CS241611B1 - The method of construction of high-rise buildings with supporting vertical structures - Google Patents

The method of construction of high-rise buildings with supporting vertical structures Download PDF

Info

Publication number
CS241611B1
CS241611B1 CS838273A CS827383A CS241611B1 CS 241611 B1 CS241611 B1 CS 241611B1 CS 838273 A CS838273 A CS 838273A CS 827383 A CS827383 A CS 827383A CS 241611 B1 CS241611 B1 CS 241611B1
Authority
CS
Czechoslovakia
Prior art keywords
building
skeleton
sliding formwork
metal
concrete
Prior art date
Application number
CS838273A
Other languages
Czech (cs)
Other versions
CS827383A1 (en
Inventor
Teodor Benes
Original Assignee
Teodor Benes
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Teodor Benes filed Critical Teodor Benes
Priority to CS838273A priority Critical patent/CS241611B1/en
Publication of CS827383A1 publication Critical patent/CS827383A1/en
Publication of CS241611B1 publication Critical patent/CS241611B1/en

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Úkolem je vyvinout způsob stavby výškových budov s výztužnými nosnými vertikálními konstrukcemi a sloupy skeletu, u kterého nedodjde k předimenzování sloupů skeletu ve stadiu jejich provozního využívání. Při stavbě výškové budovy se k hornímu konci výztužného vertikálního nosného jádra připevní tuhý kovový rošt, na který se zavěsí kovové trouby sloupů skeletu, načež se tuhý kovový rošt vybetonuje na posuvném bednění. V další fázi se posuvné bednění ostupně spouští vždy o výšku jednoho podaží budovy vždy po vybetonování stropu podlaží do fáze, kdy vzpěr volných délek kovových trub sloupů skeletu je nepodstatný pro jejich dimenzování. V této fázi se kovové trouby vyplní betonem, které se po zatvrdnutí betonu opřou o základ budovy. V další fázi se pokračuje se spouštěním posuvného bednění a s betonováním dalších stropů jednotlivých podlaží budovy.The task is to develop a method for constructing high-rise buildings with reinforcing supporting vertical structures and skeleton columns, which will not result in over-dimensioning of the skeleton columns at the stage of their operational use. During the construction of a high-rise building, a rigid metal grid is attached to the upper end of the reinforcing vertical supporting core, on which the metal tubes of the skeleton columns are hung, after which the rigid metal grid is concreted on sliding formwork. In the next phase, the sliding formwork is gradually lowered by the height of one building floor, always after the concrete has been poured into the floor ceiling, to the stage when the buckling of the free lengths of the metal tubes of the skeleton columns is insignificant for their dimensioning. In this phase, the metal tubes are filled with concrete, which, after the concrete has hardened, rest on the foundation of the building. In the next phase, the sliding formwork is lowered and the concreting of the other ceilings of the individual floors of the building continues.

Description

Vynález se týká způsobu stavby výškových budov s výztužnými nosnými vertikálními konstrukcemi a sloupy skeletu systémem spouštění posuvného bednění^ uloženého na zvedacím zařízení»BACKGROUND OF THE INVENTION 1. Field of the Invention

Je známo, že u staveb větších výšek jsou sloupy skeletu při výstavbě s použitím spouštěného bednění, to je betonováním stropních desek od shora dolů, dimenzo.vány na zatížení v montážním stadiu, to je·na zatížení větrem a na zatížení od vlastní tíhy a tíhy nejvyšších stropů a bednící plošiny. Sloupy skeletu jsou namáhány na ohyb a chovají se jako konzoly vetknuté do základů a dále na vzpěr s tím, že jejich uchycení v rovině zvednuté bednící plošiny se posuzuje jako kloubové. Po dokončení stavby jsou sloupy namáhány pouze tlakem a s ohledem k tuhosti stropních desek ve své rovině se považují za krátké.It is known that in the construction of higher heights, the skeleton pillars are dimensioned to the load at the assembly stage, that is, to the wind load and to the load due to self-weight, the highest ceilings and formwork platforms. The skeleton columns are subjected to bending and behave like brackets fixed to the foundations and further to struts, with their attachment in the plane of the raised formwork platform being considered articulated. After completion of the construction, the columns are only subjected to pressure and are considered short due to the rigidity of the ceiling slabs in their plane.

Nevýhodou staveb vybudovaných dosavadním způsobem je, že sloupy skeletu tvořené ocelovými troubami, které jsou po vztyčení ukotveny do základu, jsou ve stadiu využívaní stavby předimenzovány.The disadvantage of constructions built up to now is that the skeleton columns made of steel pipes, which are anchored to the foundation after erection, are over-dimensioned at the stage of use of the construction.

Uvedené nevýhody dosud známých způsobů staveb výškových budov s výztužnými nosnými vertikálními konstrukcemi budovy, jako jádra a stěny budovy a sloupy skeletu budovy systémem spouštěného posuvného bednění stropů podlaží budovy, uloženého na zvedacím zařízení, se odstraní způsobem podle vynálezu, jehož podstata spočívá v tom, že k hornímu konci výztužného vertikálního nosného jádra nebo stěn budovy se připevní tuhý kovový rošt s odnímatelnými pruty nebo lany pro přenášení tahových zatížení, na který se zavěsí kovové trouby sloupů skeletu při ponechání vůle mezi základem budovy a spodními konci kovových trub. Kovový rošt se v další fázi vybetonuje na posuvném bednění, načežThe above-mentioned disadvantages of the previously known methods of high-rise building construction with reinforcing vertical building constructions, such as the core and walls of the building and the skeleton of the building skeleton of the lowered sliding formwork of the building flooring mounted on the lifting device are eliminated by the method of the invention. a rigid metal grate with removable tensile load-carrying bars or ropes is attached to the upper end of the reinforcing vertical load-bearing core or walls of the building, to which the metal tubes of the skeleton pillars are suspended while leaving a clearance between the foundation and the lower ends of the metal tubes. In the next phase, the metal grate is concreted on a sliding formwork, and then

- 2 241 611 se posuvné bednění postupně spouští vždy o výšku jednoho podlaží budovy po předchozím vybetonování a zatvrdnutí stropu podlaží, spojeného jak s kovovými troubami sloupů skeletu, tak s vertikálním výztužným nosným jádrem nebo stěnou budovy, do fáze, kdy vzpěr volných délek kovových trub sloupů skeletu je nepodstatný pro jejich dimenzování, načež se kovové trouby vyplní betonem a po jeho zatvrdnutí a uvolnění prutů nebo lan pro přenášení tahových zatížení tuhého kovového roštu se pokračuje se spouštěním posuvného bednění a betonováním stropů jednotlivých podlaží budovy*- 2 241 611, the sliding formwork is lowered gradually by the height of one storey of the building after previous concrete concreting and hardening of the floor ceiling connected to both metal pipes of the skeleton pillars and vertical reinforcing bearing core or wall of the building, the skeleton columns are irrelevant for their dimensioning, whereupon the metal pipes are filled with concrete and after its hardening and loosening of the bars or ropes for carrying the tensile loads of the rigid metal grate, the sliding formwork is started and the ceilings of the individual floors of the building continue

Výhodou způsobu stavby výškových budov podle vynálezu je to, že dimenzování sloupů skeletu se provádí jako krátkých sloupů na tlak, dále že na tuhý kovový rošt zalitý betonem, spojený s horním koncem výztužného vertikálního nosného jádra nebo stěn budovy jsou napojeny sloupy skeletu budovy, které s ním spolupůsobí při přenášení vodorovných zatížení a dále, že kovový pláš^t sloupů skeletu působí po uvolnění prutů nebo lan pro přenášení tahových zatížení od tuhého kovového roštu na beton těchto sloupů jako předpínací výztuž, čímž je zamezeno možnosti vzniku trhlin od vodorovných zatížení. Dimenzování sloupů skeletu jako krátkých na tlak, spolupráce sloupů s výztužným vertikálním nosným jádrem a částečné předpětí sloupů skeletu přinese úspory oceli a betonu jak u samotných sloupů skeletu, tak i u vertikálních výztužných nosných konstrukcí budov*The advantage of the method of construction of high-rise buildings according to the invention is that the dimensioning of the skeleton columns is carried out as short columns for compression, furthermore that the skeleton columns are connected to the rigid metal grate embedded in concrete connected to the upper end of the and that the metal shell of the skeleton columns acts as a prestressing reinforcement after releasing the tensile members or ropes to transfer the tensile loads from the rigid metal grate to the concrete, thereby avoiding the possibility of cracks from horizontal loads. Dimensioning the skeleton columns as short in compression, the cooperation of the columns with the reinforcing vertical support core and the partial prestressing of the skeleton columns will save steel and concrete for both the skeleton columns themselves and the vertical reinforcing structure of buildings *

Způsob stavby výškových budov podle vynálezu je jako příklad schematicky postupově znázorněn na přiloženém výkresu, kde obr. 1 znázorňuje nosné jádro budovy ze železobetonu, spojené se základem, obr. 2 znázorňuje nosné jádro budovy,na svém horním konci opatřené tuhým kovovým roštem s odnímatelnými pruty nebo lany pro přenášení tahových zatížení, obr. 3 znázorňuje navíc zavěšení kovových trub sloupů skeletu na tuhém kovovém roštu, obr. 4 znázorňuje navíc smontované posuvné bednění na základu stavby, obr. 5 znázorňuje smontované posuvné bednění v horní poloze a na něm vybetonovaný kotový rošt, obr. 6 znázorňuje polohu posuvného bednění ve fázi, kdy vzpěr volných délek kovovýchThe method of construction of high-rise buildings according to the invention is illustrated schematically by way of example in the accompanying drawing, in which Fig. 1 shows the supporting core of a reinforced concrete building connected to the foundation. Fig. 2 shows the supporting core of a building provided with a solid metal grate with detachable bars Fig. 3 shows in addition the suspension of metal tubes of the skeleton columns on a rigid metal grate, Fig. 4 shows in addition assembled sliding formwork on the foundation of the building, Fig. 5 shows assembled sliding formwork in the upper position and concreted anchor grate Fig. 6 shows the position of the sliding formwork in the phase where the struts of the free lengths of the metal

- 3 241 611 trub sloupů skeletu je nepodstatný pro jejich dimenzování a kdy nad posuvným bedněním je vybetonováno několik stropů podlaží a obr· 7 skelet výškové budovy se stropy podlaží.- 3 241 611 skeleton pillar tubes are irrelevant for their sizing and when several floor ceilings are concreted above the sliding formwork, and Fig. 7 is a high-rise skeleton with floor ceilings.

Podle příkladného provedení se stavba výškové budovy provádí tak, že na základ 2 se postaví výztužné vertikální nosné jádro 1 budovy, které se na svém horním konci opatří vodorovným tuhým kovovým roštem 2· Puhý kovový rošt 2 se spojí s jádrem 1 odnímatelnými pruty nebo lany Pro přenos tahových zatížení. Na tuhý kovový rošt 2 se zavěsí kovové trouby 2 sloupů skeletu, které jsou se základem 2 spojeny naváděcími čepy, V další fázi se na základu 2 smontuje posuvné bednění 6, které se zvedacím zařízením 8 zvedne pod tuhý kovový rošt 2 a 'tuhý kovový rošt 2 se zaleje betonem 2· V dalších fázích se posuvné bednění 6 spouští vždy o výšku jednoho podlaží budovy, a to po předchozím vybetonování stropu 2 jednoho podlaží, spojeného jak s kovovými troubami 2 sloupů skeletu, tak 's vertikálním výztužným nosným jádrem 1 budovy. Stropy 2 podlaží budovy se takto vytvářejí do fáze, kdy vzpěr volných délek kowvých trub 2 slou pů skeletu je nepodstatný pro jejich dimenzování· V této fázi se kovové trouby 2 vyplní betonem· Po zatvrdnutí betonu v kovových troubách 2 se uvolní odnímatelní pruty nebo lana 4 od tuhého kovového roštu a od vertikálního nosného jádra 1 budovy, čímž doj,de k dosednutí sloupů skeletu na základ 2. V následující fázi se pokračuje v betonování stropů 2 podlaží budovy, a to na posuvném bednění 6, uloženém na zvedacím zařízení 8. Po vybetonování posledního stropu 2 podlaží budovy se demontuje zvedací zařízení 8 a posuvné bednění 6»According to an exemplary embodiment of the construction of high-rise buildings is carried out so that the base 2 stands reinforcing vertical support core 1 of a building, which at its upper end provided with a horizontal solid metal grate 2 · naked metal grid 2 is combined with the core 1 removable rods or ropes P ro transfer of tensile loads. On the rigid metal grate 2 , metal tubes 2 of the skeleton columns are suspended, which are connected to the foundation 2 by means of guide pins. In the next stage, a sliding formwork 6 is assembled on the base 2 and lifted under the rigid metal grate 2 . In the following stages, the sliding formwork 6 is lowered by the height of one storey of the building, after previously concreting the ceiling 2 of one storey, connected to both the metal pipes 2 of the skeleton columns and the vertical reinforcing support core 1 of the building. The ceilings 2 of the building floor are thus formed to a stage where the free lengths of the metal pipes 2 serve as a part of the skeleton is irrelevant for their dimensioning · At this stage the metal pipes 2 are filled with concrete. from the rigid metal grate and from the vertical load-bearing core 1 of the building, thereby bringing the skeleton columns onto the foundation 2. Subsequently, the ceilings 2 of the building of the building continue to be concreted on the sliding formwork 6 mounted on the lifting device 8. the lifting of the lifting device 8 and the sliding formwork 6 »

Claims (1)

PŘEDMĚT VYNÁLEZUSUBJECT OF THE INVENTION 241 611241 611 Způsob stavby výškových budov s výztužnými nosnými vertikálními konstrukcemi budovy, ze jména..jádry, nebo stěnami^ a sloupy skeletu budovy systémem spouštěného posuvného bednění stropů podlaží budovy, uloženého na zvedacím zařízení, vyznačený 'tím, že k hornímu konci výztužného vertikálního nosného jádra (1) nebo stěn budovy se připevní tuhý kovový rošt (3) s odnímatelnými pruty nebo lany (4) pro přenášení tahových zatížení, na který se zavěsí kovové trouby (5) sloupů skeletu při ponechání vůle mezi základem.(2) budovy a spodními konci kovových trub (5), kde tuhý kovový rošt (3) se v další fázi vybetonuje betonem (7) na posuvném bednění (6), načež se posuvné bednění (6) postupně spouští vždy o výšku jednoho podlaží budovy po předchozím vybetonování a zatvrdnutí stropu (9) podlaží, spojeného s kovovými troubami (5) sloupů skeletu a s vertikálním výztužným nosným jádrem (1) nebo stěnou budovy do fáze, kdy vzpěr volných délek kovových trub (5) sloupů skeletu je nepodstatný pro jejich dimenzování, načež se kovové trouby (5) vyplní betonem a po jeho zatvrdnutí a uvolnění prutů nebo lan (4) pro přenášení tahových zatížení(tuhého kovového roštu (3) se pokračuje se spouštěním posuvného bednění (6) a betonování stropů (9) jednotlivých podlaží budovy.A method of constructing high-rise buildings with reinforcing vertical supporting structures of a building, namely cores or walls and skeleton pillars of a building skeleton-lowered sliding formwork of ceilings of a building supported by a lifting device, characterized in that to the upper end of the reinforcing vertical support core 1) or a rigid metal grate (3) with removable rods or ropes (4) to attach tensile loads to which the metal pipes (5) of the skeleton columns are suspended while leaving a play between the foundation. metal pipes (5), where the rigid metal grate (3) is then concreted with concrete (7) on the sliding formwork (6), whereupon the sliding formwork (6) is gradually lowered by one floor of the building after previous concreting and ceiling hardening (9) floors connected to metal tubes (5) skeleton columns and vertical reinforcing support core (1) or with the metal pipes (5) is filled with concrete and after its hardening and releasing of bars or ropes (4) for transfer of tensile loads (solid metal) of the grate (3) continues with lowering the sliding formwork (6) and concreting the ceilings (9) of the individual floors of the building.
CS838273A 1983-11-09 1983-11-09 The method of construction of high-rise buildings with supporting vertical structures CS241611B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CS838273A CS241611B1 (en) 1983-11-09 1983-11-09 The method of construction of high-rise buildings with supporting vertical structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CS838273A CS241611B1 (en) 1983-11-09 1983-11-09 The method of construction of high-rise buildings with supporting vertical structures

Publications (2)

Publication Number Publication Date
CS827383A1 CS827383A1 (en) 1985-08-15
CS241611B1 true CS241611B1 (en) 1986-04-17

Family

ID=5433107

Family Applications (1)

Application Number Title Priority Date Filing Date
CS838273A CS241611B1 (en) 1983-11-09 1983-11-09 The method of construction of high-rise buildings with supporting vertical structures

Country Status (1)

Country Link
CS (1) CS241611B1 (en)

Also Published As

Publication number Publication date
CS827383A1 (en) 1985-08-15

Similar Documents

Publication Publication Date Title
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
US3239990A (en) Multi-storey buildings
CN112554535A (en) Construction method for large silo top plate without supporting frame
CN216787874U (en) Large-scale ring type truss hoisting structure in large-span high altitude
CN115538678A (en) Construction method for large-angle overhanging landscape platform side small platform
JPH09317183A (en) Building construction method
US3156071A (en) Building structure
US3851024A (en) Reinforced concrete construction method
US3552080A (en) Method for erecting multistory buildings
CN216664766U (en) Assembled parapet that cornices
JPH0525933A (en) Support type scaffolding formwork raising device and concrete skeleton construction method
CN213477596U (en) Large-span high suspended structure formwork supporting platform connecting structure
US3295266A (en) Suspended floor system for a multi-level building
CN114737750A (en) Construction method for reinforced concrete silo top plate template
RU2032047C1 (en) Building skeleton erection method
CN216276830U (en) Super high-rise core tube formwork lowering construction device
JP3338240B2 (en) Construction method for reinforced concrete structures
KR20250048507A (en) Elevator machine room steel structure and construction method
KR20250048506A (en) Elevator machine room steel structure and construction method
JP3018947B2 (en) Construction method of reinforced concrete building with balcony
JP2696486B2 (en) Building construction method
JP7462475B2 (en) How to build a building
CS261357B1 (en) Way of building a high-rise building with a rigid grate
KR20250061106A (en) Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures
CS242930B1 (en) Method of assembly of columns of high-rise buildings with reinforcing vertical structures