WO2017018765A1 - 용융로의 미분탄 취입장치 및 그 취입방법 - Google Patents

용융로의 미분탄 취입장치 및 그 취입방법 Download PDF

Info

Publication number
WO2017018765A1
WO2017018765A1 PCT/KR2016/008111 KR2016008111W WO2017018765A1 WO 2017018765 A1 WO2017018765 A1 WO 2017018765A1 KR 2016008111 W KR2016008111 W KR 2016008111W WO 2017018765 A1 WO2017018765 A1 WO 2017018765A1
Authority
WO
WIPO (PCT)
Prior art keywords
pulverized coal
burner
melting furnace
blowing
dust
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/KR2016/008111
Other languages
English (en)
French (fr)
Other versions
WO2017018765A8 (ko
Inventor
이창형
정병환
김태훈
조일현
허금식
최응수
배진찬
강태인
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Posco Holdings Inc
Original Assignee
Posco Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from KR1020150106152A external-priority patent/KR101739861B1/ko
Application filed by Posco Co Ltd filed Critical Posco Co Ltd
Priority to EP16830798.1A priority Critical patent/EP3330387B1/en
Priority to CN201680054310.9A priority patent/CN108026596A/zh
Publication of WO2017018765A1 publication Critical patent/WO2017018765A1/ko
Publication of WO2017018765A8 publication Critical patent/WO2017018765A8/ko
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/0006Making spongy iron or liquid steel, by direct processes obtaining iron or steel in a molten state
    • C21B13/0013Making spongy iron or liquid steel, by direct processes obtaining iron or steel in a molten state introduction of iron oxide into a bath of molten iron containing a carbon reductant
    • C21B13/002Reduction of iron ores by passing through a heated column of carbon
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D99/00Subject matter not provided for in other groups of this subclass
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/0066Preliminary conditioning of the solid carbonaceous reductant
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B5/00Making pig-iron in the blast furnace
    • C21B5/001Injecting additional fuel or reducing agents
    • C21B5/003Injection of pulverulent coal
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B5/00Making pig-iron in the blast furnace
    • C21B5/006Automatically controlling the process

Definitions

  • the present invention relates to a pulverized coal blowing device for blowing pulverized coal over the charges of a melting furnace and a blowing method thereof.
  • a dust burner is a facility that collects iron ore dust and coal dust in a gas generated from a melting furnace in a hot cyclone, burns it, and re-blows it to the upper part of a melting furnace internal charge (Bed).
  • the dust generated in the smelter flows into the hot cyclone, which is a vibration suppression system, is separated by the principle of cyclone and flows into the lower pipe, and is transferred into the furnace by injection nitrogen inside the dust burner, and then at the dust burner tip. The oxygen is blown into the furnace as it is burned.
  • the hot cyclone which is a vibration suppression system
  • the amount of carbon monoxide (CO) gas which is a reducing gas, is increased due to carbon combustion at the end of the dust burner, and the temperature of the melting part is increased due to the heat of combustion generated during the combustion reaction. Occurs.
  • a dust burner for decomposing and burning dust and dry gas generated in the melting furnace is installed at the dome part of the melting furnace.
  • the position of the dust burner is positioned too close to the charge bed, the flame of the dust burner is charged with the charge bed. Too much dust contacting the top surface of the At the same time there is a risk of damage to the dust burner.
  • the position of the dust burner is located too far from the charge bed, most of the heat generated from the dust burner is not used to heat up the charge bed, but is used to heat up the dome part, so that the temperature of the stem is unnecessarily increased. On the other hand, there is a problem that the operating efficiency of the melting furnace is lowered.
  • Pulverized coal injection device of smelting furnace in which pulverized coal is injected from the upper part of the smelting furnace to improve the degree of oxidation of reducing gas generated in the smelting furnace while improving the ore reduction rate, thereby reducing the specific gravity of carbon dioxide in the smelting furnace and increasing the proportion of carbon monoxide.
  • the pulverized coal blowing oxygen can be blown through the pulverized coal blowing burner to provide calories to the top of the charge bed of the melting furnace.
  • the pulverized coal injection device of a smelting furnace includes: at least one pulverized coal injection burner installed at an upper portion of a charge of the melting furnace; And it may include a control unit provided to control the blowing amount of the pulverized coal supplied to the pulverized coal blowing burner.
  • the pulverized coal injection burner may be supplied with pulverized coal in connection with pulverized coal production equipment, or pulverized coal is supplied with pulverized coal distribution valves installed between the pulverized coal outlet installed in the pulverized coal production equipment and a melting furnace.
  • It may further include a dust burner provided at least one or more on the lower side of the pulverized coal injection burner to the top of the charge of the melting furnace and optionally additionally pulverized pulverized coal.
  • the dust burner may be additionally blown with the dust in the melting furnace in conjunction with the pulverized coal manufacturing equipment, or in connection with the pulverized coal distribution valve installed between the tuyere installed in the melting furnace.
  • the pulverized coal distribution valve may include a pulverized coal supply pipe, each of which is provided with a manual valve and an orifice for adjusting the blowing amount of pulverized coal.
  • the pulverized coal supply pipe may be a structure in which three sides are installed which are remotely controlled by the controller.
  • the three-way side may have a structure in which an inert gas is blown in order to prevent clogging of the pulverized coal supply pipe when the pulverized coal is not blown.
  • the pulverized coal injection burner may further include an ejector for injecting an inert gas into the pulverized coal which is installed and supplied at a rear end thereof.
  • the pulverized coal injection burner is installed on the outside thereof so as to prevent thermal damage to the tip of the pulverized coal injection burner. It may further comprise a blown water pipe.
  • the cooling water pipe may further include an auxiliary pipe through which an inert gas may be blown together with or without the water angle.
  • the pulverized coal injection burner may further include an inner pipe inserted into the inner pulverized coal to secure the flow rate of the pulverized coal injected.
  • the pulverized coal injection burner may have a structure in which oxygen is contacted with pulverized coal passing through the inner pipe by forming one or more oxygen supply holes therein.
  • the inner pipe may have a structure in which one or more supports are installed at intervals outside thereof for assembly.
  • the ejector may have a structure in which a gas supply pipe is connected to the pulverized coal inlet pipe so that an inert gas is injected into the pulverized coal supplied.
  • the pentagonal water pipe may have a structure in which a pentagonal inlet pipe and a pentagonal outlet pipe connected to the pulverized coal injection burner are separately installed in a pipe installed in the dust burner.
  • the pulverized coal injection method of a smelting furnace includes: injecting pulverized coal into an upper portion of a charge of a smelter using a pulverized coal blowing burner installed in the melting furnace; And, it may include a control step of controlling the blowing environment of the pulverized coal.
  • the pulverized coal blowing step of blowing the pulverized coal into the upper part of the melting furnace charge through the pipe and the pulverized coal blowing burner installed as described above may be further included.
  • the pulverized coal may be supplied in connection with the pulverized coal production equipment, or the pulverized coal may be supplied in connection with the pulverized coal distribution valve installed between the pulverized coal production equipment and the tuyere installed in the melting furnace.
  • the pulverized coal injection burner installation step may further include a dust burner provided at least one lower side of the pulverized coal injection burner to the top of the charge of the melting furnace and optionally additionally blow the pulverized coal.
  • the dust burner may be selectively blown with the dust in the melting furnace in conjunction with the pulverized coal distribution valves installed in connection with the pulverized coal manufacturing equipment or installed in the melting furnace.
  • a pentagonal water pipe is installed in the pulverized coal injection burner, and an auxiliary pipe is connected to the pentagonal water pipe to prevent pulverized coal injection and leakage of nitrogen when the cooling water leaks.
  • Pulverized coal can be blown through one process.
  • a control unit for controlling the amount of pulverized coal is installed, and the total amount of the blast furnace is controlled by controlling the rotational speed of the rotary feeder included in the pulverized coal supply facility, thereby blowing into the upper part of the furnace charges. It is possible to control the blowing amount of the pulverized coal.
  • the presence or absence of pulverized coal injection of the dust burner may be calculated through a flow meter by calculating the amount of carbon dioxide in the excess gas of the melting furnace.
  • the pulverized coal blowing device of the melting furnace the reducing furnace for providing reduced iron, and the reducing iron is connected to the reducing furnace is charged, a charge bed made of charged iron and coal and carbonized char (char) is formed therein
  • a pulverized coal blowing burner which blows pulverized coal and oxygen to combust the pulverized coal is included.
  • the dust burner may be located between the charge bed and the crest, and may be located at a height of 2 m or more and 3 m or less from the surface of the charge bed.
  • the dust burner may be provided in plurality along the inner circumference of the melting furnace.
  • the pulverized coal blow burner may be located between the dust burner and the charge bed.
  • the pulverized coal injection burner may be positioned to be non-overlapping with the dust burner along the inner circumference of the melting furnace.
  • the pulverized coal injection burner may be located at a height of 1.3 m or more and 1.7 m or less from the charge bed surface.
  • Oxygen injected into the dust burner and the pulverized coal injection burner may be in a ratio of 6: 4 to 7: 3.
  • the amount of oxygen blown into the dust burner is reduced, and the amount of oxygen blown into the pulverized coal injection burner may be adjusted.
  • the amount of oxygen blown into the dust burner is increased, and the amount of oxygen blown into the pulverized coal blowing burner may be adjusted.
  • the pulverized coal injection burner may inject and combust pulverized coal, liquefied natural gas, and C fuel of any one of ce oven gas.
  • this apparatus it is easy to control the ore reduction rate of the flow furnace by controlling the gas oxidation degree when the powdered coal is blown into the charge of the melting furnace, thereby reducing the sudden fluctuation of the molten iron temperature due to the reduction rate.
  • the heat of combustion generated from the pulverized coal injection burner is transferred to the charge bed to improve the operating efficiency of the melting furnace, thereby increasing the amount of molten iron and reducing the reducing agent ratio.
  • FIG. 1 is a schematic diagram showing a pulverized coal blowing device of a melting furnace according to the present embodiment.
  • FIG. 2 is a schematic view showing an arrangement of the pulverized coal injection burner according to the present embodiment.
  • FIG 3 is a schematic view showing the structure of the pulverized coal injection device according to the present embodiment.
  • FIG 4 is an enlarged schematic view illustrating the inside of the pulverized coal injection burner according to the present embodiment.
  • Fig. 5 is a schematic view showing the internal lance of the pulverized coal injection burner according to the present embodiment.
  • FIG. 6 is a schematic view showing an ejector structure of the pulverized coal injection device according to the present embodiment.
  • FIG. 7 is a schematic diagram showing a condensed water pipe configuration of the pulverized coal injection device according to the present embodiment.
  • 8 is a flowchart illustrating a process of the pulverized coal injection method according to the present embodiment.
  • FIG. 9 is a view schematically showing a pulverized coal blowing apparatus of a melting furnace according to an embodiment of the present invention.
  • FIG. 10 is a view schematically showing a melting furnace according to an embodiment of the present invention.
  • FIG. 11 is an enlarged view of a portion 'A' of FIG. 2.
  • FIG. 12 is a plan view schematically illustrating a melting furnace according to an embodiment of the present invention.
  • Figure 13 is a graph showing the temperature increase rate of the charge of the charge bed of the melting furnace according to an embodiment of the present invention.
  • FIG. 14 is a graph showing the temperature rise temperature of the charge bed of the melting furnace according to an embodiment of the present invention compared with the conventional.
  • 15 is a graph showing the effect of increasing the molten iron production amount of the pulverized coal injection apparatus of the melting furnace according to an embodiment of the present invention.
  • 16 is a graph showing the effect of reducing the coal use cost of the pulverized coal blowing apparatus of the melting furnace according to an embodiment of the present invention.
  • FIG. 1 is a schematic diagram showing a pulverized coal blowing device of a melting furnace according to the present embodiment.
  • FIG. 2 is a schematic view showing an arrangement of the pulverized coal injection burner according to the present embodiment.
  • the pulverized coal blowing device for blowing pulverized coal into the upper part of the melting furnace charge is installed with the pulverized coal blowing burner 20 on the dust burner 10 installed in the melting furnace 1 to melt the pulverized coal. Blow on the top of the charge.
  • the pulverized coal injection device includes a dust burner 10, a pulverized coal injection burner 20, a pulverized coal distribution valve 30, and a controller 40.
  • the dust burner 10 is installed at least one along the circumferential direction of the melting furnace 1 so that the dust can be collected and burned and re-injected into the upper part of the melting furnace 1, and the pulverized coal blowing burner One or more (20) is installed along the circumferential direction of the furnace (1) in the upper side of the dust burner (10) so as to blow the pulverized coal into the upper portion of the charge of the furnace (1).
  • the gas oxidation degree can be controlled through the pulverized coal blown by blowing pulverized coal into the upper part of the smelting furnace charge through the pulverized coal blowing burner 20, thereby preventing the deterioration of the furnace heat of the smelting furnace 1 due to the reduction of the reduction rate.
  • a combustion medium such as LNG may be selectively blown together with the pulverized coal.
  • the dust burner 10 may be connected to the pulverized coal distribution valve 30 through a separate pipe to blow the pulverized coal into the upper part of the melting furnace charge.
  • the pulverized coal distribution valve 30 is supplied with pulverized coal from the pulverized coal production facility 2 so as to supply an appropriate amount of pulverized coal to the pulverized coal injection burner 20, and the control unit 40 supplies the pulverized coal distribution valve 30. Is electrically connected to) to control the amount of powdered coal supplied to the powdered coal blowing burner 20.
  • the pulverized coal injection device comprises the pulverized coal distribution valve 30.
  • the pulverized coal is supplied to the pulverized coal injection burner 20 through the pulverized coal, and the blowing amount of the pulverized coal may be controlled through the control unit 40 in the process of supplying the pulverized coal.
  • the pulverized coal injection burner 20 is supplied with pulverized coal in association with the pulverized coal production facility 2, or pulverized coal distribution valve 30 installed between the pulverized coal production facility 2 and the tuyere 50 installed in the melting furnace 1.
  • Coal dust can be supplied in conjunction with
  • the control unit 40 is connected to a connection line to the pulverized coal manufacturing facility 2 and the pulverized coal injection burner 20 or the dust burner 10 or to the pulverized coal distribution valve between the pulverized coal production facility 2 and the tuyere 50 ( 30 may be controlled in conjunction with coal dust.
  • At least one dust burner 10 may be further provided on the lower side of the pulverized coal blowing burner 20 and optionally further blows pulverized coal into the upper portion of the melting furnace.
  • the dust burner 10 is linked with the pulverized coal production facility 2 or selectively connected with the dust in the smelting furnace 1 in connection with the pulverized coal distribution valve 30 installed between the tuyere 50 installed in the melting furnace 1.
  • the fine powder can be further blown with.
  • the pulverized coal injection burners 20 are disposed at 90 intervals along the circumferential direction of the melting furnace 1 so as to form the same direction as the installation position of the dust burner 10, and the upper portion at the position of the dust burner 10. It can be installed at a height of 2.6m-3.2m.
  • the pulverized coal distribution valve 30 is to supply the pulverized coal and oxygen to the tuyere 50 of the melting furnace through a pipe, the branched pulverized coal pipe blown into the tuyere 50 bifurcated into the dust burner 10 The pulverized coal can be blown into the upper part of the melting furnace charge through the dust burner 10 by connecting to.
  • FIG 3 is a schematic view showing the structure of the pulverized coal injection device according to the present embodiment.
  • the pulverized coal distribution valve 30 is made of pulverized coal.
  • the pulverized coal supply pipe 60 may be provided with a manual valve 61 and an orifice 62 for adjusting the blowing amount, respectively.
  • the orifice 62 allows the amount of the pulverized coal supplied from the pulverized coal distribution valve 30 to be adjusted so that the amount of the pulverized coal injected into the melting furnace 1 can be adjusted.
  • the pulverized coal supply pipe 60 is provided with a triangular 63 which is remotely controlled by the control unit 40, the triangular 63 is a blockage of the pulverized coal supply pipe 60 when the pulverized coal is not blown.
  • the inert gas may be a structure.
  • the inert gas may include nitrogen.
  • the pulverized coal Since the pulverized coal should be selectively blown only when the oxidation degree of the gas generated in the smelting furnace 1 is higher than the reference value, the pulverized coal is installed by installing the three-way valve 63 which is automatically controlled remotely by the controller 40. If not blown, allow nitrogen to be blown into the pipe.
  • the pulverized coal injection burner 20 further includes an ejector 70 which injects an inert gas into the pulverized coal which is installed at the rear end thereof, and the ejector 70 prevents the blockage of the pipe. Nitrogen is spouted at high speed.
  • the pulverized coal injection burner 20 further includes a coolant pipe 80 installed at an outer side thereof to prevent thermal damage of the tip of the pulverized coal injection burner 20, wherein the coolant pipe 80 is further provided. It may further include an auxiliary pipe 81 through which an inert gas may be blown together with the angle of water or independently.
  • the cooling water pipe 80 and the auxiliary pipe 81 installed around the pulverized coal injection burner 20 are installed to ensure the safety of the facility.
  • nitrogen can be blown into the water supply pipe 80 through the auxiliary pipe 81 while automatically preventing the injection of pulverized coal.
  • FIG. 4 is an enlarged schematic view illustrating the inside of the pulverized coal injection burner according to the present embodiment.
  • Fig. 5 is a schematic view showing the internal lance of the pulverized coal injection burner according to the present embodiment.
  • the pulverized coal injection burner 20 may further include an inner pipe 21 is inserted into it to ensure the flow rate of the pulverized coal injected therein, the pulverized coal injection
  • One or more oxygen supply holes 22 are formed inside the burner 20 so that oxygen is in contact with the pulverized coal passing through the inner pipe 21.
  • the inner pipe 21 is installed at least one support 23 at intervals on the outside for the assembly, it can facilitate the assembly of the inner pipe 21 through the support 23.
  • the pulverized coal injection burner 20 has an inner pipe 21 having a reduced diameter inside thereof, so that the flow rate of pulverized coal passing through the pulverized coal injection burner 20 is increased, thereby making pulverized coal and oxygen easier. Make contact.
  • FIG. 6 is a schematic view showing an ejector structure of the pulverized coal injection device according to the present embodiment.
  • the ejector 70 has a structure in which a gas supply pipe 72 is connected to a pulverized coal inlet pipe 71 so that an inert gas is introduced into the pulverized coal supplied.
  • nitrogen is supplied through the gas supply pipe 72 at a high speed as if pumped.
  • FIG. 7 is a schematic diagram showing a condensed water pipe configuration of the pulverized coal injection device according to the present embodiment.
  • the pentagonal water pipe 80 is a coolant inlet pipe 80A and a coolant outlet which are connected to the pulverized coal injection burner 20 in a pipe installed in the dust burner 10.
  • the pentagonal water pipe of the pulverized coal injection burner 20 newly installed in the cooling water pipe of the dust burner 10 previously installed is additionally installed.
  • the angle inlet pipe 80A and the angle outlet outlet pipe 80B are respectively installed around the pulverized coal injection burner 20, and the dust burner 10
  • the angle inlet pipe 80a and the angle inlet pipe 80A of the pulverized coal injection burner 20 are connected to each other, and the angle angle outlet pipe 80b of the dust burner 10 and the powdered coal injection burner 20 are connected to each other.
  • the angle outlet pipe 80B is connected.
  • the pentagonal water pipe 80 is installed to prevent thermal damage to the distal end of the pulverized coal injection burner 20, and it is possible to secure facility stability by injecting the pentagonal water.
  • FIG. 8 is a flowchart illustrating a process of the pulverized coal injection method according to the present embodiment.
  • the pulverized coal injection method of the smelting furnace includes: blowing pulverized coal into the upper portion of the charge of the smelting furnace using a pulverized coal blowing burner 20 installed in the smelting furnace 1; And, it may include a control step of controlling the blowing environment of the pulverized coal.
  • the step of blowing the pulverized coal and the control step the pipe installation step (S1) for connecting the dust burner (10) using a separate pipe to blow the pulverized coal into the upper portion of the furnace charge; Pulverized coal injection burner installation step (S2) for installing the pulverized coal injection burner 20, which is the same as the dust burner 10 disposed on the dust burner (10); And pulverized coal blowing step (S3) for blowing the pulverized coal to the upper portion of the blast furnace charge through the pipe and the pulverized coal blowing burner 20 installed as described above.
  • the method for blowing pulverized coal is to blow pulverized coal into an upper portion of the charging material of the smelting furnace 1, and to install the pipe in the dust burner 10 in order to use the dust burner 10, and to independently melt the furnace.
  • the pulverized coal is supplied in connection with the pulverized coal manufacturing equipment 2, or the pulverized coal powder installed between the pulverized coal manufacturing equipment 2 and the tuyere 50 installed in the melting furnace 1.
  • Pulverized coal may be supplied in association with defecation 30.
  • the pulverized coal injection burner installation step (S2) to the top of the charge of the melting furnace (1) It may further include a dust burner 10 provided at least one or more on the lower side of the pulverized coal blowing burner 20 and optionally additionally blowing pulverized coal.
  • the dust burner 10 is connected to the pulverized coal manufacturing facility 2 or in conjunction with the pulverized coal distribution valve 30 installed between the tuyere 50 installed in the melting furnace 1. The pulverized coal can be further blown into the melting furnace 1 selectively with dust.
  • the pulverized coal is blown through the dust burner 10 by branching the pulverized coal pipe blown into the tuyere 50 of the smelting furnace 1 in the pipe installation step (S1) to the dust burner 10.
  • the pulverized coal may be blown through the dust burner 10 by installing the pulverized coal blowing pipe in the pulverized coal distribution valve 30 supplying the pulverized coal in the pipe installation step (S1) and connecting the dust burner 10 to the dust burner 10.
  • the pulverized coal can be blown in the upper part of the charge of the melting furnace 1 using the dust burner 10 as described above.
  • the pulverized coal injection burner 20 may be installed at intervals of 90 ° along the circumferential direction of the melting furnace 1 at a height of 2.6m-3.2m above the dust burner 10. have.
  • the pulverized coal injection burner 20 is disposed along the circumferential direction of the melting furnace 1 at the same position as the dust burner 10 while having a height difference in the upper portion of the dust burner 10.
  • a coolant pipe 80 is installed in the pulverized coal injection burner 20, and an auxiliary pipe 81 is connected to the coolant pipe 80, so that pulverized coal is blown when the coolant is leaked. And nitrogen can be blown back up.
  • the pentagonal water pipe 80 and the auxiliary pipe 81 installed around the pulverized coal injection burner 20 are installed to ensure the safety of the facility.
  • the pulverized coal blowing burner 20 is directly blown.
  • the control unit 40 for controlling the amount of pulverized coal is installed is installed through the control of the rotation speed of the rotary feeder included in the pulverized coal supply equipment to the entire melting furnace (1) By controlling the blowing amount, the blowing amount of the pulverized coal blown into the upper part of the melting furnace charge can be controlled.
  • the presence or absence of pulverized coal injection of the dust burner 10 is calculated based on the change amount of carbon dioxide in the excess gas of the melting furnace 1 through a flow meter. It can be measured.
  • the oxidation degree when the oxidation degree rapidly increases, the oxidation degree can be kept constant by increasing the amount of fine coal blown to supplement the carbon monoxide content.
  • the pulverized coal injection device of the melting furnace includes a reducing furnace 7 and a melting furnace 1.
  • the pulverized coal blowing device of the melting furnace may include other devices as necessary.
  • Iron ore is charged and reduced in the reduction furnace 7.
  • the iron ore charged into the reduction furnace 7 is made of reduced iron while passing through the reduction furnace 7 after being pre-dried.
  • the reduction furnace 7 is a layered layer type reduction furnace, and receives a reducing gas from the melting furnace 1 to form a layered layer therein.
  • the smelting furnace 1 is connected to the reduction furnace 7, and the reduced iron produced in the reduction furnace 7 is supplied, and coal briquettes or coal produced in the coal briquette manufacturing apparatus may be charged.
  • the reduced iron and coal charged into the melting furnace 1 and the char charred form a charge bed 3 inside the melting furnace 1.
  • a cuff 9 is formed in the upper part of the smelting furnace 1.
  • the cuff 9 is formed above the charge bed 3, is formed in a larger space than other parts of the melting furnace 1, and a high temperature reducing gas exists.
  • the coal briquettes are charged to the dome part 9 of the melting furnace 1, and then rapidly heated to fall to the lower portion of the melting furnace 1.
  • the steam generated by the pyrolysis reaction of the coal briquettes moves to the lower part of the melting furnace 1 to react with the exothermic reaction with oxygen supplied through the tuyere 50.
  • the coal briquettes can be used as a heat source for keeping the melting furnace 1 at a high temperature.
  • provides air permeability, so that a large amount of gas generated in the lower part of the melting furnace 1 and the reduced iron supplied from the reducing furnace 7 can pass through the charge bed 3 in the melting furnace 1 more easily and uniformly. have.
  • a bulk coal material or coke may be charged into the melting furnace 1 as necessary.
  • An air vent 50 is provided on the outer wall of the melting furnace 1 to blow in oxygen. Oxygen is blown into the charge bed 3 to form the combustion zone 8.
  • the coal briquettes may be burned in the combustion zone 8 to generate a reducing gas.
  • the melting furnace 1 includes a dust burner 10 and a pulverized coal blowing burner 20.
  • the dust burner 10 blows oxygen into the cuff 9 to decompose and burn dust and dry gas generated in the melting furnace 1.
  • the dust burner 10 is located between the charge bed 3 and the slit 9, and may be provided in plurality along the inner circumference of the melting furnace 1.
  • the dust burner 10 is at a constant distance from the top surface of the charge bed 3, i.e. about
  • It may be installed at a height of 2 m or more and about 3 m or less, and if the position of the dust burner 10 is placed too close to the charge bed 3, the flame of the dust burner 10 will rise to the top surface of the charge bed 3. The excessive contact with the dust increases the risk of dust dust burner 10 being damaged at the same time.
  • the dust burner 10 is positioned at least about 2 m and about 3 m below the surface of the charge bed 3, in which case most of the heat generated by the dust burner 10 is stored in the charge bed 3.
  • the temperature of the dome 9 may be unnecessarily raised while the temperature of the dome 9 is unnecessarily increased while not being used to raise the temperature, and the operating efficiency of the melting furnace 1 may be lowered.
  • pulverized coal between the dust burner 10 and the charge bed 3 Position the blow burner 20.
  • the pulverized coal blowing burner 20 may be located at a height of about 1.3 m or more and about 1.7 m or less from the charge bed 3 surface.
  • the pulverized coal injection burner 20 is positioned at a position where the flame of the pulverized coal injection burner 20 can supply sufficient heat to the surface of the charge bed 3 without directly contacting the charge bed 3. If the pulverized coal blow burner 20 is too far from the surface of the charge bed 3, it will not effectively heat the charge bed 3, and conversely, the pulverized coal blow burner 20 will be applied to the charge bed 3 surface. If too close, there may be a problem that the pulverized coal injection burner 20 is broken.
  • FIG. 3 is an enlarged view of a portion 'A' of FIG. 2.
  • the pulverized coal injection burner 20 injects pulverized coal 5 and oxygen 6 into the melting furnace 1 to combust the pulverized coal 5. At this time, the generated combustion heat of the pulverized coal injection burner 20 is transmitted to the charge bed 3 by the combustion flame 11 to sublimate the charge bed 3.
  • the pulverized coal injection burner 20 may be a pulverized coal, liquefied natural gas, and the fuel of any one of the (ke) Oven Gas to blow and burn.
  • the dust burner 10 may be provided in plurality along the inner circumference of the melting furnace 1, and as shown in FIG. Four dust burners 10 may be installed.
  • the pulverized coal injection burner 20 may be positioned so as not to overlap the dust burner 10 along the inner circumference of the melting furnace 1. That is, the pulverized coal injection burner 20 may be located between the dust burners 10 in the circumferential direction, and may be provided as four. If the pulverized coal injection burner 20 is not located between the dust burners 10, the dust burner 10 located above the pulverized coal injection burner 20 may be damaged by the combustion flame of the pulverized coal injection burner 20. have.
  • the oxygen blown into the dust burner 10 and the pulverized coal injection burner 20 is about
  • the oxygen injection ratio management of the pulverized coal injection burner 20 is based on the temperature of the dome 9.
  • the temperature of the dome part 9 rises by about 1070 degrees or more, the amount of oxygen of the dust burner 10 is reduced, and the amount of oxygen of the pulverized coal injection burner 20 is increased, so that the heat of combustion of the pulverized coal injection burner 20 is generated in the charge bed 3. So you can go more.
  • the temperature of the dome part 9 falls below about 1030 degrees, the amount of oxygen of the pulverized coal injection burner 20 is decreased, and the amount of oxygen of the dust burner 10 is increased to generate combustion heat of the dust burner 10 to generate gas from the dome part 9 gas. Allow it to warm up further.
  • Figure 13 is a graph showing the temperature increase rate of the charge bed of the melting furnace according to an embodiment of the present invention compared to the conventional
  • Figure 14 is a conventional diagram showing the temperature rise of the charge bed of the charge bed of the melting furnace according to an embodiment of the present invention
  • 15 is a graph showing a comparison with the conventional molten iron production increase effect of the pulverized coal injection device of the melting furnace according to an embodiment of the present invention
  • Figure 8 is a pulverized coal of the melting furnace according to an embodiment of the present invention It is a graph showing the effect of reducing the coal consumption cost of the blower.
  • the actual simulation test operation was carried out by lowering the distance between the dust burner 10 and the charge bed 3 of the melting furnace 1 from 1.5 m to 1.5 m.
  • the rate of heat raising the dome portion 9 among the heat of combustion generated in the dust burner 10 and the pulverized coal blowing burner 20 decreases, while the temperature of the charge bed 3 is increased.
  • the proportion of heat increased from about 22% to about 31%.
  • the temperature rise of the charge bed 3 increased from about 210 degrees to about 340 degrees.
  • the increase in silver content of the charge bed 3 indicates an improvement in operation performance, and as shown in FIG. 15, daily charter production increased from about 5,200 tons to about 5,500 tons, and on the contrary, coal use costs (fuel costs) ), As shown in FIG. 16, it can be seen that the current is lowered from about 860 kg / tp to about 820 kg / tp.
  • the flame of the dust burner is the top of the charge bed. Contact with the surface and dust is generated and the dust burner It can prevent damage.
  • the supply amount can be kept constant.
  • the heat of combustion generated from the pulverized coal injection burner is transferred to the charge bed to improve the operating efficiency of the melting furnace, thereby increasing the amount of molten iron and reducing the reducing agent ratio.
  • this apparatus it is easy to control the ore reduction rate of the flow furnace by controlling the gas oxidation degree when the fine coal is charged in the upper part of the melting furnace, thereby reducing the sudden rise and fall of the molten iron temperature due to the reduction rate.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Environmental & Geological Engineering (AREA)
  • Manufacture Of Iron (AREA)

Abstract

용융로의 장입물 상부에서 미분탄을 취입함으로써 용융로에서 발생하는 환원가스의 산화도를 개선하면서 광석 환원율을 향상시켜 용융로 내의 이산화탄소 비중은 낮춤과 동시에 일산화탄소 비중을 높여줄 수 있도록, 용융로의 장입물 상부에 적어도 하나 이상 설치되는 미분탄 취입 버너; 및 상기 미분탄 취입 버너로 공급되는 미분탄의 취입량을 제어하도록 제공된 제어부를 포함하는 용융로의 미분탄 취입장치 및, 상기 용융로에 설치된 미분탄 취입 버너를 이용하여 미분탄을 취입하는 단계;와 상기 미분탄의 용융로 취입 환경을 제어하는 제어단계를 포함하는 미분탄 취입방법을 제공한다.

Description

【명세서】
【발명의 명칭】
용융로의 미분탄 취입장치 및 그 취입방법
【기술분야】
본 기재는 용융로의 장입물 상부에 미분탄을 취입하는 미분탄 취입장치 및 그 취입방법에 관한 것이다.
【배경기술】
일반적으로 더스트 버너 (Dust Burner)는 용융로에서 발생되는 가스 중의 철광석 더스트, 석탄 더스트를 핫 사이클론 (Hot Cyclone)에서 포집하고, 이를 연소시켜 용융로 내부 장입물 (Bed) 상부로 재취입하는 설비이다.
용융로에서 발생된 더스트는 제진설비인 핫 사이클론으로 유입된 후, 사이클론의 원리에 의하여 분리되어 하부 배관으로 유입되고, 상기 더스트 버너 내부의 인젝션 (Injection) 질소에 의해 노 내로 이송된 후 더스트 버너 선단부에서 취입되는 산소를 만나 연소되면서 노 내로 재취입된다.
상기와 같이 더스트 버너 단부에서의 탄소 (Carbon) 연소현상으로 환원가스인 일산화탄소 (CO) 가스의 발생량이 증가하고, 연소반웅 중 발생하는 연소열로 인해 용융로 듬 (Dome)부의 온도를 상승시켜 주는 효과가 발생한다.
그러나, 용융로에 더스트 재취입량이 감소하거나 더스트 중 탄소 함량이 감소하는 경우, 더스트 중 탄소를 연소시킬 만큼의 필요 산소량 이상으로 산소가 과잉 취입됨으로써 융융로의 장입물로부터 발생되어 상승하는 가스 중 일산화탄소를 연소시키게 되고, 이에 따라 환원가스 중 이산화탄소 (C02) 함량이 증가되어 유동로의 광석 환원율이 저하되는 문제가 있었다.
또한, 이산화탄소가 단시간내에 급속히 증가할 경우, 환원율이 감소하여 용선 온도의 감소를 유발하는 문제도 있었다.
또한, 용융로의 돔부에는 용융로 내에서 발생되는 분진류 및 건류 가스를 분해 연소시키는 더스트 버너가 설치되는데, 더스트 버너의 위치가 장입물 베드와 지나치게 근접하게 위치하게 되면, 더스트 버너의 화염이 장입물 베드의 상부 표면을 치면서 접촉하여 분진이 지나치게 많이 발생하는 동시에 더스트 버너가 손상될 위험이 있다. 또한, 더스트 버너의 위치가 장입물 베드와 지나치게 멀리 위치하게 되면, 더스트 버너에서 발생하는 열량의 대부분이 장입물 베드를 승온하는데 사용되지 못하고 돔부를 승온하는데 사용되어, 듬부의 온도가 불필요하게 상승하는 한편, 용융로의 조업 효율이 저하되는 문제점이 있다.
【발명의 상세한 설명】
【기술적 과제】
용융로의 장입물 상부에서 미분탄을 취입함으로써 용융로에서 발생하는 환원가스의 산화도를 개선하면서 광석 환원율을 향상시켜 용융로 내의 이산화탄소 비중은 낮춤과 동시에 일산화탄소 비중을 높여줄 수 있도록 된 용융로의 미분탄 취입장치 및 그 취입방법을 제공한다.
또한, 용융로의 더스트 버너와 용융로의 장입물 베드 사이에 미분탄을 연소시킬 수 있는 미분탄 취입 버너를 설치함으로써, 미분탄 취입 버너를 통해 미분탄과 산소를 취입하여 용융로의 장입물 베드 상부에 열량을 제공할 수 있다.
【기술적 해결방법】
용융로의 미분탄 취입장치는, 용융로의 장입물 상부에 적어도 하나 이상 설치되는 미분탄 취입 버너; 및 상기 미분탄 취입 버너로 공급되는 미분탄의 취입량을 제어하도록 제공된 제어부를 포함할 수 있다.
상기 미분탄 취입 버너는, 미분탄 제조설비와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비와 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 미분탄이 공급될 수 있다.
상기 용융로의 장입물 상부로 상기 미분탄 취입 버너의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너를 더 포함할 수 있다.
상기 더스트 버너는 미분탄 제조설비와 연계되거나 또는, 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 상기 용융로에 더스트와 함께 선택적으로 미분탄을 추가 취입할 수 있다.
상기 미분탄 분배변은 미분탄의 취입량을 조절하는 수동 밸브와 오리피스가 각각 설치된 미분탄 공급 배관을 포함할 수 있다. 상기 미분탄 공급 배관은 상기 제어부에 의해 원격 자동 제어되는 삼방변이 설치된 구조일 수 있다.
상기 삼방변은 미분탄 미취입시 상기 미분탄 공급 배관의 막힘을 방지하기 위하여 불활성가스를 취입하는 구조일 수 있다.
상기 미분탄 취입 버너는 그 후단부에 설치되어 공급되는 미분탄에 불활성가스를 투입하는 이젝터를 더 포함할 수 있다.
상기 미분탄 취입 버너는 그 외측에 설치되어 미분탄 취입 버너 선단부의 열 손상을 방지하기 위해 넁각수가. 취입되는 넁각수 배관을 더 포함할 수 있다.
상기 냉각수 배관은 넁각수와 함께 또는 독립적으로 불활성가스가 취입될 수 있는 보조 배관을 더 포함할 수 있다.
상기 미분탄 취입 버너는 그 내측에 삽입되어 취입되는 미분탄의 유속을 확보할 수 있도록 된 인너 파이프를 더 포함할 수 있다.
상기 미분탄 취입 버너는 그 내측에 하나 이상의 산소 공급홀이 형성되어 상기 인너 파이프를 지나는 미분탄에 산소가 접촉되는 구조일 수 있다.
상기 인너 파이프는 조립을 위해 그 외측에 간격을 두고 하나 이상의 지지대가 설치된 구조일 수 있다.
상기 이젝터는 공급되는 미분탄에 불활성가스가 투입될 수 있도록 미분탄 유입관에 가스 공급관이 연결설치된 구조일 수 있다.
상기 넁각수 배관은 상기 더스트 버너에 설치된 배관에 상기 미분탄 취입 버너와 연결되는 넁각수 인렛 배관 및 넁각수 아웃렛 배관이 별도로 설치된 구조일 수 있다.
용융로의 미분탄 취입방법은, 용융로의 장입물 상부로, 상기 용융로에 설치된 미분탄 취입 버너를 이용하여 미분탄을 취입하는 단계; 및, 상기 미분탄의 용융로 취입 환경을 제어하는 제어단계를 포함할 수 있다.
상기 미분탄을 취입하는 단계와 제어단계는, 미분탄을 용융로 장입물의 상부에 취입하기 위하여 별도의 배관을 이용하여 더스트 버너와 연결하는 배관 설치단계; 상기 더스트 버너 상부에 더스트 버너와 동일 배치되는 미분탄 취입 버너를 설치하는 미분탄 취입 버너 설치단계; 및 상기와 같이 설치된 배관 및 미분탄 취입 버너를 통해 용융로 장입물 상부로 미분탄을 취입하는 미분탄 취입단계를 더 포함할 수 있다.
상기 미분탄 취입 버너 설치단계에서 미분탄 제조설비와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비와 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 미분탄이 공급될 수 있다.
상기 미분탄 취입 버너 설치단계에서 용융로의 장입물 상부로 상기 미분탄 취입 버너의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너를 더 포함할 수 있다.
상기 미분탄 취입단계에서 상기 더스트 버너는 미분탄 제조설비와 연계되거나 또는, 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 상기 용융로에 더스트와 함께 선택적으로 미분탄을 추가 취입할 수 있다.
상기 미분탄 취입 버너 설치단계에서 상기 미분탄 취입 버너에 넁각수 배관이 설치되고, 상기 넁각수 배관에 보조 배관이 연결되어 냉각수의 누출시 미분탄 취입을 막고 질소가 백업 취입될 수 있다.
상기 용융로 장입물 상부로 미분탄을 취입하는 단계에서 상기 미분탄 취입 버너로 직접 취입하거나 상기 풍구로 취입되는 미분탄 배관을 분기하여 더스트 버너로 취입하거나 상기 미분탄 취입용 배관을 통해 더스트 버너로 취입하는 것 중 어느 하나의 공정을 통해 미분탄을 취입할 수 있다.
상기 용융로 장입물 상부로 미분탄을 취입하는 단계에서 미분탄 취입량을 제어하는 제어부가 설치되어 미분탄 공급설비에 포함된 회전 공급장치의 회전수 제어를 통해 용융로 전체 취입량을 제어함으로써 용융로 장입물 상부로 취입되는 미분탄의 취입량을 제어할 수 있다.
상기 용융로 장입물 상부로 미분탄을 취입하는 단계에서 상기 더스트 버너의 미분탄 취입 유무 및 취입량은 용융로의 초과 가스 중 이산화탄소의 변화량을 기반으로 계산하여 유량계를 통해 측정할 수 있다.
한편, 용융로의 미분탄 취입장치는, 환원철을 제공하는 환원로, 및 상기 환원로에 연결되어 상기 환원철이 장입되며, 장입된 환원철과 석탄 및 건류된 촤 (Char)로 이루어진 장입물 베드가 내부에 형성되며, 상기 장입물 베드 상측에, 가스로 채워지는 듬부를 구비하는 용융로를 포함하고, 상기 용융로는, 상기 듬부 내로 산소를 취입하여 상기 용융로 내에서 발생되는 분진류 및 건류 가스를 분해 연소시키는 더스트 버너와, 상기 용융로 내로 미분탄과 산소를 취입하여 상기 미분탄을 연소시키는 미분탄 취입 버너를 포함한다.
상기 더스트 버너는 상기 장입물 베드와 상기 듬부 사이에 위치하며, 상기 장입물 베드 표면으로부터 2m 이상 3m 이하의 높이에 위치할 수 있다. 상기 더스트 버너는 상기 용융로 내부 둘레를 따라 복수로 구비될 수 있다.
상기 미분탄 취입 버너는 상기 더스트 버너와 상기 장입물 베드 사이에 위치할 수 있다.
상기 미분탄 취입 버너는 상기 용융로 내부 둘레를 따라 상기 더스트 버너와 비중첩하도록 위치할 수 있다.
상기 미분탄 취입 버너는 상기 장입물 베드 표면으로부터 1.3m 이상 1.7m 이하의 높이에 위치할 수 있다.
상기 더스트 버너와 상기 미분탄 취입 버너에 취입되는 산소는 6:4 내지 7:3의 비율로 이루어질 수 있다.
상기 듬부의 온도가 1070도 이상으로 상승하면, 상기 더스트 버너에 취입되는 산소량이 감소되고, 상기 미분탄 취입 버너에 취입되는 산소량은 증가되도록 조절될 수 있다.
상기 돔부의 온도가 1030도 이하로 저하되면, 상기 더스트 버너에 취입되는 산소량이 증가되고, 상기 미분탄 취입 버너에 취입되는 산소량은 감소되도록 조절될 수 있다.
상기 미분탄 취입 버너는 미분탄과, 액화천연가스, 및 C이 ce Oven Gas 중 어느 하나의 연료를 취입하여 연소시킬 수 있다.
【발명의 효과】
본 장치에 따르면, 용융로의 장입물 상부에 미분탄 취입시 가스산화도의 제어를 통해 유동로의 광석 환원율 제어가 용이해지고, 이에 따라 환원율 저하에 의한 반복적인 용선 온도의 급등락 현상을 감소시킬 수 있다. 또한, 용융로의 정상 조업을 지속적으로 유지함으로써 용선 품질을 안정화하고 용선 제조원가를 절감할 수 있다.
또한, 더스트 버너와 장입물 베드 표면 사이에 미분탄과 산소를 취입하여 미분탄을 연소시키는 미분탄 취입 버너를 설치함으로써, 더스트 버너의 화염이 장입물 베드의 상부 표면을 치면서 접촉하여 분진이 발생되고 더스트 버너가 손상되는 것을 방지할 수 있다.
또한, 미분탄 취입 버너를 적절한 위치에 설치함으로써, 미분탄 취입 버너의 화염이 장입물 베드에 직접 접촉하지 않으면서 장입물 베드의 표면에 층분한 열량을 공급할 수 있다.
또한, 미분탄 취입 버너에 취입되는 산소량만큼 상부의 더스트 버너에 취입되는 산소량을 줄여줌으로써, 듬부에 공급량이 일정하게 유지되도록 할 수 있다.
또한, 미분탄 취입 버너에서 발생되는 연소 열량이 장입물 베드로 전달되어 용융로의 조업 효율이 향상되어 용선 생산량이 증대되고, 환원제비가 감소되는 효과를 얻을 수 있다.
【도면의 간단한 설명】
도 1은 본 실시예에 따른 용융로의 미분탄 취입장치를 도시한 개략적인 도면이다.
도 2은 본 실시예에 따른 미분탄 취입 버너의 배치상태를 도시한 개략적인 도면이다.
도 3은 본 실시예에 따른 미분탄 취입장치의 구조를 도시한 개략적인 도면이다.
도 4는 본 실시예에 따른 미분탄 취입 버너의 내부를 확대하여 도시한 개략적인 도면이다.
도 5는 본 실시예에 따른 미분탄 취입 버너의 내부 랜스를 도시한 개략적인 도면이다.
도 6은 본 실시예에 따른 미분탄 취입장치의 이젝터 구조를 도시한 개략적인 도면이다.
도 7은 본 실시예에 따른 미분탄 취입장치의 넁각수 배관 구성을 도시한 개략적인 도면이다. 도 8은 본 실시예에 따른 미분탄 취입방법의 과정을 도시한 순서도이다.
도 9는 본 발명의 일 실시예에 따른 용융로의 미분탄 취입장치를 개략적으로 나타내는 도면이다.
도 10은 본 발명의 일 실시예에 따른 용융로를 개략적으로 나타내는 도면이다.
도 11은 도 2의 'A'부분을 확대하여 도시한 도면이다.
도 12는 본 발명의 일 실시예에 따른 용융로를 개략적으로 나타내는 평면도이다.
도 13은 본 발명의 일 실시예에 따른 용융로의 장입물 베드의 승온 비율을 기존과 비교하여 나타낸 그래프이다.
도 14는 본 발명의 일 실시예에 따른 용융로의 장입물 베드의 승온 온도를 기존과 비교하여 나타낸 그래프이다.
도 15는 본 발명의 일 실시예에 따른 용융로의 미분탄 취입장치의 용선 생산량 증대 효과를 기존과 비교하여 나타낸 그래프이다.
도 16은 본 발명의 일 실시예에 따른 용융로의 미분탄 취입장치의 석탄 사용비 감소 효과를 기존과 비교하여 나타낸 그래프이다.
【발명의 실시를 위한 형태】
이하에서 사용되는 전문용어는 단지 특정 실시예를 언급하기 위한 것이며, 본 발명을 한정하는 것을 의도하지 않는다. 여기서 사용되는 단수 형태들은 문구들이 이와 명백히 반대의 의미를 나타내지 않는 한 복수 형태들도 포함한다. 명세서에서 사용되는 "포함하는"의 의미는 특정 특성, 영역, 정수, 단계, 동작, 요소 및 /또는 성분을 구체화하며, 다른 특정 특성, 영역, 정수, 단계, 동작, 요소, 성분 및 /또는 군의 존재나 부가를 제외시키는 것은 아니다.
이하, 첨부한 도면을 참조하여, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 설명한다. 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 이해할 수 있는 바와 같이, 후술하는 실시예는 본 발명의 개념과 범위를 벗어나지 않는 한도 내에서 다양한 형태로 변형될 수 있다. 이에, 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다.
도 1은 본 실시예에 따른 용융로의 미분탄 취입장치를 도시한 개략적인 도면이다.
도 2은 본 실시예에 따른 미분탄 취입 버너의 배치상태를 도시한 개략적인 도면이다.
도 1 및 도 2에 도시된 바와 같이, 용융로 장입물 상부로 미분탄을 취입하는 미분탄 취입장치는 용융로 (1)에 설치되는 더스트 버너 (10) 상부에 미분탄 취입 버너 (20)를 설치하여 미분탄을 용융로 장입물의 상부에 취입한다.
이를 위해 상기 미분탄 취입장치는 더스트 버너 (10), 미분탄 취입 버너 (20), 미분탄 분배변 (30) 및, 제어부 (40)를 포함하여 이루어진다.
본 실시예에서 상기 더스트 버너 (10)는 더스트를 포집 및 연소시켜 용융로 (1)의 장입물 상부로 재취입할 수 있도록 용융로 (1)의 원주방향을 따라 하나 이상 설치되는 것이고, 상기 미분탄 취입 버너 (20)는 용융로 (1)의 장입물 상부에 미분탄을 취입할 수 있도록 상기 더스트 버너 (10)의 상부쪽에 용융로 (1)의 원주방향을 따라 하나 이상 설치된다.
즉, 상기 미분탄 취입 버너 (20)를 통해 용융로 장입물 상부에 미분탄을 취입함으로써 취입된 미분탄을 통해 가스 산화도를 제어할 수 있고, 이에 따라 환원율 저하에 의한 용융로 (1)의 노열 저하 현상을 예방할 수 있다. 상기 미분탄 취입 버너 (20)에 미분탄과 함께 LNG 등 연소매질이 선택적으로 같이 취입될 수도 있다.
상기 더스트 버너 (10)는 별도의 배관을 통해 상기 미분탄 분배변 (30)에 연결되어 용융로 장입물의 상부로 미분탄을 취입할 수 있다.
또한, 상기 미분탄 분배변 (30)은 상기 미분탄 취입 버너 (20)에 적정량의 미분탄을 공급할 수 있도록 미분탄 제조설비 (2)에서 미분탄을 공급받는 것이고, 상기 제어부 (40)는 상기 미분탄 분배변 (30)에 전기적으로 연결설치되어 상기 미분탄 취입 버너 (20)로 공급되는 미분탄의 취입량을 제어한다.
본 실시예에서 상기 미분탄 취입장치는 상기 미분탄 분배변 (30)을 통해 상기 미분탄 취입 버너 (20)로 미분탄을 공급하고, 이렇게 미분탄을 공급하는 과정에서 상기 제어부 (40)를 통해 미분탄의 취입량을 제어할 수 있다.
상기 미분탄 취입 버너 (20)는, 미분탄 제조설비 (2)와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비 (2)와 용융로 (1)에 설치된 풍구 (50) 사이에 설치된 미분탄 분배변 (30)과 연계되어 미분탄이 공급될 수 있다.
상기 제어부 (40)는, 미분탄 제조설비 (2)와 미분탄 취입 버너 (20) 또는 더스트 버너 (10)에 연결 라인과 연계되거나 또는 미분탄 제조설비 (2)와 풍구 (50) 사이의 미분탄 분배변 (30)과 연계되어 미분탄 취입을 제어할 수도 있다.
그리고, 상기 용융로의 장입물 상부로 상기 미분탄 취입 버너 (20)의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너 (10)를 더 포함할 수도 있다.
상기 더스트 버너 (10)는 미분탄 제조설비 (2)와 연계되거나 또는, 용융로 (1)에 설치된 풍구 (50) 사이에 설치된 미분탄 분배변 (30)과 연계되어 상기 용융로 (1)에 더스트와 함께 선택적으로 미분탄올 추가 취입할 수 있다. 또한, 상기 미분탄 취입 버너 (20)는 상기 더스트 버너 (10)의 설치위치와 동일한 방향을 이루도록 용융로 (1)의 원주방향을 따라 90 간격으로 각각 배치되고, 상기 더스트 버너 (10)의 위치에서 상부로 2.6m-3.2m 높이에 설치될 수 있다.
상기와 같이 미분탄 취입 버너 (20)를 용융로 (1)의 최적화된 위치에 설치함으로써 미분탄을 용융로 장입물의 상부에 효과적으로 취입할 수 있다. 한편, 상기 미분탄 분배변 (30)은 배관을 통해 용융로의 풍구 (50)에 미분탄 및 산소를 공급하는 것으로, 상기 풍구 (50)로 취입되는 미분탄 배관을 두 갈래로 분기하여 상기 더스트 버너 (10)에 연결함으로써 더스트 버너 (10)를 통해 용융로 장입물의 상부에 미분탄을 취입할 수 있다.
도 3은 본 실시예에 따른 미분탄 취입장치의 구조를 도시한 개략적인 도면이다.
도 3에 도시된 바와 같이, 상기 미분탄 분배변 (30)은 미분탄의 취입량을 조절하는 수동 밸브 (61)와 오리피스 (Orifice, 62))가 각각 설치된 미분탄 공급 배관 (60)을 포함할 수 있다.
상기 오리피스 (62)는 미분탄 분배변 (30)으로부터 공급되는 미분탄이 통과하면서 그 양이 조절되게 하여 결국 용융로 (1)에 취입되는 미분탄의 취입량을 조절할 수 있다.
또한, 상기 미분탄 공급 배관 (60)은 상기 제어부 (40)에 의해 원격 자동 제어되는 삼방변 (63)이 설치되고, 상기 삼방변 (63)은 미분탄 미취입시 상기 미분탄 공급 배관 (60)의 막힘을 방지하기 위하여 불활성가스를 취입하는 구조일 수 있다.
상기 불활성가스는 질소를 포함할 수 있다.
상기 미분탄은 용융로 (1)에서 발생하는 가스의 산화도가 기준치 이상으로 상승될 경우에만 선택적으로 취입되어야 하기 때문에 상기 제어부 (40)에 의해 원격으로 자동 제어되는 상기 삼방변 (63)을 설치하여 미분탄 미취입시 배관에 질소가 취입될 수 있도록 한다.
본 실시예에서 상기 미분탄 취입 버너 (20)는 그 후단부에 설치되어 공급되는 미분탄에 불활성가스를 투입하는 이젝터 (Ejector, 70)를 더 포함하고, 상기 이젝터 (70)는 배관의 막힘을 방지하기 위하여 질소를 고속으로 분출한다.
또한, 상기 미분탄 취입 버너 (20)는 그 외측에 설치되어 미분탄 취입 버너 (20) 선단부의 열 손상을 방지하기 위해 넁각수가 취입되는 냉각수 배관 (80)을 더 포함하고, 상기 냉각수 배관 (80)은 넁각수와 함께 또는, 독립적으로 불활성가스가 취입될 수 있는 보조 배관 (81)을 더 포함할 수 있다.
즉, 상기 미분탄 취입 버너 (20)의 주변에 설치되는 상기 냉각수 배관 (80) 및 보조 배관 (81)은 설비의 안전성을 확보하기 위해 설치되는 것으로, 특히 상기 넁각수 배관 (80)에서 넁각수가 샐 경우, 미분탄의 취입을 자동을 막으면서 상기 보조 배관 (81)을 통해 넁각수 배관 (80)에 질소를 취입할 수 있다.
도 4는 본 실시예에 따른 미분탄 취입 버너의 내부를 확대하여 도시한 개략적인 도면이다. 도 5는 본 실시예에 따른 미분탄 취입 버너의 내부 랜스를 도시한 개략적인 도면이다.
도 4 및 도 5에 도시된 바와 같이, 상기 미분탄 취입 버너 (20)는 그 내측에 삽입되어 취입되는 미분탄의 유속을 확보할 수 있도록 된 인너 파이프 (21)를 더 포함할 수 있고, 상기 미분탄 취입 버너 (20)의 내측에 하나 이상의 산소 공급홀 (22)이 형성되어 상기 인너 파이프 (21)를 지나는 미분탄에 산소가 접촉되는 구조이다.
또한, 상기 인너 파이프 (21)는 조립을 위해 그 외측에 간격을 두고 하나 이상의 지지대 (23)가 설치된 것으로, 상기 지지대 (23)를 통해 인너 파이프 (21)의 조립을 용이하게 할 수 있다.
여기서, 상기 미분탄 취입 버너 (20)는 그 내부에 직경이 축소된 인너 파이프 (21)가 설치됨으로써 미분탄 취입 버너 (20)를 지나는 미분탄의 유속이 빨라지게 하고, 이를 통해 미분탄과 산소가 보다 용이하게 접촉될 수 있도록 한다.
도 6은 본 실시예에 따른 미분탄 취입장치의 이젝터 구조를 도시한 개략적인 도면이다.
도 6에 도시된 바와 같이, 상기 이젝터 (70)는 공급되는 미분탄에 불활성가스가 투입될 수 있도록 미분탄 유입관 (71)에 가스 공급관 (72)이 연결설치된 구조로서, 미분탄이 공급되는 상기 미분탄 유입관 (71)의 막힘을 방지하기 위하여 상기 가스 공급관 (72)을 통해 질소를 펌핑하듯이 빠른 속도로 공급한다.
도 7은 본 실시예에 따른 미분탄 취입장치의 넁각수 배관 구성을 도시한 개략적인 도면이다.
도 7에 도시된 바와 같이, 상기 넁각수 배관 (80)은 상기 더스트 버너 (10)에 설치된 배관에 상기 미분탄 취입 버너 (20)와 연결되는 냉각수 인렛 (Inlet) 배관 (80A) 및 냉각수 아웃렛 (Outlet) 배관 (80B)이 별도로 설치된 구조로서, 기존에 설치된 상기 더스트 버너 (10)의 냉각수 배관에 신설되는 상기 미분탄 취입 버너 (20)의 넁각수 배관을 추가로 설치한다.
즉, 상기 미분탄 취입 버너 (20)를 중심으로 넁각수 인렛 배관 (80A)과 넁각수 아웃렛 배관 (80B)이 각각 설치되는 바, 상기 더스트 .버너 (10)의 넁각수 인렛 배관 (80a)과 상기 미분탄 취입 버너 (20)의 넁각수 인렛 배관 (80A)이 연결되고, 상기 더스트 버너 (10)의 넁각수 아웃렛 배관 (80b)과 상기 미분탄 취입 버너 (20)의 넁각수 아웃렛 배관 (80B)이 연결된다.
상기 넁각수 배관 (80)은 상기 미분탄 취입 버너 (20) 선단부의 열손상을 방지하기 위해 설치되는 것으로, 넁각수의 취입을 통해 설비 안정성을 확보할 수 있다.
도 8은 본 실시예에 따른 미분탄 취입방법의 과정을 도시한 순서도이다.
도 8에 도시된 바와 같이, 용융로의 미분탄 취입방법은, 용융로의 장입물 상부로, 상기 용융로 (1)에 설치된 미분탄 취입 버너 (20)를 이용하여 미분탄을 취입하는 단계; 및, 상기 미분탄의 용융로 취입 환경을 제어하는 제어단계를 포함할 수 있다.
상기 미분탄을 취입하는 단계와 제어단계는, 미분탄을 용융로 장입물의 상부에 취입하기 위하여 별도의 배관을 이용하여 더스트 버너 (10)와 연결하는 배관 설치단계 (S1); 상기 더스트 버너 (10) 상부에 더스트 버너 (10)와 동일 배치되는 미분탄 취입 버너 (20)를 설치하는 미분탄 취입 버너 설치단계 (S2); 및 상기와 같이 설치된 배관 및 미분탄 취입 버너 (20)를 통해 용융로 장입물 상부로 미분탄을 취입하는 미분탄 취입단계 (S3)를 더 포함할 수 있다.
본 실시예에 따른 미분탄 취입방법은 용융로 (1)의 장입물 상부로 미분탄을 취입하는 것으로, 상기 더스트 버너 (10)를 이용하기 위하여 더스트 버너 (10)에 배관을 설치하는 과정과, 독자적으로 용융로 (1)에 미분탄을 취입하는 미분탄 취입 버너 (20)를 설치하는 과정 및, 이렇게 설치된 더스트 버너 (10)와 미분탄 취입 버너 (20)를 이용하여 선택적으로 용융로 (1)의 장입물 상부에 미분탄을 취입하는 과정이다.
또한, 상기 미분탄 취입 버너 설치단계 (S2)에서 미분탄 제조설비 (2)와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비 (2)와 용융로 (1)에 설치된 풍구 (50) 사이에 설치된 미분탄 분배변 (30)과 연계되어 미분탄이 공급될 수 있다.
상기 미분탄 취입 버너 설치단계 (S2)에서 용융로 (1)의 장입물 상부로 상기 미분탄 취입 버너 (20)의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너 (10)를 더 포함할 수 있다. 그리고, 상기 미분탄 취입단계 (S3)에서 상기 더스트 버너 (10)는 미분탄 제조설비 (2)와 연계되거나 또는, 용융로 (1)에 설치된 풍구 (50) 사이에 설치된 미분탄 분배변 (30)과 연계되어 상기 용융로 (1)에 더스트와 함께 선택적으로 미분탄을 추가 취입할 수 있다.
또한, 상기 배관 설치단계 (S1)에서 용융로 (1)의 풍구 (50)로 취입되는 미분탄 배관을 두 갈래로 분기하여 상기 더스트 버너 (10)에 연결함으로써 더스트 버너 (10)를 통해 미분탄을 취입할 수 있다.
상기 배관 설치단계 (S1)에서 미분탄을 공급하는 미분탄 분배변 (30)에 미분탄 취입용 배관을 설치하여 상기 더스트 버너 (10)에 연결함으로써 더스트 버너 (10)를 통해 미분탄을 취입할 수 있다.
즉, 상기와 같이 더스트 버너 (10)를 이용하여 용융로 (1)의 장입물 상부에 미분탄을 취입할 수 있다.
그리고, 상기 미분탄 취입 버너 설치단계 (S2)에서 상기 미분탄 취입 버너 (20)가 더스트 버너 (10) 상부의 2.6m-3.2m 높이에서 용융로 (1)의 원주방향을 따라 90°간격으로 설치될 수 있다. 상기 미분탄 취입 버너 (20)는 상기 더스트 버너 (10) 상부에서 높이 차이를 가지면서 더스트 버너 (10)와 동일한 위치에 용융로 (1)의 원주방향을 따라 배치된다.
또한, 상기 미분탄 취입 버너 설치단계 (S2)에서 상기 미분탄 취입 버너 (20)에 냉각수 배관 (80)이 설치되고, 상기 냉각수 배관 (80)에 보조 배관 (81)이 연결되어 냉각수의 누출시 미분탄 취입을 막고 질소가 백업 취입될 수 있다.
상기 미분탄 취입 버너 (20)의 주변에 설치되는 상기 넁각수 배관 (80) 및 보조 배관 (81)은 설비의 안전성을 확보하기 위해 설치된다.
상술한 바와 같이, 본 실시예에서 용융로 (1)의 미분탄 취입방법은 세가지가 있다.
첫째, 상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 상기 미분탄 취입 버너 (20)로 직접 취입한다.
둘째, 상기 풍구 (50)로 취입하는 미분탄 배관을 분기하여 더스트 버너 (10)로 취입한다.
셋째, 상기 미분탄 취입용 배관을 통해 더스트 버너 (10)로 취입한다. 그러므로, 용융로 (1)의 장입불 상부로 미분탄을 취입하는 방법에 있어서, 상기 세가지 중 어느 하나의 공정을 통해 미분탄을 취입할 수 있다. 한편, 상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 미분탄 취입량을 제어하는 제어부 (40)가 설치되어 미분탄 공급설비에 포함된 회전 공급장치의 회전수 제어를 통해 용융로 (1) 전체 취입량을 제어함으로써 용융로 장입물 상부로 취입되는 미분탄의 취입량을 제어할 수 있다.
또한, 상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 상기 더스트 버너 (10)의 미분탄 취입 유무 및 취입량은 용융로 (1)의 초과 가스 중 이산화탄소의 변화량을 기반으로 계산하여 유량계를 통해 측정할 수 있다.
여기서, 상기 더스트 버너 (10)의 미분탄 취입량에 따른 가스 산화도 및 광석 환원율의 변화량을 [표 1 ]로 나타내면 다음과 같다.
【표 11
PCI Burner 산소 4400 Nm3/h, PC (미분탄) 5.6 t/h 취입 용량의 설비구성으로
환원가스 중 CO2 2.0% 저하를 통한 환원율 3.0% 상승 효과 기대 ' 그리고, 용융로 돔 (Domme)부에 미분탄 취입장치가 설치되어 가동시킨 결과를 [표 2]로 나타내면 다음과 같다. (환원율 상승 효과) [it 2】
Figure imgf000017_0001
환원율 60%이하로 저하시에만 선택적으로 Dome부로 PC를 취입하여 환원율 저하 억제 → E/G C02 2.0% 저하에 의한 환원율 3.0% 증대 효과 확인 (설계 기준 충족)
따라서, 상기와 같이 용융로 (1)의 장입물 상부로 미분탄을 투입함으로써 잉여 산소에 의한 일산화탄소 가스의 연소를 차단하고, 일산화탄소 .가스 발생량을 증대하여 환원가스의 산화도를 획기적으로 낮추어 유동로의 광석 환원율올 증대할 수 있다.
또한, 산화도가 급증할 경우 미분탄 취입량을 증가시켜 일산화탄소 함량을 보층시킴으로써 산화도를 일정하게 유지할 수 있다.
한편, 도 9를 참조하면, 용융로의 미분탄 취입장치는 환원로 (7) 및 용융로 (1)를 포함한다. 이외에 용융로의 미분탄 취입장치는 필요에 따라 기타 다른 장치를 포함할 수 있다. 환원로 (7)에는 철광석이 장입되어 환원된다. 환원로 (7)에 장입되는 철광석은 사전 건조된 후에 환원로 (7)를 통과하면서 환원철로 제조된다. 환원로 (7)는 층전층형 환원로로서, 용융로 (1)로부터 환원가스를 공급받아 그 내부에 층전층을 형성한다.
용융로 (1)는 환원로 (7)에 연결되어, 환원로 (7)에서 제조된 환원철이 공급되며, 성형탄 제조 장치에서 제조된 성형탄 또는 석탄이 장입될 수 있다. 용융로 (1) 내로 장입된 환원철과 석탄 및 건류된 촤 (char)는 용융로 (1) 내부에 장입물 베드 (3)를 형성한다. 용융로 (1)의 상부에는 듬부 (9)가 형성된다. 듬부 (9)는 장입물 베드 (3) 상측에 형성되어 있으며, 용융로 (1)의 다른 부분에 비해 넓은 공간으로 형성되며, 고온의 환원 가스가 존재한다.
성형탄은 용융로 (1)의 돔부 (9)에 장입된 후 급속 가열되어 용융로 (1)의 하부까지 낙하한다. 성형탄의 열분해 반웅에 의해 생성된 촤는 용융로 (1)의 하부로 이동하여 풍구 (50)를 통해 공급되는 산소와 발열 반웅한다. 그 결과, 성형탄은 용융로 (1)를 고온으로 유지하는 열원으로서 사용될 수 있다. 한편, 촤는 통기성을 제공하므로, 용융로 (1)의 하부에서 발생한 다량의 가스와 환원로 (7)에서 공급된 환원철이 용융로 (1) 내의 장입물 베드 (3)를 좀더 쉽고 균일하게 통과할 수 있다.
전술한 성형탄 이외에 필요에 따라 괴상 탄재 또는 코크스를 용융로 (1)에 장입할 수도 있다. 용융로 (1)의 외벽에는 풍구 (50)를 설치하여 산소를 취입한다. 산소는 장입물 베드 (3)에 취입되어 연소대 (8)를 형성한다. 성형탄은 연소대 (8)에서 연소되어 환원 가스를 발생시킬 수 있다.
용융로 (1)는 더스트 버너 (10)와 미분탄 취입 버너 (20)를 포함한다. 더스트 버너 (10)는 듬부 (9) 내로 산소를 취입하여 용융로 (1) 내에서 발생되는 분진류 및 건류 가스를 분해 연소시킨다. 더스트 버너 (10)는 장입물 베드 (3)와 듬부 (9) 사이에 위치하며, 용융로 (1) 내부 둘레를 따라 복수로 구비될 수 있다.
더스트 버너 (10)는 장입물 베드 (3) 상부 표면과 일정한 거리, 즉, 약
2m 이상 약 3m 이하의 높이에 설치될 수 있는데, 더스트 버너 (10)의 위치가 장입물 베드 (3)와 지나치게 근접하게 위치하게 되면 더스트 버너 (10)의 화염이 장입물 베드 (3) 상부 표면을 치면서 접촉하여 분진이 지나치게 발생하는 동시에 더스트 버너 (10)가 손상될 위험이 높아진다.
이러한 위험을 피하고자 더스트 버너 (10)를 장입물 베드 (3)의 표면으로부터 약 2m 이상 약 3m 이하로 위치시키며, 이 경우 더스트 버너 (10)에서 발생하는 열량의 대부분이 장입물 베드 (3)를 승온하는데 사용되지 못하고 듬부 (9)를 승온하는데 사용되어, 돔부 (9)의 온도가 불필요하게 상승하는 한편, 용융로 (1)의 조업 효율이 저하될 수 있다. 이러한 문제점을 방지하기 위해, 더스트 버너 (10)와 장입물 베드 (3) 사이에 미분탄 취입 버너 (20)를 위치시킨다.
미분탄 취입 버너 (20)는 장입물 베드 (3) 표면으로부터 약 1.3m 이상 약 1.7m 이하의 높이에 위치할 수 있다. 미분탄 취입 버너 (20)의 화염이 장입물 베드 (3)에 직접 접촉하지 않으면서 장입물 베드 (3) 표면에 충분한 열량을 공급할 수 있는 위치에 미분탄 취입 버너 (20)를 위치시킨다. 미분탄 취입 버너 (20)가 장입물 베드 (3)의 표면에서 지나치게 멀어지면, 장입물 베드 (3)에 열을 효과적으로 주지 못하게 되며, 반대로 미분탄 취입 버너 (20)가 장입물 베드 (3) 표면에 지나치게 가까울 경우 미분탄 취입 버너 (20)가 파손되는 문제가 발생할 수 있다.
도 3은 도 2의 'A'부분을 확대하여 도시한 도면이다. 미분탄 취입 버너 (20)는 용융로 (1) 내로 미분탄 (5)과 산소 (6)를 취입하여 미분탄 (5)을 연소시킨다. 이때, 연소 화염 (1 1)에 의해 미분탄 취입 버너 (20)의 발생 연소열이 장입물 베드 (3)로 전달되어 장입물 베드 (3)를 승은시킨다.
한편, 미분탄 취입 버너 (20)는 미분탄과, 액화천연가스, 및 )ke Oven Gas 중 어느 하나의 연료를 취입하여 연소시키는 것일 수 있다.
도 4는 본 발명의 일 실시예에 따른 용융로를 개략적으로 나타내는 평면도이다 더스트 버너 (10)는 용융로 (1) 내부 둘레를 따라 복수로 구비될 수 있으며, 도 4에 도시된 바와 같이, 듬부 (9)에 4개의 더스트 버너 (10)가 설치될 수 있다. 또한, 미분탄 취입 버너 (20)는 용융로 (1) 내부 둘레를 따라 더스트 버너 (10)와 비중첩하도록 위치할 수 있다. 즉, 미분탄 취입 버너 (20)는 원주 방향으로 더스트 버너 (10) 사이에 위치할 수 있으며, 4개로 구비될 수 있다. 미분탄 취입 버너 (20)가 더스트 버너 (10) 사이에 위치하지 않을 경우, 미분탄 취입 버너 (20)의 연소 화염에 의해 미분탄 취입 버너 (20)의 상부에 위치한 더스트 버너 (10)가 손상을 입을 수 있다.
한편, 더스트 버너 (10)와 미분탄 취입 버너 (20)에 취입되는 산소는 약
6:4 내지 약 7:3의 비율로 이루어질 수 있다. 미분탄 취입 버너 (20)에 취입되는 산소가 지나치게 많으면 더스트 버너 (10)에 취입되는 산소의 양이 적어져 듬부 (9) 내 분진과 석탄에서 나오는 휘발분을 층분히 연소, 분해시킬 수 없게 된다. 반대로, 미분탄 취입 버너 (20)로 취입되는 산소 양이 너무 적으면 연소 화염의 크기가 작아져 장입물 베드 (3)의 승온 효과가잡소하게 된다.
미분탄 취입 버너 (20)의 산소 취입비 관리는 돔부 (9) 온도를 기준으로 한다. 돔부 (9)의 온도가 약 1070도 이상 상승하면, 더스트 버너 (10)의 산소량을 줄이고, 미분탄 취입 버너 (20)의 산소량을 늘려 줌으로써 미분탄 취입 버너 (20) 발생 연소열이 장입물 베드 (3)로 더 많이 갈 수 있도록 한다. 반면, 돔부 (9) 온도가 약 1030도 이하로 저하되면, 미분탄 취입 버너 (20)의 산소량을 줄이고, 더스트 버너 (10)의 산소량을 늘여 더스트 버너 (10) 발생 연소열이 돔부 (9) 가스를 더욱 승온시킬 수 있도록 한다.
도 13은 본 발명의 일 실시예에 따른 용융로의 장입물 베드의 승온 비율을 기존과 비교하여 나타낸 그래프이고, 도 14는 본 발명의 일 실시예에 따른 용융로의 장입물 베드의 승온 은도를 기존과 비교하여 나타낸 그래프이며, 도 15는 본 발명의 일 실시예에 따른 용융로의 미분탄 취입장치의 용선 생산량 증대 효과를 기존과 비교하여 나타낸 그래프이며, 도 8은 본 발명의 일 실시예에 따른 용융로의 미분탄 취입장치의 석탄 사용비 감소 효과를 기존과 비교하여 나타낸 그래프이다.
본 발명의 효과를 입증하기 위하여 용융로 (1)의 더스트 버너 (10)와 장입물 베드 (3) 사이의 간격을 종전 3m에서 1.5m로 낮춰 실기모사 테스트 조업을 실시하였다. 그 결과, 도 13에 도시된 바와 같이, 더스트 버너 (10)와 미분탄 취입 버너 (20)에서 발생한 연소열 중 돔부 (9)를 승온하는 열의 바율이 감소하는 반면, 장입물 베드 (3)를 승온하는 열의 비율이 기존 약 22%에서 약 31%로 증가함을 확인하였다. 그 결과, 도 14에 도시된 바와 같이, 장입물 베드 (3)의 온도 상승은 기존 약 210도에서 약 340도로 증가하였다.
장입물 베드 (3)의 은도 상승 효과는 조업 실적 개선으로 나타나, 도 15에 도시된 바와 같이, 일 용선 생산량이 기존 약 5,200 톤 (ton)에서 약 5,500톤으로 증가하였으며, 반대로 석탄 사용비 (연료비)는 도 16에 도시된 바와 같이, 기존 약 860kg/t-p 에서 약 820kg/t-p로 저하됨을 알 수 있다.
이상에서 살펴 본 바와 같이, 본 발명의 일 실시예에서는 더스트 버너와 장입물 베드 표면 사이에 미분탄과 산소를 취입하여 미분탄을 연소시키는 미분탄 취입 버너를 설치함으로써, 더스트 버너의 화염이 장입물 베드의 상부 표면을 치면서 접촉하여 분진이 발생되고 더스트 버너가 손상되는 것을 방지할 수 있다.
또한, 미분탄 취입 버너를 적절한 위치에 설치함으로써, 미분탄 취입 버너의 화염이 장입물 베드에 직접 접촉하지 않으면서 장입물 베드의 표면에 층분한 열량을 공급할 수 있다.
또한, 미분탄 취입 버너에 취입되는 산소량만큼 상부의 더스트 버너에 취입되는 산소량을 줄여줌으로써, 돔부에 공급량이 일정하게 유지되도록 할 수 있다.
또한, 미분탄 취입 버너에서 발생되는 연소 열량이 장입물 베드로 전달되어 용융로의 조업 효율이 향상되어 용선 생산량이 증대되고, 환원제비가 감소되는 효과를 얻을 수 있다.
이상 설명한 바와 같이 본 발명의 예시적인 실시예가 도시되어 설명되었지만, 다양한 변형과 다른 실시예가 본 분야의 숙련된 기술자들에 의해 행해질 수 있을 것이다. 이러한 변형과 다른 실시예들은 첨부된 청구범위에 모두 고려되고 포함되어, 본 발명의 진정한 취지 및 범위를 벗어나지 않는다 할 것이다.
【산업상 이용가능성】
본 장치에 따르면, 용융로의 장입물 상부에 미분탄 취입시 가스산화도의 제어를 통해 유동로의 광석 환원율 제어가 용이해지고, 이에 따라 환원율 저하에 의한 반복적인 용선 온도의 급등락 현상을 감소시킬 수 있다.
또한, 용융로의 정상 조업을 지속적으로 유지함으로써 용선 품질을 안정화하고 용선 제조원가를 절감할 수 있다.

Claims

【청구범위】
【청구항 1 ]
용융로의 장입물 상부에 적어도 하나 이상 설치되는 미분탄 취입 버너; 및
상기 미분탄 취입 버너로 공급되는 미분탄의 취입량을 제어하도록 제공된 제어부를
포함하는 용융로의 미분탄 취입장치 .
【청구항 2】
거 1 1 항에 있어서,
상기 미분탄 취입 버너는, 미분탄 제조설비와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비와 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 미분탄이 공급되는 용융로의 미분탄 취입장치.
【청구항 3]
제 1 항 또는 제 2 항에 있어서,
상기 용융로의 장입물 상부로 상기 미분탄 취입 버너의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너를 더 포함하는 용융로의 미분탄 취입장치 .
【청구항 4】
제 3 항에 있어서,
상기 더스트 버너는 미분탄 제조설비와 연계되거나 또는, 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 상기 용융로에 더스트와 함께 선택적으로 미분탄을 추가 취입하는 용융로의 미분탄 취입장치.
【청구항 5】
제 2 항 또는 제 4 항에 있어서,
상기 미분탄 분배변은 미분탄의 취입량을 조절하는 수동 밸브와 오리피스가 각각 설치된 미분탄 공급 배관을 포함하는 용융로의 미분탄 취입장치.
【청구항 6】 제 5 항에 있어서,
상기 미분탄 공급 배관은 상기 제어부에 의해 원격 자동 제어되는 삼방변이 설치된 용융로의 미분탄 취입장치.
【청구항 7]
제 6 항에 있어서,
상기 삼방변은 미분탄 미취입시 상기 미분탄 공급 배관의 막힘을 방지하기 위하여 불활성가스를 취입하는 구조의 용융로의 미분탄 취입장치 .
【청구항 8】
제 1 항에 있어서,
상기 미분탄 취입 버너는 그 후단부에 설치되어 공급되는 미분탄에 불활성가스를 투입하는 이젝터를 더 포함하는 용융로의 미분탄 취입장치.
【청구항 9】
제 3 항에 있어서,
상기 미분탄 취입 버너는 그 외측에 설치되어 미분탄 취입 버너 선단부의 열 손상을 방지하기 위해 넁각수가 취입되는 넁각수 배관을 더 포함하는 용융로의 미분탄 취입장치.
【청구항 10]
제 9 항에 있어서,
상기 냉각수 배관은 넁각수와 함께 또는 독립적으로 불활성가스가 취입될 수 있는 보조 배관을 더 포함하는 용융로의 미분탄 취입장치.
【청구항 11 ]
계 1 항에 있어서,
상기 미분탄 취입 버너는 그 내측에 삽입되어 취입되는 미분탄의 유속을 확보할 수 있도록 된 인너 파이프를 더 포함하는 용융로의 미분탄 취입장치 .
【청구항 12】
제 11 항에 있어서,
상기 미분탄 취입 버너는 그 내측에 하나 이상의 산소 공급홀이 형성되어 상기 인너 파이프를 지나는 미분탄에 산소가 접촉되는 구조의 용융로의 미분탄 취입장치.
【청구항 13】
제 11 항에 있어서,
상기 인너 파이프는 조립을 위해 그 외측에 간격을 두고 하나 이상의 지지대가 설치된 용융로의 미분탄 취입장치.
【청구항 14】
제 8 항에 있어서,
상기 이젝터는 공급되는 미분탄에 불활성가스가 투입될 수 있도록 미분탄 유입관에 가스 공급관이 연결설치된 용융로의 미분탄 취입장치.
【청구항 15]
제 9 항에 있어서,
상기 넁각수 배관은 상기 더스트 버너에 설치된 배관에 상기 미분탄 취입 버너와 연결되는 넁각수 인렛 배관 및 넁각수 아웃렛 배관이 별도로 설치된 용융로의 미분탄 취입장치.
【청구항 16】
용융로의 장입물 상부로,
상기 용융로에 설치된 미분탄 취입 버너를 이용하여 미분탄을 취입하는 단계; 및,
상기 미분탄의 용융로 취입 환경을 제어하는 제어단계;
를 포함하는 용융로의 미분탄 취입방법 .
【청구항 17】
제 16 항에 있어서,
상기 미분탄을 취입하는 단계와 제어단계는,
미분탄을 용융로 장입물의 상부에 취입하기 위하여 별도의 배관을 이용하여 더스트 버너와 연결하는 배관 설치단계 (S1);
상기 더스트 버너 상부에 더스트 버너와 동일 배치되는 미분탄 취입 버너를 설치하는 미분탄 취입 버너 설치단계 (S2); 및
상기와 같이 설치된 배관과 미분탄 취입 버너 및 용융로에 설치된 풍구를 통해 용융로 장입물 상부로 미분탄을 취입하는 미분탄 취입단계 (S3) 를 더 포함하는 용융로의 미분탄 취입방법 .
【청구항 18】 거 1 17 항에 있어서,
상기 미분탄 취입 버너 설치단계 (S2)에서 미분탄 제조설비와 연계되어 미분탄이 공급되거나 또는, 상기 미분탄 제조설비와 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 미분탄이 공급되는 용융로의 미분탄 취입방법.
【청구항 19]
제 17 항에 있어서,
상기 미분탄 취입 버너 설치단계 (S2)에서 용융로의 장입물 상부로 상기 미분탄 취입 버너의 하부 측에 적어도 하나 이상 제공되고 선택적으로 미분탄을 추가 취입하는 더스트 버너를 더 포함하는 용융로의 미분탄 취입방법.
【청구항 20】
거 1 17 항에 있어서,
상기 미분탄 취입단계 (S3)에서 상기 더스트 버너는 미분탄 제조설비와 연계되거나 또는, 용융로에 설치된 풍구 사이에 설치된 미분탄 분배변과 연계되어 상기 용융로에 더스트와 함께 선택적으로 미분탄을 추가 취입하는 용융로의 미분탄 취입방법 .
【청구항 21】
제 17 항에 있어서,
상기 미분탄 취입 버너 설치단계 (S2)에서 상기 미분탄 취입 버너에 넁각수 배관이 설치되고, 상기 넁각수 배관에 보조 배관이 연결되어 넁각수의 누출시 미분탄 취입을 막고 질소가 백업 취입될 수 있는 용융로의 미분탄 취입방법.
【청구항 22】
게 17 항에 있어서,
상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 상기 미분탄 취입 버너로 직접 취입하거나 상기 용융로에 설치된 풍구로 취입되는 미분탄 배관을 분기하여 더스트 버너로 취입하거나 상기 미분탄 취입용 배관을 통해 더스트 버너로 취입하는 것 중 어느 하나의 공정을 통해 미분탄을 취입하는 용융로의 미분탄 취입방법 .
【청구항 23]
제 17 항에 있어서,
상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 미분탄 취입량을 제어하는 제어부가 설치되어 미분탄 공급설비에 포함된 회전 공급장치의 회전수 제어를 통해 용융로 전체 취입량을 제어함으로써 용융로 장입물 상부로 취입되는 미분탄의 취입량을 제어하는 용융로의 미분탄 취입방법.
【청구항 24】
제 23 항에 있어서,
상기 용융로 장입물 상부로 미분탄을 취입하는 단계 (S3)에서 상기 더스트 버너의 미분탄 취입 유무 및 취입량은 용융로의 초과 가스 중 이산화탄소의 변화량을 기반으로 계산하여 유량계를 통해 측정할 수 있는 용융로의 미분탄 취입방법 .
【청구항 25]
환원철을 제공하는 환원로; 및
상기 환원로에 연결되어 상기 환원철이 장입되며, 장입된 환원철과 석탄 및 건류된 좌 (Char)로 이루어진 장입물 베드가 내부에 형성되며, 상기 장입물 베드 상측에, 가스로 채워지는 돔부를 구비하는 용융로를 포함하고, 상기 용융로는, 상기 듬부 내로 산소를 취입하여 상기 용융로 내에서 발생되는 분진류 및 건류 가스를 분해 연소시키는 더스트 버너와,
상기 용융로 내로 미분탄과 산소를 취입하여 상기 미분탄을 연소시키는 미분탄 취입 버너를 포함하는 용융로의 미분탄 취입장치.
【청구항 26】
제 25 항에서,
상기 더스트 버너는 상기 장입물 베드와 상기 돔부 사이에 위치하며, 상기 장입물 베드 표면으로부터 2m 이상 3m 이하의 높이에 위치하는 용융로의 미분탄 취입장치.
【청구항 27】
제 25 항에서,
상기 더스트 버너는 상기 용융로 내부 둘레를 따라 복수로 구비되는 용융로의 미분탄 취입장치 .
【청구항 28】
제 25 항에서,
상기 미분탄 취입 버너는 상기 더스트 버너와 상기 장입물 베드 사이에 위치하는 용융로의 미분탄 취입장치.
【청구항 29】
제 25 항에서,
상기 미분탄 취입 버너는 상기 용융로 내부 둘레를 따라 상기 더스트 버너와 비중첩하도록 위치하는 용융로의 미분탄 취입장치.
【청구항 30】
제 25 항에서,
상기 미분탄 취입 버너는 상기 장입물 베드 표면으로부터 1.3m 이상 1.7m 이하의 높이에 위치하는 용융로의 미분탄 취입장치.
【청구항 31 ]
제 25 항에서,
상기 더스트 버너와 상기 미분탄 취입 버너에 취입되는 산소는 6:4 내지 7:3의 비율로 이루어지는 용융로의 미분탄 취입장치 .
【청구항 32】
제 31 항에서,
상기 동부의 온도가 1070도 이상으로 상승하면, 상기 더스트 버너에 취입되는 산소량이 감소되고, 상기 미분탄 취입 버너에 취입되는 산소량은 증가되도록 조절되는 용융로의 미분탄 취입장치.
【청구항 331
제 25 항에서,
상기 듬부의 온도가 1030도 이하로 저하되면, 상기 더스트 버너에 취입되는 산소량이 증가되고, 상기 미분탄 취입 버너에 취입되는 산소량은 감소되도록 조절되는 용융로의 미분탄 취입장치.
【청구항 34]
제 25 항에서,
상기 미분탄 취입 버너는 미분탄과, 액화천연가스, 및 Coke Oven Gas 중 어느 하나의 연료를 취입하여 연소시키는 용융로의 미분탄 취입장치.
PCT/KR2016/008111 2015-07-27 2016-07-25 용융로의 미분탄 취입장치 및 그 취입방법 Ceased WO2017018765A1 (ko)

Priority Applications (2)

Application Number Priority Date Filing Date Title
EP16830798.1A EP3330387B1 (en) 2015-07-27 2016-07-25 Apparatus for blowing dust coal of melting furnace
CN201680054310.9A CN108026596A (zh) 2015-07-27 2016-07-25 熔炉的粉煤吹入装置及其吹入方法

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR1020150106152A KR101739861B1 (ko) 2015-07-27 2015-07-27 용융로의 미분탄 취입장치 및 그 취입방법
KR10-2015-0106152 2015-07-27
KR10-2015-0174150 2015-12-08
KR20150174150 2015-12-08

Publications (2)

Publication Number Publication Date
WO2017018765A1 true WO2017018765A1 (ko) 2017-02-02
WO2017018765A8 WO2017018765A8 (ko) 2017-03-16

Family

ID=57884840

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2016/008111 Ceased WO2017018765A1 (ko) 2015-07-27 2016-07-25 용융로의 미분탄 취입장치 및 그 취입방법

Country Status (3)

Country Link
EP (1) EP3330387B1 (ko)
CN (1) CN108026596A (ko)
WO (1) WO2017018765A1 (ko)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117004784A (zh) * 2023-10-07 2023-11-07 山西建龙实业有限公司 一种高炉喷吹煤粉用氮气的预热系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR920010525B1 (ko) * 1990-09-08 1992-12-04 포항종합제철 주식회사 압축공기를 이용한 미분탄 취입라인의 관통방법
JPH09273715A (ja) * 1996-04-02 1997-10-21 Mitsubishi Heavy Ind Ltd 湿式炉用バーナ
KR20030030495A (ko) * 2001-10-11 2003-04-18 주식회사 포스코 콜 더스트 취입장치를 갖는 코렉스 용융로
KR20050005984A (ko) * 2003-07-08 2005-01-15 주식회사 포스코 고로 가스이용률 변동에 따른 미분탄 취입량 제어장치
WO2015000604A1 (de) * 2013-07-01 2015-01-08 Siemens Vai Metals Technologies Gmbh Entschwefelung von gasen bei der herstellung von roheisen

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0995724A (ja) * 1995-10-02 1997-04-08 Nkk Corp スクラップ溶解法
CN100455678C (zh) * 2006-01-25 2009-01-28 中冶赛迪工程技术股份有限公司 熔融还原炉喷吹煤粉工艺
CN101498554B (zh) * 2009-03-12 2010-09-15 北京首钢自动化信息技术有限公司 高炉串罐自动喷煤控制系统及方法
JP6015915B2 (ja) * 2012-09-20 2016-10-26 三菱重工業株式会社 高炉設備
CN104946841A (zh) * 2014-03-27 2015-09-30 宝山钢铁股份有限公司 利用corex炉进行炼铁的工艺

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR920010525B1 (ko) * 1990-09-08 1992-12-04 포항종합제철 주식회사 압축공기를 이용한 미분탄 취입라인의 관통방법
JPH09273715A (ja) * 1996-04-02 1997-10-21 Mitsubishi Heavy Ind Ltd 湿式炉用バーナ
KR20030030495A (ko) * 2001-10-11 2003-04-18 주식회사 포스코 콜 더스트 취입장치를 갖는 코렉스 용융로
KR20050005984A (ko) * 2003-07-08 2005-01-15 주식회사 포스코 고로 가스이용률 변동에 따른 미분탄 취입량 제어장치
WO2015000604A1 (de) * 2013-07-01 2015-01-08 Siemens Vai Metals Technologies Gmbh Entschwefelung von gasen bei der herstellung von roheisen

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3330387A4 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117004784A (zh) * 2023-10-07 2023-11-07 山西建龙实业有限公司 一种高炉喷吹煤粉用氮气的预热系统
CN117004784B (zh) * 2023-10-07 2023-11-28 山西建龙实业有限公司 一种高炉喷吹煤粉用氮气的预热系统

Also Published As

Publication number Publication date
EP3330387A4 (en) 2018-06-20
CN108026596A (zh) 2018-05-11
WO2017018765A8 (ko) 2017-03-16
EP3330387A1 (en) 2018-06-06
EP3330387B1 (en) 2020-05-06

Similar Documents

Publication Publication Date Title
JP5840202B2 (ja) 高炉のための羽口装置
CN102042614B (zh) 电站燃煤锅炉天然气点火系统
TWI639805B (zh) 燒結設備及燒結方法
CN103667569B (zh) 部分还原铁制造装置
KR102469391B1 (ko) 금속 합금을 생산하는 야금로
EP2871247B1 (en) Method for operating blast furnace
JP6012360B2 (ja) 微粉炭吹き込み装置、これを備えた高炉設備、および微粉炭供給方法
CN102459652B (zh) 高炉操作方法和用于其的低发热量气体的燃烧方法以及高炉设备
WO2017018765A1 (ko) 용융로의 미분탄 취입장치 및 그 취입방법
JPH0129847B2 (ko)
TW591101B (en) Method and apparatus for dry quenching of coke
CN103148477B (zh) 一种螺旋入粉式煤粉燃烧机
CN203238278U (zh) 一种用于高炉开炉预热炉缸的导气装置
BR102013033702B1 (pt) Forno metalúrgico
JP4685671B2 (ja) 廃棄物溶融処理装置
JPS6332842B2 (ko)
AU634436B2 (en) Method of starting a plant for the production of pig iron or steel pre-material as well as arrangement for carrying out the method
CN106931783A (zh) 烧结机的点火保温炉
CN212398107U (zh) 一种中间包烘烤装置
CN115094174A (zh) 一种节省高炉燃料的喷煤热补偿装置
CN206269161U (zh) 多功能汽化燃烧炉
CN2560850Y (zh) 竖炉半无焰式高炉煤气燃烧器
CN204478792U (zh) 一种天然气冲天炉
CN205957160U (zh) 一种锅炉热烟气点火装置
CN210831954U (zh) 一种超低热值气体燃烧炉

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16830798

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 2016830798

Country of ref document: EP