CN109299546A - Curtain wall engineering amount statistical method based on BIM - Google Patents

Curtain wall engineering amount statistical method based on BIM Download PDF

Info

Publication number
CN109299546A
CN109299546A CN201811138944.XA CN201811138944A CN109299546A CN 109299546 A CN109299546 A CN 109299546A CN 201811138944 A CN201811138944 A CN 201811138944A CN 109299546 A CN109299546 A CN 109299546A
Authority
CN
China
Prior art keywords
curtain wall
cladding glass
detail list
software
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811138944.XA
Other languages
Chinese (zh)
Inventor
施海斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Dajibu Technology Development Co Ltd
Original Assignee
Zhejiang Dajibu Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Dajibu Technology Development Co Ltd filed Critical Zhejiang Dajibu Technology Development Co Ltd
Priority to CN201811138944.XA priority Critical patent/CN109299546A/en
Publication of CN109299546A publication Critical patent/CN109299546A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a kind of curtain wall engineering amount statistical methods, include the following steps, set up the original curtain wall model of modularization, parametrization in Revit or Rhino software according to construction drawing;The cladding glass in original curtain wall model is numbered by dynamo or grasshopper software and quantity statistics;To the cladding glass number and quantity statistics shown in Revit or Rhino software in original curtain wall model, and the cladding glass geometric dimension and cladding glass area of each number is calculated, generate the detail list including cladding glass number, cladding glass area and cladding glass geometric dimension;Curtain wall construction scheme is preset in BIM software, detail list is uploaded to BIM software, default curtain wall construction scheme and detail list are combined and automatically generate secondary detail list, and generates project amount statistics.The present invention improves the speed and efficiency of area statistics and curtain wall number, and the time for shortening modeling and corresponding data processing substantially increases construction speed so as to shorten the project cycle.

Description

Curtain wall engineering amount statistical method based on BIM
Technical field
The present invention relates to a kind of the realm of building construction, in particular to a kind of curtain wall engineering amount statistical method.
Background technique
Large-scale with the development of society and the progress of science and technology, high-rise complicated building is more and more, curtain wall engineering Also increase gradually, the statistics of curtain wall engineering amount is caused also more to be taken seriously, there are curtain walls for traditional curtain wall engineering amount statistics It does not number, the problem of information content deficiency brings inconvenience to the Maintenance and Repair in later period.
Summary of the invention
The object of the present invention is to provide a kind of curtain wall engineering amount statistical methods.The present invention improves area statistics and curtain The speed and efficiency of wall number, the time for shortening modeling and corresponding data processing greatly improve so as to shorten the project cycle Construction speed;In addition, also being recorded in detail to the information of cladding glass, thus to the follow-up maintenance side of bringing of cladding glass Just.
Technical solution of the present invention: a kind of curtain wall engineering amount statistical method includes the following steps,
S1: original curtain wall model is established in Revit or Rhino software according to construction drawing;
S2: being numbered the cladding glass in original curtain wall model by dynamo or grasshopper software and Quantity statistics;
S3: showing cladding glass number and the quantity statistics in original curtain wall model in Revit or Rhino software, And the cladding glass geometric dimension and cladding glass area of each number is calculated, generating includes cladding glass number, curtain wall The detail list of transparency area and cladding glass geometric dimension;
S4: curtain wall construction scheme is preset in BIM software, detail list is uploaded to BIM software, by default curtain wall construction side Case and detail list combine construction requirement, mounting means, erection sequence and the curtain wall glass for automatically generating each number cladding glass The secondary detail list of the attribute of glass, and generate project amount statistics.
Above-mentioned curtain wall engineering amount statistical method, according to step S4, by the curtain wall construction side for obtaining project under construction scene Case adjusts original curtain wall model in Revit or Rhino according to live curtain wall construction scheme, obtains secondary curtain wall model, and generate The detail list of corresponding secondary curtain wall model.
It further include the installation component letter of cladding glass in secondary detail list described in curtain wall engineering amount statistical method above-mentioned Breath, floor location information;The installation component information includes the model specification of installation component, technical parameter.
Curtain wall engineering amount statistical method above-mentioned, the attribute of the cladding glass include the physical property of cladding glass, Specifications and models, unit price, technical parameter and material category.
Curtain wall engineering amount statistical method above-mentioned, when change, parametrization occur for the component in the secondary curtain wall model When the engineering attribute of component changes or increases component newly, the detail of secondary curtain wall model described in simultaneously synchronized update is counted again Table.
Compared with prior art, the invention has the following advantages:
1, the present invention improves the speed and efficiency of area statistics and curtain wall number, shortens modeling and corresponding data processing Time, so as to shorten the project cycle.
2, the present invention is by establishing corresponding curtain wall model according to construction drawing, and to the cladding glass in curtain wall model into Row number, so that the detail list containing cladding glass area, cladding glass area geometric dimension, number and quantity is generated, system The project amount of cladding glass is counted out, is controlled convenient for the construction speed to curtain wall.
3, the combining default curtain wall construction scheme and detail list of the cladding glass in the present invention automatically generates each number The construction requirement of cladding glass, mounting means, erection sequence and cladding glass attribute secondary detail list, convenient for intuitive Understand the shape specification of corresponding cladding glass.Wherein, the attribute of cladding glass includes the physical property of cladding glass, specification type Number, unit price, technical parameter and material category, it is detailed to provide the information of corresponding cladding glass, to give curtain wall glass The follow-up maintenance of glass is brought convenience.
4, when change occurs for the component in secondary curtain wall model, the engineering attribute of parametrization component changes or increase newly structure When part, the detail list of the secondary curtain wall model of project amount described in simultaneously synchronized update is counted again, timely updates and keeps information It synchronizes, so that the follow-up maintenance to cladding glass is brought convenience.
5, the present invention solves curtain wall number, and reference area counts the technological difficulties of integration, convenient for carrying out to construction speed Control;In addition, also being recorded in detail to the information of cladding glass, so that the follow-up maintenance to cladding glass is brought convenience.
Detailed description of the invention
Fig. 1 is step flow chart of the invention;
Fig. 2 is the schematic diagram for building original curtain wall model;
Fig. 3 is the interface schematic diagram that original curtain wall model is numbered;
Fig. 4 is the interface schematic diagram that original curtain wall model detail list is generated in Revit software;
Fig. 5 is the interface schematic diagram that project amount statistics is generated in BIM software.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples, but be not intended as to the present invention limit according to According to.
Embodiment: a kind of curtain wall engineering amount statistical method, as shown in Figs. 1-5, specifically as shown in Figure 1, including the following steps,
S1: the original curtain wall model of modularization, parametrization is set up in Revit or Rhino software according to construction drawing. As shown in Fig. 2, Fig. 2 is the schematic diagram for building original curtain wall model.
S2: being numbered the cladding glass in original curtain wall model by dynamo or grasshopper software and Quantity statistics.As shown in figure 3, Fig. 3 is the schematic diagram that original curtain wall model is numbered.
S3: showing cladding glass number and the quantity statistics in original curtain wall model in Revit or Rhino software, And the cladding glass geometric dimension and cladding glass area of each number is calculated, generating includes cladding glass number, curtain wall The detail list of transparency area and cladding glass geometric dimension.
S4: curtain wall construction scheme is preset in BIM software, detail list is uploaded to BIM software, by default curtain wall construction side Case and detail list combine construction requirement, mounting means, erection sequence and the curtain wall glass for automatically generating each number cladding glass The secondary detail list of the attribute of glass, and generate project amount statistics.It is specific as shown in Figure 4 and Figure 5.Wherein, the secondary detail It further include installation component information, the floor location information of cladding glass in table;The installation component information includes installation component Model specification, technical parameter.The attribute of the cladding glass includes the physical property, specifications and models, unit valence of cladding glass Lattice, technical parameter and material category.Cladding glass in the present invention default curtain wall construction scheme and detail list are combined from Move the secondary bright of the attribute of the construction requirement for generating each number cladding glass, mounting means, erection sequence and cladding glass Thin table, convenient for getting information about the shape specification of corresponding cladding glass.Wherein, the attribute of cladding glass includes cladding glass Physical property, specifications and models, unit price, technical parameter and material category, it is detailed to provide the letter of corresponding cladding glass Breath, so that the follow-up maintenance to cladding glass is brought convenience
According to step S4, by obtaining the curtain wall construction scheme at project under construction scene, exist according to live curtain wall construction scheme Revit or Rhino adjusts original curtain wall model, obtains secondary curtain wall model, and generates the detail of corresponding secondary curtain wall model Table.
When change occurs for the component in the secondary curtain wall model, the engineering attribute of parametrization component changes or newly When increasing component, attribute list described in simultaneously synchronized update is counted again.It timely updates and keeps the synchronization of information, to give curtain wall glass The follow-up maintenance of glass is brought convenience.
The present invention carries out the cladding glass in curtain wall model by establishing corresponding curtain wall model according to construction drawing Number counts the project amount of cladding glass to generate the detail list containing cladding glass number and quantity, consequently facilitating The construction speed of curtain wall is controlled.

Claims (5)

1. curtain wall engineering amount statistical method, it is characterised in that: include the following steps,
S1: original curtain wall model is set up in Revit or Rhino software according to construction drawing;
S2: being numbered the cladding glass in original curtain wall model by dynamo or grasshopper software and quantity Statistics;
S3: cladding glass number and the quantity statistics in original curtain wall model are shown in Revit or Rhino software, and are counted Calculation obtains the cladding glass geometric dimension and cladding glass area of each number, and generating includes cladding glass number, cladding glass The detail list of area and cladding glass geometric dimension;
S4: presetting curtain wall construction scheme in BIM software, detail list be uploaded to BIM software, by default curtain wall construction scheme and Detail list combines the construction requirement for automatically generating each number cladding glass, mounting means, erection sequence and cladding glass The secondary detail list of attribute, and generate project amount statistics.
2. curtain wall engineering amount statistical method according to claim 1, it is characterised in that: according to step S4, applied by obtaining The curtain wall construction scheme at work project scene adjusts original curtain wall model in Revit or Rhino according to live curtain wall construction scheme, Secondary curtain wall model is obtained, and generates the detail list of corresponding secondary curtain wall model.
3. curtain wall engineering amount statistical method according to claim 1, it is characterised in that: also wrapped in the secondary detail list Include installation component information, the floor location information of cladding glass;The installation component information include installation component model specification, Technical parameter.
4. curtain wall engineering amount statistical method according to claim 1, it is characterised in that: the attribute packet of the cladding glass Include physical property, specifications and models, unit price, technical parameter and the material category of cladding glass.
5. curtain wall engineering amount statistical method according to claim 2, it is characterised in that: when in the secondary curtain wall model Component engineering attribute when changing or increasing component newly of change, parametrization component occurs, statistics and synchronized update institute again The detail list for the secondary curtain wall model stated.
CN201811138944.XA 2018-09-28 2018-09-28 Curtain wall engineering amount statistical method based on BIM Pending CN109299546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811138944.XA CN109299546A (en) 2018-09-28 2018-09-28 Curtain wall engineering amount statistical method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811138944.XA CN109299546A (en) 2018-09-28 2018-09-28 Curtain wall engineering amount statistical method based on BIM

Publications (1)

Publication Number Publication Date
CN109299546A true CN109299546A (en) 2019-02-01

Family

ID=65164618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811138944.XA Pending CN109299546A (en) 2018-09-28 2018-09-28 Curtain wall engineering amount statistical method based on BIM

Country Status (1)

Country Link
CN (1) CN109299546A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109885975A (en) * 2019-03-25 2019-06-14 陕西鑫雨节能科技有限公司 Continuous beam prestress pipe model treatment method and system
CN111005483A (en) * 2019-06-20 2020-04-14 方传斌 Curtain wall production and processing method based on BIM technology
CN111339640A (en) * 2020-02-12 2020-06-26 北京中外建建筑设计有限公司 Automatic building parking space number creation method based on Revit plug-in Dynamo
CN111737806A (en) * 2020-07-01 2020-10-02 山西省工业设备安装集团有限公司 BIM technology-based cantilever type double-clay-plate curtain wall dry hanging construction method
CN112395672A (en) * 2020-11-17 2021-02-23 中国电力工程顾问集团西南电力设计院有限公司 BIM technology-based substation engineering enclosure modeling method
CN115587412A (en) * 2022-10-19 2023-01-10 中国建筑第五工程局有限公司 Light wood structure wall frame modeling and calculating method based on Rhino Inside Revit
CN117195373A (en) * 2023-09-25 2023-12-08 中国十七冶集团有限公司 Special-shaped curtain wall glass production method based on BIM+Grasshopper
CN118133390A (en) * 2024-03-07 2024-06-04 五矿瑞和(上海)建设有限公司 Method and system for calculating curtain wall material consumption

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080134589A1 (en) * 2006-08-26 2008-06-12 Alexander Abrams System for modular building construction
CN101368412A (en) * 2007-08-17 2009-02-18 苏少宁 Composite curtain wall structure and its construction method
US20100235206A1 (en) * 2008-11-14 2010-09-16 Project Frog, Inc. Methods and Systems for Modular Buildings
US20120132117A1 (en) * 2009-03-16 2012-05-31 Bermudez Miquel Jose Miguel Set of stowable rigid sails
CN102535690A (en) * 2010-12-15 2012-07-04 深圳市瑞华建设股份有限公司 Automatic statistical and numbering method of materials of building curtain wall
CN103230187A (en) * 2013-04-18 2013-08-07 无锡奇纬智能视膜科技有限公司 Intelligent interactive display cabinet
WO2014100243A1 (en) * 2012-12-19 2014-06-26 Patco, Llc Method and system of using standardized structural components
CN104818787A (en) * 2015-04-17 2015-08-05 常州汇森电子有限公司 Installation and construction method for large suspension glass curtain walls
CN105804298A (en) * 2016-03-24 2016-07-27 广西建工集团第五建筑工程有限责任公司 Construction method of honeycomb-shaped convex irregular curtain wall
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN205976154U (en) * 2016-07-28 2017-02-22 中国建筑第八工程局有限公司 Curtain tripe angle can be adjusted installing support
WO2017095343A1 (en) * 2015-12-01 2017-06-08 Tug Konut Teknolojisi Ve Tasarim Sanayi Ticaret Limited Sirketi Wall structure with cells having an earthquake absorption and increased resistance
CN106968370A (en) * 2017-02-21 2017-07-21 中建七局建筑装饰工程有限公司 A kind of high speed payout, positioning and the baiting method of ball curtain wall
CN107587632A (en) * 2017-09-20 2018-01-16 南京国豪家装饰设计有限公司 A kind of curtain wall installation method and system based on BIM technology
CN207184665U (en) * 2017-09-25 2018-04-03 杭州凌望建筑科技有限公司 A kind of dynamic human face identification intelligent is deployed to ensure effective monitoring and control of illegal activities early warning camera
CN207182836U (en) * 2017-09-25 2018-04-03 杭州凌望建筑科技有限公司 A kind of LED display of networking control
CN107958487A (en) * 2017-12-06 2018-04-24 金刚幕墙集团有限公司 A kind of method and system for automatically generating curtain wall member figure
CN108121873A (en) * 2017-12-25 2018-06-05 广州江河幕墙系统工程有限公司 A kind of application process of buildings model in curtain wall construction
CN108442586A (en) * 2018-03-06 2018-08-24 上海宝冶集团南京建筑有限公司 A kind of point-supporting curtain rope bar composite structure building and its construction method
CN108460189A (en) * 2018-02-06 2018-08-28 华北水利水电大学 A kind of curtain wall mounting design method based on BIM technology

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080134589A1 (en) * 2006-08-26 2008-06-12 Alexander Abrams System for modular building construction
CN101368412A (en) * 2007-08-17 2009-02-18 苏少宁 Composite curtain wall structure and its construction method
US20100235206A1 (en) * 2008-11-14 2010-09-16 Project Frog, Inc. Methods and Systems for Modular Buildings
US20120132117A1 (en) * 2009-03-16 2012-05-31 Bermudez Miquel Jose Miguel Set of stowable rigid sails
CN102535690A (en) * 2010-12-15 2012-07-04 深圳市瑞华建设股份有限公司 Automatic statistical and numbering method of materials of building curtain wall
WO2014100243A1 (en) * 2012-12-19 2014-06-26 Patco, Llc Method and system of using standardized structural components
CN103230187A (en) * 2013-04-18 2013-08-07 无锡奇纬智能视膜科技有限公司 Intelligent interactive display cabinet
CN104818787A (en) * 2015-04-17 2015-08-05 常州汇森电子有限公司 Installation and construction method for large suspension glass curtain walls
WO2017095343A1 (en) * 2015-12-01 2017-06-08 Tug Konut Teknolojisi Ve Tasarim Sanayi Ticaret Limited Sirketi Wall structure with cells having an earthquake absorption and increased resistance
CN105804298A (en) * 2016-03-24 2016-07-27 广西建工集团第五建筑工程有限责任公司 Construction method of honeycomb-shaped convex irregular curtain wall
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN205976154U (en) * 2016-07-28 2017-02-22 中国建筑第八工程局有限公司 Curtain tripe angle can be adjusted installing support
CN106968370A (en) * 2017-02-21 2017-07-21 中建七局建筑装饰工程有限公司 A kind of high speed payout, positioning and the baiting method of ball curtain wall
CN107587632A (en) * 2017-09-20 2018-01-16 南京国豪家装饰设计有限公司 A kind of curtain wall installation method and system based on BIM technology
CN207184665U (en) * 2017-09-25 2018-04-03 杭州凌望建筑科技有限公司 A kind of dynamic human face identification intelligent is deployed to ensure effective monitoring and control of illegal activities early warning camera
CN207182836U (en) * 2017-09-25 2018-04-03 杭州凌望建筑科技有限公司 A kind of LED display of networking control
CN107958487A (en) * 2017-12-06 2018-04-24 金刚幕墙集团有限公司 A kind of method and system for automatically generating curtain wall member figure
CN108121873A (en) * 2017-12-25 2018-06-05 广州江河幕墙系统工程有限公司 A kind of application process of buildings model in curtain wall construction
CN108460189A (en) * 2018-02-06 2018-08-28 华北水利水电大学 A kind of curtain wall mounting design method based on BIM technology
CN108442586A (en) * 2018-03-06 2018-08-24 上海宝冶集团南京建筑有限公司 A kind of point-supporting curtain rope bar composite structure building and its construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
MA ZHILIANG ET,AL: "An integrated approach for managing cladding construction in high-rise buildings", 《AUTOMATION IN CONSTRUCTION》 *
张鹏等: "BIM技术在幕墙工程中的应用", 《施工技术》 *
汪兵: "玻璃幕墙的施工工艺研究", 《四川水泥》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109885975A (en) * 2019-03-25 2019-06-14 陕西鑫雨节能科技有限公司 Continuous beam prestress pipe model treatment method and system
CN109885975B (en) * 2019-03-25 2023-04-18 陕西鑫雨节能科技有限公司 Continuous beam prestressed pipeline model processing method and system
CN111005483A (en) * 2019-06-20 2020-04-14 方传斌 Curtain wall production and processing method based on BIM technology
CN111339640A (en) * 2020-02-12 2020-06-26 北京中外建建筑设计有限公司 Automatic building parking space number creation method based on Revit plug-in Dynamo
CN111737806A (en) * 2020-07-01 2020-10-02 山西省工业设备安装集团有限公司 BIM technology-based cantilever type double-clay-plate curtain wall dry hanging construction method
CN112395672A (en) * 2020-11-17 2021-02-23 中国电力工程顾问集团西南电力设计院有限公司 BIM technology-based substation engineering enclosure modeling method
CN112395672B (en) * 2020-11-17 2022-10-04 中国电力工程顾问集团西南电力设计院有限公司 BIM technology-based substation engineering enclosure modeling method
CN115587412A (en) * 2022-10-19 2023-01-10 中国建筑第五工程局有限公司 Light wood structure wall frame modeling and calculating method based on Rhino Inside Revit
CN117195373A (en) * 2023-09-25 2023-12-08 中国十七冶集团有限公司 Special-shaped curtain wall glass production method based on BIM+Grasshopper
CN118133390A (en) * 2024-03-07 2024-06-04 五矿瑞和(上海)建设有限公司 Method and system for calculating curtain wall material consumption
CN118133390B (en) * 2024-03-07 2024-11-26 五矿瑞和(上海)建设有限公司 A method and system for calculating the amount of curtain wall materials

Similar Documents

Publication Publication Date Title
CN109299546A (en) Curtain wall engineering amount statistical method based on BIM
CN105550386B (en) A kind of precast concrete Deepen Design method based on Revit
CN109583033B (en) Application method and system of BIM adaptive model in special-shaped curtain wall construction
CN110929328A (en) Concrete assembly type building construction method based on BIM
CN104102765A (en) BIM (Building Information Modeling)-based curtain wall parametrization design method
CN105551077B (en) The construction method and device of panel beating three-dimensional process model
CN106013535A (en) BIM-based pre-assembling method for double-curved glass curtain wall
CN107515991A (en) A kind of house type full trim simulation shows method and display systems based on BIM technology
CN105781064A (en) Floor tile laying construction method based on building information modeling (BIM)
CN109784004A (en) A kind of profiled metal roofing construction method of installation based on BIM technology
CN114003996B (en) BIM technology-based special-shaped curtain wall grid optimization solution method
CN105320012A (en) Multimedia dynamic stage control method and system
CN108121873A (en) A kind of application process of buildings model in curtain wall construction
CN107292065A (en) A kind of quick composing system of floor tile based on BIM technology and method
CN108664670A (en) House type CAD automatically generates the implementation method of 3D house type models
CN117540459A (en) BIM model generation method and system based on BIM semi-forward design
CN103902757A (en) System and method for rapid creation and interaction of three-dimensional model
CN108647468A (en) A kind of row's of building by laying bricks or stones brick method based on BIM technology
CN110866295A (en) Three-dimensional modeling method and device for building
CN110378039A (en) A kind of aluminum alloy pattern plate design method and system based on Revit
CN106952346B (en) System and method for generating suspended ceiling 3D model based on drawing plane polygon
CN111783270B (en) Construction progress digital simulation method based on BIM technology
CN102880646A (en) Method for converting CAD drawing paper into VISIO drawing paper
CN105589978A (en) Three-dimensional process design method based on model
CN116512248B (en) Robot process debugging system and method based on three-dimensional visualization

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190201