AT144036B - Furnace for obtaining coke and a mixed gas of distillation gas and water gas. - Google Patents

Furnace for obtaining coke and a mixed gas of distillation gas and water gas.

Info

Publication number
AT144036B
AT144036B AT144036DA AT144036B AT 144036 B AT144036 B AT 144036B AT 144036D A AT144036D A AT 144036DA AT 144036 B AT144036 B AT 144036B
Authority
AT
Austria
Prior art keywords
gas
chamber
water gas
degassing
water
Prior art date
Application number
Other languages
German (de)
Original Assignee
Didier Werke Ag
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Didier Werke Ag filed Critical Didier Werke Ag
Application granted granted Critical
Publication of AT144036B publication Critical patent/AT144036B/en

Links

Landscapes

  • Physical Water Treatments (AREA)

Description

  

   <Desc/Clms Page number 1> 
 



  Ofen zur Gewinnung von Koks und eines Misehgases aus   Destillationsgas   und Wassergas. 



   Bei Öfen zur Gewinnung eines   Mischgases   aus Destillationsgas und Wassergas mit gemeinsamer Beheizungseinriehtung für den Entgasungsraum und die Wassergaskammer sind bereits Einrichtungen bekannt, bei denen sich an das Ende der Entgasungsräume oder an die Unterseite der Retorte eine Wassergaskammer anschliesst, die in offener oder wie bei der Ofenanlage nach der schweizerischen Patentschrift Nr. 159360 in absperrbarer Verbindung mit den   Entgasungsräumen   steht und in die der ausgegarte Brennstoff vor Neubeschickung der Entgasungsräume ganz oder teilweise direkt   übergeführt   wird. Diese Einrichtungen haben den Nachteil, dass der Betrieb der beiden Gaserzeugungsräume vollkommen voneinander abhängt.

   Entweder richtet sich die Entleerung der Wassergaskammer nach der Ausstehzeit des oder der zugehörigen Entgasungsräume, wobei der Koks in der Wassergaskammer keineswegs   erschöpft   zu sein braucht, oder der Entgasungsraum wird nur in dem Masse beschickt, wie der Koks in der Wassergaskammer durch die Wassergaserzeugung aufgezehrt wird. Auch wird bei diesen Einrichtungen der Koks in seiner   Bildungsform,   d. h. ohne jegliche Zerkleinerung und oft sogar als ganzer Kokskuchen in die Wassergaskammer   übergefiihrt,   so dass dem   Wasserdampf nur eine im Verhältnis zur Koksmenge   
 EMI1.1 
 ist es auch ohne Beeinflussung des einen oder andern   Gaserzeugungsraumes nicht möglich,   die Wassergaserzeugung bzw. Wassergaszugabe weitgehendst zu verändern.

   Hängt die Chargierung des Wassergasraumes von der Ausstehzeit des Entgasungsraumes ab, so kann bei starker Wassergaserzeugung die während einer Charge im Wassergasraum lagernde Koksmenge für eine vollständige Zersetzung des Wasserdampfes nicht ausreichen ; anderseits würde für den Fall, dass die Beschickung des Entgasungraumes von der Aufzehrung des Kokses in der Wassergaskammer abhängt, bei geringer Wassergaserzeugung durch verminderte Dampfzufuhr der sich im Entgasungsraum bildende Koks durch zu langes Überstehen nutzlos verbrennen, wobei noch das Gas durch die Verbrennungsgase   unnötig   verdünnt würde. 



   'Nach der Erfindung werden diese Nachteile dadurch vermieden, dass bei gemeinsamer Beheizungseinrichtung für die Entgasungskammer, in der ausser   Mischgas   auch Koks erzeugt wird, und für die Wassergaskammer die letztere als für sieh abgeschlossener, selbständiger, unabhängig zu beschickender und zu betreibender Vergasungsraum an die Entgasungskammer angeschlossen ist. Dadurch ist es   möglich.   die Wassergaskammer unter Beibehaltung aller Vorteile für die bauliche und   beheizungsteehnisehe   Anordnung eines einzigen Raumes unabhängig von der Entgasungskammer, durch welche das   Misehgas   hindurchgeleitet wird, zu betreiben.

   Dies wirkt sich auch dahin aus, dass alle Vorteile, die bei einer von dem Entgasungsofen baulich getrennt angeordneten Wassergaskammer vorhanden sind, nunmehr auch der Ofenanlage mit   Ent-und Vergasungsraum   und mit gemeinsamen Beheizungskanälen für beide Räume eigen sind. Es ist bei vorliegender Anordnung deshalb möglich, den aus der Entgasungskammer anfallenden Koks in der vorhandenen Güte zu verwerten und für die Wassergaskammer nur eine jeweils zu bestimmende Auswahl von diesem Koks zu verwenden. Dieser Koks kann dann weiter in die für die Wassergaserzeugung   zweckmässige   Stückgrösse gebrochen oder sonstwie vorbehandelt und gegebenenfalls zweckentsprechend lose in die Wassergaskammer eingelagert werden.

   Der Betrieb beider   Gaserzeugungsräume   ist auch bezüglich ihrer Ausstehzeit vollständig unabhängig voneinander. Die Neubeschickung der Wassergaskammer braucht erst bei   Aufzehrung des Kokses zu erfolgen, wobei   die   Beschickung   der Wassergas- 

 <Desc/Clms Page number 2> 

 kammer unabhängig von dem Betrieb des Entgasungsraumes diskontinuierlich, kontinuierlich, gegebenenfalls auch halbkontinuierlich erfolgen kann. Auch die Menge des zu erzeugenden Wassergases kann unabhängig vom Betrieb des Entgasungsraumes geregelt werden. 



   Durch die gemeinsame Beheizungseinrichtung für die Entgasungskammer und die Wassergaskammer ist der Vorteil einer baulich einfachen und betrieblich leicht zu übersehenden Anlage gewahrt. 



  Wenn auch nur eine Beheizungseinrichtung für beide Räume vorgesehen ist, so lässt sieh durch geeignete Anordnung der einzelnen Heizzüge in bezug auf die beiden Gasungsräume noch eine unterschiedliche Beheizung der beiden Räume erreichen ; dies kann beispielsweise dadurch erzielt werden, dass die Heizzüge parallel zur Längsachse der Entgasungskammer und der Wassergaskammer laufen und durch Schieber die Heizgaszufuhr in die Heizzüge neben der Wassergaskammer und dem Entgasungsraum reguliert wird. Sofern die Heizzüge senkrecht zur grossen Längsachse der Entgasungsräume verlaufen, kann die unterschiedliche Beheizung durch stufenweise Verbrennung des Heizgases in den   Heizzügen   erreicht werden.

   Man wird dabei bestrebt sein, die Wassergaskammer, in der sieh ein besonders stark wärmeverbrauchender Vorgang abspielt, zeitweise oder dauernd stärker zu beheizen als den Entgasungsraum ; es wird deshalb   zweckmässig   sein, die Wassergaskammer möglichst an die Eintrittsstelle der Heizgase in 
 EMI2.1 
 anzupassen. 



   Das in der Wassergaskammer entstehende Wassergas wird zweckmässig dem Entgasungsraum 
 EMI2.2 
 ordnet sein. Soll nur eine Anreicherung des Wassergases mit den Bestandteilen des   Leuchtgases   erfolgen, so ist nur eine Austrittsstelle im   Entgasungsraum Über   der   Kohlenbesehickung   vorzusehen. 



   Die Umleitung des Wassergases von der Wasqergaskammer zur Entgasungskammer erfolgt entweder direkt durch eine oder mehrere Öffnungen in der Trennwand zwischen den beiden Kammern oder   durch Umführungskanäle.   Diese Kanäle werden, wenn die Wärme des Wassergases möglichst erhalten 
 EMI2.3 
   schiedener   Höhe versehen sind. 



   Ein Ausführungsbeispiel des Erfindungsgegenstandes ist in der Zeichnung dargestellt. Fig. l 
 EMI2.4 
 Weise durch Heizkanäle, in diesem Falle vertikale Heizzüge 3, von aussen beheizt werden.   Unterhalb   einer jeden Entgasungskammer 1 liegt eine räumlich für sieh abgeschlossene Kammer 2, die als selbständiger, unabhängig von der Entgasungskammer zu betreibender, nicht unmittelbar aus   dieser beschiek-   
 EMI2.5 
 raum 1 beheizt wird. 



   Die Ent- und Vergasungskammern 1 und 2 mit den für beide gemeinsamen Heizzügen J bilden ein geschlossenes Ganzes zur Gewinnung eines   l\1ischgases     aus Destillationsgas und Wassergas. In   der   Entgasungskammer 1   wird lediglich hochwertiges Gas und hochwertiger Koks gewonnen. Die Wassergaskammer 2 wird   bezüglich   Beschickung und Entleerung und auch   bezüglich   des   Besrhirkungsgutes   unabhängig von der Entgasungskammer 1 betrieben. Dabei ist es aber   möglich,   dass ein Teil des in der Kammer   j ! gewonnenen Kokses gegebenenfalls nach entsprechender Zerkleinerung   in der Kammer 2 verarbeitet wird. 



   Das in der Kammer 2 sich bildende Wassergas wird an dem der Gasabzugsseite der   Kammer   1 entgegengesetzten Ende dieser Kammer zugeleitet und zieht nach Durchströmen derselben zusammen mit dem entstandenen Leuchtgas über die   Steigleitung-   und die Vorlage zur   Gassammelleitung J ab.   Die Überleitung des Wassergases in die Entgasungskammer kann entweder durch eine oder mehrere Öffnungen 6 in der Trennwand zwischen   Ent-und Vergasungskammer   erfolgen oder durch   Umleitungs-   
 EMI2.6 
 oder von den vor der Ofenwand liegenden Steigrohren 7 gebildet werden. Für die Zuleitung des Wassergases aus der Kammer 2 in die Kammer 1 sind Öffnungen   8   in der   Kammerseitenwand vorgesehen.  



   <Desc / Clms Page number 1>
 



  Furnace for the production of coke and a mixture gas from distillation gas and water gas.



   In furnaces for obtaining a mixed gas from distillation gas and water gas with a common heating unit for the degassing chamber and the water gas chamber, devices are already known in which a water gas chamber is connected to the end of the degassing chambers or to the underside of the retort, which is open or as in the furnace system According to Swiss patent specification No. 159360, it is in a lockable connection with the degassing rooms and into which the cooked fuel is wholly or partly directly transferred before the degassing rooms are re-charged. These devices have the disadvantage that the operation of the two gas generation spaces is completely dependent on one another.

   Either the emptying of the water gas chamber depends on the remaining time of the associated degassing room (s), whereby the coke in the water gas chamber does not need to be exhausted, or the degassing chamber is only charged to the same extent as the coke in the water gas chamber is consumed by the water gas generation. The coke in its form of formation, i.e. H. Transferred into the water-gas chamber without any comminution and often even as a whole coke cake, so that the water vapor only has one in relation to the amount of coke
 EMI1.1
 It is also not possible, without influencing one or the other gas generation space, to change the water gas generation or water gas addition as far as possible.

   If the charging of the water-gas space depends on the standing time of the degassing space, the amount of coke stored in the water-gas space during a batch may not be sufficient for complete decomposition of the water vapor in the case of strong water gas generation; on the other hand, in the event that the charging of the degassing space depends on the consumption of coke in the water gas chamber, if there is little water gas generation due to reduced steam supply, the coke that forms in the degassing space would burn uselessly as a result of standing too long, with the gas being unnecessarily diluted by the combustion gases .



   According to the invention, these disadvantages are avoided in that with a common heating device for the degassing chamber, in which coke is produced in addition to mixed gas, and for the water gas chamber, the latter as a self-contained, independent gasification chamber that can be charged and operated independently of the degassing chamber connected. This makes it possible. to operate the water gas chamber while retaining all the advantages for the structural and heated arrangement of a single room independently of the degassing chamber through which the mixed gas is passed.

   This also has the effect that all the advantages that are present in a water gas chamber that is structurally separated from the degassing furnace are now also inherent in the furnace system with degassing and gasification space and with common heating channels for both rooms. With the present arrangement, it is therefore possible to utilize the coke obtained from the degassing chamber in the existing quality and to use only one selection of this coke that is to be determined in each case for the water gas chamber. This coke can then be broken down further into the appropriate piece size for the generation of water gas or otherwise pretreated and, if necessary, stored loosely in the water gas chamber as appropriate.

   The operation of both gas generation rooms is completely independent of one another, also with regard to their standing time. The water gas chamber does not need to be re-charged until the coke is used up, whereby the water gas

 <Desc / Clms Page number 2>

 chamber can be carried out discontinuously, continuously, optionally also semi-continuously, independently of the operation of the degassing chamber. The amount of water gas to be generated can also be regulated independently of the operation of the degassing space.



   Due to the common heating device for the degassing chamber and the water gas chamber, the advantage of a structurally simple and operationally easily overlooked system is preserved.



  If only one heating device is provided for both rooms, a different heating of the two rooms can be achieved by suitable arrangement of the individual heating flues in relation to the two gas chambers; This can be achieved, for example, in that the heating flues run parallel to the longitudinal axis of the degassing chamber and the water gas chamber and the heating gas supply into the heating flues next to the water gas chamber and the degassing chamber is regulated by slides. If the heating flues run perpendicular to the large longitudinal axis of the degassing chambers, the different heating can be achieved by gradually burning the heating gas in the heating flues.

   Efforts will be made to temporarily or permanently heat the water gas chamber, in which a particularly high heat-consuming process takes place, than the degassing chamber; it will therefore be advisable to place the water gas chamber as close as possible to the point at which the heating gases enter
 EMI2.1
 adapt.



   The water gas produced in the water gas chamber is expediently transferred to the degassing chamber
 EMI2.2
 be in order. If only an enrichment of the water gas with the constituents of the luminous gas is to take place, only one exit point is to be provided in the degassing space above the coal feed.



   The diversion of the water gas from the Wasqergaskammer to the degassing chamber takes place either directly through one or more openings in the partition between the two chambers or through bypass channels. These channels are preserved when the heat of the water gas is possible
 EMI2.3
   different heights are provided.



   An embodiment of the subject matter of the invention is shown in the drawing. Fig. L
 EMI2.4
 Way through heating channels, in this case vertical heating flues 3, are heated from the outside. Below each degassing chamber 1 there is a spatially closed chamber 2 which, as an independent, independent of the degassing chamber, is not directly accessible from it.
 EMI2.5
 room 1 is heated.



   The degassing and gasification chambers 1 and 2 with the heating flues J common to both form a closed whole for the production of a mixed gas from distillation gas and water gas. In the degassing chamber 1 only high quality gas and high quality coke is obtained. The water gas chamber 2 is operated independently of the degassing chamber 1 with regard to charging and emptying and also with regard to the material to be sprayed. But it is possible that part of the in chamber j! The coke obtained is processed in the chamber 2, if appropriate after appropriate comminution.



   The water gas that forms in the chamber 2 is fed to the end of this chamber opposite the gas discharge side of the chamber 1 and, after flowing through it, is withdrawn to the gas collecting line J via the riser pipe and the receiver, together with the resulting luminous gas. The transfer of the water gas into the degassing chamber can take place either through one or more openings 6 in the partition between the degassing and gasification chambers or by diversion
 EMI2.6
 or be formed by the riser pipes 7 in front of the furnace wall. For the supply of the water gas from the chamber 2 into the chamber 1, openings 8 are provided in the chamber side wall.

 

Claims (1)

PATENT-ANSPRÜCHE : 1. Ofen zur Gewinnung von Koks und eines Misehgases aus Destillationsgas und Wassergas mit gemeinsamen Beheizungskanälen für die Entgasungskammer und die Wassergaskammer, dadurch gekennzeichnet, dass die Wassergaskammer (2) als selbständiger, unabhängig von der Entgasungskammer (1) zu betreibender, nicht unmittelbar aus dieser zu beschickender Vergasungsraum an die Entgasungskammer angeschlossen ist, durch welche das Mischgas hindurchgeleitet wird. PATENT CLAIMS: 1. Oven for the production of coke and a miseh gas from distillation gas and water gas with common heating channels for the degassing chamber and the water gas chamber, characterized in that the water gas chamber (2) as an independent, independent of the degassing chamber (1) to be operated, not directly from this The gasification chamber to be charged is connected to the degassing chamber through which the mixed gas is passed. 2. Ofen nach Anspruch 1 mit sehrägliegenden bzw. waagreehten Entgasungskammern, dadurch gekennzeichnet, dass das Wassergas der Entgasungskammer (1) an dem ihrer Gasabzugsseite entgegengesetzten Ende durch'an ihrer Sohle bzw. kurz über dieser oder über die Seitenwandhöhe verteilt angeordnete Eintrittsöffnungen (6, 8) oder nur über der Kohlebesehiekung der Entgasungskammer zugeleitet wird. 2. Furnace according to claim 1 with very similar or horizontal degassing chambers, characterized in that the water gas of the degassing chamber (1) at the end opposite its gas outlet side through inlet openings (6, 6, just above this or over the height of the side wall) 8) or is fed to the degassing chamber only via the coal reservoir. 3. Ofen nach den Ansprüchen 1 und 2, dadurch gekennzeichnet, dass die Umleitungskanäle für das Wassergas im Mauerwerk der Ofenwand liegen. 3. Furnace according to claims 1 and 2, characterized in that the diversion channels for the water gas are in the masonry of the furnace wall. 4. Ofen nach den Ansprüchen 1 bis 3, dadurch gekennzeichnet, dass die Umleitungskanäle für das Wassergas nach Art von Steigrohren vor der Ofenwand liegen, die mit über die Höhe der Steigrohr verteilt angeordneten absperrbaren Abzweigstutzen für die Einfihrung des Wassergases in die Entgasungskammer in verschiedenen Höhen versehen sind. EMI3.1 4. Furnace according to claims 1 to 3, characterized in that the diversion channels for the water gas are located in front of the furnace wall in the manner of riser pipes, which are arranged with shut-off branches distributed over the height of the riser pipe for introducing the water gas into the degassing chamber at different heights are provided. EMI3.1
AT144036D 1933-09-30 1934-03-09 Furnace for obtaining coke and a mixed gas of distillation gas and water gas. AT144036B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE144036T 1933-09-30

Publications (1)

Publication Number Publication Date
AT144036B true AT144036B (en) 1935-12-27

Family

ID=34257616

Family Applications (1)

Application Number Title Priority Date Filing Date
AT144036D AT144036B (en) 1933-09-30 1934-03-09 Furnace for obtaining coke and a mixed gas of distillation gas and water gas.

Country Status (1)

Country Link
AT (1) AT144036B (en)

Similar Documents

Publication Publication Date Title
AT144036B (en) Furnace for obtaining coke and a mixed gas of distillation gas and water gas.
DE661182C (en) Furnace for obtaining a mixed gas of distillation gas and water gas
DE672721C (en) Process for gasifying coal in hydrocarbon gas plants with alternating operation
DE697470C (en) Vertical smoldering furnace made of refractory material
DE599483C (en) Device for carrying out a process consisting of several phases for the gasification of fuels when using water vapor as the gas-forming reaction medium
AT114040B (en) Process for the production of water gas in continuous operation.
AT124062B (en) Process and apparatus for degassing and gasifying bituminous fuels in alternating mode generators.
DE580426C (en) Process and device for the complete gasification of solid or liquid fuels in dust form
DE958235C (en) Method and device for the combustion of a gas-air mixture with a low calorific value, in particular for the utilization of mine weather
AT147798B (en) Distillation device for the production of town gas or hydrocarbon gas from lignite and other fuels with a lower calorific value.
AT141322B (en) Method and device for operating discontinuous chamber furnaces for the production of gas and coke.
AT130254B (en) Process for obtaining a mixed gas from distillation gas and water gas in furnaces for the production of gas and coke using low-quality coked fuel.
AT134276B (en) Process and device for the gasification of finely divided, pulverulent fuels.
AT157113B (en) Generator firing.
DE503704C (en) Method and device for producing water gas
DE539731C (en) Process for obtaining a mixed gas from distillation gas and water gas in open-air furnaces for the production of gas and coke with the joint use of inferior fuel
DE578822C (en) Device for smoldering solid, especially bituminous substances, such as lignite and the like.
DE630593C (en) Method and device for carbonizing fuels in multi-chamber furnaces
DE458516C (en) Process for generating a high-quality gas similar to luminous gas
DE475866C (en) Large water boiler with pulverized coal combustion
AT114865B (en) Process for processing moist fuels in a generator respectively. Smoldering shaft through internal heating.
AT73416B (en) Furnace for hot water or steam production.
AT122016B (en) Water gas generator for the production of water gas from coal dust and water vapor.
AT110551B (en) Process for the use of baking coals in gas generators.
AT47146B (en) Heating system for vertical retorts.