WO2022156545A1 - 集气管组件 - Google Patents
集气管组件 Download PDFInfo
- Publication number
- WO2022156545A1 WO2022156545A1 PCT/CN2022/070640 CN2022070640W WO2022156545A1 WO 2022156545 A1 WO2022156545 A1 WO 2022156545A1 CN 2022070640 W CN2022070640 W CN 2022070640W WO 2022156545 A1 WO2022156545 A1 WO 2022156545A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- pipe
- main pipe
- sleeve
- gas collecting
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F9/00—Casings; Header boxes; Auxiliary supports for elements; Auxiliary members within casings
- F28F9/02—Header boxes; End plates
- F28F9/04—Arrangements for sealing elements into header boxes or end plates
- F28F9/16—Arrangements for sealing elements into header boxes or end plates by permanent joints, e.g. by rolling
- F28F9/18—Arrangements for sealing elements into header boxes or end plates by permanent joints, e.g. by rolling by welding
- F28F9/185—Arrangements for sealing elements into header boxes or end plates by permanent joints, e.g. by rolling by welding with additional preformed parts
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K1/00—Soldering, e.g. brazing, or unsoldering
- B23K1/0008—Soldering, e.g. brazing, or unsoldering specially adapted for particular articles or work
- B23K1/0012—Brazing of heat exchangers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L41/00—Branching pipes; Joining pipes to walls
- F16L41/02—Branch units, e.g. made in one piece, welded, riveted
- F16L41/03—Branch units, e.g. made in one piece, welded, riveted comprising junction pieces for four or more pipe members
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L5/00—Devices for use where pipes, cables or protective tubing pass through walls or partitions
- F16L5/02—Sealing
- F16L5/10—Sealing by using sealing rings or sleeves only
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B39/00—Evaporators; Condensers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B39/00—Evaporators; Condensers
- F25B39/02—Evaporators
- F25B39/028—Evaporators having distributing means
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F21/00—Constructions of heat-exchange apparatus characterised by the selection of particular materials
- F28F21/08—Constructions of heat-exchange apparatus characterised by the selection of particular materials of metal
- F28F21/081—Heat exchange elements made from metals or metal alloys
- F28F21/082—Heat exchange elements made from metals or metal alloys from steel or ferrous alloys
- F28F21/083—Heat exchange elements made from metals or metal alloys from steel or ferrous alloys from stainless steel
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F21/00—Constructions of heat-exchange apparatus characterised by the selection of particular materials
- F28F21/08—Constructions of heat-exchange apparatus characterised by the selection of particular materials of metal
- F28F21/081—Heat exchange elements made from metals or metal alloys
- F28F21/085—Heat exchange elements made from metals or metal alloys from copper or copper alloys
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F9/00—Casings; Header boxes; Auxiliary supports for elements; Auxiliary members within casings
- F28F9/02—Header boxes; End plates
- F28F9/04—Arrangements for sealing elements into header boxes or end plates
- F28F9/16—Arrangements for sealing elements into header boxes or end plates by permanent joints, e.g. by rolling
- F28F9/18—Arrangements for sealing elements into header boxes or end plates by permanent joints, e.g. by rolling by welding
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F9/00—Casings; Header boxes; Auxiliary supports for elements; Auxiliary members within casings
- F28F9/26—Arrangements for connecting different sections of heat-exchange elements, e.g. of radiators
- F28F9/262—Arrangements for connecting different sections of heat-exchange elements, e.g. of radiators for radiators
- F28F9/264—Arrangements for connecting different sections of heat-exchange elements, e.g. of radiators for radiators by sleeves, nipples
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K2101/00—Articles made by soldering, welding or cutting
- B23K2101/04—Tubular or hollow articles
- B23K2101/14—Heat exchangers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2500/00—Problems to be solved
- F25B2500/22—Preventing, detecting or repairing leaks of refrigeration fluids
- F25B2500/221—Preventing leaks from developing
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F2275/00—Fastening; Joining
- F28F2275/04—Fastening; Joining by brazing
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F2275/00—Fastening; Joining
- F28F2275/06—Fastening; Joining by welding
Definitions
- the present application relates to the technical field of refrigeration, and in particular, to a gas collecting pipe assembly.
- the gas collecting pipe assembly is often used to distribute the flow of the refrigerant, and this gas collecting pipe assembly is mostly connected to the inlet and outlet ends of the condenser and the evaporator.
- the main pipe and the branch pipe are directly brazed in the furnace, so that the welding space is limited, and the hardness of the branch pipe after direct brazing in the furnace is too low, which is easy to deform during transportation.
- the present application provides a gas collecting pipe assembly with high hardness and not easily deformed.
- a gas collecting pipe assembly includes a main pipe and a branch pipe, the branch pipe is fixed on the main pipe and communicated with the inside of the main pipe; the gas collecting pipe assembly also includes a sleeve, and the outer side wall of the main pipe is provided with a mounting pipe One end of the sleeve is fixed in the installation hole, the other end is located outside the main pipe, one end of the branch pipe extends into the sleeve from the end of the sleeve away from the main pipe, and is connected with the main pipe The casing is welded and connected.
- the present application solves the problem that the hardness of the branch pipe caused by the direct welding connection between the main pipe and the branch pipe is too low.
- the sleeve includes a neck section and a flare section, the neck section is connected to the main pipe, and the flare section is connected to the branch pipe.
- the sleeve further includes a limiting section, the limiting section is located between the constricting section and the flaring section, and the outer diameter of the limiting section is larger than the mounting hole aperture.
- the limiting section restricts the sleeve from extending too far into the main pipe, which plays a positioning role, ensures sufficient contact between the solder and the welding seam, and avoids leakage.
- the main pipe is provided with a protruding portion, the mounting hole is opened on the protruding portion, and the constricted portion is connected to the protruding portion.
- the protruding portion and the main pipe are provided in one piece.
- the necked section and the main pipe are welded by means of furnace brazing.
- the flared section and the branch pipe are welded by flame welding.
- the diameter of the main pipe is defined as D
- the depth of the sleeve inserted into the main pipe through the installation hole is defined as H
- D and H satisfy the following relationship Formula: H ⁇ 0.5D.
- the main pipe is a stainless steel pipe.
- the sleeve and the branch pipe are copper pipes.
- the gas collecting pipe assembly provided by the present application solves the problem caused by the direct welding connection of the main pipe and the branch pipe by adopting the method of connecting the sleeve between the main pipe and the branch pipe.
- the hardness of the branch pipe is too low, and it is easy to deform during transportation.
- Fig. 1 is the structural schematic diagram of the gas collecting pipe assembly provided by this application;
- FIG. 2 is a partial enlarged view of A in FIG. 1 .
- a component when referred to as being “mounted on” another component, it can be directly on the other component or there may also be an intervening component.
- a component When a component is considered to be “set on” another component, it may be directly set on the other component or there may be a co-existing centered component.
- a component When a component is said to be “fixed” to another component, it may be directly fixed to the other component or there may also be an intervening component.
- the present application provides a gas collecting pipe assembly 100 , which is applied in the refrigerant pipeline of the air conditioning system, and is mostly connected to the inlet and outlet ends of the condenser and the evaporator, and is usually used for to distribute the flow of refrigerant.
- the gas collecting pipe assembly 100 includes a main pipe 10 and a branch pipe 20.
- the branch pipe 20 is fixed on the main pipe 10 and communicates with the interior of the main pipe 10; 11.
- One end of the sleeve 30 is fixed in the installation hole 11 and the other end is located outside the main pipe 10.
- the main pipe and the branch pipe are directly brazed in the furnace, so that the welding space is limited, and the hardness of the branch pipe after direct brazing in the furnace is too low, which is easy to deform during transportation.
- the sleeve 30 between the main pipe 10 and the branch pipe 20 by connecting the sleeve 30 between the main pipe 10 and the branch pipe 20 , the problem of the branch pipe 20 being too low in hardness and easily deformed during transportation caused by the direct welding connection between the main pipe 10 and the branch pipe 20 is solved.
- the sleeve 30 is used as the transition pipe for welding the main pipe 10 and the branch pipe 20.
- the sleeve 30 and the main pipe 10 are brazed in the furnace, and then the branch pipe 20 is welded. 10 and the branch pipe 20 are directly welded and connected, resulting in the problem that the hardness of the branch pipe 20 is too low and is easily deformed during transportation.
- the material of the main pipe 10 is SUS304 stainless steel; of course, in other embodiments, the material of the main pipe 10 is carbon steel or aluminum, which is not limited herein.
- the material of the branch pipe 20 is selected from TP2Y copper material; of course, in other embodiments, the material of the branch pipe 20 can also be selected from other types, which is not limited herein.
- the main pipe 10 is provided with a plurality of installation holes 11 , and a plurality of branch pipes 20 are correspondingly installed in each installation hole 11 .
- the main pipe 10 is provided with a convex portion 12, the mounting hole 11 is opened on the convex portion 12, and the convex portion 12 and the main pipe 10 are set as one piece.
- the convex portion 12 is formed by punching the main pipe 10 from the inside of the main pipe 10 toward the outside of the main pipe 10 , so as to facilitate welding between the main pipe 10 and the sleeve 30 .
- one end of the main pipe 10 also has a connecting section 13, and the connecting section 13 is connected with the pipeline components of the refrigeration system.
- a plurality of branch pipes 20 are opened on the side of the main pipe 10, and the branch pipes 20 are used for connecting with the system. heat exchanger connection.
- a copper sleeve 131 is connected to the end of the connecting section 13. Since the main pipe 10 and the connecting section 13 are made of stainless steel, the setting of the copper sleeve 131 is convenient for the connecting section 13 and the pipeline of the refrigeration system made of copper metal material. piece connection.
- the main pipe 10 is a straight pipe structure
- the connecting section 13 is a bent pipe section with a bending angle of approximately 180°, so that the connecting section 13 and the main pipe 10 are approximately parallel, so that in the refrigeration system, the system piping components and the gas collecting pipe are connected.
- the assemblies 100 are generally arranged in parallel, which reduces the assembly space, makes the structure more compact, and improves the space utilization rate.
- the sleeve 30 includes a necked section 31 and a flared section 32 , the necked section 31 is connected to the main pipe 10 , and the flared section 32 is connected to the branch pipe 20 , thus enhancing the welding between the main pipe 10 and the branch pipe 20 Reliability.
- the material of the sleeve 30 is made of copper; of course, in other embodiments, the material of the branch pipe 20 can also be made of other types, which is not limited here.
- the necked section 31 and the main pipe 10 are welded by brazing in the furnace, which not only improves the welding efficiency, but also reduces the cost; of course, in other embodiments, the necked section 31 and the main pipe 10 can also be welded in other ways, which are not limited here.
- the flared section 32 and the branch pipe 20 are welded by flame welding, which makes the process simpler and the operation technique easier to grasp; of course, in other embodiments, the flared The segment 32 and the branch pipe 20 may also be welded in other ways, which are not limited herein.
- the sleeve 30 further includes a limiting section 33, the limiting section 33 is located between the constricting section 31 and the flaring section 32, the outer diameter of the limiting section 33 is larger than the diameter of the mounting hole 11, and the limiting section 33 limits the diameter of the mounting hole 11.
- the sleeve 30 protrudes into the main pipe 10 excessively, which plays a positioning role, ensures the sufficient contact between the solder and the welding seam, and avoids leakage.
- the diameter of the main pipe 10 is defined as D
- the depth of the sleeve 30 inserted into the main pipe 10 through the installation hole 11 is defined as H, and D and H satisfy the following relationship: H ⁇ 0.5D; If the pipe 30 is inserted into the main pipe 10 too deeply, the cost will be increased and blockage will be caused;
- the plurality of branch pipes 20 and the plurality of sleeves 30 are punched. Since the punching is guaranteed by the die, the consistency of the parts is ensured and the precision of the parts is also ensured.
- the manufacturing process of the gas collector assembly 100 includes the following steps:
- the first step is to prepare the main pipe 10, cut a stainless steel pipe of suitable length, chamfer the stainless steel pipe, and then use a shrinking machine to shrink both ends of the stainless steel pipe, and then use a drawing machine to pull out the side wall of the stainless steel pipe For welding the mounting hole 11 of the sleeve 30, then use a pipe bender to bend the connecting section 13 of the main pipe 10, and finally clean and dry;
- the second step is to prepare the branch pipe 20, intercept a copper pipe of suitable length, and align the copper pipe.
- the sleeve 30 is prepared, the copper pipe of suitable length is intercepted, the copper pipe is chamfered, and then the copper pipe is used for welding one end of the branch pipe 20 using a flaring machine. Flaring is carried out according to the requirements, so that the diameter of the flared section of the copper pipe matches the diameter of the branch pipe 20, and then the end of the copper pipe used for welding the main pipe 10 is narrowed according to the requirements, so that the diameter of the narrowing section of the copper pipe is slightly smaller.
- the installation hole 11 smaller than the side wall of the main pipe 10 is cleaned and dried at the end; the fourth step, assembling, insert the constricted section 31 of the sleeve 30 into the installation hole 11 of the side wall of the main pipe 10, and insert the solid annular bronze solder sleeve into The branch pipe 20; the fifth step, welding, pass the assembled sleeve 30 and the main pipe 10 through the welding furnace, the temperature of the welding furnace is controlled at 930 ° C, and the speed of the sleeve 30 and the main pipe 10 passing through the welding furnace is 0.3 m/min; sixth Step: Insert the branch pipe 20 into the flared section 32 of the sleeve 30 so that the branch pipe 20 and the main pipe 10 are fixed and welded to each other, and flame welding, laser welding or argon arc welding can be used. Check whether the air tube assembly 100 is poorly welded.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Branch Pipes, Bends, And The Like (AREA)
- Sampling And Sample Adjustment (AREA)
Abstract
Description
Claims (10)
- 一种集气管组件,包括主管及支管,所述支管固定于所述主管上,并与所述主管的内部连通设置;其特征在于,所述集气管组件还包括套管,所述主管的外侧壁开设有安装孔,所述套管的一端固定于所述安装孔内,另一端位于所述主管外侧,所述支管的一端从所述套管远离所述主管的一端伸入所述套管内,并与所述套管焊接连接。
- 根据权利要求1所述的集气管组件,其特征在于,所述套管包括缩口段和扩口段,所述缩口段与所述主管连接,所述扩口段与所述支管连接。
- 根据权利要求2所述的集气管组件,其特征在于,所述套管还包括限位段,所述限位段位于所述缩口段和所述扩口段之间,所述限位段的外径大于所述安装孔的孔径。
- 根据权利要求2所述的集气管组件,其特征在于,所述主管上设有凸部,所述安装孔开设于所述凸部上,所述缩口段与所述凸部连接。
- 根据权利要求4所述的集气管组件,其特征在于,所述凸部与所述主管设置为一体式。
- 根据权利要求2所述的集气管组件,其特征在于,所述缩口段与所述主管通过炉中钎焊的方式进行焊接。
- 根据权利要求2所述的集气管组件,其特征在于,所述扩口段与所述支管通过火焰焊接的方式进行焊接。
- 根据权利要求4所述的集气管组件,其特征在于,所述主管的直径定义为D,沿所述安装孔的轴线方向,所述套管通过所述安装孔插入所述主管的深度定义为H,D和H满足以下关系式:H≤0.5D。
- 根据权利要求1所述的集气管组件,其特征在于,所述主管为不锈钢管。
- 根据权利要求9所述的集气管组件,其特征在于,所述套管和所述支管为铜管。
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2023525994A JP2024501916A (ja) | 2021-01-21 | 2022-01-07 | 集気管アセンブリ |
| KR1020237018623A KR20230101859A (ko) | 2021-01-21 | 2022-01-07 | 가스 수집관 어셈블리 |
| EP22742024.7A EP4283220A4 (en) | 2021-01-21 | 2022-01-07 | Gas collecting pipe assembly |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202120170856.9U CN215063003U (zh) | 2021-01-21 | 2021-01-21 | 集气管组件 |
| CN202120170856.9 | 2021-01-21 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2022156545A1 true WO2022156545A1 (zh) | 2022-07-28 |
Family
ID=79251855
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2022/070640 Ceased WO2022156545A1 (zh) | 2021-01-21 | 2022-01-07 | 集气管组件 |
Country Status (5)
| Country | Link |
|---|---|
| EP (1) | EP4283220A4 (zh) |
| JP (1) | JP2024501916A (zh) |
| KR (1) | KR20230101859A (zh) |
| CN (1) | CN215063003U (zh) |
| WO (1) | WO2022156545A1 (zh) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117773503A (zh) * | 2024-01-10 | 2024-03-29 | 蚌埠凯盛工程技术有限公司 | 拉边杆冷却水包的加工方法及拉边机 |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN215063003U (zh) * | 2021-01-21 | 2021-12-07 | 浙江盾安人工环境股份有限公司 | 集气管组件 |
| JP2026081611A (ja) * | 2024-11-05 | 2026-05-19 | ボッシュホームコンフォートジャパン株式会社 | 室外ユニットおよび冷凍サイクル装置 |
| CN119609603A (zh) * | 2024-12-31 | 2025-03-14 | 含山瑞可金属有限公司 | 集液管组件加工方法、集液管组件、换热器及制冷系统 |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102848139A (zh) * | 2012-06-08 | 2013-01-02 | 浙江三花制冷集团有限公司 | 一种连接管及其制造方法和集气管组件 |
| CN202813895U (zh) * | 2012-08-21 | 2013-03-20 | 浙江盾安人工环境股份有限公司 | 一种空调换热器 |
| CN104015019A (zh) * | 2014-05-29 | 2014-09-03 | 浙江三花制冷集团有限公司 | 一种集气管部件的制造方法及使用该集气管部件的热交换器 |
| CN205481966U (zh) * | 2016-01-29 | 2016-08-17 | 颜兆赞 | 一种不锈钢集气管组件 |
| CN212338320U (zh) * | 2020-03-02 | 2021-01-12 | 绍兴新锐大进焊接设备有限公司 | 一种管口结构及四通阀 |
| CN215063003U (zh) * | 2021-01-21 | 2021-12-07 | 浙江盾安人工环境股份有限公司 | 集气管组件 |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5360836A (en) * | 1976-11-12 | 1978-05-31 | Toa Seiki Co Ltd | Constructing method of indoor piping |
| JPH04288461A (ja) * | 1991-03-14 | 1992-10-13 | Matsushita Refrig Co Ltd | 冷媒分流器の製造方法 |
| JPH0594593U (ja) * | 1991-06-12 | 1993-12-24 | 日本軽金属株式会社 | 異種金属の継手構造 |
| JP2005121131A (ja) * | 2003-10-16 | 2005-05-12 | Ranco Japan Ltd | 弁ハウジングに管を接合する方法及びそのための接続部材 |
| JP5328724B2 (ja) * | 2010-06-30 | 2013-10-30 | 三菱電機株式会社 | 冷媒分配器及びこの冷媒分配器を用いたヒートポンプ装置 |
| CN102873508A (zh) * | 2011-11-01 | 2013-01-16 | 浙江三花制冷集团有限公司 | 一种集气管组件的制造方法及空调系统 |
| CN102853513A (zh) * | 2012-06-08 | 2013-01-02 | 浙江三花制冷集团有限公司 | 一种集气管组件及一种集气管组件的制造方法 |
| AU2020323253B2 (en) * | 2019-07-31 | 2024-02-01 | Daikin Industries, Ltd. | Refrigeration apparatus, and refrigerant piping of refrigeration apparatus |
-
2021
- 2021-01-21 CN CN202120170856.9U patent/CN215063003U/zh active Active
-
2022
- 2022-01-07 JP JP2023525994A patent/JP2024501916A/ja active Pending
- 2022-01-07 WO PCT/CN2022/070640 patent/WO2022156545A1/zh not_active Ceased
- 2022-01-07 EP EP22742024.7A patent/EP4283220A4/en active Pending
- 2022-01-07 KR KR1020237018623A patent/KR20230101859A/ko not_active Ceased
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102848139A (zh) * | 2012-06-08 | 2013-01-02 | 浙江三花制冷集团有限公司 | 一种连接管及其制造方法和集气管组件 |
| CN202813895U (zh) * | 2012-08-21 | 2013-03-20 | 浙江盾安人工环境股份有限公司 | 一种空调换热器 |
| CN104015019A (zh) * | 2014-05-29 | 2014-09-03 | 浙江三花制冷集团有限公司 | 一种集气管部件的制造方法及使用该集气管部件的热交换器 |
| CN205481966U (zh) * | 2016-01-29 | 2016-08-17 | 颜兆赞 | 一种不锈钢集气管组件 |
| CN212338320U (zh) * | 2020-03-02 | 2021-01-12 | 绍兴新锐大进焊接设备有限公司 | 一种管口结构及四通阀 |
| CN215063003U (zh) * | 2021-01-21 | 2021-12-07 | 浙江盾安人工环境股份有限公司 | 集气管组件 |
Non-Patent Citations (1)
| Title |
|---|
| See also references of EP4283220A4 * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117773503A (zh) * | 2024-01-10 | 2024-03-29 | 蚌埠凯盛工程技术有限公司 | 拉边杆冷却水包的加工方法及拉边机 |
Also Published As
| Publication number | Publication date |
|---|---|
| EP4283220A1 (en) | 2023-11-29 |
| JP2024501916A (ja) | 2024-01-17 |
| EP4283220A4 (en) | 2024-06-19 |
| KR20230101859A (ko) | 2023-07-06 |
| CN215063003U (zh) | 2021-12-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP4283220A1 (en) | Gas collecting pipe assembly | |
| US20150033789A1 (en) | Heat exchanger and air conditioner provided with heat exchanger | |
| US20110139416A1 (en) | Internal Heat Exchanger for Air Conditioning System of Motor Vehicle and Such a Circuit | |
| CN213631075U (zh) | 集气管组件 | |
| US5092398A (en) | Automotive parallel flow type heat exchanger | |
| US20250003691A1 (en) | Heat exchanger and air conditioning system having same | |
| JP2013066911A (ja) | 銅管とステンレス鋼管の接続体及びその製造方法 | |
| JP2023507921A (ja) | 消音器及び空調 | |
| CN102873508A (zh) | 一种集气管组件的制造方法及空调系统 | |
| JP5709733B2 (ja) | 二重管 | |
| CN213685372U (zh) | 配管组件、四通阀组件以及空调系统 | |
| KR101422074B1 (ko) | 열교환용 인아웃렛 파이프의 고정구조 | |
| CN101639303B (zh) | 一种换热器及包括该换热器的热交换装置 | |
| JP2011099620A (ja) | 熱交換器 | |
| CN210165565U (zh) | 换热装置及燃气热水器 | |
| CN217636884U (zh) | 换热器 | |
| WO2022037635A1 (zh) | 管组件连接结构、配管组件、四通阀组件及空调系统 | |
| KR20160117376A (ko) | 입출구파이프를 포함한 열교환기 제조방법 | |
| JPH10197186A (ja) | 熱交換器 | |
| JP2007177848A (ja) | 配管 | |
| CN218627927U (zh) | 集气管及具有其的换热器组件 | |
| CN217979241U (zh) | 集气管 | |
| KR101694671B1 (ko) | 입출구파이프를 포함한 열교환기 제조방법 | |
| KR101694670B1 (ko) | 열교환기용 입출구파이프 연결부재 | |
| CN103134238B (zh) | 一种空调平行流热交换器及其加工工艺 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 22742024 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2023525994 Country of ref document: JP |
|
| ENP | Entry into the national phase |
Ref document number: 20237018623 Country of ref document: KR Kind code of ref document: A |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 202327042037 Country of ref document: IN |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| ENP | Entry into the national phase |
Ref document number: 2022742024 Country of ref document: EP Effective date: 20230821 |
|
| WWR | Wipo information: refused in national office |
Ref document number: 1020237018623 Country of ref document: KR |
|
| WWC | Wipo information: continuation of processing after refusal or withdrawal |
Ref document number: 1020237018623 Country of ref document: KR |