One-time sintering bimetallic bearing manufacturing method Download PDFInfo
- Publication number
- CN101363473A CN101363473A CNA2008101210336A CN200810121033A CN101363473A CN 101363473 A CN101363473 A CN 101363473A CN A2008101210336 A CNA2008101210336 A CN A2008101210336A CN 200810121033 A CN200810121033 A CN 200810121033A CN 101363473 A CN101363473 A CN 101363473A
- Authority
- CN
- China
- Prior art keywords
- copper
- bimetallic bearing
- bimetallic
- steel
- sintering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Powder Metallurgy (AREA)
Abstract
本发明公开了一种一次烧结的双金属轴承制造方法。旨在提供一种工艺简单、能耗小、制造成本低、周期短的一次烧结的双金属轴承制造方法。它依次包括有下列步骤:在钢板表面均匀地铺上铜合金粉烧结→制成铜-钢双金属轴承材料的板材→根据双金属轴承的尺寸用铜-钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面,校正轴套的内孔和外圆的尺寸→对轴套切削加工,达到双金属轴承的成品要求→检验→包装、入库。该方法在铜-钢双金属轴承材料的板材制造过程中,只用了一次烧结,比原来两次烧结、两次轧制,省去了一次烧结和两次轧制,使尺寸控制和挤压,在后面校正的工序中一次完成,使工艺大大简化。The invention discloses a one-time sintered bimetallic bearing manufacturing method. The invention aims to provide a method for manufacturing a bimetallic bearing with primary sintering, which has simple process, low energy consumption, low manufacturing cost and short period. It includes the following steps in turn: evenly spread copper alloy powder on the surface of the steel plate and sinter → make a plate of copper-steel bimetallic bearing material → use the plate of copper-steel bimetallic bearing material as a blank according to the size of the bimetallic bearing → roll Make the blank into a roughly circular shaft sleeve → extrude the inner and outer surfaces of the shaft sleeve with a correction sleeve and mandrel, and correct the size of the inner hole and outer circle of the shaft sleeve → cut and process the shaft sleeve to meet the finished product requirements of bimetallic bearings → Inspection→Packing and storage. In this method, only one sintering is used in the plate manufacturing process of copper-steel bimetallic bearing material, compared with the original two sintering and two rolling, which saves one sintering and two rolling, so that the size control and extrusion , which is completed once in the subsequent correction process, which greatly simplifies the process.
Description
技术领域 technical field
本发明涉及一种复合轴承的制造方法,尤其涉及一种一次烧结的双金属轴承的制造方法。The invention relates to a manufacturing method of a composite bearing, in particular to a manufacturing method of a once-sintered bimetallic bearing.
背景技术 Background technique
传统的滑动轴承大多是全部用铜合金浇注铸成轴套,再经切削加工而成,这样的结构制造成本高,特别是随着有色金属价格的上涨,这种整体的铜合金轴承被称作双金属轴承所替代。目前的双金属轴承的制造方法是以钢板为基体,在钢板的表面均匀地铺上铜合金粉末,并使其具有一定的铺撒厚度;然后进行一次烧结,以使铜合金粉末粘结在钢板上;再进行一次轧制,以使铜合金层挤压致密;接着进行二次烧结,以使铜合金层牢固地粘结在钢背上;最后进行二次轧制,以精确控制双金属板材的尺寸;最终生产出符合所需尺寸要求的铜—钢双金属轴承材料,其中专利申请号为200510110718.7的含磷量大于0.1%的磷青铜-钢双金属轴承材料制造工艺就是以这样的工艺来生产铜—钢双金属轴承材料的。双金属轴承的制造一般是:根据双金属轴承的尺寸用铜—钢双金属轴承材料下坯料→卷制坯料成圆形→用校正套和芯棒校正→对轴套切削加工达到双金属轴承的成品要求→检验→包装入库。在铜—钢双金属轴承材料的生产中需要经两次烧结、两次轧制,工艺复杂、能耗大,制造成本高,生产周期长,一些铜合金中还含有铅、磷等有害物质,在多次烧结加热时,对周围的环境造成污染。Most of the traditional sliding bearings are made of copper alloy pouring and casting into shaft sleeves, and then processed by cutting. This kind of structure has high manufacturing cost, especially as the price of non-ferrous metals rises. This kind of integral copper alloy bearing is called Bimetallic bearings are replaced. The current manufacturing method of bimetallic bearings is based on the steel plate, and the copper alloy powder is uniformly spread on the surface of the steel plate to make it have a certain spreading thickness; ; Carry out another rolling to make the copper alloy layer compact; then carry out secondary sintering to make the copper alloy layer firmly bonded to the steel back; finally carry out secondary rolling to precisely control the bimetallic sheet Dimensions: finally produce copper-steel bimetallic bearing materials that meet the required size requirements, and the manufacturing process of phosphor bronze-steel bimetallic bearing materials with a phosphorus content greater than 0.1% in patent application No. 200510110718.7 is produced by such a process Copper-steel bimetallic bearing material. The manufacture of bimetallic bearings is generally: according to the size of the bimetallic bearing, use copper-steel bimetallic bearing material to lower the billet → roll the billet into a circle → correct with a correction sleeve and mandrel → cut the shaft sleeve to achieve the bimetallic bearing Finished product requirements → inspection → packaging and storage. In the production of copper-steel bimetallic bearing materials, two sintering and two rolling are required. The process is complicated, the energy consumption is large, the manufacturing cost is high, and the production cycle is long. Some copper alloys also contain harmful substances such as lead and phosphorus. During multiple sintering and heating, it will pollute the surrounding environment.
发明内容 Contents of the invention
本发明的目的在于提供一种工艺简单、能耗小、制造成本低、周期短的一次烧结的双金属轴承制造方法。The purpose of the present invention is to provide a bimetallic bearing manufacturing method with simple process, low energy consumption, low manufacturing cost and short period of one-time sintering.
为了达到上述目的,一次烧结的双金属轴承制造方法是:它依次包括有下列步骤:在钢板表面均匀地铺上铜合金粉烧结→制成铜—钢双金属轴承材料的板材→根据双金属轴承的尺寸用铜—钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面,校正轴套的内孔和外圆的尺寸→对轴套切削加工,达到双金属轴承的成品要求→检验→包装、入库。In order to achieve the above purpose, the manufacturing method of a sintered bimetallic bearing is: it includes the following steps in turn: spread copper alloy powder evenly on the surface of the steel plate and sinter → make a plate of copper-steel bimetallic bearing material → according to the bimetallic bearing Dimensions: use copper-steel bimetallic bearing material as the lower blank → roll the blank into a roughly circular bushing → extrude the inner and outer surfaces of the bushing with a correction sleeve and mandrel, and correct the size of the inner hole and outer circle of the bushing →Cutting and processing the shaft sleeve to meet the finished product requirements of bimetallic bearings →Inspection →Packing and warehousing.
按照上述一次烧结的双金属轴承制造方法,在铜—钢双金属轴承材料的板材制造过程中,它只用了一次烧结,比原来两次烧结、两次轧制,省去了一次烧结和两次轧制,使尺寸的控制,在最后用校正套和芯棒挤压轴套的内外表面时,使轴套的内孔和外圆的尺寸以及对铜合金层的挤压在后面校正的工序中一次完成。使工艺大大简化,设备的通用性好,工艺继承性好,节约了烧结和轧制所消耗的能量、劳动力和制造成本,产品的质量还是同样保证,又利于环境的保护。According to the above-mentioned one-time sintering bimetallic bearing manufacturing method, in the plate manufacturing process of the copper-steel bimetallic bearing material, it only uses one sintering, which saves one sintering and two rolling compared with the original two sintering and two rolling. The second rolling is to control the size. When the inner and outer surfaces of the bushing are extruded with the correction sleeve and the mandrel at the end, the size of the inner hole and outer circle of the bushing and the extrusion of the copper alloy layer are corrected later. Completed in one go. The process is greatly simplified, the versatility of the equipment is good, the process inheritance is good, the energy, labor and manufacturing costs consumed by sintering and rolling are saved, the quality of the product is still guaranteed, and it is also conducive to environmental protection.
具体实施方式 Detailed ways
下面通过实施例对本发明作进一步的描述。The present invention will be further described below by way of examples.
实施例一:Embodiment one:
一次烧结的双金属轴承制造方法是:它依次包括有下列步骤:在普通碳素结构钢板Q235A钢板的表面均匀地铺上CuPb10Sn10铜合金粉末,铺粉的厚度取决于所要求的成品双金属轴承对铜合金层的厚度,放入烧结炉中烧结,烧结温度760—850℃;烧结时间24分钟→制成铜—钢双金属轴承材料的板材→根据双金属轴承的尺寸用铜—钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面使轴套的内孔和外圆的尺寸校正,并达到双金属轴承要求的尺寸→切削轴套的端面和倒角→检验→包装、入库。The manufacturing method of a sintered bimetal bearing is: it includes the following steps in turn: evenly spread CuPb10Sn10 copper alloy powder on the surface of the ordinary carbon structural steel plate Q235A steel plate, and the thickness of the powder depends on the required finished bimetal bearing to copper The thickness of the alloy layer is put into the sintering furnace for sintering, the sintering temperature is 760-850°C; the sintering time is 24 minutes → the plate made of copper-steel bimetallic bearing material → the copper-steel bimetallic bearing material is used according to the size of the bimetallic bearing The lower blank of the sheet → roll the blank into a roughly circular shaft sleeve → extrude the inner and outer surfaces of the shaft sleeve with a correction sleeve and mandrel to correct the inner hole and outer circle of the shaft sleeve and reach the required size of the bimetallic bearing → Cutting the end face and chamfering of the bushing → Inspection → Packing and storage.
实施例二:Embodiment two:
一次烧结的双金属轴承制造方法是:它依次包括有下列步骤:在优质碳素结构钢板20钢板的表面均匀地铺上CuSn6Zn6Pb3铜合金粉末,铺粉的厚度取决于所要求的成品双金属轴承对铜合金层的厚度,放入烧结炉中烧结,烧结温度850—920℃;烧结时间16分钟→制成铜—钢双金属轴承材料的板材→经板材校平机校平→根据双金属轴承的尺寸用铜—钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面使轴套的内孔和外圆的尺寸校正,并达到双金属轴承要求的尺寸→切削轴套的端面和倒角→在轴套的外表面涂锡,进行防锈处理→检验→包装、入库。The manufacturing method of a sintered bimetal bearing is: it includes the following steps in turn: evenly spread CuSn6Zn6Pb3 copper alloy powder on the surface of the high-quality carbon structural steel plate 20 steel plate, and the thickness of the powder depends on the required finished bimetal bearing. The thickness of the alloy layer is put into a sintering furnace for sintering, the sintering temperature is 850-920°C; the sintering time is 16 minutes → a plate made of copper-steel bimetallic bearing material → leveled by a plate leveling machine → according to the size of the bimetallic bearing Use the copper-steel bimetallic bearing material to lower the blank → roll the blank into a roughly circular shaft sleeve → squeeze the inner and outer surfaces of the shaft sleeve with a correction sleeve and mandrel to correct the size of the inner hole and outer circle of the shaft sleeve, And reach the size required by the bimetallic bearing → Cut the end face and chamfer of the shaft sleeve → Coat the outer surface of the shaft sleeve with tin for anti-rust treatment → Inspection → Packing and storage.
实施例三:Embodiment three:
在不锈钢板304钢板的表面均匀地铺上CuPb24Sn4铜合金粉末,铺粉的厚度取决于所要求的成品双金属轴承对铜合金层的厚度,放入烧结炉中烧结,烧结温度800—900℃;烧结时间20分钟→制成铜—钢双金属轴承材料的板材→经滚轧机轧制和用校平机校平,使铜—钢双金属轴承材料的板材达到规定的厚度和平面度→根据双金属轴承的尺寸用铜—钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面,校正轴套的内孔和外圆的尺寸→对轴套切削加工,达到双金属轴承的成品要求→检验→包装、入库。Spread CuPb24Sn4 copper alloy powder evenly on the surface of the stainless steel 304 steel plate. The thickness of the powder depends on the required thickness of the finished bimetallic bearing to the copper alloy layer. Put it into a sintering furnace for sintering at a sintering temperature of 800-900°C; sintering The time is 20 minutes → the plate of copper-steel bimetallic bearing material is made → rolled by a rolling mill and leveled with a leveling machine, so that the plate of copper-steel bimetallic bearing material reaches the specified thickness and flatness → according to the bimetallic bearing material The size of the bearing is made of the copper-steel bimetallic bearing material plate lower blank→rolling the blank into a roughly circular bushing→extruding the inner and outer surfaces of the bushing with a correction sleeve and mandrel, and correcting the inner hole and outer circle of the bushing The size → cutting and processing of the shaft sleeve to meet the finished product requirements of the bimetallic bearing → inspection → packaging and storage.
实施例四:Embodiment four:
一次烧结的双金属轴承制造方法是:它依次包括有下列步骤:在优质碳素结构钢板08钢板的表面均匀地铺上CuPb30铜合金粉末,铺粉的厚度取决于所要求的成品双金属轴承对铜合金层的厚度,放入烧结炉中烧结,烧结温度820—880℃;烧结时间22分钟→制成铜—钢双金属轴承材料的板材→经滚轧机轧制,使铜—钢双金属轴承材料的板材达到规定的厚度→根据双金属轴承的尺寸用铜—钢双金属轴承材料的板材下坯料→卷制坯料成大致圆形的轴套→用校正套和芯棒挤压轴套的内外表面,校正轴套的内孔和外圆的尺寸→对轴套切削加工,达到双金属轴承的成品要求→检验→包装、入库。The manufacturing method of a sintered bimetal bearing is: it includes the following steps in turn: evenly spread CuPb30 copper alloy powder on the surface of the high-quality carbon structural steel plate 08 steel plate, and the thickness of the powder depends on the required finished bimetal bearing. The thickness of the alloy layer is put into the sintering furnace for sintering, the sintering temperature is 820-880°C; the sintering time is 22 minutes → the plate made of copper-steel bimetallic bearing material → rolled by a rolling mill to make the copper-steel bimetallic bearing material The plate reaches the specified thickness→according to the size of the bimetallic bearing, use the copper-steel bimetallic bearing material as the lower blank→roll the blank into a roughly circular bushing→extrude the inner and outer surfaces of the bushing with a correction sleeve and mandrel , Calibrate the size of the inner hole and outer circle of the shaft sleeve → cut and process the shaft sleeve to meet the finished product requirements of bimetallic bearings → inspection → packaging and storage.
除了上面所用的几种铜合金粉外,还可以使用如CuSn6.5P0.1等的铜合金粉末。对于双金属轴承尺寸精度要求较高或壁厚较厚的或是原烧结前钢板的精度较低,为保证精度也可以在下坯料前,对铜—钢双金属轴承材料的板材进行轧制和/或校平,如实施例二至四,但即便如此,其工艺比原来仍大有简化。In addition to the several copper alloy powders used above, copper alloy powders such as CuSn6.5P0.1 can also be used. For bimetallic bearings that require high dimensional accuracy or thick wall thickness or low precision of the original steel plate before sintering, in order to ensure accuracy, the copper-steel bimetallic bearing material plate can be rolled and / Or leveling, as embodiment two to four, but even so, its technology is still greatly simplified than before.
上述各种加工的设备、加工工艺参数和方法除了已提到的外,其余与现有的相同,此处不再细述。The above-mentioned various processing equipment, processing parameters and methods are the same as the existing ones except those mentioned, and will not be described in detail here.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2008101210336A CN101363473A (en) | 2008-09-18 | 2008-09-18 | One-time sintering bimetallic bearing manufacturing method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2008101210336A CN101363473A (en) | 2008-09-18 | 2008-09-18 | One-time sintering bimetallic bearing manufacturing method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN101363473A true CN101363473A (en) | 2009-02-11 |
Family
ID=40390018
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNA2008101210336A Pending CN101363473A (en) | 2008-09-18 | 2008-09-18 | One-time sintering bimetallic bearing manufacturing method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101363473A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102806349A (en) * | 2012-08-24 | 2012-12-05 | 李艳 | Method for manufacturing steel and copper bimetallic bearing for excavating machine |
| CN105014068A (en) * | 2015-08-06 | 2015-11-04 | 潘桂枝 | Preparing method for thermometal composite material |
| CN105848812A (en) * | 2013-11-06 | 2016-08-10 | 美国鲁吉斯新泽西州立大学 | Production of monolithic bodies from a porous matrix using low temperature solidification in an additive manufacturing process |
| CN109332704A (en) * | 2018-10-30 | 2019-02-15 | 西安工业大学 | A kind of bimetallic bearing base material and preparation method thereof |
| CN112958768A (en) * | 2021-01-29 | 2021-06-15 | 向朝霞 | Manufacturing process for producing bimetallic sliding bearing by adopting radial reaming method |
-
2008
- 2008-09-18 CN CNA2008101210336A patent/CN101363473A/en active Pending
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102806349A (en) * | 2012-08-24 | 2012-12-05 | 李艳 | Method for manufacturing steel and copper bimetallic bearing for excavating machine |
| CN105848812A (en) * | 2013-11-06 | 2016-08-10 | 美国鲁吉斯新泽西州立大学 | Production of monolithic bodies from a porous matrix using low temperature solidification in an additive manufacturing process |
| CN105848812B (en) * | 2013-11-06 | 2019-04-05 | 美国鲁吉斯新泽西州立大学 | Using low temperature curing in an additive manufacturing process to produce monoliths from porous substrates |
| US10315357B2 (en) | 2013-11-06 | 2019-06-11 | Rutgers, The State University Of New Jersey | Production of monolithic bodies from a porous matrix using low temperature solidification in an additive manufacturing process |
| CN105014068A (en) * | 2015-08-06 | 2015-11-04 | 潘桂枝 | Preparing method for thermometal composite material |
| CN109332704A (en) * | 2018-10-30 | 2019-02-15 | 西安工业大学 | A kind of bimetallic bearing base material and preparation method thereof |
| CN112958768A (en) * | 2021-01-29 | 2021-06-15 | 向朝霞 | Manufacturing process for producing bimetallic sliding bearing by adopting radial reaming method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100486754C (en) | Roll forming method of large and medium hollow disc-shaped forge piece | |
| CN101695739B (en) | Forging process of large tee and large skew tee | |
| US20120214014A1 (en) | Method for producing a composite part | |
| CN104259762A (en) | Forging and forming method for F22 flange ring pieces with non-uniform sections | |
| CN103252627B (en) | A kind of two-layer combined die and processing method | |
| CN102935516A (en) | Sintered metal matrix friction sheet and deep processing production technology thereof | |
| CN109570912A (en) | Titanium alloy ring rolling and bulging combined shaping method | |
| CN103056369A (en) | Process for producing part by powder metallurgy | |
| CN102189263A (en) | Method for efficiently manufacturing bimetal friction plate | |
| CN102922238A (en) | Production process of body flange | |
| CN201618741U (en) | Rolling square and flat steel cover die | |
| CN201350464Y (en) | Liner bushing manufacturing device and liner bushing | |
| CN102049891A (en) | Wear-resistant board and manufacturing method thereof | |
| CN105522087A (en) | Die forging process of granulator press roll | |
| CN102848634A (en) | Easily-molded environment-friendly beryllium bronze-steel bimetallic bearing material and manufacturing method thereof | |
| EP2707158B1 (en) | Method for producing composite parts by means of a combination of deep drawing and impact extrusion | |
| CN100546759C (en) | Rolling forming method of large and medium solid disc-shaped forge piece | |
| CN1059303A (en) | The production technology of powder metallurgy for mechanical structure parts | |
| CN103878550B (en) | A kind of processing technology of the brass bushing with/without flange | |
| CN103831585A (en) | Method for manufacturing flow guiding encirclement plate for nuclear power reactor internals | |
| CN102489513A (en) | Rolling method of high tungsten content tungsten copper sheet | |
| CN102489961A (en) | Method for producing high-purity aluminum-based composite board | |
| CN101532537A (en) | Thin wall embedded self-lubricating bearing and manufacturing method thereof | |
| CN201900465U (en) | Adjustable mandrel for processing fan-shaped plate | |
| CN101831576B (en) | Ti-Al-Cr-Mo alloy and preparation method of plate thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C12 | Rejection of a patent application after its publication | ||
| RJ01 | Rejection of invention patent application after publication |