CN107587497A - A kind of method for improving hydraulic reclamation flatness - Google Patents
A kind of method for improving hydraulic reclamation flatness Download PDFInfo
- Publication number
- CN107587497A CN107587497A CN201710748133.0A CN201710748133A CN107587497A CN 107587497 A CN107587497 A CN 107587497A CN 201710748133 A CN201710748133 A CN 201710748133A CN 107587497 A CN107587497 A CN 107587497A
- Authority
- CN
- China
- Prior art keywords
- pipe
- blow
- hydraulic reclamation
- fill
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
技术领域technical field
本发明涉及水利工程技术领域,更具体地,涉及一种提高吹填平整度的方法。The invention relates to the technical field of water conservancy engineering, in particular to a method for improving the levelness of dredging and filling.
背景技术Background technique
随着我国改革开放的不断深化,社会经济迅猛发展,在人口稠密、经济发达的沿海地区,特别是沿海港口,对土地的需求日益增长,围海造地项目日益增多,吹填逐渐被广泛应用于这些工程之中。现在越来越多的吹填技术被用于围海造地,港区开发,建造场地。吹填后需要在吹填的砂面进行后期堆载预压等一些列的施工项目,所以吹填的平整度对后期施工有着至关重要的作用。With the continuous deepening of my country's reform and opening up and the rapid development of social economy, in densely populated and economically developed coastal areas, especially coastal ports, the demand for land is increasing, and reclamation projects are increasing, and dredging reclamation is gradually being widely used. among these projects. Now more and more dredging reclamation technologies are being used for land reclamation, port area development, and site construction. After dredging, it is necessary to carry out a series of construction projects such as post-loading and preloading on the sand surface of dredging, so the flatness of dredging plays a vital role in the later construction.
吹填区平整度控制方法一般有水力法、机械整平法。水力法即在施工中,通过水流的挟泥能力,合理的控制泥浆的流向、流速,使得最终的平整度达到设计及规范要求。机械法主要采用挖掘机、推土机、自卸汽车等在吹填区内进行二次倒运,将高程高的位置的泥土运至高程不足的位置,达到平整场地、控制吹填平整度的目的。一个吹填工程,吹填面积动辄数平方公里,依托于机械整平很不经济,且受施工场地条件限制大。There are generally hydraulic methods and mechanical leveling methods for controlling the flatness of dredged reclamation areas. The hydraulic method means that during the construction, the flow direction and flow velocity of the mud are reasonably controlled through the mud-carrying ability of the water flow, so that the final flatness meets the design and specification requirements. The mechanical method mainly uses excavators, bulldozers, dump trucks, etc. to carry out secondary transportation in the dredging reclamation area, and transport the soil from the position with high elevation to the position with insufficient elevation, so as to achieve the purpose of leveling the site and controlling the flatness of dredging and filling. For a dredging reclamation project, the dredging reclamation area can be several square kilometers, and it is uneconomical to rely on mechanical leveling, and it is greatly restricted by the conditions of the construction site.
在一些礁疏浚吹填工程中,吹填区沉淀池下层是粉细砂,标高已接近设计标高,需要补吹的吹填层厚较薄,而常规吹填管头的冲刷力较强,扩散面积小,无法满足工程需要。In some reef dredging and reclamation projects, the lower layer of the sedimentation tank in the reclamation area is fine sand, and its elevation is close to the design elevation. The area is small and cannot meet the needs of the project.
发明内容Contents of the invention
本发明提供一种提高吹填平整度的方法,以解决上现有吹填方法吹填平整度不高及精确度低的技术问题。The invention provides a method for improving the levelness of blow-filling, so as to solve the technical problems of low levelness and low accuracy of blow-filling in the existing blow-filling method.
根据本发明的一个方面,提供一种提高吹填平整度的方法,包括以下步骤:According to one aspect of the present invention, there is provided a method for improving the levelness of dredging and filling, comprising the following steps:
S1、在待吹填区域布设吹填管,并在所述吹填管末端装设消能器;S1. Arrange blowing and filling pipes in the area to be blown and filled, and install an energy dissipator at the end of the blowing and filling pipes;
S2、在吹填管不摆动状态下,获取所述吹填管管头与所述吹填管管头可覆盖范围边界点之间的距离、所述吹填管管头与所述吹填管管头可覆盖范围边界点之间连线与所述吹填管头轴线之间的角度和所述吹填管管头轴线与临时围堰之间的垂直距离,计算获取吹填管的摆动角度;S2. In the state where the blowing and filling pipe is not swinging, obtain the distance between the head of the blowing and filling pipe and the boundary point of the range that the head of the blowing and filling pipe can cover, the distance between the head of the blowing and filling pipe and the boundary point of the blowing and filling pipe Calculate and obtain the swing angle of the blow-fill pipe by calculating the angle between the line between the boundary points of the pipe head and the axis of the blow-fill pipe head and the vertical distance between the pipe head axis of the blow-fill pipe and the temporary cofferdam ;
S3、基于所述吹填管的摆动角度,对吹填区进行填充。S3. Based on the swing angle of the blow-fill pipe, fill the blow-fill area.
在上述方案基础上优选,所述步骤S1还包括:在所述吹填管的消能器末端加装橡胶摆动管。Preferably, on the basis of the above solution, the step S1 further includes: installing a rubber swing pipe at the end of the energy dissipator of the blow-fill pipe.
在上述方案基础上优选,所述橡胶摆动管的摆动角度为0°至90°。Preferably, on the basis of the above solution, the swing angle of the rubber swing tube is 0° to 90°.
在上述方案基础上优选,所述步骤S2的数学计算公式为:Preferably on the basis of the above scheme, the mathematical calculation formula of the step S2 is:
α=arcsin(Lb/La)-β;α=arcsin(Lb/La)-β;
其中,La表示所述吹填管管头与所述吹填管管头可覆盖范围边界点之间的距离,β表示所述吹填管管头与所述吹填管管头可覆盖范围边界点之间连线与所述吹填管头轴线之间的角度、Lb表示所述吹填管管头轴线与临时围堰之间的垂直距离,α表示所述吹填管的摆动角度。Wherein, La represents the distance between the nozzle head of the blow-fill pipe and the boundary point of the coverable range of the head of the blow-fill pipe, and β represents the boundary point of the coverable range between the head of the blow-fill pipe and the head of the blow-fill pipe The angle between the line connecting the points and the axis of the blow-fill pipe head, Lb represents the vertical distance between the head axis of the blow-fill pipe and the temporary cofferdam, and α represents the swing angle of the blow-fill pipe.
在上述方案基础上优选,所述吹填管为橡胶自浮管。Preferably on the basis of the above scheme, the blow-fill pipe is a rubber self-floating pipe.
本发明的一种提高吹填平整度的方法,通过在吹填管上增设消能器,以提高吹填管的扩散面积,降低管口冲力,从而以起到准确控制吹填区标高,提高吹填平整度的目的。A method for improving the flatness of blow-fill according to the present invention, by adding an energy dissipator on the blow-fill pipe, to increase the diffusion area of the blow-fill pipe and reduce the impulse force of the nozzle, so as to accurately control the elevation of the blow-fill area and improve The purpose of blow fill levelness.
作为本发明的另一优点在于,本发明还可根据吹填管头与待吹填区域之间的距离等,以准确获取不同待吹填区域的吹填管所需摆动角度,以进一步精确控制吹填区的平整度及其标高。Another advantage of the present invention is that the present invention can also accurately obtain the required swing angles of the blow-fill pipes in different areas to be filled according to the distance between the head of the blow-fill pipe and the area to be filled, so as to further precisely control The flatness and elevation of the reclamation area.
附图说明Description of drawings
图1为本发明的一种提高吹填平整度的方法的流程框图;Fig. 1 is a kind of process block diagram of the method for improving blow-fill levelness of the present invention;
图2为本发明的一种提高吹填平整度的方法的原理图;Fig. 2 is a schematic diagram of a method for improving the flatness of blow filling of the present invention;
图3为本发明的消能器的结构示意图。Fig. 3 is a structural schematic diagram of the energy dissipator of the present invention.
具体实施方式detailed description
下面结合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific implementation manners of the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
需要说明的是,本发明的一种提高吹填平整度的方法,是基于浮动式临时围堰进行的,其中,浮动式临时围堰,包括浮动式防波堤、内侧挡堰和反回流堰,浮动式防波堤与反回流堰垂直设置形成L形的围栏,内侧挡堰装设在反回流堰外侧与浮动式防波堤平行设置,且反回流堰上装设有吹填管,吹填管穿过反回流堰向浮动式防波堤一侧延伸,且浮动式防波堤由橡胶自浮管拼接而成It should be noted that a method of improving the levelness of dredging and filling according to the present invention is based on floating temporary cofferdams, wherein the floating temporary cofferdams include floating breakwaters, inner weirs and reverse flow weirs, floating The vertical breakwater and the anti-reflux weir are arranged vertically to form an L-shaped fence. The inner barrier weir is installed outside the anti-reflux weir in parallel with the floating breakwater, and the anti-reflux weir is equipped with a blow-fill pipe, which passes through the anti-reflux weir. Extending to one side of the floating breakwater, and the floating breakwater is spliced by rubber self-floating pipes
使用时,首先根据需要吹填的区域,将浮动式临时围堰装设在吹填边界方向上并予以固定,然后通过本发明的技术方案,对吹填区进行吹填。When in use, firstly, according to the area to be filled, the floating temporary cofferdam is installed in the direction of the boundary of the filling and fixed, and then the filling area is blown and filled through the technical scheme of the present invention.
为了进一步详细说明本发明的技术方案,请参阅图1所示,本发明提供一种提高吹填平整度的方法,包括以下步骤:In order to further describe the technical solution of the present invention in detail, please refer to Fig. 1, the present invention provides a method for improving the levelness of blowing and filling, comprising the following steps:
S1、在待吹填区域布设吹填管,并在吹填管末端装设消能器,以降低管头处吹填物料的流速,防止冲刷,使得吹填物料均匀的散落在吹填区内;S1. Arrange the blow-fill pipe in the area to be blow-filled, and install an energy dissipator at the end of the blow-fill pipe to reduce the flow rate of the blow-fill material at the head of the pipe, prevent erosion, and make the blow-fill material evenly scattered in the blow-fill area ;
S2、在吹填管不摆动状态下,通过测量以获取吹填管管头与吹填管管头可覆盖范围边界点之间的距离、吹填管管头与吹填管管头可覆盖范围边界点之间的连线与吹填管头轴线之间的角度和吹填管管头轴线与临时围堰之间的垂直距离,计算获取吹填管的摆动角度;S2. In the state where the blow-fill pipe does not swing, measure to obtain the distance between the head of the blow-fill pipe and the boundary point of the coverage area of the head of the blow-fill pipe, and the coverable range of the head of the blow-fill pipe and the head of the blow-fill pipe Calculate the swing angle of the blow-fill pipe from the angle between the line between the boundary points and the axis of the blow-fill pipe head and the vertical distance between the head axis of the blow-fill pipe and the temporary cofferdam;
S3、根据计算获得到的吹填管的摆动角度,调整吹填管的摆动角度对吹填区进行填充。S3. According to the calculated swing angle of the blow-fill pipe, adjust the swing angle of the blow-fill pipe to fill the blow-fill area.
本发明由于在吹填管管头装设了消能器,利用消能器以控制吹填物料的流速,并通过检测计算,以获取吹填管的摆动角度,根据吹填管的摆动角度,以填充吹填区,从而以防止摆动角度过小造成的吹填高度过高或者摆动角度过大造成的吹填高度过低的问题,以保证其吹填平整度,提高其施工效率。其中,消能器的结构请参阅图3所示。In the present invention, an energy dissipator is installed at the head of the blow-fill pipe, and the energy dissipator is used to control the flow rate of the blow-fill material, and through detection and calculation, to obtain the swing angle of the blow-fill pipe, according to the swing angle of the blow-fill pipe, To fill the dredging filling area, so as to prevent the problem of too high filling height caused by too small swing angle or too low filling height caused by too large swing angle, so as to ensure the flatness of blown filling and improve its construction efficiency. Wherein, please refer to Fig. 3 for the structure of the energy dissipator.
在本发明的另一优选实施方案中,本发明的步骤S1还包括:在吹填管的消能器末端加装橡胶摆动管,通过橡胶摆动管进一步增大吹填管的摆动角度,从而不仅可扩大其吹填面积,提高其施工效率,而且由于橡胶摆动管的特性,可有效提高吹填区的平整度。优选的,本实用新型的橡胶摆动管的摆动角度为0°至90°。In another preferred embodiment of the present invention, step S1 of the present invention also includes: installing a rubber swing tube at the end of the energy dissipator of the blow-fill tube, and further increasing the swing angle of the blow-fill tube through the rubber swing tube, so that not only Enlarging the blowing filling area, improving its construction efficiency, and due to the characteristics of the rubber swing pipe, it can effectively improve the flatness of the blowing filling area. Preferably, the swing angle of the rubber swing tube of the present invention is 0° to 90°.
请继续参阅图2所示,本发明的步骤S2的数学计算公式为:Please continue to refer to shown in Figure 2, the mathematical calculation formula of step S2 of the present invention is:
α=arcsin(Lb/La)-β;α=arcsin(L b /L a )-β;
其中,La表示所述吹填管管头与所述吹填管管头可覆盖范围边界点之间的距离,β表示所述吹填管管头与所述吹填管管头可覆盖范围边界点之间连线与所述吹填管头轴线之间的角度、Lb表示所述吹填管管头轴线与临时围堰之间的垂直距离,α表示所述吹填管的摆动角度。Wherein, L a represents the distance between the head of the blowing and filling pipe and the boundary point of the coverage of the head of the blowing and filling pipe, and β represents the covering range between the head of the blowing and filling pipe and the head of the blowing and filling pipe The angle between the line between the boundary points and the axis of the blow-fill pipe head, L b represents the vertical distance between the head axis of the blow-fill pipe and the temporary cofferdam, and α represents the swing angle of the blow-fill pipe .
值得说明的是,本发明的吹填管为橡胶自浮管,且吹填管的布设分为水上管线布设和陆上管线布设。It is worth noting that the blow-fill pipe of the present invention is a rubber self-floating pipe, and the layout of the blow-fill pipe is divided into the laying of pipelines on water and the laying of land pipelines.
其中,水上铺设管线应根据施工地点的自然条件确定合理的管线连接方式,防止在风浪大的时候出现断管的施工事故。水上固定管段的吹填管多采用自浮管,或钢管与挠性管间接相连,钢管段由双体平台承载,并用管线锚固定。特殊情况下可采用沉管。水上浮管一般是先组装成分段,分段长度以150-160m为宜。在组装水上浮管分段的同时应将施工锚布置妥当。然后将每段水上浮管拖带到施工区就位,通常从沉管头或水陆架头开始依次对接。Among them, the laying of pipelines on water should determine a reasonable pipeline connection method according to the natural conditions of the construction site, so as to prevent construction accidents of broken pipes when there are strong winds and waves. The blow-fill pipes for the fixed pipe sections on the water mostly use self-floating pipes, or steel pipes are indirectly connected with flexible pipes, and the steel pipe sections are carried by double-body platforms and fixed with pipeline anchors. Immersed tubes can be used in special cases. Floating pipes on water are generally assembled into segments first, and the segment length is preferably 150-160m. The construction anchors should be arranged properly while assembling the floating pipe sections above water. Then each section of floating pipe on the water is towed to the construction area and placed in place, usually starting from the immersed pipe head or the water shelf head and docking sequentially.
在海区或感潮河段浮管一般利用高平潮进行。其方法如下:先将卡接好浮管与陆上排泥管头卡接好或固定在排泥区;然后将浮管的另一端与挖泥船艉排泥管卡接好;最后用拖轮或锚艇顶顺水浮管,及时将涨、落潮方向的管子锚抛设好。Floating pipes in sea areas or tidal river sections are generally carried out using high and low tides. The method is as follows: firstly connect the floating pipe with the head of the onshore mud discharge pipe or fix it in the mud discharge area; then connect the other end of the floating pipe with the stern pipe of the dredger; Or the top of the anchor boat floats along the water pipe, and the pipe anchors in the direction of rising and falling tides are set in time.
而陆上吹填管线布设包括陆上吹填管和水陆管架二部分,水陆管线连接有二种方法:一种是直接与水上吹填管软管联接,一种是中间架设管架或平台连接。The layout of land-based dredging-fill pipelines includes two parts: land-based dredging-fill pipes and water-land pipe racks. There are two ways to connect land-water pipelines: one is to directly connect with the hoses of the water-based dredging-fill pipes, and the other is to erect pipe racks or platforms in the middle. connect.
在吹填管纤布设的过程中,应尽量布设陆上吹填管,而减少水上布设吹填管,从而减少水上排泥管水力损失。In the process of laying out the dredging and filling pipe fibers, it is necessary to arrange the land dredging and filling pipes as much as possible, and reduce the laying of the dredging and filling pipes on the water, so as to reduce the hydraulic loss of the mud discharge pipes on the water.
本发明的一种提高吹填平整度的方法,通过在吹填管上增设消能器,以提高吹填管的扩散面积,降低管口冲力,从而以起到准确控制吹填区标高,提高吹填平整度的目的。A method for improving the flatness of blow-fill according to the present invention, by adding an energy dissipator on the blow-fill pipe, to increase the diffusion area of the blow-fill pipe and reduce the impulse force of the nozzle, so as to accurately control the elevation of the blow-fill area and improve The purpose of blow fill levelness.
作为本发明的另一优点在于,本发明还可根据吹填管头与待吹填区域之间的距离等,以准确获取不同待吹填区域的吹填管所需摆动角度,以进一步精确控制吹填区的平整度及其标高。Another advantage of the present invention is that the present invention can also accurately obtain the required swing angles of the blow-fill pipes in different areas to be filled according to the distance between the head of the blow-fill pipe and the area to be filled, so as to further precisely control The flatness and elevation of the reclamation area.
最后,本申请的方法仅为较佳的实施方案,并非用于限定本发明的保护范围。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, the method of the present application is only a preferred embodiment, and is not intended to limit the protection scope of the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710748133.0A CN107587497B (en) | 2017-08-28 | 2017-08-28 | A Method of Improving the Levelness of Blow Filling |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710748133.0A CN107587497B (en) | 2017-08-28 | 2017-08-28 | A Method of Improving the Levelness of Blow Filling |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107587497A true CN107587497A (en) | 2018-01-16 |
| CN107587497B CN107587497B (en) | 2019-09-27 |
Family
ID=61041763
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710748133.0A Active CN107587497B (en) | 2017-08-28 | 2017-08-28 | A Method of Improving the Levelness of Blow Filling |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107587497B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109137943A (en) * | 2018-08-28 | 2019-01-04 | 中交上海航道局有限公司 | A kind of earthwork filling construction technique of Perioperative cardiac events |
| CN110258690A (en) * | 2019-06-28 | 2019-09-20 | 中交天航港湾建设工程有限公司 | Anti-extrusion become silted up in hydraulic reclamation area dissipates paving construction energy dissipator and energy-dissipating system and construction method |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1027328A1 (en) * | 1981-03-25 | 1983-07-07 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова | Method and apparatus for hydraulic filling of dams |
| CN202989978U (en) * | 2012-11-07 | 2013-06-12 | 中交天航南方交通建设有限公司 | Scattered energy dissipative device |
| CN204570663U (en) * | 2015-05-07 | 2015-08-19 | 程义吉 | Hydraulic reclamation district barged-in fill isotropic deposit tapping equipment |
-
2017
- 2017-08-28 CN CN201710748133.0A patent/CN107587497B/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1027328A1 (en) * | 1981-03-25 | 1983-07-07 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова | Method and apparatus for hydraulic filling of dams |
| CN202989978U (en) * | 2012-11-07 | 2013-06-12 | 中交天航南方交通建设有限公司 | Scattered energy dissipative device |
| CN204570663U (en) * | 2015-05-07 | 2015-08-19 | 程义吉 | Hydraulic reclamation district barged-in fill isotropic deposit tapping equipment |
Non-Patent Citations (1)
| Title |
|---|
| 张志卿: "厦门港海沧港区疏浚及吹填造地施工质量控制", 《沿海企业与科技》 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109137943A (en) * | 2018-08-28 | 2019-01-04 | 中交上海航道局有限公司 | A kind of earthwork filling construction technique of Perioperative cardiac events |
| CN110258690A (en) * | 2019-06-28 | 2019-09-20 | 中交天航港湾建设工程有限公司 | Anti-extrusion become silted up in hydraulic reclamation area dissipates paving construction energy dissipator and energy-dissipating system and construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN107587497B (en) | 2019-09-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105672195B (en) | Suction Dredging Construction engineering method is twisted under a kind of urban ecology urban river water | |
| CN111254981B (en) | Draw formula suspension tunnel structure to one side under water | |
| CN106120859B (en) | Construction method for river crossing by multi-pipe-section immersed tube | |
| CN103628507B (en) | Push pipe passes through the shallow earthing anti-floating construction method in seabed | |
| CN1256531C (en) | Construction method for river crossing pipeline | |
| CN204491693U (en) | Long distance blast system | |
| CN111424716B (en) | An artificial island relay extension cable-stayed anchor-type suspension tunnel structure | |
| CN104975612A (en) | Novel water open caisson construction technology | |
| CN109137943B (en) | Earth filling construction process for sea reclamation | |
| CN109024525B (en) | An artificial island structure considering the development and utilization of underground space and its construction method | |
| CN107587497B (en) | A Method of Improving the Levelness of Blow Filling | |
| CN108867758B (en) | A dock caisson water intake device and construction method | |
| CN109356184A (en) | A kind of construction method of immersed pipe with anti-rainbow culvert across the river | |
| CN103510486A (en) | Method for carrying out south-to-north water diversion along coastline cofferdam | |
| CN108532546B (en) | Method for reversed-order excavation of harbor basin and channel | |
| CN106638651A (en) | Sea fan buoyant foundation integral installing technology | |
| CN106368217A (en) | Assembled barge water operation platform and construction method thereof | |
| CN1262780C (en) | Construction method for polyvinyl plastic pipeline long distance deep water crossing river | |
| CN113047215B (en) | High stake pier structure of medium plate stake | |
| CN118621791A (en) | A method for laying underwater submerged pipe | |
| CN102191775A (en) | Pile stabilizing method in combination of artificial foundation bed of exposed bedrock and cantilever | |
| CN106120802A (en) | It is close to the most wired large-span continuous beam deep water foundation excavation method under water | |
| CN216618771U (en) | Underwater immersed tube structure | |
| CN115748871A (en) | Construction method for river dredging engineering | |
| CN101408028B (en) | Control method of steel buoyant tank sinking plane position |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |