WO2016196452A1 - Method and apparatus for constructing a concrete tower - Google Patents

Method and apparatus for constructing a concrete tower Download PDF

Info

Publication number
WO2016196452A1
WO2016196452A1 PCT/US2016/034994 US2016034994W WO2016196452A1 WO 2016196452 A1 WO2016196452 A1 WO 2016196452A1 US 2016034994 W US2016034994 W US 2016034994W WO 2016196452 A1 WO2016196452 A1 WO 2016196452A1
Authority
WO
WIPO (PCT)
Prior art keywords
cast concrete
concrete element
rebar
alignment jig
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/US2016/034994
Other languages
French (fr)
Inventor
Bryant ZAVITZ
Kevin KIRKLEY
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tindall Corp
Original Assignee
Tindall Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tindall Corp filed Critical Tindall Corp
Priority to MX2017015201A priority Critical patent/MX2017015201A/en
Priority to EP16804217.4A priority patent/EP3303734A4/en
Priority to US15/578,057 priority patent/US20180155951A1/en
Priority to CA2987405A priority patent/CA2987405A1/en
Publication of WO2016196452A1 publication Critical patent/WO2016196452A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/342Arrangements for stacking tower sections on top of each other
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/16Prestressed structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/91Mounting on supporting structures or systems on a stationary structure
    • F05B2240/912Mounting on supporting structures or systems on a stationary structure on a tower

Definitions

  • the present invention relates to a method and apparatus for constructing a concrete tower.
  • the invention relates to constructing a concrete tower using pre-cast concrete components.
  • the present invention broadly comprises a method and apparats for constructing a concrete tower, in one embodiment, a tower construction apparatus includes an alignment jig and a pre-cast concrete element located on the alignment jig.
  • FIG. 1 illustrates an embodiment of a concrete tower that can be constructed according to an exemplary embodiment of the present invention
  • FIG.2 illustrates close up view of portions of the concrete tower in FIG. 1 ;
  • FIGS. 3 and 4 illustrate a first exemplary process for making subassemblies for the tower shown in FIG. 1;
  • FIGS.5-9 illustrate a second exemplary process for making subassemblies for the tower shown in FIG. 1 ;
  • FIGS. 10-14 illustrate an exemplar ⁇ ' process for stacking the subassemblies for the tower shown in FIG. 1
  • FIG. 15 illustrate several views of the element that make up the subassemblies
  • FIG. 16 shows an embodiment of a form far creating the elements that make up the subassemblies
  • FIG. 17 iilusirates exemplary structures for joining the pieces.
  • FIGS. 18-21 show multiple embodiments of towers made in accordance with the present invention.
  • FIG. 1 shows a tower 10 built according to one embodiment of the present invention.
  • Tower 10 includes a fonndation 20. a concrete portion 30, a metal portion 40. and a wind turbine 50.
  • towers used for purposes other than supporting wind turbines may be built in accordance with the present invention, and towers without any metal portion may also be built according to the present invention, Such modifications are within the scope of the invention as claimed.
  • the embodiment of the tower 10 shown in Figure 1 may include a concrete portion 30 including sections 32.
  • each section 32 is made of two precast elements. 33 A and 33B.
  • each section may be made of more than two elements.
  • Concrete portion 30 also includes a transition region 38 in contact with the bottom of metal portion 40.
  • Transition region 38 may include a precast transition ring 39 including a plurality of apertures 39A through, which post tensioning strands 22 pass through. Post tensioning strands may be anchored in the foundation 20 and are capped off as they pass through apertures 39A.
  • a pos-tensioning strand 22 is inserted into one of apertures 39A and fed through the aperture until it reaches the foundation level.
  • An elbow passageway 24 in the foundation 20 (shown in Figure 10) then guides the post-tensioning strand 22 up an adjacent aperture 39A.
  • the strain is cut and each end is anchored on the top of transition ring 39 as shown in Figure 2.
  • Transition ring 39 may also include a plurality of post tensioning rods 39B. These rods 39B extend through passages in transition ring 39 and a bottom flange of metal portion 40, and are capped off ' just above the flange of metal portion 40 and just below the surface of transition ring 39. This fixes the metal portion 40 to the concrete portion 30.
  • FIGs 3 and 4 show a first embodiment for assembling sections 32.
  • each section 32 is made of two elements 33A and 33ft which are sealed together at the factory.
  • the sealed sections 32 are then transported to the worksite by truck 60A.
  • second section 32B may be connected to first section 32A while first section 32A is still located on truck 60A to create subassembly 34.
  • Subassembly 34 may then be moved onto foundation 20 using a crane (not shown), m the embodiment shown in Figure 4, second section 32A is rotated with respect to section 32A before connection such that the joints between the elements of each section do not line up. but are 90 degrees from each other. This is done for each succeeding section- as shown in Figure 1 to provide additional structural strength.
  • each section is made of two elements that are transported from the factory separately and then assembled at the worksite.
  • This embodiment is shown in Figure 5- 9.
  • Figure 5 shows truck 60A with alignment jig 62 mounted on die trailer of the truck 60A.
  • First element 33A is brought in by truck 60B, and element 32A is moved onto alignment jig 62 using a crane (not shown).
  • Figure 6 shows truck 60C bringing second element 33B. which is also moved onto jig 62 and then attached to element 33B to create a first section 32A.
  • Figure 7 shows truck 60D bringing element 33C, which is then stacked onto first section 32A by a crane (not shown). Element 33C is placed such that approximately half of element 33C is located on element 33A and half on element 33B. This ensures that the joints between the wo sections in the subassembly will be rotated by 90 degrees with respect to each other, as noted above.
  • Figure 8 shows element 33D on truck 60E for completion of subassembly 34.
  • Figure 9 shows completed subassembly 34, along with a close up of the connection between the sections. Rods 35 are used to secure the sections together.
  • Figure 10 shows subassembly 34 A next to foundation 20.
  • Subassembly 34 A is moved onto foundation 20 by a crane (not shown).
  • Figure 1 1 shows subassembly 34B is then brought to foundation 20 so thai subassembly 34R can be stacked on subassembly 34 A.
  • the subassemblies are stacked such that joints between elements in consecutive sections do not line up.
  • Figure 12 shows subassembly 34C ready to be stacked onto subassembly 34B.
  • Each succeeding subassembly may also have a tapering width, such that the tower becomes narrower as it gets higher.
  • Figures 13 and 14 show subassemblies 34D and 34E, which again are successively stacked on foundation 20 to form concrete portion 20 of tower 10.
  • FIG 15 shows one embodiment of the elements 32, Elements 32 include ducts 37 through which post tensioning strands 22 pass. They also include openings 36 through which rods
  • Alignment jig may include pegs 63 (labeled in Figure 5) which enter openings 36 and ducts 37 to hold the elements 32 on the jig 62.
  • FIG 16 shows an embodiment of a form 70 for creating elements 32.
  • the arms of the clement 32 are facing down.
  • alternate embodiments forming the element in any configuration are also within the scope of the invention.
  • Figure 17 shows two exemplary embodiments for -fosterling the elements 32 -together, in each of the embodiments shown, rebar 80A and 80B extend from the opposing ends of the adjacent elements into an open space. One side of the open space is sealed with a caulked joint 82. The other side of the open space is sealed with plate 84. The open space is then filled with a grout to join the elements together.
  • the elements in a section may be joined with a grout joint as shown in Figure 17 on one side of the section 32, but only sealed with a waterproof adhesive on the other side.
  • a grout joint will bear any significant load, as the waterproof adhesive cannot bear any significant structural load.
  • Structural connections must be able to withstand compression, tension and shear loads, with a minimum factor of safety.
  • the number of areas which need to be certified is advantageously minimized.
  • the grouted joints are structurally fastened together, but the adhesive joints have no structural connection between elements. Further, the sections 32 are rotated such that the adhesive joints are staggered as you go up the tower. That is, the adhesive joint for two consecutive sections 32 are not facing the same direction. This provides further structural strength for the tower.
  • Figures 18-21 shows a plurality of configurations that can be made in accordance with the present invention
  • f igures 18 and 19 show towers with 15 sections 32, some of which taper and some of which have straight sides.
  • Figure 20 shows a tower with 15 sections 32 and a tower with 18 sections 32.
  • Figure 21 shows diree exemplary tower configurations, one with 15 sections 32, one with 18 sections 32, and one with 28 sections 32. All of these embodiments are within the scope of the invention as claimed.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Wind Motors (AREA)
  • Foundations (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)

Abstract

The present invention broadly comprises a method and apparatus for constructing a concrete tower. In one embodiment, a tower construction apparatus includes an alignment jig and a pre-cast concrete element located on the alignment jig.

Description

METHOD AND APPARATUS FOR CONSTRUCTING A CONCRETE TOWER
CROSS REFERENCE TO RELA TED APPLICATIONS
[0001] This application claims priority to U .S. Patent Application No. 15/168,284. filed May 31, 2016 and under 35 U.S.C. §119(e) to U.S. Application No. «2/168-203, filed May 29, 2015, the entire content of each of which is incorporated into the present application by reference.
FIELD OF THE INVENTION
[0002] The present invention relates to a method and apparatus for constructing a concrete tower. In particular, the invention relates to constructing a concrete tower using pre-cast concrete components.
BACKGROUND OF THE INVENTION
[0003] Conventional methods and apparatuses for constructing a tower with pre-cast components can be labor intensive. Accordingly, a need for a more efficient method and apparatus has been developed by the present inventors.
SUMMARY OF THE INVENTION
[0004] The present invention broadly comprises a method and apparats for constructing a concrete tower, in one embodiment, a tower construction apparatus includes an alignment jig and a pre-cast concrete element located on the alignment jig. BRIEF DESCRIPTION OF THE DRAWINGS
[0005] A full and enabling disclosure of the present subject matter, including the best mode thereof; directed to one of ordinary skill in the an, is set forth in the specification, which makes reference to the appended figures, in which:
[0006] FIG. 1 illustrates an embodiment of a concrete tower that can be constructed according to an exemplary embodiment of the present invention;
[0007] FIG.2 illustrates close up view of portions of the concrete tower in FIG. 1 ;
[0008] FIGS. 3 and 4 illustrate a first exemplary process for making subassemblies for the tower shown in FIG. 1;
[0009] FIGS.5-9 illustrate a second exemplary process for making subassemblies for the tower shown in FIG. 1 ;
[0010] FIGS. 10-14 illustrate an exemplar}' process for stacking the subassemblies for the tower shown in FIG. 1
[0011] FIG. 15 illustrate several views of the element that make up the subassemblies;
[0012] FIG. 16 shows an embodiment of a form far creating the elements that make up the subassemblies;
[0013] FIG. 17 iilusirates exemplary structures for joining the pieces; and
[0014] FIGS. 18-21 show multiple embodiments of towers made in accordance with the present invention.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0015] Reference is presently made in detail to exemplary embodiments of the present subject matter, one or more examples of which are illustrated in or represented by the drawings. Each example is provided by way of explanation of the present subject matter, not limitation of the present subject matter, in fact, it will be apparent to those skilled in the art that various modifications and variations can be made in the present subject matter without departing from the scope or spirit of the present subject matter. For instance, features illustrated or described as part of one embodiment can be used with another embodiment to yield a still further embodiment. Thus, it is intended that the present subject matter covers such modifictions and variations as come within the scope of the disclosure and equivalents thereof.
[0016] Figure 1 shows a tower 10 built according to one embodiment of the present invention. Tower 10 includes a fonndation 20. a concrete portion 30, a metal portion 40. and a wind turbine 50. However, towers used for purposes other than supporting wind turbines may be built in accordance with the present invention, and towers without any metal portion may also be built according to the present invention, Such modifications are within the scope of the invention as claimed.
[0017] As shown in Figure 2, the embodiment of the tower 10 shown in Figure 1 may include a concrete portion 30 including sections 32. In one embodiment, each section 32 is made of two precast elements. 33 A and 33B. However, each section may be made of more than two elements. Concrete portion 30 also includes a transition region 38 in contact with the bottom of metal portion 40. Transition region 38 may include a precast transition ring 39 including a plurality of apertures 39A through, which post tensioning strands 22 pass through. Post tensioning strands may be anchored in the foundation 20 and are capped off as they pass through apertures 39A.
[0018] In another embodiment, a pos-tensioning strand 22 is inserted into one of apertures 39A and fed through the aperture until it reaches the foundation level. An elbow passageway 24 in the foundation 20 (shown in Figure 10) then guides the post-tensioning strand 22 up an adjacent aperture 39A. When the strand front end reaches the top of the adjacent aperture 39A, the strain, is cut and each end is anchored on the top of transition ring 39 as shown in Figure 2.
[1019] Transition ring 39 may also include a plurality of post tensioning rods 39B. These rods 39B extend through passages in transition ring 39 and a bottom flange of metal portion 40, and are capped off' just above the flange of metal portion 40 and just below the surface of transition ring 39. This fixes the metal portion 40 to the concrete portion 30.
[0020] Figures 3 and 4 show a first embodiment for assembling sections 32. in Figures 3 and 4, each section 32 is made of two elements 33A and 33ft which are sealed together at the factory. The sealed sections 32 are then transported to the worksite by truck 60A. As shown in Figure 4, second section 32B may be connected to first section 32A while first section 32A is still located on truck 60A to create subassembly 34. Subassembly 34 may then be moved onto foundation 20 using a crane (not shown), m the embodiment shown in Figure 4, second section 32A is rotated with respect to section 32A before connection such that the joints between the elements of each section do not line up. but are 90 degrees from each other. This is done for each succeeding section- as shown in Figure 1 to provide additional structural strength.
[0021] In another embodiment, each section is made of two elements that are transported from the factory separately and then assembled at the worksite. This embodiment is shown in Figure 5- 9. Figure 5 shows truck 60A with alignment jig 62 mounted on die trailer of the truck 60A. First element 33A is brought in by truck 60B, and element 32A is moved onto alignment jig 62 using a crane (not shown). Figure 6 shows truck 60C bringing second element 33B. which is also moved onto jig 62 and then attached to element 33B to create a first section 32A.
[0022] Figure 7 shows truck 60D bringing element 33C, which is then stacked onto first section 32A by a crane (not shown). Element 33C is placed such that approximately half of element 33C is located on element 33A and half on element 33B. This ensures that the joints between the wo sections in the subassembly will be rotated by 90 degrees with respect to each other, as noted above. Figure 8 then shows element 33D on truck 60E for completion of subassembly 34. Figure 9 shows completed subassembly 34, along with a close up of the connection between the sections. Rods 35 are used to secure the sections together.
[0023] Figure 10 shows subassembly 34 A next to foundation 20. Subassembly 34 A is moved onto foundation 20 by a crane (not shown). Figure 1 1 shows subassembly 34B is then brought to foundation 20 so thai subassembly 34R can be stacked on subassembly 34 A. The subassemblies are stacked such that joints between elements in consecutive sections do not line up. Figure 12 shows subassembly 34C ready to be stacked onto subassembly 34B. Each succeeding subassembly may also have a tapering width, such that the tower becomes narrower as it gets higher. Figures 13 and 14 show subassemblies 34D and 34E, which again are successively stacked on foundation 20 to form concrete portion 20 of tower 10.
[8024] Figure 15 shows one embodiment of the elements 32, Elements 32 include ducts 37 through which post tensioning strands 22 pass. They also include openings 36 through which rods
- 35 pass. Alignment jig may include pegs 63 (labeled in Figure 5) which enter openings 36 and ducts 37 to hold the elements 32 on the jig 62.
|002S| Figure 16 shows an embodiment of a form 70 for creating elements 32. In this embodiment, the arms of the clement 32 are facing down. However, alternate embodiments forming the element in any configuration are also within the scope of the invention.
[00211] Figure 17 shows two exemplary embodiments for -fosterling the elements 32 -together, in each of the embodiments shown, rebar 80A and 80B extend from the opposing ends of the adjacent elements into an open space. One side of the open space is sealed with a caulked joint 82. The other side of the open space is sealed with plate 84. The open space is then filled with a grout to join the elements together.
[0027] in another embodiment, the elements in a section may be joined with a grout joint as shown in Figure 17 on one side of the section 32, but only sealed with a waterproof adhesive on the other side. Thus, only the grout joint, will bear any significant load, as the waterproof adhesive cannot bear any significant structural load. This may be done because structural connections between joints are required to be certified, which is both costly and time consuming. Structural connections must be able to withstand compression, tension and shear loads, with a minimum factor of safety. In an exemplar)' embodiment, the number of areas which need to be certified is advantageously minimized. The grouted joints are structurally fastened together, but the adhesive joints have no structural connection between elements. Further, the sections 32 are rotated such that the adhesive joints are staggered as you go up the tower. That is, the adhesive joint for two consecutive sections 32 are not facing the same direction. This provides further structural strength for the tower.
[0028] Figures 18-21 shows a plurality of configurations that can be made in accordance with the present invention, f igures 18 and 19 show towers with 15 sections 32, some of which taper and some of which have straight sides. Figure 20 shows a tower with 15 sections 32 and a tower with 18 sections 32. Figure 21 shows diree exemplary tower configurations, one with 15 sections 32, one with 18 sections 32, and one with 28 sections 32. All of these embodiments are within the scope of the invention as claimed.
[0029] The present written description uses examples to disclose the present subject matter, including the best mode, and also to enable any person skilled in the art to practice the present subject matter, including making and using any devices or systems and performing any incorporated and/or associated methods. While the present subject matter has been described in detail with respect to specific embodiments thereof, it will be appreciated that those skilled In the art, upon attaining an understanding of the foregoing may readily produce alterations to, variations of, and equivalents to such embodiments. Accordingly, the scope of the present disclosure is by way of example rather than by way of limitation, and the subject disclosure does not preclude inclusion of such modifications, variations and/or additions to the present subject matter as would be readily apparent to one of ordinary skill in the art.

Claims

CLAIMS:
1. A tower construction apparatus comprising:
an alignment jig; and
a pre-cast concrete element located on the alignment jig.
2. The tower construction apparatus according to claim 1, wherein the alignment jig includes a plurality of pegs each projecting upward from a top surface of the alignment jig, the pre-cast concrete element includes a plurality of openings, and the pre-cast concrete element is located on the alignment jig such that each of the plurality of pegs extends into one of the plurality of openings.
3. The tower construction apparatus according to claim 1 , further comprising;
a second pre-cast concrete element located on the alignment jig.
4. The tower construction apparatus according to claim 3, wherein a first end of the pre-cast concrete element is adjacent a first end of the second pre-cast concrete element, and a second end of the pre-cast concrete element is adjacent a second end of the second pre-cast concrete element
5. The tower construction apparatus according to claim 4, wherein a first rebar extends from the first end of the pre-cast concrete element and a second rebar extends from the first end of the second pre-cast concrete element
6. The tower construction apparatus according to claim 5, further comprising; a caulked joint located between the first end of the pre-cast concrete element and the first end of the second pre-cast concrete element along one side of the first rebar and the second rebar;
a plate extending between the first end of the pre-cast concrete element and the first end of the second pre-cast concrete element along an opposite side of the first rebar and the second rebar; and
a grout joint surrounding the first rebar and the second rebar and extending between the caulked joint and the plate.
7. Hie tower construction apparatus according to claim 5, further comprising:
a waterproof adhesive located between the second end of the pre-cast concrete element and the second end of the second pre-cast concrete element
8. The tower construction apparatus according to claim 3, further comprising:
third and fourth pre-cast concrete elements located on the pre-cast concrete element and the second pre-cast concrete element; and
rods extending vertically to connect the third and fourth pre-cast concrete elements to the pre-cast concrete element and the second pre-cast concrete element.
9. A method comprising:
providing a foundation:
providing an alignment jig; assembling a first and a second pre-cast concrete element together on the alignment jig to create a tower section; and
transferring the tower section onto the foundation.
10. The method according to claim 9, wherein the alignment jig includes a plurality of pegs each projecting upward from a top surface of the alignment jig and each of the first and second pre-cast concrete elements include a plurality of openings, and the method further comprises: placing the first pre-cast concrete element on the alignment jig such that at least one of the plurality of pegs extends into at least one of the plurality of openings in the first pre-cast concrete element; and
placing the second pre-cast concrete element on the alignment jig such that at least one of the plurality of pegs extends into at least one of the plurality of openings in the second pre- cast concrete element.
11. The method according to claim 9, further comprising:
placing the first and second pre-cast concrete elements on the alignment jig such that a first end of the first pre-cast concrete element is adjacent a first end of the second pre-cast concrete element, and a second end of the first pre-cast concrete element is adjacent a second end of the second pre-cast concrete element
12. The method according to claim 11 , wherein a first rebar extends from the first end of the first pre-cast concrete element and a second rebar extends from the first end of the second pre- cast concrete element.
13. The method according to claim 12, further comprising:
providing a caulked joint between the first end of the first pre-cast concrete element and the first end of the second pre-cast concrete element along one side of the first rebar and the second rebar;
providing a plate extending between the first end of the first pre-casl concrete element and the first end of the second pre-cast concrete element along an opposite side of the first rebar and the second rebar; and
providing a grout joint surrounding the first rebar and the second rebar and extending between the caulked joint and the plate.
14. 'The method according to claim 13, further comprising:
providing a waterproof adhesive located between the second end of the first pre-cast concrete element and the second end of the second pre-cast concrete dement.
PCT/US2016/034994 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower Ceased WO2016196452A1 (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
MX2017015201A MX2017015201A (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower.
EP16804217.4A EP3303734A4 (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower
US15/578,057 US20180155951A1 (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower
CA2987405A CA2987405A1 (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
US201562168203P 2015-05-29 2015-05-29
US62/168,203 2015-05-29
US15/168,284 2016-05-31
US15/168,284 US20160348391A1 (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower

Publications (1)

Publication Number Publication Date
WO2016196452A1 true WO2016196452A1 (en) 2016-12-08

Family

ID=57397368

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2016/034994 Ceased WO2016196452A1 (en) 2015-05-29 2016-05-31 Method and apparatus for constructing a concrete tower

Country Status (5)

Country Link
US (2) US20180155951A1 (en)
EP (1) EP3303734A4 (en)
CA (1) CA2987405A1 (en)
MX (1) MX2017015201A (en)
WO (1) WO2016196452A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485573A (en) * 2020-03-19 2020-08-04 衡水衡源电力建设有限责任公司 Transmission project prefabricated foundation installation and iron tower assembly coherent construction method
CN111946556A (en) * 2020-07-29 2020-11-17 上海市机电设计研究院有限公司 Construction positioning method for precast concrete shell ring
CN113602954A (en) * 2021-07-16 2021-11-05 上海市机电设计研究院有限公司 Single hoisting method for multiple concrete shell sections

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017211092A1 (en) * 2017-06-29 2019-01-03 Ventur GmbH Tower and method of manufacture
EP3461971A1 (en) * 2017-09-29 2019-04-03 Holcim Technology Ltd. Method for joining two elements
EP3462016A1 (en) * 2017-10-02 2019-04-03 Ventus Engineering GmbH Use of a new material in wind turbine parts and apparatus and methods hereof
EP3744928B1 (en) * 2019-05-27 2022-09-14 Soletanche Freyssinet Wind turbine tower and method of fabrication and assembling
WO2023133498A1 (en) 2022-01-07 2023-07-13 Pittsburg Tank & Tower Group Elevated tank tower

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050129504A1 (en) * 2002-02-12 2005-06-16 De Roest Anton H. Wind turbine
US20100257797A1 (en) * 2006-08-16 2010-10-14 Inneo 21, S.L. Assembly structure and procedure for concrete towers used in wind turbines
US20140069046A1 (en) * 2012-09-07 2014-03-13 General Electric Company Wind turbine tower base assembly with detachable tower base rings
US20150020467A1 (en) * 2013-07-05 2015-01-22 Acciona Windpower S.A Precast segment for wind turbine tower and method for building a wind turbine tower using said precast segment

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5038540A (en) * 1981-11-20 1991-08-13 Krautz Alfons O Sectional smokestack
FR2652115B1 (en) * 1989-09-18 1991-11-29 Pierrel Guy IMPROVEMENTS IN A PROCESS FOR CONSTRUCTING STRUCTURES, SUCH AS TANKS, SILOS, TOWERS, CHIMNEYS, HIGH CONDUITS AND COMPONENTS FOR ITS IMPLEMENTATION.
US5029426A (en) * 1990-07-11 1991-07-09 Pitt-Des Moines, Inc. Precast concrete panels, support pedestals constructed therefrom and an associated method
JP2000356042A (en) * 1999-06-17 2000-12-26 Ando Corp Jig and method for joining precast concrete columns
EP2256338B1 (en) * 2008-11-03 2014-01-01 Siemens Aktiengesellschaft Foundation particularly for a wind turbine and wind turbine
EP2199469B1 (en) * 2008-12-16 2012-06-06 Vestas Wind Systems A/S Foundation for enabling anchoring of a wind turbine tower thereto by means of replaceable through-bolts
EP2667017B1 (en) * 2012-05-22 2015-02-25 Siemens Aktiengesellschaft A set of multiple aligning tools in the field of wind turbines for aligning tower and base
CN104919177B (en) * 2012-11-15 2018-03-09 维斯塔斯风力系统有限公司 Method and apparatus for being directed at illustrated tower sections
DK177908B1 (en) * 2013-02-26 2014-12-15 Envision Energy Denmark Aps Tower assembly system for wind turbines and method thereof
WO2014160951A1 (en) * 2013-03-29 2014-10-02 Tindall Corporation Core component and tower assembly for a tower structure
WO2015131174A1 (en) * 2014-02-28 2015-09-03 University Of Maine System Board Of Trustees Hybrid concrete - composite tower for a wind turbine
EP2998569B1 (en) * 2014-09-22 2017-08-02 Siemens Aktiengesellschaft Arrangement to align a part of a wind turbine

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050129504A1 (en) * 2002-02-12 2005-06-16 De Roest Anton H. Wind turbine
US20100257797A1 (en) * 2006-08-16 2010-10-14 Inneo 21, S.L. Assembly structure and procedure for concrete towers used in wind turbines
US20140069046A1 (en) * 2012-09-07 2014-03-13 General Electric Company Wind turbine tower base assembly with detachable tower base rings
US20150020467A1 (en) * 2013-07-05 2015-01-22 Acciona Windpower S.A Precast segment for wind turbine tower and method for building a wind turbine tower using said precast segment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LANIER.: "LWST Phase I Project Conceptual Design Study: Evaluation of Design and Construction Approaches for Economical Hybrid Steel/Concrete Wind Turbine Towers.", January 2005 (2005-01-01), pages 107 - 124, XP055335379, Retrieved from the Internet <URL:http://www.nrel.gov/docs/ly05osti/36777.pdf> [retrieved on 20160728] *
See also references of EP3303734A4 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485573A (en) * 2020-03-19 2020-08-04 衡水衡源电力建设有限责任公司 Transmission project prefabricated foundation installation and iron tower assembly coherent construction method
CN111946556A (en) * 2020-07-29 2020-11-17 上海市机电设计研究院有限公司 Construction positioning method for precast concrete shell ring
CN113602954A (en) * 2021-07-16 2021-11-05 上海市机电设计研究院有限公司 Single hoisting method for multiple concrete shell sections

Also Published As

Publication number Publication date
EP3303734A1 (en) 2018-04-11
US20160348391A1 (en) 2016-12-01
US20180155951A1 (en) 2018-06-07
EP3303734A4 (en) 2019-03-06
MX2017015201A (en) 2018-04-13
CA2987405A1 (en) 2016-12-08

Similar Documents

Publication Publication Date Title
WO2016196452A1 (en) Method and apparatus for constructing a concrete tower
US9366237B2 (en) Segmented jacket construction, in particular for a foundation for a wind turbine installation
CN108612254A (en) A kind of prefabricated panel and its connection structure and its construction method
KR20110008752A (en) Precast Segment with Reinforced Concrete Hole and Its Application
CN111962386A (en) Energy-consuming and shock-absorbing self-resetting prefabricated segmental pier structure and its construction method
WO2017013694A1 (en) Framework structure and construction method for same
US20140270981A1 (en) System and method for splicing precast pre-stressed concrete piles
CN106906748A (en) Construction method of prefabricated corrugated steel web composite box girder based on mixed prestress
CN108167125A (en) Connecting elements, concrete tower fragment and mold, tower and preparation method thereof
CN113356053A (en) Stay cable steel tooth block anchoring structure and construction method
CN208363404U (en) A kind of prefabricated panel and its connection structure
CN205348592U (en) Alternately precast concrete breast portion reinforcing bar communicates dedicated connection spare
CN209384395U (en) A kind of RCS combination frame beam-column connection
CN111173129A (en) A kind of prestressed assembly frame structure and construction method
CN103967129B (en) The coupled column assembled beam frame of built-in pipe high-strength concrete stem stem and constructional method thereof
JP4423644B2 (en) Hollow precast pillar
CN118390563B (en) Beam-slab pile foundation structure and construction method thereof
CN108487457A (en) A kind of prefabricated assembled frame column of curved scissors separate type and its construction method
JP7529596B2 (en) Joint structure between steel pipe concrete column and steel beam and its construction method
CN212175443U (en) Steel-concrete box girder combining section
CN111945765B (en) Emergency building prefabricated strip foundation
CN116905340B (en) A prefabricated segmental assembled hollow steel pipe-reinforced concrete composite bridge pier
CN108252215A (en) Connection structure of the board-like Suo-tower of trepanning and preparation method thereof
CN116427569A (en) Joint structure and construction method of prefabricated concrete self-resetting energy-dissipating column feet
CN111287457B (en) Construction method of anchoring tower barrel section

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16804217

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2987405

Country of ref document: CA

WWE Wipo information: entry into national phase

Ref document number: MX/A/2017/015201

Country of ref document: MX

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 2016804217

Country of ref document: EP