B (en) |
| AU (1) | AU2009349932B2 (en) |
| BR (1) | BR112012000808A2 (en) |
| DK (1) | DK2454427T3 (en) |
| WO (1) | WO2011006526A1 (en) |
Cited By (23)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ITPV20110007A1 (en) * | 2011-04-01 | 2012-10-02 | Eeco Srl | INSTALLATION PROCEDURE FOR A VERTICAL TELESCOPIC POLE AND ITS REALIZATION |
| ITGE20110108A1 (en) * | 2011-09-29 | 2013-03-30 | Casamonti Tommaso | "FLOATING PLATFORM SUPPORT FOR GAS MILLS" |
| WO2013057225A1 (en) | 2011-10-18 | 2013-04-25 | Inneo Torres, S.L. | Process for installing an offshore tower |
| WO2013083854A1 (en) | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Assembly method for a telescopic tower and means for implementing said method |
| WO2013083852A1 (en) | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Assembly process of a telescopic tower |
| WO2013083853A1 (en) * | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Horizontal joint assembly between two telescopic wind turbine tower portions and method of installing same |
| CN103243959A (en) * | 2013-05-22 | 2013-08-14 | 四川擎烽通信有限责任公司 | Quickly mounted communication tower and mounting method thereof |
| JP2014507601A (en) * | 2011-03-09 | 2014-03-27 | スウェイ タービン エーエス | Wind turbine rotor and mounting method |
| GB2507803A (en) * | 2012-11-12 | 2014-05-14 | Ship & Ocean Ind R & D Ct | Wind turbine tower and installation |
| JP2015072013A (en) * | 2011-01-26 | 2015-04-16 | ヴォッベン プロパティーズ ゲーエムベーハーWobben Properties Gmbh | Wind turbine tower construction method and work platform device |
| US9175670B2 (en) | 2012-08-03 | 2015-11-03 | James D. Lockwood | Precast concrete post tensioned segmented wind turbine tower |
| ES2558025A1 (en) * | 2014-07-30 | 2016-02-01 | Acciona Windpower, S.A. | Procedure of assembly of concrete towers of decreasing section for wind turbines and associated wind turbine (Machine-translation by Google Translate, not legally binding) |
| CN105697237A (en) * | 2016-03-05 | 2016-06-22 | 马骏 | Wind energy turbine adopting automatic control technology |
| WO2016119035A1 (en) * | 2015-01-30 | 2016-08-04 | Proacqua Construções E Comércio Ltda. | Structural material tower and assembly method |
| CN106286149A (en) * | 2016-10-27 | 2017-01-04 | 中国矿业大学 | A kind of scalable small farm wind-driven generator |
| CN107916816A (en) * | 2016-10-11 | 2018-04-17 | 普罗腾德建筑系统与方案有限公司 | Structural concrete tower and assemble method |
| WO2018108818A1 (en) * | 2016-12-14 | 2018-06-21 | Senvion Gmbh | Method for erecting a wind turbine tower from prestressed concrete and corresponding wind turbine tower |
| CN108301965A (en) * | 2018-02-01 | 2018-07-20 | 许昌学院 | Wind power generation plant |
| DE102017217516A1 (en) * | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Tower for use of high-altitude wind |
| WO2019207188A1 (en) | 2018-04-25 | 2019-10-31 | Esteyco S.A. | Movable module for hoisting telescopic towers and method for hoisting telescopic towers |
| DE112019004572T5 (en) | 2018-09-13 | 2021-07-29 | Frank Bollmann | MODULAR SYSTEM FOR CONSTRUCTION, GUIDING AND FASTENING OF ELEMENTS OF TUBULAR STRUCTURES AND CORRESPONDING TUBULAR STRUCTURE |
| CN114876270A (en) * | 2022-05-09 | 2022-08-09 | 超讯通信股份有限公司 | Active lifting type communication tower |
| CN118669271A (en) * | 2024-06-28 | 2024-09-20 | 中国华电科工集团有限公司 | Combined tower structure for wind turbine generator |
Families Citing this family (51)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US10203268B2 (en) | 2008-12-04 | 2019-02-12 | Laura P. Solliday | Methods for measuring and modeling the process of prestressing concrete during tensioning/detensioning based on electronic distance measurements |
| EP2339094B1 (en) * | 2009-12-23 | 2016-06-15 | Soletanche Freyssinet | Tower having a pre-stressed concrete column and construction method |
| CA2803886C (en) * | 2010-06-25 | 2018-08-07 | Phillip M. Schmidt | Fluid-actuated telescoping tower for supporting heavy loads |
| US20110138704A1 (en) * | 2010-06-30 | 2011-06-16 | General Electric Company | Tower with tensioning cables |
| BR112013000784B1 (en) * | 2010-07-12 | 2021-10-13 | Siemens Gamesa Renewable Energy A/S | TOWER AND WIND TURBINE CONSTRUCTION |
| US9140029B2 (en) | 2012-01-20 | 2015-09-22 | Illinois Tool Works Inc. | Tower erecting system |
| ES1090131Y (en) * | 2012-11-12 | 2013-12-18 | Merino Pablo Gascon | Helical energy accumulator |
| WO2014141214A1 (en) * | 2013-03-15 | 2014-09-18 | Douglas Brendle | Wind turbine and tower system |
| EP2781673B1 (en) * | 2013-03-21 | 2016-03-16 | ALSTOM Renewable Technologies | Tower |
| CN103266799B (en) * | 2013-06-05 | 2015-07-08 | 上海市机械施工集团有限公司 | Mast and installation technology thereof |
| DE102013225128A1 (en) * | 2013-12-06 | 2015-06-11 | Wobben Properties Gmbh | Wind turbine and wind turbine tower |
| US10364789B2 (en) | 2014-05-15 | 2019-07-30 | Illinois Tool Works Inc. | Pumped hydro tower |
| ES2555500B1 (en) * | 2014-05-27 | 2016-12-13 | Sea Wind Towers Sl | Floating work and installation procedure |
| US10050342B1 (en) * | 2014-09-10 | 2018-08-14 | Lockheed Martin Corporation | Self deploying axial drive actuator |
| FR3029231B1 (en) * | 2014-12-01 | 2016-12-30 | Lafarge Sa | CONCRETE SECTION |
| MX2018002589A (en) * | 2015-08-31 | 2019-01-24 | Siemens Gamesa Renewable Energy Inc | Concrete equipment tower with tensioning tendon guide slot. |
| CN113738586A (en) * | 2015-08-31 | 2021-12-03 | 西门子歌美飒可再生能源有限公司 | Equipment tower with concrete foundation |
| US9845792B2 (en) * | 2015-10-13 | 2017-12-19 | Huseyin Ozcan | Wind turbine system |
| JP6937627B2 (en) * | 2016-07-13 | 2021-09-22 | 戸田建設株式会社 | Offshore wind power generation equipment and its construction method |
| ES2665004B1 (en) * | 2016-10-24 | 2019-01-29 | Gamesa Innovation & Technology S L | Crane of a wind turbine |
| CN107366467B (en) * | 2017-08-01 | 2019-07-30 | 绍兴市积成包装机械有限公司 | A kind of mobile electric pole for being used to easily collapse ground based on air motor control |
| CN107237540B (en) * | 2017-08-01 | 2019-08-02 | 绍兴市积成包装机械有限公司 | A kind of mobile electric pole based on air motor control |
| DE102017217513A1 (en) | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Height-adjustable tower with a guidance system |
| DE102017217511A1 (en) | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Height-adjustable tower with a mehrflanschigen connection arrangement |
| DE102017217510A1 (en) | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Tower for vertical height adjustment |
| DE102017217514A1 (en) | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Height-adjustable tower with overlapping tower components |
| US10738497B1 (en) | 2017-10-31 | 2020-08-11 | Pecos Wind Power, Inc. | Nested wind tower assembly |
| CN107859604B (en) * | 2017-11-03 | 2023-05-16 | 大唐东北电力试验研究所有限公司 | Application method of assembled lifting operation platform in tower barrel of wind turbine generator |
| CN107917042B (en) * | 2017-11-26 | 2020-06-23 | 深圳市鑫神科技开发有限公司 | Flow energy power generation method and flow energy generator |
| CN108468621A (en) * | 2018-01-22 | 2018-08-31 | 佛山尉达科技有限公司 | Wind power generation plant |
| CN108374768A (en) * | 2018-01-22 | 2018-08-07 | 佛山尉达科技有限公司 | The manufacturing method of wind power generation plant |
| CN108468618A (en) * | 2018-01-22 | 2018-08-31 | 佛山尉达科技有限公司 | wind power plant |
| WO2020068119A1 (en) | 2018-09-28 | 2020-04-02 | General Electric Company | Method for manufacturing a telescoping wind turbine tower structure |
| CN109139386B (en) * | 2018-09-30 | 2019-08-23 | 北京金风科创风电设备有限公司 | Tower section, tower, segmentation method and wind generating set |
| CN112780496A (en) * | 2019-11-07 | 2021-05-11 | 金科新能源有限公司 | Tower, self-lifting method of tower and self-lifting equipment |
| CN112780096A (en) * | 2019-11-07 | 2021-05-11 | 金科新能源有限公司 | Pre-assembly structure for tower and tower pre-assembly method |
| IT202000004345A1 (en) * | 2020-03-02 | 2021-09-02 | Fireco S R L A Socio Unico | PNEUMATIC TELESCOPIC COLUMN ASSEMBLY |
| ES2877242B2 (en) * | 2020-05-12 | 2022-08-16 | Esteyco S A | TELESCOPIC TOWER CONSTRUCTION PROCEDURE |
| CN111692048A (en) * | 2020-06-12 | 2020-09-22 | 陆林娣 | High-efficiency wind power generation device and wind power generation method thereof |
| CN111933403A (en) * | 2020-08-25 | 2020-11-13 | 中车株洲电机有限公司 | Horizontal placement method and general device for transformer |
| JP7475682B2 (en) * | 2020-12-02 | 2024-04-30 | ベステラ株式会社 | Dismantling method for offshore tower-type wind power generation equipment |
| JP7486187B2 (en) * | 2020-12-02 | 2024-05-17 | ベステラ株式会社 | How to dismantle tower-type wind power generation equipment |
| CN112681526A (en) * | 2020-12-14 | 2021-04-20 | 中国建筑第八工程局有限公司 | Jacking and installing system and method for large-span steel structure |
| CN112796955A (en) * | 2021-02-08 | 2021-05-14 | 中国电建集团重庆工程有限公司 | Wind power tower barrel, fan and fan construction method |
| JP7371939B2 (en) * | 2021-03-25 | 2023-10-31 | ベステラ株式会社 | How to lower blades when dismantling tower-type wind power generation equipment |
| CN114109736B (en) * | 2021-11-30 | 2023-10-03 | 安徽方永新能源科技有限公司 | Wind power generation equipment applied to offshore ocean and resistant to sea salt corrosion |
| CN114893022B (en) * | 2022-06-17 | 2023-09-22 | 上海建工四建集团有限公司 | Floor lowering device for reversely dismantling building and construction method |
| US12529239B2 (en) | 2022-10-31 | 2026-01-20 | Ge Infrastructure Technology Llc | Wind turbine tower structure with stacked tower sections |
| CN115977451A (en) * | 2023-01-30 | 2023-04-18 | 上海风领新能源有限公司 | Climbing self-elevating tower and its construction technology |
| CN116044672A (en) * | 2023-01-30 | 2023-05-02 | 上海风领新能源有限公司 | Self-elevating tower and its construction technology |
| US11952977B1 (en) * | 2023-11-29 | 2024-04-09 | Donald Gehring | Telescopic wind turbine tower |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2002046552A1 (en) * | 2000-12-05 | 2002-06-13 | Allan P Henderson | Tilt-up and telescopic support tower for large structures |
| WO2003004870A1 (en) * | 2001-07-06 | 2003-01-16 | Saipem Sa | Offshore wind turbine and method for making same |
| EP1645701A2 (en) * | 2004-10-11 | 2006-04-12 | Inneo21, S.L. | Improved modular tower structure for eolic turbines and other applications |
| WO2008031912A1 (en) * | 2006-09-13 | 2008-03-20 | Gamesa Innovation & Technology, S.L. | Wind turbine tower mounted with pre-fabricated elements |
Family Cites Families (29)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2384279A (en) * | 1943-09-27 | 1945-09-04 | Charles G Calhoun | Extension pole |
| US2795303A (en) * | 1952-12-26 | 1957-06-11 | Benjamin H Muehlhause | Masts or towers |
| US3248831A (en) * | 1962-01-03 | 1966-05-03 | Craig Systems Corp | Telescoping antenna mast |
| US4151534A (en) * | 1977-09-14 | 1979-04-24 | Bond Orville R | Antenna telescoping tower |
| US4176360A (en) * | 1978-09-18 | 1979-11-27 | The United States Of America As Represented By The Administrator Of The National Aeronautics And Space Administration | Antenna deployment mechanism for use with a spacecraft |
| FR2545263B1 (en) * | 1983-04-29 | 1986-06-13 | Alsthom Atlantique | TELESCOPIC DISCONNECTOR |
| US5101215A (en) * | 1985-05-10 | 1992-03-31 | Chu Associates, Inc. | Telescoping lightweight antenna tower assembly and the like |
| US4785309A (en) * | 1986-05-12 | 1988-11-15 | Gremillion Ernest J | Extendable antenna mast with independent retracting and lifting cables |
| IE68595B1 (en) * | 1990-09-10 | 1996-06-26 | Burt Will Comp | A drive |
| US6046706A (en) * | 1997-06-20 | 2000-04-04 | Vargas; Robert A. | Antenna mast and method of using same |
| US6343440B1 (en) * | 1999-01-07 | 2002-02-05 | Rienk Ayers | Antenna towers having a natural appearance |
| US6705058B1 (en) * | 1999-02-12 | 2004-03-16 | Newmark International Inc. | Multiple-part pole |
| US20010038207A1 (en) * | 2000-05-02 | 2001-11-08 | Willis Jeffrey O. | Method and means for mounting a wind turbine on a tower |
| JP3918905B2 (en) * | 2000-11-16 | 2007-05-23 | 株式会社日立プラントテクノロジー | How to install a windmill generator |
| US7231741B2 (en) * | 2001-03-30 | 2007-06-19 | Sbc Technology Resources, Inc. | Mobile cellular telephone tower |
| JP3592313B2 (en) * | 2002-05-10 | 2004-11-24 | 大王製紙株式会社 | Internal wall work equipment for tower tank |
| DK1507975T3 (en) * | 2002-05-27 | 2006-06-19 | Vestas Wind Sys As | Methods for handling wind turbine blades and mounting the blades on a wind turbine, system and grip unit for handling a wind turbine blade |
| US7191569B2 (en) * | 2003-03-10 | 2007-03-20 | Telecopier Foundations Llc | Telescoping pier foundation |
| US7195216B2 (en) * | 2004-12-10 | 2007-03-27 | Gemmy Industries Corporation | Adjustable trunk for an artificial Christmas tree |
| ES2246734B1 (en) * | 2005-04-21 | 2007-04-16 | STRUCTURAL CONCRETE & STEEL, S.L. | PREFABRICATED MODULAR TOWER. |
| JP2007046292A (en) * | 2005-08-09 | 2007-02-22 | Oriental Construction Co Ltd | Tower constructing block |
| JP4722630B2 (en) * | 2005-09-07 | 2011-07-13 | 株式会社竹中工務店 | Method for constructing tower structure and slip foam apparatus used in the method |
| JP4701047B2 (en) * | 2005-09-07 | 2011-06-15 | 株式会社竹中工務店 | Wind power tower construction method |
| US8381460B1 (en) * | 2007-02-27 | 2013-02-26 | Patrick P. McDermott | Extendable beam structure (EBS) |
| GB0713990D0 (en) | 2007-07-18 | 2007-08-29 | Chambers Peter R | Mountings |
| WO2009056898A1 (en) * | 2007-11-02 | 2009-05-07 | Alejandro Cortina-Cordero | Post-tensioned concrete tower for wind turbines |
| US8191322B2 (en) * | 2007-10-11 | 2012-06-05 | Frank Liestenfeltz | Payload mast |
| US8146219B2 (en) * | 2008-11-07 | 2012-04-03 | Monostory Erik J | Portable renewable energy box system |
| ES2595231T3 (en) * | 2010-04-06 | 2016-12-28 | Soletanche Freyssinet | Hybrid tower construction method for a wind generator |
-
2009
- 2009-07-13 BR BR112012000808A patent/BR112012000808A2/en not_active IP Right Cessation
- 2009-07-13 EP EP09780492.6A patent/EP2454427B1/en active Active
- 2009-07-13 AU AU2009349932A patent/AU2009349932B2/en not_active Ceased
- 2009-07-13 WO PCT/EP2009/058896 patent/WO2011006526A1/en not_active Ceased
- 2009-07-13 JP JP2012519892A patent/JP5629316B2/en not_active Expired - Fee Related
- 2009-07-13 US US13/382,341 patent/US8919074B2/en not_active Expired - Fee Related
- 2009-07-13 CN CN200980160435.XA patent/CN102482892B/en not_active Expired - Fee Related
- 2009-07-13 DK DK09780492.6T patent/DK2454427T3/en active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2002046552A1 (en) * | 2000-12-05 | 2002-06-13 | Allan P Henderson | Tilt-up and telescopic support tower for large structures |
| WO2003004870A1 (en) * | 2001-07-06 | 2003-01-16 | Saipem Sa | Offshore wind turbine and method for making same |
| EP1645701A2 (en) * | 2004-10-11 | 2006-04-12 | Inneo21, S.L. | Improved modular tower structure for eolic turbines and other applications |
| WO2008031912A1 (en) * | 2006-09-13 | 2008-03-20 | Gamesa Innovation & Technology, S.L. | Wind turbine tower mounted with pre-fabricated elements |
Cited By (38)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US9534416B2 (en) | 2011-01-26 | 2017-01-03 | Wobben Properties Gmbh | Method and device for erecting a tower for a wind energy plant |
| JP2015072013A (en) * | 2011-01-26 | 2015-04-16 | ヴォッベン プロパティーズ ゲーエムベーハーWobben Properties Gmbh | Wind turbine tower construction method and work platform device |
| JP2014507601A (en) * | 2011-03-09 | 2014-03-27 | スウェイ タービン エーエス | Wind turbine rotor and mounting method |
| US9500178B2 (en) | 2011-03-09 | 2016-11-22 | Sway Turbine As | Wind turbine rotor and method of mounting |
| ITPV20110007A1 (en) * | 2011-04-01 | 2012-10-02 | Eeco Srl | INSTALLATION PROCEDURE FOR A VERTICAL TELESCOPIC POLE AND ITS REALIZATION |
| ITGE20110108A1 (en) * | 2011-09-29 | 2013-03-30 | Casamonti Tommaso | "FLOATING PLATFORM SUPPORT FOR GAS MILLS" |
| WO2013045465A1 (en) * | 2011-09-29 | 2013-04-04 | Montalti Mirko | Floating support platform for wind turbine |
| WO2013057225A1 (en) | 2011-10-18 | 2013-04-25 | Inneo Torres, S.L. | Process for installing an offshore tower |
| WO2013083852A1 (en) | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Assembly process of a telescopic tower |
| WO2013083853A1 (en) * | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Horizontal joint assembly between two telescopic wind turbine tower portions and method of installing same |
| AU2012350234B2 (en) * | 2011-12-09 | 2016-10-27 | Esteyco S.A.P | Assembly process of a telescopic tower |
| WO2013083854A1 (en) | 2011-12-09 | 2013-06-13 | Inneo Torres, S.L. | Assembly method for a telescopic tower and means for implementing said method |
| CN104040096A (en) * | 2011-12-09 | 2014-09-10 | 海上风力发电机塔有限公司 | A method of erecting a telescopic tower |
| JP2015500931A (en) * | 2011-12-09 | 2015-01-08 | シー・ウインド・タワーズ・ソシエダッド・リミターダSea Windtowers,S.L. | How to assemble telescopic tower |
| ES2407756R1 (en) * | 2011-12-09 | 2013-08-02 | Inneo Torres Sl | ASSEMBLY PROCEDURE OF A TELESCOPIC TOWER |
| CN104040096B (en) * | 2011-12-09 | 2018-08-21 | 海上风力发电机塔有限公司 | A method of erecting a telescopic tower |
| ES2407780R1 (en) * | 2011-12-09 | 2013-09-06 | Inneo Torres Sl | ASSEMBLY OF HORIZONTAL JOINT BETWEEN TWO TELESCOPIC PORTIONS OF AIRLINER TOWER AND ITS INSTALLATION PROCEDURE |
| US10465411B2 (en) | 2011-12-09 | 2019-11-05 | Esteyco S.A.P. | Assembly process of a telescopic tower |
| US9175670B2 (en) | 2012-08-03 | 2015-11-03 | James D. Lockwood | Precast concrete post tensioned segmented wind turbine tower |
| GB2507803B (en) * | 2012-11-12 | 2015-07-29 | Ship & Ocean Ind R & D Ct | An offshore installation method of a wind power generator and its fabrication segments |
| GB2507803A (en) * | 2012-11-12 | 2014-05-14 | Ship & Ocean Ind R & D Ct | Wind turbine tower and installation |
| CN103243959A (en) * | 2013-05-22 | 2013-08-14 | 四川擎烽通信有限责任公司 | Quickly mounted communication tower and mounting method thereof |
| EP2980337A1 (en) * | 2014-07-30 | 2016-02-03 | Acciona Windpower S.a. | Method for assembling diminishing section concrete towers for wind turbines and associated wind turbine |
| ES2558025A1 (en) * | 2014-07-30 | 2016-02-01 | Acciona Windpower, S.A. | Procedure of assembly of concrete towers of decreasing section for wind turbines and associated wind turbine (Machine-translation by Google Translate, not legally binding) |
| US9637944B2 (en) | 2014-07-30 | 2017-05-02 | Acciona Windpower, S.A. | Method for assembling decreasing section concrete towers for wind turbines and associated wind turbines |
| WO2016119035A1 (en) * | 2015-01-30 | 2016-08-04 | Proacqua Construções E Comércio Ltda. | Structural material tower and assembly method |
| CN105697237A (en) * | 2016-03-05 | 2016-06-22 | 马骏 | Wind energy turbine adopting automatic control technology |
| CN107916816A (en) * | 2016-10-11 | 2018-04-17 | 普罗腾德建筑系统与方案有限公司 | Structural concrete tower and assemble method |
| WO2018068117A1 (en) * | 2016-10-11 | 2018-04-19 | Protende Sistemas E Métodos De Construções Ltda. | Structural concrete tower and assembly method |
| CN106286149A (en) * | 2016-10-27 | 2017-01-04 | 中国矿业大学 | A kind of scalable small farm wind-driven generator |
| WO2018108818A1 (en) * | 2016-12-14 | 2018-06-21 | Senvion Gmbh | Method for erecting a wind turbine tower from prestressed concrete and corresponding wind turbine tower |
| DE102017217516A1 (en) * | 2017-09-29 | 2018-12-20 | Thyssenkrupp Ag | Tower for use of high-altitude wind |
| CN108301965A (en) * | 2018-02-01 | 2018-07-20 | 许昌学院 | Wind power generation plant |
| WO2019207188A1 (en) | 2018-04-25 | 2019-10-31 | Esteyco S.A. | Movable module for hoisting telescopic towers and method for hoisting telescopic towers |
| DE112019004572T5 (en) | 2018-09-13 | 2021-07-29 | Frank Bollmann | MODULAR SYSTEM FOR CONSTRUCTION, GUIDING AND FASTENING OF ELEMENTS OF TUBULAR STRUCTURES AND CORRESPONDING TUBULAR STRUCTURE |
| CN114876270A (en) * | 2022-05-09 | 2022-08-09 | 超讯通信股份有限公司 | Active lifting type communication tower |
| CN114876270B (en) * | 2022-05-09 | 2023-06-02 | 超讯通信股份有限公司 | Initiative over-and-under type communication tower |
| CN118669271A (en) * | 2024-06-28 | 2024-09-20 | 中国华电科工集团有限公司 | Combined tower structure for wind turbine generator |
Also Published As
| Publication number | Publication date |
|---|---|
| HK1167880A1 (en) | 2012-12-14 |
| US20120159875A1 (en) | 2012-06-28 |
| JP5629316B2 (en) | 2014-11-19 |
| CN102482892A (en) | 2012-05-30 |
| AU2009349932B2 (en) | 2015-10-08 |
| BR112012000808A2 (en) | 2016-02-23 |
| US8919074B2 (en) | 2014-12-30 |
| JP2012533008A (en) | 2012-12-20 |
| EP2454427B1 (en) | 2017-02-15 |
| EP2454427A1 (en) | 2012-05-23 |
| AU2009349932A1 (en) | 2012-02-02 |
| DK2454427T3 (en) | 2017-05-15 |
| CN102482892B (en) | 2014-10-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2009349932B2 (en) | Telescopic tower assembly and method | |
| EP2310576B1 (en) | Base support for wind-driven power generators | |
| CA2735625C (en) | Method of building a hybrid tower for a wind generator | |
| AU2019300466B2 (en) | Foundation for a wind turbine | |
| AU2008320532B2 (en) | Segmented concrete tower for wind power generators and method of erection thereof | |
| DK2256338T3 (en) | Foundation, especially for a wind turbine and wind turbine | |
| US8281546B2 (en) | Slip formed concrete wind turbine tower | |
| AU2019300467B2 (en) | Foundation for a wind turbine | |
| WO2017141098A1 (en) | Foundation for a wind mill | |
| KR20210094617A (en) | Foundation for wind turbine towers | |
| WO2017141095A1 (en) | Foundation for a wind mill | |
| WO2018055446A1 (en) | Foundation for a windmill | |
| EP4273326A1 (en) | Foundation for a superstructure, particularly for a wind turbine, wind turbine with the foundation, method of forming a wind turbine foundation | |
| WO2007097640A2 (en) | A method for installing and dismantling a wind power structure, and a wind turbine assembly | |
| WO2010071975A1 (en) | Wind turbine tower and method for building the same | |
| CA3091540C (en) | Semi-finished part for a foundation of a tower construction and methods for production thereof | |
| HK1167880B (en) | Telescopic tower assembly and method | |
| AU2011201502B8 (en) | Method of building a hybrid tower for a wind generator |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| WWE | Wipo information: entry into national phase |
Ref document number: 200980160435.X Country of ref document: CN |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 09780492 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2009349932 Country of ref document: AU Ref document number: 2764/MUMNP/2011 Country of ref document: IN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2012519892 Country of ref document: JP |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| REEP | Request for entry into the european phase |
Ref document number: 2009780492 Country of ref document: EP |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2009780492 Country of ref document: EP |
|
| ENP | Entry into the national phase |
Ref document number: 2009349932 Country of ref document: AU Date of ref document: 20090713 Kind code of ref document: A |
|
| REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112012000808 Country of ref document: BR Kind code of ref document: A2 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 13382341 Country of ref document: US |
|
| ENP | Entry into the national phase |
Ref document number: 112012000808 Country of ref document: BR Kind code of ref document: A2 Effective date: 20120112 |