EP0457813A1 - Verfahren zum errichten von betonbauwerken in lockerem material von der geländeoberkante aus und gerät zum durchführen dieses verfahrens. - Google Patents
Verfahren zum errichten von betonbauwerken in lockerem material von der geländeoberkante aus und gerät zum durchführen dieses verfahrens.Info
- Publication number
- EP0457813A1 EP0457813A1 EP90903056A EP90903056A EP0457813A1 EP 0457813 A1 EP0457813 A1 EP 0457813A1 EP 90903056 A EP90903056 A EP 90903056A EP 90903056 A EP90903056 A EP 90903056A EP 0457813 A1 EP0457813 A1 EP 0457813A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- erosion
- head
- grouting
- bore hole
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 27
- 238000000034 method Methods 0.000 title claims abstract description 27
- 230000003628 erosive effect Effects 0.000 claims abstract description 63
- 239000000463 material Substances 0.000 claims abstract description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 17
- 238000005553 drilling Methods 0.000 claims description 4
- 239000011381 foam concrete Substances 0.000 claims 1
- 238000002347 injection Methods 0.000 abstract description 5
- 239000007924 injection Substances 0.000 abstract description 5
- 239000004568 cement Substances 0.000 abstract description 2
- 239000011440 grout Substances 0.000 abstract 3
- 239000011800 void material Substances 0.000 description 20
- 239000002689 soil Substances 0.000 description 8
- 239000011435 rock Substances 0.000 description 4
- 239000011230 binding agent Substances 0.000 description 3
- 238000005266 casting Methods 0.000 description 3
- 239000000523 sample Substances 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000011010 flushing procedure Methods 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 230000000087 stabilizing effect Effects 0.000 description 2
- 206010052428 Wound Diseases 0.000 description 1
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 239000000654 additive Substances 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- KEUKAQNPUBYCIC-UHFFFAOYSA-N ethaneperoxoic acid;hydrogen peroxide Chemical compound OO.CC(=O)OO KEUKAQNPUBYCIC-UHFFFAOYSA-N 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 230000008014 freezing Effects 0.000 description 1
- 238000007710 freezing Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 238000013507 mapping Methods 0.000 description 1
- 239000003415 peat Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000009877 rendering Methods 0.000 description 1
- 230000002940 repellent Effects 0.000 description 1
- 239000005871 repellent Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- -1 silt Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/29—Obtaining a slurry of minerals, e.g. by using nozzles
Definitions
- a process for building a concrete structure in loose matter, from ground level, and equipment for carrying out said process is a process for building a concrete structure in loose matter, from ground level, and equipment for carrying out said process.
- the present invention relates to a process for building a concrete structure in loose matter, from ground level, by use of a rotatable erosion head and a grouting head provided with a drill bit, of the kind as stated in more detail in the preamble of the independent process claim 1 below.
- the invention also relates to equipment for carrying out said process and of a kind as stated above.
- the present invention relates to building permanent struct ⁇ ural elements in loose matter without necessitating any preliminary conventional digging operations and temporary safety measures.
- the advantages of the process according to the present invention are due to the fact that it permits drilling down into loose matter from ground level, either indoors or outdoors, irrespective of the kind of soil, to the necessary level for erecting water-proof and permanent structures.
- Upon completing the structure in the ground the only wounds in the terrain visible on the surface will be moderate "pinpricks", i. e. holes with diameters in the range of 15 cm.
- the process and equipment according to the present invention will render a series of other conventional operations redundant, e.g. soil stabilizing operations, like freezing, injection, digging, boarding, casting, also pumping wells, ground compensation and compensations for inconvenience. Also, a reduced construction period is achieved.
- the process and equipment according to the present invention is also well suited for building tunnels (culverts) below existing railway tracks and roads without interfering with traffic on the crossing railway or road line. With present methods these are problems which could only be solved by temporary by-pass roads or by-pass tracks, which are expensive arrangements per se.
- Figure 1 is a diagrammatical front view of the equipment for carrying out the process according to the present invention, shown in a position upon completed drilling and before erosion and grouting operations are started;
- Figure 2 is a diagrammatical elevation of the equipment provided on a caterpillar rig
- Figures 3-5 show the principle of the process in three steps comprising a beginning erosion of the drill hole, expansion of the bore hole by erosion, and continued expansion of the bore hole in the direction of its height with simultaneous grouting of the bore hole with concrete, respectively.
- Figure 1 shows the equipment in the position reached upon drilling down into the ground, before erosion of the drilled hole and grouting of the bore hole which is expanded by erosion.
- the equipment comprises two units, i. e. an erosion unit 2, and a grouting unit 3 for grouting with concrete.
- the erosion unit comprises an erosion head 2a with a drill bit 2b provided lowermost. Above the latter an erosion nozzle 2c is provided and comprises a water nozzle which is surrounded by an air nozzle for ejecting a radial jet stream of water and air.
- the erosion unit furthermore, comprises a guiding tube 8 on which the above mentioned components are mounted and through which water and air conduits extend to feed said erosion nozzles 2c.
- Guiding tube 8 is mounted in a bearing 8a to be raisable and lowerable as well as rotatable, and rotating motor 8b is provided in a frame 6a. Guiding tube 8 is at its uppermost end connected to supply conduits 10 and 11 for water and air, respectively, via a swivel means 10a.
- Grouting unit 3 with grouting head 3a and drill bit 3b is rotatably and raisably as well as lowerably mounted in a bearing 9a, and rotating motor 9b is provided in a frame 6b, and unit 3 is at its uppermost end connected with a supply conduit for concrete, via swivel means 11a.
- frames 6a and 6b constitute a rack 6 with adjusting means 7 of mutual spacing between frames 6a, 6b.
- Rack 6 is intended for adjustable attachment to a rig F, e.g. a caterpillar rig, as shown in Figure 2, by the aid of means F ⁇ known per se, permitting the equipment to be raised and lowered as well as inclined by the aid of pressure cylinders in a manner known per se, as shown in Figure 2.
- Erosion head 2a and grouting head 3a may, thus, be independently actuated for lowering, raising, and rotation, respectively.
- Frames 6a, 6b are movable to and from .each other for adjustment of the center distance C between erosion head 2a and grouting head 3a.
- adjusting means 7 consists of adjustable telescopic rods 7a which connect frames 6a and 6b.
- a collar 12 is provided about guiding tube 8 in order to collect and guide eroded loose matter from bore holes in a controlled manner through a mass and density gauge to permit calculation of the volume of the eroded void, i.e. the expanded void.
- adjustable spacer means 7a By the aid of adjustable spacer means 7a the center distance between erosion head 2a and grouting head 3a can be adjusted according to the projected diameter of the expanded bore hole 4a.
- Grouting unit 3 comprises extendable grouting pipes 9.
- erosion unit 2 and grouting unit 3 are drilled down to rock or portative ground with a predetermined center distance C between units 2 and 3.
- the downwards directed erosion nozzle 2d on erosion head 2a is used.
- Upon erosion of the rock surface erosion head 2a and guiding tube 8 are pulled up by a raising means, not shown. Pulling up occurs slowly during constant rotation, and simultaneous ejection of highly compressed water and air at a high pressure of 100- 1000 bar, from water and air nozzle 2c. Said water jet enveloped by air will break down the particulate structure and dissolve soil in bore hole 4 which is drilled by drill bit 2b of erosion head 2a.
- An expanded bore hole 4a with a desired diameter is thus formed, its diameter being meas ⁇ urable by the aid of equipment known per se, which is not described in detail here.
- a cylindrical eroded void is formed which constitutes said expanded bore hole 4a.
- Due to the overpressure created by high-pressure jet 5a from nozzle 2c flushed down material E will be urged towards the surface through bore hole 4 and said collar 12.
- high-grade concrete D is pumped through grouting pipe 9 with grouting head 3a to fill void 4a, which will also cause expulsion up through bore hole 4 of material E which was broken down by flushing.
- Concrete D may be provided with additives rendering it water- repellent, so that flows in void 4a due to erosion jet 5a will cause a minimum of binder to be washed out from concrete D.
- grouting head 3a When guiding tube 8 with erosion head 2a and grouting pipe 9 with grouting head 3a are pulled up, grouting head 3a should preferably be positioned at least 0.5 m below erosion jet nozzle 2c if the latter is active, so as to reduce harmful flows in the eroded space which may wash out binder from concrete D.
- erosion beam 5a from nozzle 2c is started to expand bore hole 4 and provide the expanded bore hole 4a and, thus, the desired void as shown In Figure 4, with a desired diameter B and a desired height H, as shown in Figure 5.
- Figure 4 shows incipient expansion of bore hole 4 during rotation and pulling up of erosion head 2a, whereas supply pipe 9 with grouting head 3a is at rest in a peripheral position in the lower portion of the expanded bore hole 4a.
- Figure 5 shows the next step, in which erosion head 2a is pulled up approximately to a desired level H of the expanded bore hole 4, and in which concrete D is supplied through supply pipe 9 to fill up the expanded bore hole 4a. This operation is continued until the expanded bore hole 4a Is filled.
- erosion jet i.e. air and water jet 5a
- a concrete structure with a corresponding cross section may be provided.
- the process according to the present Invention may be carried out in all kinds of ground. This process is, thus, applicable in clay, silt, sand and gravel, as well as in most kinds of fillers, moraine, and boggy soil/peat.
- the erosion and grouting process may, if desired, be carried out in two phases, since trasitory tensions in cohesion soils will generally prevent the eroded void from collapsing If it is filled with water. There are several advantages of carrying out the erosion and grouting process in two operations:
- void 4a In friction soils both operations, i.e. erosion and grouting, must be carried out in one operation, since the provided void 4a will generally collapse before grouting with concrete D is completed.
- the void i.e. the expanded bore hole 4a, may however be stabilized if a heavy stabilizing liquid, e.g. bentonite, is introduced into the void. Said liquid will, however, tend to mix with the return matter, i.e. the eroded soils and flushing water, so that the extent, i.e. width B of the structure/pile can only be measured by the aid of an acoustic probe or by measuring the volume of concrete D which is cast inside void 4a.
- a heavy stabilizing liquid e.g. bentonite
- the distance between erosion head 2a and grouting head 3a is adjustable by the aid of telescopic rods 7a in rack 6. It is, thus, possible to ensure that grouting head 3a and erosion head 2a receive a desired mutual center distance when drilled down into ground A, causing grouting head 3a to be located in the periphery of the eroded/expanded bore hole 4a, as shown in Figures 4 and 5. Consequently, concrete D which Is injected through the relatively thick supply pipe 9 will fill the expanded bore hole 4a from a location at the hole wall and will, thus, expel any eroded matter and water up through bore hole 4.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Soil Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Geochemistry & Mineralogy (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Earth Drilling (AREA)
- Orthopedics, Nursing, And Contraception (AREA)
- Steroid Compounds (AREA)
- Compounds Of Unknown Constitution (AREA)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| NO890420 | 1989-02-02 | ||
| NO890420A NO167051C (no) | 1989-02-02 | 1989-02-02 | Fremgangsmaate for etablering av betongkonstruksjoner i loesmasser, fra terrengnivaa, samt utstyr for utoevelse av fremgangsmaaten |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| EP0457813A1 true EP0457813A1 (de) | 1991-11-27 |
| EP0457813B1 EP0457813B1 (de) | 1993-08-04 |
Family
ID=19891690
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP90903056A Expired - Lifetime EP0457813B1 (de) | 1989-02-02 | 1990-02-01 | Verfahren zum errichten von betonbauwerken in lockerem material von der geländeoberkante aus und gerät zum durchführen dieses verfahrens |
Country Status (10)
| Country | Link |
|---|---|
| EP (1) | EP0457813B1 (de) |
| JP (1) | JP2532751B2 (de) |
| KR (1) | KR0174725B1 (de) |
| AU (1) | AU5090090A (de) |
| DE (1) | DE69002615T2 (de) |
| DK (1) | DK0457813T3 (de) |
| FI (1) | FI92506C (de) |
| NO (1) | NO167051C (de) |
| RU (1) | RU2042012C1 (de) |
| WO (1) | WO1990008855A1 (de) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109441441A (zh) * | 2018-11-15 | 2019-03-08 | 华北科技学院 | 一种承压动水作用下煤层底板多角度倾斜钻孔注浆工艺模拟试验装置及方法 |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2701973B1 (fr) * | 1993-02-22 | 1995-04-07 | Sif | Installation à sas pour dispositif de traitement des sols par jet(s) rotatif(s). |
| US6957220B2 (en) | 2000-11-07 | 2005-10-18 | Research Investment Networks, Inc. | System, method and article of manufacture for tracking and supporting the distribution of content electronically |
| SE0202501L (sv) * | 2002-08-23 | 2004-02-24 | Soilex Ab | Sätt att tillverka en påle och/eller ett dragstag |
| RU2303101C1 (ru) * | 2005-12-01 | 2007-07-20 | Владимир Александрович Бреннер | Способ закрепления грунта |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FI65833C (fi) * | 1977-12-27 | 1984-07-10 | Kajima Corp | Sprutanordning foer cementvaelling |
| SE444195B (sv) * | 1982-08-16 | 1986-03-24 | Nit Co Ltd | Sett och apparat for insprutning av solidifieringsmaterial i en jordmaterialkropp |
-
1989
- 1989-02-02 NO NO890420A patent/NO167051C/no not_active IP Right Cessation
-
1990
- 1990-02-01 DK DK90903056.1T patent/DK0457813T3/da active
- 1990-02-01 DE DE90903056T patent/DE69002615T2/de not_active Expired - Lifetime
- 1990-02-01 AU AU50900/90A patent/AU5090090A/en not_active Abandoned
- 1990-02-01 EP EP90903056A patent/EP0457813B1/de not_active Expired - Lifetime
- 1990-02-01 KR KR1019900701981A patent/KR0174725B1/ko not_active Expired - Lifetime
- 1990-02-01 JP JP2503217A patent/JP2532751B2/ja not_active Expired - Lifetime
- 1990-02-01 WO PCT/NO1990/000025 patent/WO1990008855A1/en not_active Ceased
-
1991
- 1991-08-02 RU SU915001470A patent/RU2042012C1/ru active
- 1991-08-02 FI FI913689A patent/FI92506C/fi active
Non-Patent Citations (1)
| Title |
|---|
| See references of WO9008855A1 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109441441A (zh) * | 2018-11-15 | 2019-03-08 | 华北科技学院 | 一种承压动水作用下煤层底板多角度倾斜钻孔注浆工艺模拟试验装置及方法 |
| CN109441441B (zh) * | 2018-11-15 | 2022-02-22 | 华北科技学院 | 一种承压动水作用下煤层底板多角度倾斜钻孔注浆工艺模拟试验装置及方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| DK0457813T3 (da) | 1993-12-27 |
| DE69002615D1 (de) | 1993-09-09 |
| JPH07507362A (ja) | 1995-08-10 |
| DE69002615T2 (de) | 1993-11-11 |
| FI92506C (fi) | 1994-11-25 |
| KR0174725B1 (ko) | 1999-02-18 |
| NO167051C (no) | 1991-09-25 |
| JP2532751B2 (ja) | 1996-09-11 |
| FI913689A0 (fi) | 1991-08-02 |
| NO167051B (no) | 1991-06-17 |
| KR910700383A (ko) | 1991-03-15 |
| RU2042012C1 (ru) | 1995-08-20 |
| FI92506B (fi) | 1994-08-15 |
| AU5090090A (en) | 1990-08-24 |
| NO890420L (no) | 1990-08-03 |
| NO890420D0 (no) | 1989-02-02 |
| WO1990008855A1 (en) | 1990-08-09 |
| EP0457813B1 (de) | 1993-08-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101962949B (zh) | 长螺旋二重管高压搅喷桩施工方法及其装置 | |
| US3354657A (en) | Method for installing anchoring or supporting columns in situ | |
| CN103233469B (zh) | 旋扩桩施工工艺、设备及进浆装置 | |
| CN205172598U (zh) | 管幕旋喷桩支护结构 | |
| CN110130909B (zh) | 一种在粉土地层中盾构下穿既有车站的施工方法 | |
| CN111173038A (zh) | 一种竖井的施工工艺 | |
| CN107338789B (zh) | 一种潜孔冲击式三重管高压旋喷桩的施工方法 | |
| CN1206417C (zh) | 防水桩挡墙的成型方法 | |
| CN201649093U (zh) | 长螺旋二重管高压搅喷桩施工装置 | |
| EP0457813B1 (de) | Verfahren zum errichten von betonbauwerken in lockerem material von der geländeoberkante aus und gerät zum durchführen dieses verfahrens | |
| CN113322936B (zh) | 一种厚砂层岩溶区域土体加固施工方法及施工辅助装置 | |
| CN113216148A (zh) | 承压水地下防空洞坍塌地段桩基施工方法 | |
| CN116752524A (zh) | 高水位连砂石地质条件下抗浮锚杆施工方法 | |
| CN117145381A (zh) | 一种可防塌孔的桩体钻进装置及施工方法 | |
| RU2013495C1 (ru) | Способ выравнивания зданий, сооружений | |
| CN112392487A (zh) | 用于强透水岩体下饱和含水砂土层中的洞挖施工方法 | |
| JP2958426B2 (ja) | 不同沈下修正工法 | |
| EP2009225B1 (de) | Verfahren zur Bereitstellung einer fliesenförmigen Bodenstruktur | |
| JPS6131244B2 (de) | ||
| CN118065935A (zh) | 隧道软弱基底后注浆复合地基施工方法 | |
| CN210684675U (zh) | 一种用于含块石层的搅拌桩止水结构 | |
| JPS5826115A (ja) | 拡底杭工法 | |
| CN119824744A (zh) | 一种用于高速公路软土路基的防沉降施工方法 | |
| CN116356844A (zh) | 用于高水位砂土地质一级基坑的支护施工方法及基坑结构 | |
| JPH0522769B2 (de) |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| 17P | Request for examination filed |
Effective date: 19910731 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): DE DK FR GB IT NL SE |
|
| 17Q | First examination report despatched |
Effective date: 19921030 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): DE DK FR GB IT NL SE |
|
| ITF | It: translation for a ep patent filed | ||
| REF | Corresponds to: |
Ref document number: 69002615 Country of ref document: DE Date of ref document: 19930909 |
|
| ET | Fr: translation filed | ||
| REG | Reference to a national code |
Ref country code: DK Ref legal event code: T3 |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| 26N | No opposition filed | ||
| EAL | Se: european patent in force in sweden |
Ref document number: 90903056.1 |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 19960201 |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: 728V |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: 728Y |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 19980228 Year of fee payment: 9 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19990901 |
|
| EUG | Se: european patent has lapsed |
Ref document number: 90903056.1 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: RN |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: FC |
|
| NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee |
Effective date: 19990901 |
|
| NLXE | Nl: other communications concerning ep-patents (part 3 heading xe) |
Free format text: A REQUEST FOR RESTORATION TO THE PRIOR STATE AS PROVIDED FOR IN ART. 17A OF THE PATENTS ACT (SEE PUBLICATION IN HEADING XE OF THE PATENT BULLETIN OF 03.01.2001/01) HAS BEEN REJECTED. |
|
| REG | Reference to a national code |
Ref country code: DK Ref legal event code: EGE |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: IF02 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20060228 Year of fee payment: 17 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DK Payment date: 20090213 Year of fee payment: 20 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20090129 Year of fee payment: 20 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20090128 Year of fee payment: 20 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20090206 Year of fee payment: 20 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070201 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20090213 Year of fee payment: 20 |
|
| REG | Reference to a national code |
Ref country code: DK Ref legal event code: EUP |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: PE20 Expiry date: 20100131 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION Effective date: 20100131 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION Effective date: 20100201 |