AT122785B - Method for controlling several alternating current or multi-phase power plants that are coupled to one another. - Google Patents

Method for controlling several alternating current or multi-phase power plants that are coupled to one another.

Info

Publication number
AT122785B
AT122785B AT122785DA AT122785B AT 122785 B AT122785 B AT 122785B AT 122785D A AT122785D A AT 122785DA AT 122785 B AT122785 B AT 122785B
Authority
AT
Austria
Prior art keywords
power plants
alternating current
coupled
another
phase power
Prior art date
Application number
Other languages
German (de)
Original Assignee
Siemens Schuckertwerke Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens Schuckertwerke Gmbh filed Critical Siemens Schuckertwerke Gmbh
Application granted granted Critical
Publication of AT122785B publication Critical patent/AT122785B/en

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Description

  

   <Desc/Clms Page number 1> 
 



  Verfahren zur Regelung von mehreren miteinander gekuppelten Wechselstrom-oder
Mehrphasenkraftwerken. 



    Die fortschreitende Entwicklung der Technik bedingt einen immer grösseren Verbrauch an elektrischer Energie. Dieser Umstand hat zur Folge, dass entweder neue elektrische Kraftwerke gebaut, oder die bereits gebauten erweitert oder mit anderen Kraftwerken zusammengeschlossen werden müssen, auch wenn diese räumlich entfernt voneinander liegen.

   Eine solche Kupplung von entfernt liegenden Kraft- 5 werken ist sogar unter Umständen vorteilhaft, wenn hiedurch eine kostspielige Erweiterung eines bestehen-   
 EMI1.1 
 
Ist ein solcher   Zusammenschluss   von mehreren Kraftwerken einmal erfolgt, so ist die richtige Verteilung der Belastung auf die einzelnen Kraftwerke eine wirtschaftliche und technische Notwendigkeit. 
 EMI1.2 
 jedoch ergeben sich bei der praktischen Ausführung des Vertrages grosse Schwierigkeiten, insbesondere wegen der richtigen Verteilung der   Blindströme.   Es   können nämlich   die   Ausgleichsleitungen   zwischen den einzelnen Kraftwerken mit starken Strömen von sehr schlechtem Leistungsfaktor belastet werden.

   
 EMI1.3 
 zentral gelegenen Kommandostelle, bei der telephonisch die Meldungen über die zurzeit vorhandene Belastungsverteilung einlaufen. Von dieser Kommandostelle wurden telephonisch die Befehle zur Regelung der Belastungsverteilung nach den einzelnen Kraftwerken hin gegeben. Es versteht sich von selbst, dass 
 EMI1.4 
 
Die Erfindung betrifft ein Verfahren zum Betrieb von mehreren miteinander gekuppelten Kraft- werken   für Ein-und Mehrphasenwechselstrom, nach welchem   einzelne, bestimmten Verbrauchern zugeordnete Kraftwerke so geregelt werden, dass sie den wechselnden   Watt-und Blindleistungsbedarf   gerade   dieser Verbraucher selbsttätig übernehmen.   



   In welcher Weise das Verfahren gemäss der Erfindung   durchgeführt   werden kann, ist in den nach- folgenden Figuren dargestellt. Fig. 1 bedeutet hiebei ein grundsätzliches Schema, ebenso wie Fig.   3,   
 EMI1.5 
 Belastungsfaktor hat, wenn es in der Lage ist, mit grösserer Wirtschaftlichkeit zu arbeiten oder wenn es das einzige Kraftwerk ist, welches aus der Zusammensehaltung der Kraftwerke Vorteile erzielt, so kann der Gesellschaft, die dieses Kraftwerk betreibt, auferlegt werden, die Blindleistung der Übertragungsleitung bei allen Belastungen zu liefern. 



   Die Blindkomponente der durch das Kraftwerk 3 gelieferten Leistung wird nun mittels des Diffe-   rentialrelais JO   (z. B. nach Art einer elektrodynamischen Waage nach Lord Kelvin) mit der Blindkomponente des dem genannten Kraftwerk zugeteilten Unterwerks 6 verglichen. Der Ausschlag der Waage 

 <Desc/Clms Page number 2> 

 
 EMI2.1 
 zeigen die Watt-bzw. die Blindleistung des Unterwerks 6 an. 



   Wegen der Entfernung des Unterwerks 6 vom Kraftwerk 3 ist eine   Fernubertragung     der Momentan-   
 EMI2.2 
 gebauten Instrumente 34 und 35 bzw. 33 und   13,   deren Anker 40 aus einem Unterbrecher besteht. Die
Zahl der Umdrehungen dieser zählerartigen Instrumente ist proportional dem ihnen zugeführten Strom ; diesem ebenfalls proportional ist daher die Zahl der Unterbrechungen pro Sekunde. Die Unterbrechen 40 schalten einen   Gleiehstromkreis   mit der   Primärwicklung   41 eines Transformators 42 zusammen.

   Die 
 EMI2.3 
 
Die Schalter 47 drehen sich mit so grosser Geschwindigkeit, dass die Relais   45   und 46 durch die Hilfsleitung 8 häufiger verbunden werden, als das Relais   43   infolge der   Spitzenbela, tung arbeitet.   Die 
 EMI2.4 
 des Kondensators geht durch die Wicklungen der Wagen 9 und 10 und der Instrumente 14 und 36. 



   Die Instrumente 13 und   33   sind mit   ähnlichen     Impulsrelais 55   versehen, die auf den anderen Teil der Waagen 9 und 10 arbeiten. Wird das Gleichgewicht der Differentialrelais 9 oder   40 gestört, so   hat dies zur Folge, dass Motor 27 bewegt und die von der Kraftmaschine 25 zugeführte   Leistung geändert wird.   In ähnlicher Weise steuert Differentialrelais 10 den   Drehtransformator 12 für   Generator 1. Unter diesen 
 EMI2.5 
 



   Diese Aufgabe kann z. B. in dem Falle praktiseh werden, wenn eine   Gesellschaft. 1. die in) Besitz   der Werke 60 und 62 ist, während   der Spitzenbelastungsperiode Kraft   von der die Werke 61   und 63   

 <Desc/Clms Page number 3> 

 besitzenden Gesellschaft B entnehmen will. Die Leistungsfähigkeit des Kraftwerkes 60 genügt zur Übernahme der Blindleistung nur bei normaler Belastung. Da die Gesellschaft B keinen Vorteil aus dem Zu-   sammemchluss     hat-ausser   der Möglichkeit, dass im Notfalle eine Reservekraftquelle da ist-so ist 
 EMI3.1 
 sobald das Werk nicht überlastet ist. 



   PATENT-ANSPRÜCHE :
1. Verfahren zum Betrieb von mehreren miteinander gekuppelten Kraftwerken für Wechsel-oder Mehrphasenstrom, dadurch gekennzeichnet, dass einzelne, bestimmten Verbrauchern zugeordnete Werke 
 EMI3.2 
 selbsttätig   übernehmen.  



   <Desc / Clms Page number 1>
 



  Method for regulating several alternating current or alternating current or
Multiphase power plants.



    The advancing development of technology requires an ever greater consumption of electrical energy. The consequence of this is that either new electrical power plants have to be built, or those that have already been built have to be expanded or connected with other power plants, even if they are spatially distant from each other.

   Such a coupling of distant power plants is even advantageous under certain circumstances if it means an expensive expansion of an existing one.
 EMI1.1
 
Once such a merger of several power plants has taken place, the correct distribution of the load on the individual power plants is an economic and technical necessity.
 EMI1.2
 however, there are great difficulties in the practical execution of the contract, in particular because of the correct distribution of the reactive currents. This is because the equalizing lines between the individual power plants can be loaded with strong currents with a very poor power factor.

   
 EMI1.3
 Centrally located command center, which receives reports by telephone about the current load distribution. The commands for regulating the load distribution to the individual power plants were given by telephone from this command post. It goes without saying that
 EMI1.4
 
The invention relates to a method for operating several coupled power plants for single- and multi-phase alternating current, according to which individual power plants assigned to certain consumers are regulated in such a way that they automatically take over the changing watt and reactive power requirements of these consumers.



   The way in which the method according to the invention can be carried out is shown in the following figures. Fig. 1 means a basic scheme, just like Fig. 3,
 EMI1.5
 Load factor, if it is able to work with greater economic efficiency or if it is the only power plant that derives advantages from the combination of the power plants, the company that operates this power plant can be imposed on the reactive power of the transmission line to deliver all loads.



   The reactive component of the power supplied by the power station 3 is now compared by means of the differential relay JO (for example in the manner of an electrodynamic scale according to Lord Kelvin) with the reactive component of the substation 6 assigned to the named power station. The deflection of the scales

 <Desc / Clms Page number 2>

 
 EMI2.1
 show the watt or the reactive power of substation 6.



   Because of the distance between substation 6 and power plant 3, remote transmission of the instantaneous
 EMI2.2
 built instruments 34 and 35 or 33 and 13, the anchor 40 of which consists of a breaker. The
The number of revolutions of these counter-like instruments is proportional to the current supplied to them; This is also proportional to the number of interruptions per second. The interrupters 40 connect a shunt circuit with the primary winding 41 of a transformer 42.

   The
 EMI2.3
 
The switches 47 rotate at such a high speed that the relays 45 and 46 are connected by the auxiliary line 8 more frequently than the relay 43 operates due to the peak load. The
 EMI2.4
 of the capacitor goes through the windings of carriages 9 and 10 and instruments 14 and 36.



   The instruments 13 and 33 are provided with similar pulse relays 55 which operate on the other part of the scales 9 and 10. If the equilibrium of the differential relay 9 or 40 is disturbed, this has the consequence that the motor 27 is moved and the power supplied by the engine 25 is changed. Similarly, differential relay 10 controls rotary transformer 12 for generator 1. Among these
 EMI2.5
 



   This task can e.g. B. in the case when a society. 1. who is in) possession of plants 60 and 62 during the peak load period of plants 61 and 63

 <Desc / Clms Page number 3>

 from owning company B. The capacity of the power plant 60 is sufficient to take over the reactive power only under normal load. Since company B has no advantage from the merger - apart from the possibility that a reserve power source is there in an emergency - so is
 EMI3.1
 as soon as the plant is not overloaded.



   PATENT CLAIMS:
1. A method for operating several power plants coupled to one another for alternating or multi-phase electricity, characterized in that individual plants assigned to specific consumers
 EMI3.2
 take over automatically.

 

Claims (1)

2. Anordnung zur Ausführung des verfahrens nach Anspruch 1, bei der für die Watt-und wattlosen Ströme gesonderte Messvorrichtungen und von diesen jeweils beeinflusste Regelvorrichtungen vorgesehen sind, gekennzeichnet durch ein Differentialrelais, auf das einerseits der im Kraftwerk erzeugte Strom, anderseits der Strom der diesem Kraftwerk zugeordneten Verbraucher im Wege der Impulsfern- übertragung einwirken. 2. Arrangement for carrying out the method according to claim 1, in which separate measuring devices and control devices influenced by these are provided for the wattless and wattless currents, characterized by a differential relay to which on the one hand the current generated in the power plant, on the other hand the current of this Act on consumers assigned to the power plant by way of remote impulse transmission. 3. Anordnung nach Anspruch 1, bei welcher Messinstrumente verwendet werden, welche Gleich- EMI3.3 relais ein Kondensator geschaltet ist. 3. Arrangement according to claim 1, in which measuring instruments are used which equal EMI3.3 relay a capacitor is connected. 5. Anordnung nach Anspruch 3, dadurch gekennzeichnet, dass das Empfangsrelais einen Umschalter im Stromkreis des Differentialrelais steuert, wodurch das Differentialrelais im Takte der Gleichstrom- EMI3.4 EMI3.5 5. Arrangement according to claim 3, characterized in that the receiving relay controls a changeover switch in the circuit of the differential relay, whereby the differential relay in the cycle of the direct current EMI3.4 EMI3.5
AT122785D 1926-01-16 1927-01-15 Method for controlling several alternating current or multi-phase power plants that are coupled to one another. AT122785B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US122785XA 1926-01-16 1926-01-16

Publications (1)

Publication Number Publication Date
AT122785B true AT122785B (en) 1931-05-11

Family

ID=21754205

Family Applications (1)

Application Number Title Priority Date Filing Date
AT122785D AT122785B (en) 1926-01-16 1927-01-15 Method for controlling several alternating current or multi-phase power plants that are coupled to one another.

Country Status (1)

Country Link
AT (1) AT122785B (en)

Similar Documents

Publication Publication Date Title
AT122785B (en) Method for controlling several alternating current or multi-phase power plants that are coupled to one another.
AT130456B (en) Transformer arrangement to be switched on in a multi-phase line to regulate the size ratio and the phase difference of the voltages that prevail in the line before and after the switch-on point.
DE546725C (en) Process for regulating the power distribution to several interconnected power plants for alternating or multi-phase current
DE640872C (en) Arrangement for the excitation of synchronous machines
AT124191B (en) Power plant with a device to increase the operational safety of your auxiliary companies fed from the main network.
DE911038C (en) Power transformer with a device for reactive power compensation
DE674926C (en) Frequency converter
DE2542205A1 (en) CONTROLLABLE MULTI-PHASE TRANSFORMER SYSTEM FOR COUPLING TWO DISTRIBUTION GRIDS
AT208962B (en) Method for achieving transformer-analog active power behavior of a frequency-elastic converter
DE844026C (en) Improvements to electrical power generation systems
DE578544C (en) Device for regulating the load distribution
DE572969C (en) Arrangement for the generation of low-frequency electricity from an overland network of normal frequency
DE755539C (en) Arrangement for regulating the load distribution in electric power plants with intermittent loading or unloading
DE648678C (en) Device for block feeding of single-phase alternating current railways by means of a converter
DE931110C (en) Arrangement for the power supply of single-phase consumers, especially electric long-distance trains
AT80848B (en) Device for identifying coil defects. Device for identifying coil defects.
DE592309C (en) Arrangement for regulating AC power lines
DE469943C (en) Device for establishing an artificial zero point for connecting extinguishing coils to three-phase networks
DE583010C (en) Device for voltage regulation of electricity consumers connected to an alternating current network via a transformer with the interposition of a rotary transformer
AT111479B (en) Frequency converter for setting the power that flows through one, two or more AC power plants (power slider).
DE629060C (en) Device for maintaining the readiness for parallel switching of several AC power distribution networks
AT119424B (en) Arrangement for zero point regulation of the voltage in rectifier systems.
AT121189B (en) Device for regulating AC power lines.
DE721947C (en) Process for increasing the performance in electrical power plants, in particular railway power plants
DE496655C (en) Locomotive drive with phase converter for converting single or multi-phase electricity