CN105888198A CN201510009177.2A CN201510009177A CN105888198A CN 105888198 A CN105888198 A CN 105888198A CN 201510009177 A CN201510009177 A CN 201510009177A CN 105888198 A CN105888198 A CN 105888198A
Authority
CN
China
Prior art keywords
building
pipeline
pedestal
piping shaft
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510009177.2A
Other languages
Chinese (zh)
Inventor
虞和登
胡小川
苏天成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DALI CONSTRUCTION GROUP Co Ltd
Hangzhou Xing Yao Construction Group Co Ltd
HUAHENG CONSTRUCTION GROUP CO Ltd
Original Assignee
DALI CONSTRUCTION GROUP Co Ltd
Hangzhou Xing Yao Construction Group Co Ltd
HUAHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALI CONSTRUCTION GROUP Co Ltd, Hangzhou Xing Yao Construction Group Co Ltd, HUAHENG CONSTRUCTION GROUP CO Ltd filed Critical DALI CONSTRUCTION GROUP Co Ltd
Priority to CN201510009177.2A priority Critical patent/CN105888198A/en
Publication of CN105888198A publication Critical patent/CN105888198A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The invention relates to a building pipeline mounting structure, in particular to a mounting structure of a pipeline in a pipeline shaft. Before the end of building construction and the completion of the pipeline shaft, the pipeline is lifted into the pipeline shaft by utilizing a crane, and the height of the crane is corresponding to that of a building; as the height of the building is increased in the construction process, the height of the crane is also increased. The mounting structure of the pipeline, provided by the invention, has the characteristics of being simple, lower in construction cost, smaller in potential safety hazards, shorter in mounting period, smaller in limit on pipeline mounting length, better in mounting efficiency and the like.

Description

Piping shaft Pipe installing structure
Technical field
The present invention relates to a kind of building pipe mounting structure, especially relate to a kind of piping shaft Pipe installing Structure.
Background technology
In modern building, a lot of Pipe installing are in piping shaft, and the piping shaft degree of depth is relatively big, and cross section is empty Between the narrowest, the Pipe installing in piping shaft needs to spend more man power and material.Tradition is built Build the piping shaft pipe installation method in thing by hoist engine as elevating mechanism, complete at architecture construction After, pipeline is first divided into installing the length into piping shaft, is then transported to below the piping shaft of basement, Suspension hook is set at piping shaft top, pipeline is pulled and installs after rising.This mounting means has three shortcomings, Need to spend a large amount of manpower and materials by pipeline transportation to basement, need reserved corresponding engineering, need Piping shaft is installed interim elevating mechanism, if interim fixing point, draws temporary electricity circuit, install Dismounting equipment is needed after one-tenth, and the braking ability less stable of hoist engine, the most vertical operation There is bigger potential safety hazard.
Summary of the invention
It is relatively big that the present invention is primarily directed to the potential safety hazard existing for prior art, and installation period is longer, Pipe installing length limited is relatively big, the technical problem of the poor grade of installation effectiveness, it is provided that a kind of simple in construction, Construction cost is relatively low, and potential safety hazard is less, and installation period is shorter, and Pipe installing length limited is less, Installation effectiveness preferable piping shaft Pipe installing structure.
The above-mentioned technical problem of the present invention is mainly addressed by following technical proposals: in building Before thing construction not yet terminates, piping shaft does not bind, and utilizes tower crane to hang in piping shaft by pipeline, builds If building thing to be made up of subterranean layer and ground dried layer, Pipe installing, in the piping shaft of building, is built Building and be provided with piping shaft in thing, building is outside equipped with tower crane, sets between each floor in building Being equipped with pedestal, pedestal is fixed on piping shaft, and pedestal becomes round pie, two half identical cakes spell Dress composition, pedestal is provided with hole for hoist, and pedestal is outside equipped with kayser, and lifting pipeline is inserted by tower crane In pedestal.The height of the height correspondence building of tower crane, building increases at building course camber, The height of tower crane is identical to be increased.
In architecture construction often increases by one layer of piping shaft that pipeline can hang in each layer, minimizing is hung Tower in the time of work high above the ground, simultaneously as pipeline by under hang in installation, not by space shadow Ringing, it is not necessary to every segment pipe length reduced, the hole for hoist on pedestal can ensure that pipeline is in lifting simultaneously Entering the perpendicularity after building, after having lifted, unclamp the kayser outside pedestal, pedestal can conveniently be removed.
Therefore, the present invention has simple in construction, and construction cost is relatively low, and potential safety hazard is less, erector The features such as the phase is shorter, and Pipe installing length limited is less, and installation effectiveness is preferable.
Accompanying drawing explanation
Accompanying drawing 1 is the overall structure schematic diagram of the present invention;
Accompanying drawing 2 is the base construction schematic diagram of the present invention.
Detailed description of the invention
Below by embodiment, and combine accompanying drawing, technical scheme is made the most concrete Explanation.
Embodiment 1: building 4, by subterranean layer and ground up of three layers, is provided with one in building 4 Individual piping shaft 5, building 4 is outside equipped with a tower crane 6, arranges between each floor in building 4 Having a pedestal 1, pedestal 1 is fixed on piping shaft 5, and pedestal 1 becomes round pie, by two identical half Cake is assemblied to form, and pedestal 1 is provided with three holes for hoist 2, and hole for hoist 2 is along assembled line arrangement, base Seat 1 is outside equipped with kayser 3, and pipeline 7 is lifted in the hole for hoist 2 inserted in pedestal 1 by tower crane 6, has lifted Cheng Hou, opens kayser 3, removes pedestal 1 (as illustrated in fig. 1 and 2).
The height of building 4 is that three floors are high, and the height of tower crane 6 is that five floors are high, when building of building 4 Making when being highly raised to four floor height, the height of tower crane 6 is that six floors are high.

Claims (2)

1. a piping shaft Pipe installing structure, if building is made up of subterranean layer and ground dried layer, Pipe installing is in the piping shaft of building, it is characterised in that arrange in described building (4) Piping shaft (5), building (4) is had to be outside equipped with tower crane (6), every in building (4) Being provided with pedestal (1) between individual floor, pedestal (1) is fixed on piping shaft (5), pedestal (1) becoming round pie, two half identical cakes be assemblied to form, pedestal is provided with on (1) Hole for hoist (2), pedestal (1) is outside equipped with kayser (3), and tower crane (6) is by pipeline (7) Lifting is inserted in pedestal (1).
Piping shaft Pipe installing structure the most according to claim 1, it is characterised in that described tower crane (6) The height of height correspondence building (4), building (4) increases at building course camber, The height of tower crane (6) is identical to be increased.
CN201510009177.2A 2015-01-02 2015-01-02 Mounting structure of pipeline in pipeline shaft Pending CN105888198A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510009177.2A CN105888198A (en) 2015-01-02 2015-01-02 Mounting structure of pipeline in pipeline shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510009177.2A CN105888198A (en) 2015-01-02 2015-01-02 Mounting structure of pipeline in pipeline shaft

Publications (1)

Publication Number Publication Date
CN105888198A true CN105888198A (en) 2016-08-24

Family

ID=56999295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510009177.2A Pending CN105888198A (en) 2015-01-02 2015-01-02 Mounting structure of pipeline in pipeline shaft

Country Status (1)

Country Link
CN (1) CN105888198A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107737A (en) * 2019-05-10 2019-08-09 中国建筑第八工程局有限公司 The pipe installation method and its mounting device for the pipe well being connected to basement
CN113137033A (en) * 2021-04-06 2021-07-20 北京中科中电电力工程管理有限公司 Power pipe well and construction process thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0762884A (en) * 1993-08-31 1995-03-07 Mitsui Eng & Shipbuild Co Ltd Building prefabricated shaft unit
JP2000230272A (en) * 1999-02-10 2000-08-22 Mk:Kk Pre-assembling method for kitchen and sanitary room for building
CN103243926A (en) * 2013-05-13 2013-08-14 中建五局第三建设有限公司 Construction method for hoisting pipe well vertical pipe in high-rise building engineering
CN103603504A (en) * 2013-11-26 2014-02-26 中建二局第三建筑工程有限公司 Method of hoisting super high-rise building electrochemical large-diameter rises along with progress of main structure
CN103692195A (en) * 2013-12-20 2014-04-02 中国五冶集团有限公司 Pipe installation method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0762884A (en) * 1993-08-31 1995-03-07 Mitsui Eng & Shipbuild Co Ltd Building prefabricated shaft unit
JP2000230272A (en) * 1999-02-10 2000-08-22 Mk:Kk Pre-assembling method for kitchen and sanitary room for building
CN103243926A (en) * 2013-05-13 2013-08-14 中建五局第三建设有限公司 Construction method for hoisting pipe well vertical pipe in high-rise building engineering
CN103603504A (en) * 2013-11-26 2014-02-26 中建二局第三建筑工程有限公司 Method of hoisting super high-rise building electrochemical large-diameter rises along with progress of main structure
CN103692195A (en) * 2013-12-20 2014-04-02 中国五冶集团有限公司 Pipe installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107737A (en) * 2019-05-10 2019-08-09 中国建筑第八工程局有限公司 The pipe installation method and its mounting device for the pipe well being connected to basement
CN113137033A (en) * 2021-04-06 2021-07-20 北京中科中电电力工程管理有限公司 Power pipe well and construction process thereof

Similar Documents

Publication Publication Date Title
CN203064994U (en) Lifting device for disassembling negative ring segments
CN105836640B (en) Climbing tower-crane is from climbing fixing device and method
CN105888198A (en) Mounting structure of pipeline in pipeline shaft
CN205077878U (en) Unit type curtain plate hoisting device
CN203889942U (en) Lifting device
CN202882376U (en) Elevator shaft template support platform
CN202220435U (en) Reverse construction underground concrete structure formwork descending equipment
CN203461720U (en) Simple cantilever hoisting machine
CN101660660A (en) Novel installing method of gas cabinet
CN203998724U (en) A kind of tower machine attached wall assembling and disassembling stand
CN204592635U (en) A kind of flange with pile body mounting hole mould
CN209890068U (en) Temporary fixing device for hoisting reinforcement cage and placing grouting pipe
CN204435856U (en) A kind of special steel concrete sliding formwork
CN203187370U (en) Inner mast hoisting device
CN203361662U (en) Large net rack short-distance lifting device
CN103121629B (en) Hoisting method of large support equipment for basement
CN201942529U (en) Alumina decomposition tank
CN204626263U (en) A kind of outrigger structure for installing steel box-girder
CN202007087U (en) Ultralow gantry crane with electric hoist
CN202744172U (en) Ground-to-air transfer frame for separable colorful steel plates
CN205099232U (en) Hanging flower basket formula hoisting apparatus
CN206188271U (en) Tower crane chassis supports ballast structure
CN202124413U (en) Self-discharging brick hoisting cage
CN204626459U (en) Electric power communication cable active well
CN203903876U (en) Convenient embedded part lifting adjusting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160824