CN105200920A - Concrete construction technology in high-pier non-bracket turnover formwork construction - Google Patents

Concrete construction technology in high-pier non-bracket turnover formwork construction Download PDF

Info

Publication number
CN105200920A
CN105200920A CN201410233672.7A CN201410233672A CN105200920A CN 105200920 A CN105200920 A CN 105200920A CN 201410233672 A CN201410233672 A CN 201410233672A CN 105200920 A CN105200920 A CN 105200920A
Authority
CN
China
Prior art keywords
concrete
construction
support over
high pier
construction process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410233672.7A
Other languages
Chinese (zh)
Inventor
江海滢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410233672.7A priority Critical patent/CN105200920A/en
Publication of CN105200920A publication Critical patent/CN105200920A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a concrete construction technology in high-pier non-bracket turnover formwork construction. The concrete construction technology comprises the steps of 1 concrete raw material preparing; 2 concrete mixing proportion setting; 3 concrete blending; 4 concrete transporting; 5 concrete pouring; 6 first-segment concrete intensity forming; 7 maintaining. According to the concrete construction technology in high-pier non-bracket turnover formwork construction, the significant superiority and scientificity are achieved, and compared with support construction, the advantages that labors and materials are saved, and the speed is high are achieved, and the construction safety coefficients are increased while the good economic benefit is created.

Description

High pier is without the concrete construction process in support over-form construction
Technical field
The invention belongs to building field, particularly relate to a kind of high pier without the concrete construction process in support over-form construction.
Background technology
The western Expressway Development of China is swift and violent in recent years, and highway construction starts to extend to mountain area, and these regional mountain shapes are precipitous, and the discrepancy in elevation is very large, and narrow space, makes to adopt high pier structure in a large number in bridge construction.Conventional rack construction need set up a large amount of scaffolds, and the not only human and material resources of at substantial, and complex procedures, progress are slow, safety factor is low.
Summary of the invention
The object of this invention is to provide a kind of high pier without the concrete construction process in support over-form construction, solve the problems of the prior art.
For achieving the above object, the present invention is by the following technical solutions:
High pier, without the concrete construction process in support over-form construction, comprises steps A: concrete material, step B: concrete ratio, step C: the mix of concrete, step D: concrete transports, step e: concrete is poured into a mould, step F: first segment concrete strength and step G: maintenance.
Steps A: concrete material, the quality of every raw material that mixing concrete uses and mixture, through inspection, meets the regulation of existing " highway engineering cement concrete testing regulation " (JTJ053).
Step B: concrete ratio, concrete ratio by quality ratio, by design and examination is joined selected; The actual material adopted of construction, the concrete mixture of mixing should meet the execution conditions such as workability, rate of set, and the concrete made meets the quality requirement such as intensity, durability (frost resistance, impervious, anti-erosion).
Step C: the mix of concrete, concrete mix adopts forced mixer, and the mixture mixed should be even, solid colour, must not have segregation and excreting water phenomenon; In discharge process, from unload stream 1/4 to 3/4 between position, take sample, test, ensure that the relative error of slurry density twice measured value is not more than 0.8% in concrete, in unit volume concrete, coarse aggregate content twice measured value relative error is not more than 5%; Concrete mixture must not more than 15min to entering the mould time from lorry mounted mixer discharging.
Step D: concrete transports, concrete transport capacity should adapt to the needs of concrete condensation and poring rate, still keeps the slump of uniformity and regulation when making cast work uninterrupted and make concrete transport to cast place.
Step e: concrete is poured into a mould, if concrete transport reinforcing bar and template find it is qualified on inspection, then can arrange pouring concrete chute between inner and outer template, what concrete conveying adopted is semi-automatic hopper, sends into mould by chute or artificial shovel; Concrete adopts horizontal slice perfusion, vibrates with spud vibrator, and use internal vibration rod to insert soon and pull out slowly, slotting point is evenly distributed, and pointwise is moved, and order is carried out, and moving interval must not exceed 1.5 times of the operating radius that vibrates; Relevant personnel will be had to carry out observation at any time when building concrete, whether all work well, and in the event of any problem, will carry out process in time and complete before the concrete initial set of having built.
Step F: first segment concrete strength, when first segment concrete strength is more than 10Mpa, dabbing cleaning top of concrete, then carry out next joint pier construction.
Step G: maintenance, after often saving concrete form removal, should wrap up geotextiles in time and prevent new fluid concrete to be exposed to the sun under the sun, and watering keeps concrete surface moistening.Curing time is 7-10 days.
Beneficial effect of the present invention: the high pier that the present invention adopts has significant superiority and science without in the concrete construction process in support over-form construction, compared with rack construction, there is saving of labor, material-saving, fireballing advantage, while creating good economic benefit, turn improve construction safety coefficient.
Detailed description of the invention
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with embodiment, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
High pier, without the concrete construction process in support over-form construction, comprises steps A: concrete material, step B: concrete ratio, step C: the mix of concrete, step D: concrete transports, step e: concrete is poured into a mould, step F: first segment concrete strength and step G: maintenance.
Steps A: concrete material, the quality of every raw material that mixing concrete uses and mixture, through inspection, meets the regulation of existing " highway engineering cement concrete testing regulation " (JTJ053).
Step B: concrete ratio, concrete ratio by quality ratio, by design and examination is joined selected; The actual material adopted of construction, the concrete mixture of mixing should meet the execution conditions such as workability, rate of set, and the concrete made meets the quality requirement such as intensity, durability (frost resistance, impervious, anti-erosion).
Step C: the mix of concrete, concrete mix adopts forced mixer, and the mixture mixed should be even, solid colour, must not have segregation and excreting water phenomenon; In discharge process, from unload stream 1/4 to 3/4 between position, take sample, test, ensure that the relative error of slurry density twice measured value is not more than 0.8% in concrete, in unit volume concrete, coarse aggregate content twice measured value relative error is not more than 5%; Concrete mixture must not more than 15min to entering the mould time from lorry mounted mixer discharging.
Step D: concrete transports, concrete transport capacity should adapt to the needs of concrete condensation and poring rate, still keeps the slump of uniformity and regulation when making cast work uninterrupted and make concrete transport to cast place.
Step e: concrete is poured into a mould, if concrete transport reinforcing bar and template find it is qualified on inspection, then can arrange pouring concrete chute between inner and outer template, what concrete conveying adopted is semi-automatic hopper, sends into mould by chute or artificial shovel; Concrete adopts horizontal slice perfusion, vibrates with spud vibrator, and use internal vibration rod to insert soon and pull out slowly, slotting point is evenly distributed, and pointwise is moved, and order is carried out, and moving interval must not exceed 1.5 times of the operating radius that vibrates; Relevant personnel will be had to carry out observation at any time when building concrete, whether all work well, and in the event of any problem, will carry out process in time and complete before the concrete initial set of having built.
Step F: first segment concrete strength, when first segment concrete strength is more than 10Mpa, dabbing cleaning top of concrete, then carry out next joint pier construction.
Step G: maintenance, after often saving concrete form removal, should wrap up geotextiles in time and prevent new fluid concrete to be exposed to the sun under the sun, and watering keeps concrete surface moistening.Curing time is 7-10 days.
The specific embodiment of the present invention is described although above-mentioned in conjunction with the embodiments; but not limiting the scope of the invention; one of ordinary skill in the art should be understood that; on the basis of technical scheme of the present invention, those skilled in the art do not need to pay various amendment or distortion that performing creative labour can make still within protection scope of the present invention.

Claims (8)

1. high pier is without the concrete construction process in support over-form construction, it is characterized in that: comprise steps A: concrete material, step B: concrete ratio, step C: the mix of concrete, step D: concrete transports, step e: concrete is poured into a mould, step F: first segment concrete strength and step G: maintenance.
2. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: steps A: concrete material, the quality of every raw material that mixing concrete uses and mixture, through inspection, meets the regulation of existing " highway engineering cement concrete testing regulation " JTJ053.
3. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step B: concrete ratio, concrete ratio by quality ratio, by design and examination is joined selected; The actual material adopted of construction, the concrete mixture of mixing should meet the execution conditions such as workability, rate of set, and the concrete made meets intensity, durability, frost resistance, impervious, anti-erosion quality requirement.
4. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step C: the mix of concrete, concrete mix adopts forced mixer, and the mixture mixed should be even, solid colour, must not have segregation and excreting water phenomenon; In discharge process, from unload stream 1/4 to 3/4 between position, take sample, test, ensure that the relative error of slurry density twice measured value is not more than 0.8% in concrete, in unit volume concrete, coarse aggregate content twice measured value relative error is not more than 5%; Concrete mixture must not more than 15min to entering the mould time from lorry mounted mixer discharging.
5. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step D: concrete transports, concrete transport capacity should adapt to the needs of concrete condensation and poring rate, still keeps the slump of uniformity and regulation when making cast work uninterrupted and make concrete transport to cast place.
6. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step e: concrete is poured into a mould, if concrete transport reinforcing bar and template find it is qualified on inspection, then can pouring concrete chute be set between inner and outer template, what concrete conveying adopted is semi-automatic hopper, sends into mould by chute or artificial shovel; Concrete adopts horizontal slice perfusion, vibrates with spud vibrator, and use internal vibration rod to insert soon and pull out slowly, slotting point is evenly distributed, and pointwise is moved, and order is carried out, and moving interval must not exceed 1.5 times of the operating radius that vibrates; Relevant personnel will be had to carry out observation at any time when building concrete, whether all work well, and in the event of any problem, will carry out process in time and complete before the concrete initial set of having built.
7. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step F: first segment concrete strength, when first segment concrete strength is more than 10Mpa, dabbing cleaning top of concrete, then carry out next joint pier construction.
8. high pier according to claim 1 is without the concrete construction process in support over-form construction, it is characterized in that: step G: maintenance, after often saving concrete form removal, should wrap up geotextiles in time prevents new fluid concrete to be exposed to the sun under the sun, and watering keeps concrete surface moistening, curing time is 7-10 days.
CN201410233672.7A 2014-05-30 2014-05-30 Concrete construction technology in high-pier non-bracket turnover formwork construction Pending CN105200920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410233672.7A CN105200920A (en) 2014-05-30 2014-05-30 Concrete construction technology in high-pier non-bracket turnover formwork construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410233672.7A CN105200920A (en) 2014-05-30 2014-05-30 Concrete construction technology in high-pier non-bracket turnover formwork construction

Publications (1)

Publication Number Publication Date
CN105200920A true CN105200920A (en) 2015-12-30

Family

ID=54948853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410233672.7A Pending CN105200920A (en) 2014-05-30 2014-05-30 Concrete construction technology in high-pier non-bracket turnover formwork construction

Country Status (1)

Country Link
CN (1) CN105200920A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107366230A (en) * 2017-07-19 2017-11-21 中国冶集团有限公司 A kind of bridge pier column rollover board and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107366230A (en) * 2017-07-19 2017-11-21 中国冶集团有限公司 A kind of bridge pier column rollover board and construction method

Similar Documents

Publication Publication Date Title
CN110903056B (en) High-strength self-compacting fair-faced concrete and preparation method thereof
CN108529966B (en) Design method of anti-seepage and anti-cracking pumping concrete components and pouring forming method
CN103936360A (en) High-performance concrete and its preparation method
CN105198347B (en) A kind of early-strong-fast-hard type enrockment slip casting regeneration concrete and preparation method thereof
CN110966022B (en) Railway tunnel lining construction method based on medium-high fluidity concrete
CN107572981A (en) Self-compacting concrete for concrete repair and preparation method thereof
CN103572966B (en) The construction method of silo funnel liner
CN108218322B (en) C80 high-cast vibration-free self-compacting concrete and construction process thereof
CN104261764A (en) Shrinkage-reducing type concrete interface treating agent and interface treatment method thereof
CN105254204B (en) Channel side slopes cast-in-place concrete compound additive and preparation method thereof
CN101844894A (en) Flexible grout material for concrete pavement
CN102643057A (en) EPS (expanded polystyrene) light aggregate concrete thermal insulation building mould and construction method thereof
CN106630848B (en) A kind of low frequency vibration compacting concrete
CN101747002A (en) High-strength concrete
JP5969426B2 (en) Lightweight filled mortar composition
CN112031458A (en) Concrete structure repairing construction method
CN104712144B (en) A kind of anti-neutron irradiation barite low hydration heat concrete construction method
CN110845204A (en) Polymer repair mortar used under low-temperature condition, and preparation method and construction method thereof
CN104098287A (en) Application method of hydroxypropyl methyl cellulose as thickening agent of cement slurry
JPH0366274B2 (en)
CN108218359B (en) A kind of cement base high-performance microdilatancy filling and injecting slurry material
CN114482409B (en) Top-cast pouring construction method for self-compacting concrete of tubular column
CN110467403A (en) A kind of large expansion self-compacting fair-faced concrete material and preparation method thereof
CN108424088A (en) Self-compaction clear-water concrete and its construction method for bridge prefabrication pier stud
CN116924753A (en) Underwater non-dispersive self-compacting concrete based on multi-element composite rubber material and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20151230

WD01 Invention patent application deemed withdrawn after publication