CN207192595U - Rail clamp - Google Patents

Rail clamp Download PDF

Info

Publication number
CN207192595U
CN207192595U CN201721163960.5U CN201721163960U CN207192595U CN 207192595 U CN207192595 U CN 207192595U CN 201721163960 U CN201721163960 U CN 201721163960U CN 207192595 U CN207192595 U CN 207192595U
Authority
CN
China
Prior art keywords
track
support
clamping limb
screw rod
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721163960.5U
Other languages
Chinese (zh)
Inventor
胡伟山
谷昌满
孟晓宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN201721163960.5U priority Critical patent/CN207192595U/en
Application granted granted Critical
Publication of CN207192595U publication Critical patent/CN207192595U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses track holder belongs to the track field, and the purpose provides a track holder, and it cooperates with the form table car for lift up the track, with the reduction artifical input, improve the efficiency of construction. Comprises a bracket, wherein a U-shaped groove with a downward opening is arranged on the bracket; two clamping arms are arranged in the U-shaped groove and are arranged on the bracket; the lower ends of the opposite sides of the two clamping arms are provided with clamping pieces; and is provided with a driving mechanism for driving the clamping arms to transversely move towards or away from each other along the U-shaped groove. The utility model is matched with the template trolley, and in the jacking process, manual operation is not needed, thereby ensuring the safety of constructors, saving labor and improving the construction efficiency; in addition, when the track is lifted and put down, the motion trail of the track is determined, and the phenomenon that the lifted track deviates from the original position after being put down and the later pouring is influenced is avoided; moreover, the device has the advantages of simple structure, small size and small size, occupies less space, is convenient to use in the comprehensive pipe gallery, and can also be used for track stepping type advancing.

Description

Track clamper
Technical field
The utility model belongs to track field, particularly track clamper.
Background technology
Piping lane is urban infrastructure construction as Urban Underground is built in for the facility of constructing for accommodating municipal engineering pipeline Important component, pipe gallery, i.e. common trench, Common Ducts, that is, a tunnel space of Urban Underground is built in, by electricity The various utilities pipelines such as power, communication, combustion gas, heat supply, plumbing are integrated in one, and realize unified planning.
When carrying out city integrated piping lane construction using formwork jumbo, it is necessary to lay the track that formwork jumbo uses, template Chassis orbiting.But the flatness of the plane due to laying track and the influence of track self-deformation or bending, Skidding occurs in casting formwork chassis running, therefore, it is necessary to the height of track is adjusted at skidding, to meet template The requirement of chassis normal operation.At present, the Normal practice for adjusting orbit altitude is artificially to lever up track at this, while in this place Backing plate, which is set up, below track carrys out leveling track.But the weight of track makes troubles to artificial prize, and adds artificial input, Also improve the degree of danger of construction.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of track clamper, and it coordinates with formwork jumbo, uses In lifting track, to reduce artificial input, efficiency of construction is improved.
The technical solution adopted in the utility model is:Track clamper, including support, opening court is provided with the support Under U-lag;Two clamping limbs are provided with U-lag, the clamping limb is installed on support;In the opposite side of two clamping limbs Lower end be provided with holder;Driving clamping limb is provided with support along the drive that U-lag is laterally opposite or moves opposite to each other Motivation structure.
Further, the holder is that one end is arranged at clamping limb, and the other end extends to side where another clamping limb Directive wheel, transverse direction of the directive wheel along U-lag are set.
Further, the other end that the directive wheel is connected with clamping limb is tapered.
Further, the drive mechanism includes screw rod, the screw rod is by the side of support, sequentially passes through clamping limb, And it is through to the opposite side of support;The screw rod coordinates with holder pivots and coordinated with clamping limb screw thread;The spiro rod length side To center line both sides screw thread it is oppositely oriented.
Further, fixed mount is set on the screw rod, and the fixed mount is located between the screw thread of screw rod both sides, described solid Determine frame one end with screw rod to be connected, the other end is connected with footstock.
Further, one end of the screw rod is provided with rocking arm.
Further, the guide rod that opposite side is through to by support side is provided with the top of support;The clamping limb One end support is installed on by guide rod, its clamping limb along guide rod axially with guide rod be slidably connected.
Further, the support includes the footstock at top and the side arm at both ends;The interlude of the guide rod is polished rod, The end segments at both ends are threaded rod, and end segments and the side arm screw thread of guide rod are connected.
Further, the support is made up of channel-section steel.
The beneficial effects of the utility model are:Track clamper disclosed in the utility model, by coordinating with formwork jumbo, During jacking, without manual operation, while ensureing that workmen is safe, save manually, improve efficiency of construction;And And using the jack-up system of formwork jumbo itself, when lifting track and putting down track, the movement locus of track is determined, The track for avoiding being lifted away from, which is put down, to be retrodeviated from original position, is influenceed the later stage and is poured;Moreover the track clamper, it is simple in construction, individual Body is compact, space-consuming is few, is easy to use in pipe gallery;The track clamper can be also used for the advance of track step-by-step movement.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model front view;
Fig. 3 is the utility model rearview;
Fig. 4 is the utility model upward view.
In figure, support 1, footstock 11, side arm 12, U-lag 13, clamping limb 2, directive wheel 3, screw rod 4, fixed mount 5, rocking arm 6, Guide rod 7.
Embodiment
The utility model is described further with reference to the accompanying drawings and examples as follows:
Track clamper, as Figure 1-Figure 4, including support 1, downward opening U-lag is provided with the support 1 13;Two clamping limbs 2 are provided with U-lag, the clamping limb 2 is installed on support 1;In the opposite side of two clamping limbs 2 Lower end is provided with holder;It is provided with what driving clamping limb 2 laterally moved in opposite directions or opposite to each other along U-lag 13 on support 1 Drive mechanism.
Track clamper disclosed in the utility model, in use, support 1 is installed on the sill of formwork jumbo, lead to Mechanism of overdriving drives two clamping limbs 2 to move opposite to each other, until the spacing between the holder on two clamping limbs 2 is enough to accommodate Form track I-steel top flange plate by, and make holder positioned at form track I-steel top flange plate and bottom wing Between listrium.Then two move toward one anothers of clamping limb 2 are driven by drive mechanism, until being smaller than between two holders Form the width of the top flange plate of the I-steel of track.In this way, track can be lifted away from by jack chassis, and Schaltisch Car has the jack-up system of itself, therefore, during jacking, without manual operation, while ensureing that workmen is safe, save people Work, improve efficiency of construction;Also, utilize the jack-up system of formwork jumbo itself, when lifting track and putting down track, track Movement locus determined that the track for avoiding being lifted away from, which is put down, to be retrodeviated from original position, influenceing the later stage pours;Moreover the rail Road clamper, it is simple in construction, individual is compact, space-consuming is few, it is easy to use in pipe gallery.
The track clamper can be also used for the advance of track step-by-step movement, it is necessary to ensure to lift when advancing for track step-by-step movement When playing track, the width for being smaller than forming the top flange plate of the I-steel of track between the holder on two clamping limbs 2 And more than the width of web, after track is lifted away from, track is promoted from the afterbody of track, makes track serial forward.
Holder can be projection, rod member etc., but serial forward for the ease of track, it is preferred that the holder is One end is arranged at clamping limb 2, the directive wheel 3 that the other end extends to another place side of clamping limb 2, and the directive wheel 3 is along U-lag 13 Horizontal setting.
When track is serial forward, directive wheel 3 reduces the frictional force of holder and track with the forward rolling of track, So as to reduce the thrust for promoting track.
Because track is by I-shaped bracing members, it is in generally arc transition in the flange plate of I-steel and the joining place of web, is Adapt to the structure of I-steel, it is preferred that the other end that the directive wheel 3 is connected with clamping limb 2 is tapered.The end of taper Preferably it can coordinate with track.
Drive mechanism can be to drive the screw arbor assembly of clamping limb 2 respectively, still, in order to simplify the structure of drive mechanism, And it is easy to use, it is preferred that the drive mechanism includes screw rod 4, the screw rod 4 is by the side of support 1, sequentially passes through clamping Arm 2, and it is through to the opposite side of support 1;The screw rod 4 is rotatably assorted with support 1 and coordinated with the screw thread of clamping limb 2;The spiral shell The screw thread of the length direction center line both sides of bar 4 it is oppositely oriented.The drive mechanism, it is only necessary to which rotary screw 4 can realize two The opposite or opposite motion of clamping limb 2.
Preferably, fixed mount 5 is set on the screw rod 4, the fixed mount 5 is located between the screw thread of the mutual both sides of bar 4 of spiral shell, Described one end of fixed mount 5 is connected with screw rod 4, and the other end is connected with footstock 11.Fixed mount 5 is in the stage casing of screw rod 4 to screw rod 4 Play a supporting role, improve the rigidity of screw rod 4;Colleague, also carries out spacing to clamping limb 2, avoids clamping limb from deviateing screw rod 4 Stage casing.
Preferably, one end of the screw rod 4 is provided with rocking arm 6.
In the above-described embodiment, can be made by setting the chute being adapted to clamping limb 2 on support 1 to rise to be oriented to With still, the processing of chute is not easy, and it needs integral replacing support 1 if chute damages.For the ease of processing and fabricating and more Change, it is preferred that the guide rod 7 that opposite side is through to by the side of support 1 is provided with the top of support 1;The one of the clamping limb 2 End is installed on support 1 by guide rod 7, and its clamping limb 2 is axially slidably connected along guide rod 7 with guide rod 7.
Preferably, the support 1 includes the footstock 11 at top and the side arm 12 at both ends;The interlude of the guide rod 7 is Polished rod, the end segments at both ends are threaded rod, and end segments and the screw thread of side arm 12 of guide rod 7 are connected.
Preferably, the support 1 is made up of channel-section steel.Channel-section steel light weight, intensity is high, utilizes the intensity of support made of channel-section steel 1 And good rigidity, and, the web of channel-section steel is easy to be connected with the sill of formwork jumbo.

Claims (9)

1. track clamper, it is characterised in that:Including support (1), downward opening U-lag is provided with the support (1) (13);Two clamping limbs (2) are provided with U-lag, the clamping limb (2) is installed on support (1);In two clamping limbs (2) The lower end of opposite side be provided with holder;Driving clamping limb (2) is provided with support (1) along U-lag (13) horizontal phase To or the drive mechanism moved opposite to each other.
2. track clamper as claimed in claim 1, it is characterised in that:The holder is that one end is arranged at clamping limb (2), The directive wheel (3) that the other end extends to side where another clamping limb (2), transverse direction of the directive wheel (3) along U-lag (13) are set Put.
3. track clamper as claimed in claim 2, it is characterised in that:What the directive wheel (3) was connected with clamping limb (2) The other end is tapered.
4. the track clamper as described in claim 1-3 any one claims, it is characterised in that:The drive mechanism bag Screw rod (4) is included, the screw rod (4) is by the side of support (1), sequentially passes through clamping limb (2), and be through to the another of support (1) Side;The screw rod (4) is rotatably assorted with support (1) and coordinated with clamping limb (2) screw thread;In screw rod (4) length direction The screw thread of heart line both sides it is oppositely oriented.
5. track clamper as claimed in claim 4, it is characterised in that:Fixed mount (5) is set on the screw rod (4), it is described Fixed mount (5) is located between the screw thread of screw rod (4) both sides, and described fixed mount (5) one end is connected with screw rod (4), the other end with Footstock (11) is connected.
6. track clamper as claimed in claim 5, it is characterised in that:One end of the screw rod (4) is provided with rocking arm (6).
7. the track clamper as described in claim 1-3 any one claims, it is characterised in that:On the top of support (1) Portion is provided with the guide rod (7) that opposite side is through to by support (1) side;One end of the clamping limb (2) passes through guide rod (7) Support (1) is installed on, its clamping limb (2) is axially slidably connected along guide rod (7) with guide rod (7).
8. track clamper as claimed in claim 7, it is characterised in that:The footstock (11) of the support (1) including top and The side arm (12) at both ends;The interlude of the guide rod (7) is polished rod, and the end segments at both ends are threaded rod, the end of guide rod (7) Section is connected with side arm (12) screw thread.
9. the track clamper as described in claim 1-3 any one claims, it is characterised in that:The support (1) by Channel-section steel is made.
CN201721163960.5U 2017-09-12 2017-09-12 Rail clamp Active CN207192595U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721163960.5U CN207192595U (en) 2017-09-12 2017-09-12 Rail clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721163960.5U CN207192595U (en) 2017-09-12 2017-09-12 Rail clamp

Publications (1)

Publication Number Publication Date
CN207192595U true CN207192595U (en) 2018-04-06

Family

ID=61788569

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721163960.5U Active CN207192595U (en) 2017-09-12 2017-09-12 Rail clamp

Country Status (1)

Country Link
CN (1) CN207192595U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118148181A (en) * 2024-03-19 2024-06-07 中国十九冶集团有限公司 An outer formwork and formwork system for comprehensive pipe gallery construction
CN118207905A (en) * 2024-03-19 2024-06-18 中国十九冶集团有限公司 A template system and construction process for comprehensive pipe gallery construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118148181A (en) * 2024-03-19 2024-06-07 中国十九冶集团有限公司 An outer formwork and formwork system for comprehensive pipe gallery construction
CN118207905A (en) * 2024-03-19 2024-06-18 中国十九冶集团有限公司 A template system and construction process for comprehensive pipe gallery construction

Similar Documents

Publication Publication Date Title
CN109162157A (en) The construction method of track girder
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN107653756B (en) A kind of city rail U-type groove plate-type ballastless railway roadbed track plates bearing adjuster and its application method
CN207192595U (en) Rail clamp
CN114033423A (en) Device and method for secondary grouting of shield tunneling machine and shield tunneling machine
CN104179090A (en) Subway rail laying system
CN107335948A (en) A kind of quick assembly tool of T profile
CN206625254U (en) The guidance system of cast-in-place piping lane sliding system
CN205936639U (en) Portable tunnel segment support frame of subway construction
CN207538841U (en) A kind of hydraulic tunnel inverted arch cambered surface slip form construction device
CN108529197B (en) Carrying device of intelligent building beam column manufacturing equipment
CN207194013U (en) City utility tunnel outside mould supports guider
CN102305035B (en) Device for adjusting centration of complete vehicle-mounted service machine to wellhead
CN106367085B (en) Coke oven heating gas pipeline cock system tool formula modularization construction method of installation
CN211370439U (en) Integrated intelligent trolley for confined space operation
CN204023325U (en) A kind of subway system of laying a railway track
CN210217775U (en) Steel mould trolley for small-section tunnel
CN117514267A (en) Portable culvert platform truck
CN201588174U (en) Fast articulated zero preload track connecting device
CN204570398U (en) Chassis laid by D type just beam transport
CN204455850U (en) The interim suspension connection device of Large Steel box beam erection
CN211115815U (en) An adjustable hydraulic support for a horizontal directional drilling rig
CN207090841U (en) A kind of magnetic floats engineering evacuation platform installation chassis
CN223532683U (en) Anti-tilting sliding type assembled pipe gallery mold stabilizing structure
CN107254887B (en) City utility tunnel pours and uses outside mould guider

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant