CH370019A - Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method - Google Patents

Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method

Info

Publication number
CH370019A
CH370019A CH671261A CH671261A CH370019A CH 370019 A CH370019 A CH 370019A CH 671261 A CH671261 A CH 671261A CH 671261 A CH671261 A CH 671261A CH 370019 A CH370019 A CH 370019A
Authority
CH
Switzerland
Prior art keywords
shielding
well
armored
concrete
rock
Prior art date
Application number
CH671261A
Other languages
French (fr)
Inventor
Ott Jean-Conrad
Robert Francois
Original Assignee
Ind Soc Gen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ind Soc Gen filed Critical Ind Soc Gen
Priority to CH671261A priority Critical patent/CH370019A/en
Publication of CH370019A publication Critical patent/CH370019A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/06Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

  

  Procédé d'exécution d'un puits blindé sous pression pour aménagement hydro-électrique  et puits blindé obtenu par le procédé    Les aménagements hydroélectriques en montagne  comportent fréquemment l'utilisation de puits blindés  souterrains en lieu et place de conduites extérieures.  Dans ce genre d'exécution, le blindage supporte la  pression intérieure de l'eau correspondant à la pres  sion de service majorée du coup de     bélier.    Lorsque  le rocher est de bonne qualité, il y a intérêt à faire  supporter au rocher la plus grosse partie de la pres  sion intérieure, ce qui     permet    de diminuer le poids  et le coût des blindages.

   Pratiquement,     l'application     de ce procédé connu se heurte aux difficultés sui  vantes  1) Lors de l'enrobage du blindage par un anneau  de béton, la température de la galerie, augmen  tée de la chaleur de prise du ciment, est élevée.  Lors de la mise en service du puits, la tempéra  ture de l'eau est basse. Le blindage subit ainsi  un raccourcissement     annulaire    qui tend à le  décoller du béton et à le mettre en traction ;  2) Lorsqu'on procède à des essais de mise en pres  sion d'un massif rocheux, on note, dans la courbe    déformation-pression   une déformation ini  tiale importante correspondant à une première  fermeture des fissurations, puis à un relèvement  de la courbe de déformation lorsque les fissures  se sont refermées.  



  Pour lutter     contre    ce phénomène, il est d'usage  de bloquer, par injection après la pose du     blindage,     le rocher de façon à refermer les     fissures    et à rele  ver le module de     déformation.    D'autre part, il est  également d'usage de procéder à des injections dites  de collage, entre le blindage et le béton, de façon  à mobiliser dans toute la mesure du possible dès le  début la réaction du rocher.  



  En résumé, les procédés usuels visent donc à  appliquer, le plus     intimement    possible, la tôle au    revêtement de béton, et à obturer la fissuration du  rocher de façon à pouvoir     mobiliser,    dès le début  des déformations consécutives à la mise en pression       intérieure,    la réaction du rocher, et à     diminuer    la       participation    de la tôle à l'effet de pression inté  rieure.

   Ces procédés usuels comportent les inconvé  nients suivants  1) Il est difficile et coûteux d'obtenir la     fermeture     des fissurations par injection au large, aussi bien  que d'obtenir un collage     efficace    par injection à  basse pression du blindage ;  2) II est difficile     d'obtenir,    par injection de collage  le contact du béton avec la conduite et donc de  supprimer tout espace libre sans faire flamber  le blindage sous     l'effet    de la pression d'injection  extérieure.  



  Le breveta pour objet un     procédé    d'exécution  d'un puits blindé sous pression comportant un blin  dage     métallique    entouré d'un revêtement en béton  situé dans une galerie et dont le but est de     permettre     de     réaliser    des puits blindés dont l'épaisseur du blin  dage est faible et dans lesquels une grande partie  de la pression intérieure est prise par le rocher sur  lequel le blindage est parfaitement appuyé.

   Il est  caractérisé par le fait qu'on provoque l'expansion  du blindage, lorsqu'il est disposé à l'intérieur de la  galerie, au-delà de la limite élastique provoquant  ainsi une augmentation     permanente    du diamètre du  blindage et par conséquent l'application de     celui-ci     contre la couche     annulaire    de béton ainsi que l'ap  plication d'une contrainte sur le massif rocheux en  tourant le puits déformant cette roche,     puis    qu'on  réduit la pression à l'intérieur du blindage provo  quant sa précontrainte sous l'effet du revenu élasti  que du massif rocheux.

        Le brevet a également pour objet un puits blindé  obtenu par ce procédé caractérisé par le fait qu'il  comporte     un        blindage        métallique    expansé soumis à  un effort de précontrainte annulaire par le     massif     rocheux entourant le puits et par le fait que ce blin  dage assure l'étanchéité du puits seulement, les ef  forts dus à la pression interne de service du puits  étant absorbés pour la plus grande     partie    par le  massif rocheux lui-même.  



  Le     dessin    annexé illustre schématiquement et à  titre d'exemple une forme d'exécution et     une    va  riante d'un puits blindé obtenu par le procédé, objet  du brevet.  



  La     fig.    1 en est une coupe en long, des draina  ges étant prévus pour éviter l'accumulation d'eau  dans le     voisinage    du     blindage.     



  La     fig.    2 en est une coupe en travers avant ex  pansion du blindage.  



  La     fig.    3 en est une coupe en travers après  expansion du     blindage.     



  La     fig.    4 est une courbe indiquant la déforma  tion volumétrique du blindage en fonction de la  pression d'expansion.  



  La     fig.    5 est une. courbe illustrant les déforma  tions de la roche sous     l'effet    d'une pression cons  tante.    Selon un exemple de mise en     #uvre    du procédé,  on dépose à l'intérieur d'une galerie 1 souterraine un  blindage     métallique    2 mince, de l'ordre de 5 à  10     mm,    étanche et on coule,     d'une    façon conven  tionnelle, une couche annulaire de béton 3 entre la  roche et cette     enceinte.     



  La température du puits est relativement élevée  du fait qu'elle est située sous terre et du fait de la  chaleur dégagée par la prise du ciment. Dans ces  conditions, si l'on met cette galerie en service, la  température de l'eau étant basse, le blindage se  comprime et son diamètre     diminue    ce qui provoque  le décollement du     blindage.     



  La nouveauté du procédé décrit réside dans 1e fait  qu'on met le blindage, avant sa mise en     service,     sous une pression de 1,5 à 2 fois la pression de  service provoquant     une    expansion dudit blindage.  Cette pression doit être suffisamment élevée pour  que la     limite    d'élasticité du blindage soit dépassée  afin que celui-ci se déforme de façon     permanente     pour venir épouser aussi exactement que possible  la     forme    de la couche     annulaire    de béton 3 et pro  voquer la mise en compression radiale de cette cou  che.

   Cette pression élevée provoque également la  fermeture des fissurations de la roche, le blindage       s'expansant    de façon permanente d'une     part    pour  compenser le tassement plus ou moins plastique de  la roche, et d'autre     part    pour provoquer une certaine  déformation élastique du massif rocheux.  



  Lors de la suppression de la pression interne  élevée, le blindage ne revient pas, mais par contre    le massif rocheux     ayant    été déformé non seulement  plastiquement mais également     élastiquement,    celui-ci  revient     élastiquement,    ce qui provoque l'application  au blindage d'une pression extérieure ou   précon  trainte   assurant le maintien de la fermeture de la  fissuration du massif rocheux, le maintien en com  pression radiale de la couche de béton 3 ainsi que  l'application intime du revêtement de béton au blin  dage métallique 2 contre cette couche de béton.  



  Le procédé décrit permet donc bien de réaliser  un puits blindé dans lequel le massif rocheux sup  porte la majeure     partie    de la pression interne sans  recourir à aucune     injection    coûteuse et difficile à       exécuter    et dont les résultats sont incontrôlables.  



  En outre l'allongement permanent subi par le  blindage permet d'écrouir le métal ce qui lui confère  une plus haute résistance mécanique.  



  De plus ce procédé permet de faire apparaître les  éventuelles défectuosités de bétonnage du puits lors  de son expansion     (fig.    3), en effet aux endroits où  la couche annulaire de béton est trop éloignée du  blindage ce dernier se déforme exagérément. II est  alors possible de réparer cette défectuosité à peu de  frais. En effet, il suffit de découper la partie défec  tueuse du blindage, de remplir la cavité 4 de béton  et de ressouder une plaque de métal pour rendre  étanche le     blindage.     



  Grâce à l'écrouissage du blindage on obtient  une. meilleure résistance au flambage de celui-ci.  



  Il est évident que, comme dans les exécutions       actuelles,    lorsqu'il y a des risques de     fortes    infiltra  tions d'eau dans la galerie pouvant conduire à de       fortes    pressions externes sur le blindage il y a lieu  de prévoir des moyens permettant l'évacuation de  cette eau pour éviter la formation de pressions exter  nes exagérées.    Dans certains cas il suffit pour empêcher l'accu  mulation d'eau au voisinage du blindage de procéder  à des injections 5 dites de   blocage   à une     certaine     distance de la galerie et tendant à former une cein  ture étanche autour de la galerie     (fig.    2).

      Lorsque les infiltrations d'eau sont trop consé  quentes il est possible d'évacuer cette eau en pra  tiquant des drainages autour du blindage à l'intérieur  de la couche annulaire 3 de béton et dans le rocher.  En effet, cette couche de béton n'est pas étanche  car, d'une part,     il    est nécessaire de couler du béton  relativement liquide pour obtenir sa mise en place,  ce qui conduit à un béton de qualité médiocre et,  d'autre part, il se produit une fissuration de cette  couche par section tangentielle lors de l'expansion  du blindage.  



  Un tel drainage peut comporter un collecteur 6  disposé sous le blindage et dans lequel viennent se  déverser des drains annulaires 7. Une telle solution  est décrite dans le brevet suisse     N-    347147 et ne  sera donc pas décrite en détail ici.      Les avantages principaux du puits blindé décrit  et de son procédé d'exécution par rapport aux pro  cédés     actuellement    connus sont les suivants  1) Possibilité de réduire grandement l'épaisseur du  blindage du fait que celui-ci est précontraint par  le revenu élastique du massif rocheux et que ce  massif rocheux     participe    donc pour la plus grande       part    dans la résistance à la pression interne du  blindage.

   Cette réduction d'épaisseur du blindage  représente une économie de matière très appré  ciable et donc une réduction sensible du prix de  revient d'un tel puits blindé ;  2) Suppression des injections dites de   blocage   et  de   collage   ce qui     réduit    également grande  ment le prix de revient d'un tel puits blindé;  3) La mise en évidence, avant la mise en     service    du  puits blindé des éventuelles défectuosités de  celui-ci. Ceci permet de procéder immédiate  ment aux réparations nécessaires tout en n'entraî  nant que de minimes frais ;  4) La fabrication et le transport des tronçons du  blindage sont plus aisés et plus rapides du fait  de leur moindre poids.    REVENDICATIONS  I.

   Procédé d'exécution d'un puits blindé sous  pression comportant un blindage métallique entouré  d'un revêtement en béton situé dans une galerie, ca  ractérisé par le fait qu'on provoque l'expansion dudit  blindage, lorsqu'il est disposé à l'intérieur de la gale  rie, au-delà de la limite élastique provoquant ainsi  une augmentation permanente du diamètre du blin  dage et par conséquent l'application de celui-ci con  tre la couche annulaire de béton ainsi que l'applica  tion d'une contrainte sur le massif rocheux entou-         rant    le puits déformant cette roche, puis qu'on réduit  la pression à l'intérieur du     blindage    provoquant sa  précontrainte sous l'effet du revenu élastique<B>du</B> mas  sif rocheux.  



  II. Puits blindé obtenu par le procédé selon la  revendication I, caractérisé par le fait qu'il comporte  un blindage     métallique    expansé soumis à un     effort     de précontrainte annulaire par le massif     rocheux    en  tourant le puits et par le fait que     ce    blindage assure  l'étanchéité du puits seulement, les efforts dus à la  pression interne de     service    du puits étant absorbés  pour la plus grande partie par le massif rocheux     lui-          même.  



  Method of producing a pressurized armored well for hydroelectric development and armored well obtained by the process Mountain hydroelectric installations frequently involve the use of underground armored wells instead of external conduits. In this type of execution, the shielding supports the internal pressure of the water corresponding to the service pressure increased by the water hammer. When the rock is of good quality, it is in the interest of making the rock withstand most of the internal pressure, which makes it possible to reduce the weight and the cost of the shielding.

   In practice, the application of this known process comes up against the following difficulties 1) When the shielding is coated with a concrete ring, the temperature of the gallery, increased by the setting heat of the cement, is high. When the well is commissioned, the water temperature is low. The shielding thus undergoes an annular shortening which tends to detach it from the concrete and to put it in tension; 2) When one carries out pressure tests on a rock mass, one notes, in the deformation-pressure curve, a significant initial deformation corresponding to a first closure of the cracks, then to an increase in the pressure curve. deformation when the cracks have closed.



  To combat this phenomenon, it is customary to block, by injection after the armor plating, the rock so as to close the cracks and to raise the deformation modulus. On the other hand, it is also customary to carry out so-called bonding injections, between the shielding and the concrete, so as to mobilize the rock's reaction as far as possible from the start.



  In summary, the usual methods therefore aim to apply, as closely as possible, the sheet to the concrete coating, and to seal the cracking of the rock so as to be able to mobilize, from the start of the deformations resulting from the internal pressurization, the reaction of the rock, and to reduce the participation of the sheet in the effect of internal pressure.

   These usual methods have the following drawbacks 1) It is difficult and costly to achieve crack closure by off-shore injection, as well as to achieve effective bonding by low pressure injection of the shielding; 2) It is difficult to obtain, by bonding injection, the contact of the concrete with the pipe and therefore to eliminate any free space without causing the shielding to buckle under the effect of the external injection pressure.



  The object of the patent is a method of making a pressurized armored well comprising a metal shielding surrounded by a concrete lining located in a gallery and the aim of which is to make it possible to produce armored wells whose thickness of the blin dage is low and in which a large part of the internal pressure is taken by the rock on which the armor is perfectly supported.

   It is characterized by the fact that it causes the expansion of the armor, when it is placed inside the gallery, beyond the elastic limit thus causing a permanent increase in the diameter of the armor and consequently the application of this against the annular layer of concrete as well as the application of a stress on the rock mass by turning the shaft deforming this rock, then reducing the pressure inside the shielding causing its prestressing under the effect of the elastic income of the rock mass.

        The patent also relates to a shielded well obtained by this process, characterized in that it comprises an expanded metal shielding subjected to an annular prestressing force by the rock mass surrounding the well and by the fact that this shielding ensures the sealing of the well only, the ef forts due to the internal operating pressure of the well being absorbed for the most part by the rock mass itself.



  The appended drawing illustrates schematically and by way of example an embodiment and a variant of a shielded well obtained by the process, the subject of the patent.



  Fig. 1 is a longitudinal section thereof, with draina ges being provided to prevent the accumulation of water in the vicinity of the shielding.



  Fig. 2 is a cross section before expansion of the shielding.



  Fig. 3 is a cross section after expansion of the shield.



  Fig. 4 is a curve indicating the volumetric deformation of the shielding as a function of the expansion pressure.



  Fig. 5 is a. curve illustrating the deformation of the rock under the effect of constant pressure. According to an example of implementation of the method, is deposited inside an underground gallery 1 a thin metal shielding 2, of the order of 5 to 10 mm, waterproof and is poured, in a conventional manner. , an annular layer of concrete 3 between the rock and this enclosure.



  The temperature of the well is relatively high because it is located underground and because of the heat released by the setting of the cement. Under these conditions, if this gallery is put into service, the water temperature being low, the armor is compressed and its diameter decreases, which causes the armor to detach.



  The novelty of the process described lies in the fact that the shielding is placed, before it is put into service, under a pressure of 1.5 to 2 times the operating pressure, causing an expansion of said shielding. This pressure must be high enough so that the elastic limit of the shielding is exceeded so that it deforms permanently to come to match as exactly as possible the shape of the annular layer of concrete 3 and to cause compression. radial of this layer.

   This high pressure also causes the cracks in the rock to close, the armor expanding permanently on the one hand to compensate for the more or less plastic settlement of the rock, and on the other hand to cause a certain elastic deformation of the massif. rocky.



  When the high internal pressure is removed, the armor does not return, but on the other hand the rock mass having been deformed not only plastically but also elastically, it returns elastically, which causes the application to the armor of a pressure external or pre-stretched ensuring the maintenance of the closure of the cracking of the rock mass, the maintenance in radial com pressure of the concrete layer 3 as well as the intimate application of the concrete coating with the metal shielding 2 against this concrete layer.



  The method described therefore makes it possible to produce a shielded well in which the rock mass supports the major part of the internal pressure without resorting to any injection that is expensive and difficult to carry out and the results of which are uncontrollable.



  In addition, the permanent elongation undergone by the shielding makes it possible to harden the metal which gives it greater mechanical strength.



  In addition, this process makes it possible to reveal any defects in the concreting of the well during its expansion (fig. 3), in fact in places where the annular layer of concrete is too far from the shielding, the latter deforms excessively. It is then possible to repair this defect inexpensively. Indeed, it suffices to cut out the defective part of the shielding, to fill the cavity 4 with concrete and to re-weld a metal plate to make the shielding waterproof.



  Thanks to the strain hardening of the shielding one obtains a. better resistance to buckling thereof.



  It is obvious that, as in current executions, when there is a risk of strong infiltration of water in the gallery which could lead to strong external pressures on the shielding, it is necessary to provide means for evacuation. of this water to avoid the formation of exaggerated external pressures. In some cases, to prevent the accumulation of water in the vicinity of the shielding, it is sufficient to carry out so-called blocking injections 5 at a certain distance from the gallery and tending to form a tight belt around the gallery (fig. 2). ).

      When water infiltration is too substantial, it is possible to evacuate this water by draining around the shielding inside the annular layer 3 of concrete and in the rock. Indeed, this layer of concrete is not waterproof because, on the one hand, it is necessary to pour relatively liquid concrete to obtain its placement, which leads to a concrete of poor quality and, on the other hand , there is a cracking of this layer by tangential section during the expansion of the armor.



  Such a drainage may include a collector 6 placed under the shielding and into which annular drains 7 flow. Such a solution is described in Swiss patent N-347147 and will therefore not be described in detail here. The main advantages of the armored well described and of its method of execution compared to currently known methods are as follows 1) Possibility of greatly reducing the thickness of the armouring due to the fact that the latter is prestressed by the elastic tempering of the rock mass and that this rocky mass therefore participates for the most part in the resistance to the internal pressure of the armor.

   This reduction in thickness of the shielding represents a very appreciable saving in material and therefore a significant reduction in the cost price of such a shielded well; 2) Elimination of so-called blocking and sticking injections, which also greatly reduces the cost price of such a shielded well; 3) Demonstration, before the armored well is put into service, of any defects thereof. This enables the necessary repairs to be carried out immediately while incurring minimal costs; 4) The manufacture and transport of the armor sections are easier and faster due to their lower weight. CLAIMS I.

   A method of making a pressurized armored well comprising a metal shielding surrounded by a concrete lining located in a gallery, characterized by the fact that the said shielding is caused to expand, when it is placed in the tunnel. inside the tunnel, beyond the elastic limit thus causing a permanent increase in the diameter of the shielding and consequently the application of the latter against the annular layer of concrete as well as the application of a stress on the rock mass surrounding the well deforming this rock, then reducing the pressure inside the armor, causing it to be prestressed under the effect of the elastic tempering <B> of the </B> rock mass.



  II. Shielded well obtained by the process according to claim I, characterized in that it comprises an expanded metal shielding subjected to an annular prestressing force by the rock mass by turning the shaft and by the fact that this shielding ensures the tightness of the wells only, the forces due to the internal operating pressure of the well being absorbed for the most part by the rock mass itself.

 

Claims (1)

SOUS-REVENDICATIONS 1. Procédé selon la revendication I, caractérisé par le fait qu'on procède encore à des injections de blocage pour établir une ceinture de roche imper méable autour du puits pour éviter les surpressions extérieures au blindage dues à des accumulations d'eau autour de celui-ci. 2. Procédé selon la revendication I, caractérisé par le fait qu'on procède au drainage de la galerie en vue d'évacuer les infiltrations d'eau aux environs du blindage. 3. Procédé selon la revendication I, caractérisé par le fait qu'on provoque l'expansion du blindage en y appliquant une pression interne suffisante pour provoquer un allongement permanent de ce blindage. 4. SUB-CLAIMS 1. Method according to claim I, characterized in that blocking injections are still carried out to establish a waterproof rock belt around the well to prevent overpressures external to the shielding due to water accumulations. around this one. 2. Method according to claim I, characterized in that one proceeds to the drainage of the gallery in order to evacuate water infiltration in the vicinity of the shielding. 3. Method according to claim I, characterized in that the expansion of the shielding is caused by applying a sufficient internal pressure thereto to cause a permanent elongation of this shielding. 4. Puits blindé selon la revendication II, caracté risé par le fait que l'épaisseur du blindage est déter minée par des critères d'étanchéité uniquement. Shielded well according to claim II, characterized in that the thickness of the shielding is determined by sealing criteria only.
CH671261A 1961-06-08 1961-06-08 Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method CH370019A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH671261A CH370019A (en) 1961-06-08 1961-06-08 Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH671261A CH370019A (en) 1961-06-08 1961-06-08 Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method

Publications (1)

Publication Number Publication Date
CH370019A true CH370019A (en) 1963-06-15

Family

ID=4313859

Family Applications (1)

Application Number Title Priority Date Filing Date
CH671261A CH370019A (en) 1961-06-08 1961-06-08 Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method

Country Status (1)

Country Link
CH (1) CH370019A (en)

Similar Documents

Publication Publication Date Title
FR2768768A1 (en) PROCEDURE FOR MAINTAINING THE INTEGRITY OF A SHEATH FORMING A SEAL, IN PARTICULAR A CEMENT SHEATH FOR WELLS
UA106872C2 (en) Steel pipes, lined with cast under pressure concrete or mortar, and a method for manufacturing those
CN210716321U (en) Outer waterproof construction of building wall pipeline
FR2536680A1 (en) T-piece pipe fitting mfr system
CN104863150B (en) A kind of tension and compression type prestressed cable anchorage end device
CN102252147B (en) Method for repairing crack of pipeline
CH370019A (en) Process for the execution of a pressurized armored well for hydroelectric development and armored well obtained by the method
FR2527296A1 (en) IMPROVEMENTS TO SEALING JOINTS
CN102635365B (en) Construction method for holing of shield machine
CN116044457B (en) A waterproof treatment method for cracks in shield tunnel segments
CN216741534U (en) A kind of anti-corrosion shield tunnel double-layer structure
CN216518030U (en) Embedded metal sleeve joins externally channel concrete lining section of jurisdiction
CN116593116A (en) A high-pressure hydrogen driver that reduces the risk of hydrogen damage
CN113007461B (en) High-sealing composite material high-pressure pipeline and processing method thereof
RU2138723C1 (en) Method of manufacture of metalloplastic pipe
CN104089148A (en) Heat-preservation die and heat-preservation construction method for ultra-low temperature pipeline
CN102733350B (en) Repairing method for local defect of concrete in water level change region and repairing device
FR2563145A1 (en) Process for reinforcement of pipes made of prestressed concrete, and reinforced pipes obtained
CN218541237U (en) Exhaust pipe waterproof structure and roof exhaust device
FR3061060A1 (en) COMPRESSION MOLD WITH REDUCED HEATING SYSTEM.
CN203395490U (en) Leakage repairing device for plastic composite alloy pipe
CN117703155B (en) Insulated telegraph pole with high strength and production system thereof
RU2063574C1 (en) Method of repair of high-pressure pipe lines having surface defects
CN104439184B (en) A kind of pulling force end processing method of parking braking cable for automobile
CH339587A (en) Process for waterproofing a concrete construction