CN206220080U - Fore shaft grouting steel tube pile guide wall - Google Patents

Fore shaft grouting steel tube pile guide wall Download PDF

Info

Publication number
CN206220080U
CN206220080U CN201621102832.5U CN201621102832U CN206220080U CN 206220080 U CN206220080 U CN 206220080U CN 201621102832 U CN201621102832 U CN 201621102832U CN 206220080 U CN206220080 U CN 206220080U
Authority
CN
China
Prior art keywords
steel
pile
pipe pile
fore shaft
guide wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621102832.5U
Other languages
Chinese (zh)
Inventor
赵永军
杨军
阎仁才
周鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Provincial Transportation Engineering Group Co Ltd
Original Assignee
Jiangsu Provincial Transportation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Provincial Transportation Engineering Group Co Ltd filed Critical Jiangsu Provincial Transportation Engineering Group Co Ltd
Priority to CN201621102832.5U priority Critical patent/CN206220080U/en
Application granted granted Critical
Publication of CN206220080U publication Critical patent/CN206220080U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

Fore shaft grouting steel tube pile guide wall of the present utility model, steel-pipe pile is directly beaten in the navigation wall outer side water surface, the fore shaft being mutually interlockingly connected is formed by T-shaped slot, T-shaped convex tendon between steel-pipe pile, side sets some cast-in-situ bored piles in guide wall body, connected by cement concrete construction member between bored concrete pile;Placing cement concrete in injection in steel-pipe pile, easy construction, without advance cofferdam, do not banket in advance operation, water body will not pollute, and be not take up navigation channel, short construction period, the lock catch connector between steel-pipe pile can close steel-pipe pile gap, prevent the seepage of banketing on the inside of steel-pipe pile.

Description

Fore shaft grouting steel tube pile guide wall
Technical field
The utility model is related to a kind of fore shaft grouting steel tube pile guide wall, is applied particularly to the construction of water surface Waterway navigation facility Technology.
Background technology
Ship lock on water surface navigation channel need to build guide wall in construction, and conventional art first does when guide wall is built and encloses Weir, is banketed to form dykes and dams guide wall inside cofferdam, and guide wall is built in water using gravitational settling steel sheet-pile cofferdam into leading The wall form of boat effect, is punched after being banketed inside cofferdam, and concrete is poured into a mould in hole, is frozen into inside and outside two rows concrete column and is formed Firm wall, the water surface area taken in work progress is big, and, to contaminated water flow weight, the mode of water surface construction is also for the earthwork, mud With personal safety hidden danger very high, and construction cost is costly, and environmental pollution is big.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of construction and takes that the water surface is smaller, the structure for being formed of constructing Part good stability, the fore shaft grouting steel tube pile guide wall small to water pollution.
Fore shaft grouting steel tube pile guide wall of the present utility model, including some steel-pipe piles arranged along wall diversion face, steel pipe Pile pipe body both sides are respectively arranged with the connector that can coordinate with adjacent steel-pipe pile grafting, and connector is weldingly fixed on outside steel-pipe pile Wall both sides, and along steel-pipe pile body Longitudinal extending, the connector section of steel-pipe pile outer wall both sides is respectively T-shaped slot, T-shaped convex tendon Structure, T-shaped slot, T-shaped convex tendon form the fore shaft being mutually interlockingly connected, and wall inner side sets some cast-in-situ bored piles, between bored concrete pile Connected by cement concrete construction member;
The steel pipe pile material is Q235B spiral steel pipes;
The T-shaped slot both sides have slope reinforcement.
Fore shaft grouting steel tube pile guide wall of the present utility model, steel-pipe pile is directly beaten in the water surface, and cement injection is mixed in steel-pipe pile Solidifying soil, without advance cofferdam, operation of not banketing in advance, easy construction, water body will not pollute, and be not take up navigation channel, construction period Short, the lock catch connector between steel-pipe pile can close steel-pipe pile gap, prevent the seepage of banketing on the inside of steel-pipe pile.
Brief description of the drawings
Fig. 1 is the fore shaft grouting steel tube pile guide wall structural representation in default cofferdam in the prior art;
Fig. 2 is the fore shaft grouting steel tube pile guide wall structural representation of the utility model embodiment;
Fig. 3 is the fore shaft steel tube pile structure enlarged diagram of the fore shaft grouting steel tube pile guide wall of the utility model embodiment;
Fig. 4 is the top perspective view of Fig. 3;
Fig. 5 is the fore shaft grouting steel tube pile guide wall guide frame enlarged diagram of the utility model embodiment;
Fig. 6 is the fore shaft grouting steel tube pile guide wall integrated cast structure enlarged diagram of the utility model embodiment.
Specific embodiment
As illustrated, a kind of fore shaft grouting steel tube pile guide wall, including some steel-pipe piles 1 arranged along wall diversion face, steel Pile tube body both sides are respectively arranged with the connector that can coordinate with adjacent steel-pipe pile grafting, and connector is weldingly fixed on steel-pipe pile Outer wall both sides, and along steel-pipe pile body Longitudinal extending, the connector section of steel-pipe pile outer wall both sides is respectively T-shaped slot 3, T-shaped The structure of convex tendon 4, T-shaped slot 3, T-shaped convex tendon 4 form the fore shaft being mutually interlockingly connected, and the both sides of T-shaped slot 3 have slope reinforcement, can Increase fore shaft intensity, improve anti-current-rush power;Wall inner side sets some cast-in-situ bored piles 2, and cement is passed through between bored concrete pile 2 Concrete component is connected;Steel-pipe pile is directly beaten in the water surface, placing cement concrete in injection in steel-pipe pile forms firm navigation wall, Without advance cofferdam, operation of not banketing in advance, water body will not pollute, and be not take up navigation channel, and easy construction, the construction period is short, steel Lock catch connector between pile tube can close steel-pipe pile gap, prevent the seepage of banketing on the inside of steel-pipe pile.
Fore shaft grouting steel tube pile guide wall of the present utility model, steel-pipe pile uses Q235B spiral steel pipes, region barrier of driving piles Cleaning:Piecemeal of removing obstacles is carried out, and underwater portion is removed obstacles using dredger, and above water is removed obstacles using digging machine;Anticollision pile driving construction Shi Liyong truck crane handling bumper piles to precalculated position, sling bumper piles and pile sinking by crane barge.Surveyor's commander's crane barge slowly moves stake To pile sinking position.Adjustment pile tube, it is ensured that vertical.During the near absolute altitude of pile sinking, stake top absolute altitude is measured with spirit level.After pile sinking is finished, Unclamp vibration hammer fixture, telephone-moving, next pile of constructing in the above sequence.Finally by contact, installation police between design requirement welding stake Show lamp.
The stake of design attitude positioning and guiding is pressed first with total powerstation when leading truck is constructed, with crane barge with hammer pile sinking of extricating oneself from a predicament and brace oneself up to action;Pile sinking Welding beam and diagonal brace after in place, the inner edge locations of track are released by design coordinate, then lay track steel sheet pile, are accurately positioned Firm welding, strictly positioning guiding rack is carried out before pile sinking by coordinate afterwards.
When fore shaft steel-pipe pile is set, construct in the following order:
1. fore shaft steel-pipe pile plan-position:First pile uses 2 total powerstations to be positioned with intersection, and 1 tablecloth is placed in fore shaft steel On pile tube axis, fore shaft center is controlled, another 1 tablecloth is placed in the opposite side perpendicular to this axis, controls fore shaft steel pipe pile locking notch Sideline, is accurately positioned first pile central point, and stake is moved to design attitude with crane barge, and being close to track along control point drops down onto riverbed, enters After soil, repetition measurement adjusts pile tube position to design attitude again, first to stake static pressure, is then turned on the slow pile sinking of vibration hammer;2. fore shaft Steel pipe pile verticality:After fore shaft steel pipe pile verticality is adjusted to meet requirement, Vibration on Start-up hammers slow pile sinking into shape.Pile driving process In, 2 total powerstation tracing and monitorings, it is ensured that the perpendicularity of stake not deviation, if deviation is seriously difficult to adjust, fore shaft steel-pipe pile are pulled out Go out and squeeze into again;3. fore shaft steel-pipe pile stake top absolute altitude:Fore shaft steel-pipe pile will be beaten during to designed elevation, use spirit level test constantly Pile body scale, instructs hammering, until stake is beaten to designed elevation.
Every steel-pipe pile set finish laggard line position put, the inspection of perpendicularity and absolute altitude, can be carried out down after meeting the requirements The heavy of one pile sets, and is set by root.All fore shaft steel-pipe piles are set after finishing, and axis and elevation are checked, if any undesirable Be adjusted, until meeting design requirement.
Banketed in guide wall body to steel-pipe pile side, using water jetting at high pressure to carrying out rushing mud in steel-pipe pile body, using slush pump Mud to wadding weft variation designed elevation is inhaled, after suction mud is finished, the hole depth of fore shaft steel-pipe pile is detected, suction mud is stopped after meeting the requirements and is entered Wadding weft variation in row body, fills out steel reinforcement cage needed for core and machines inside in advance, and mud is inhaled in steel-pipe pile through supervising engineer Start that steel reinforcement cage is installed after passed examination, conduit is installed after positioning, concrete perfusion dry mixing mortar pours underwater concrete.Pour During building, depth of tremie is strictly controlled on request;Fore shaft cavity is filled out and installs oviduct when core is processed above fore shaft, and preparation is mixed Solidifying soil dry mixing mortar, mouth under oviduct is aligned the cavity of steel pipe pile locking notch, and fill concrete dry mixing mortar, makes in oviduct Negative and positive fore shaft is plugged and pounded with fine steel rib, is tamped in the cavity of fore shaft steel-pipe pile using concrete dry mixing mortar;In fore shaft steel-pipe pile It is using giant that the mud flush on fore shaft steel-pipe pile inwall is clean before filling out core;High pressure rotation is set between eliminating drilling row Itself it is socketed using fore shaft between soil body appurtenant work between spray stake reinforcing pile, fore shaft grouting steel tube pile, filling dry-mixed mortar in fore shaft, its Itself can avoid leaking soil between stake, fore shaft is connected firmly and good airproof performance, be favorably improved the stability of earth construction thing and resistance to Long property.
Guide wall breastwork veneer uses beret truss truss when constructing at fore shaft grouting steel tube pile, by truss anchor in anchoring pile Guan Liang On.Channel beam is installed in Bailey truss front end, makees hanging beam, and chain block is hung on hanging beam.It is with chain block suspention shaped steel Load-bearing basis, completes veneer and the anchor structure construction of fore shaft grouting steel tube pile.

Claims (3)

1. a kind of fore shaft grouting steel tube pile guide wall, including some steel-pipe piles arranged along wall diversion face(1), it is characterised in that: Steel-pipe pile(1)Body both sides are respectively arranged with the connector that can coordinate with adjacent steel-pipe pile grafting, and connector is weldingly fixed on Steel-pipe pile(1)Outer wall both sides, and along steel-pipe pile(1)Body Longitudinal extending, steel-pipe pile(1)The connector section difference of outer wall both sides It is T-shaped slot(3), T-shaped convex tendon(4)Structure, T-shaped slot(3), T-shaped convex tendon(4)Form the fore shaft being mutually interlockingly connected, wall inner side Some cast-in-situ bored piles are set(2), bored concrete pile(2)Between by cement concrete construction member connect.
2. fore shaft grouting steel tube pile guide wall according to claim 1, it is characterised in that:The steel-pipe pile(1)Material is Q235B spiral steel pipes.
3. fore shaft grouting steel tube pile guide wall according to claim 1, it is characterised in that:The T-shaped slot(3)Both sides have Slope reinforcement.
CN201621102832.5U 2016-10-08 2016-10-08 Fore shaft grouting steel tube pile guide wall Expired - Fee Related CN206220080U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621102832.5U CN206220080U (en) 2016-10-08 2016-10-08 Fore shaft grouting steel tube pile guide wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621102832.5U CN206220080U (en) 2016-10-08 2016-10-08 Fore shaft grouting steel tube pile guide wall

Publications (1)

Publication Number Publication Date
CN206220080U true CN206220080U (en) 2017-06-06

Family

ID=58781664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621102832.5U Expired - Fee Related CN206220080U (en) 2016-10-08 2016-10-08 Fore shaft grouting steel tube pile guide wall

Country Status (1)

Country Link
CN (1) CN206220080U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284272A (en) * 2016-10-08 2017-01-04 江苏省交通工程集团有限公司 Fore shaft grouting steel tube pile guide wall and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284272A (en) * 2016-10-08 2017-01-04 江苏省交通工程集团有限公司 Fore shaft grouting steel tube pile guide wall and construction method

Similar Documents

Publication Publication Date Title
CN101503882B (en) Underground continuous wall with connected reinforcement cage constructed by reverse construction method and construction method thereof
CN110144914A (en) Construction method of locking steel pipe pile cofferdam by deep water topdown construction method
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN101538833A (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN104131567A (en) Novel waterstop prefabricated centrifugal rectangular pile retaining structure and construction method thereof
CN102966110A (en) Vertically-combined type impermeable waterproof curtain structure and construction method thereof
CN109610470A (en) A kind of base pit stand construction using three axes agitating pile machine
CN109778836A (en) A kind of prefabricated ground connecting wall structure and construction method based on structure
CN101260664A (en) Soft soil foundation large scale steel float lock head construction method
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
CN102677630B (en) Construction method of concrete cut-off wall in sludge soil with high water content
CN111764404A (en) A partially recyclable occlusal pile supporting structure and construction method
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN110344418A (en) The structure and its construction technology of support system in a kind of deep basal pit
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN202954371U (en) Vertical combined type seepage-proofing waterproof curtain structure
CN114575355B (en) Soil protection construction method
CN113322936B (en) Soil body reinforcing construction method and construction auxiliary device for thick sand layer karst area
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
CN206220080U (en) Fore shaft grouting steel tube pile guide wall
CN207862925U (en) A kind of slip casting casing device
CN210507415U (en) Ground is wall joint sealing device even
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN106284272B (en) Locking steel pipe pile row navigation wall and construction method
CN111535298A (en) Seepage-proofing construction method for underground diaphragm wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170606

Termination date: 20211008