ES2176608T3 - Procedimiento para la construccion de una viga compuesta y viga asi construida. - Google Patents
Procedimiento para la construccion de una viga compuesta y viga asi construida.Info
- Publication number
- ES2176608T3 ES2176608T3 ES97200608T ES97200608T ES2176608T3 ES 2176608 T3 ES2176608 T3 ES 2176608T3 ES 97200608 T ES97200608 T ES 97200608T ES 97200608 T ES97200608 T ES 97200608T ES 2176608 T3 ES2176608 T3 ES 2176608T3
- Authority
- ES
- Spain
- Prior art keywords
- concrete
- cables
- iron
- slabs
- high performance
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title abstract 5
- 239000002131 composite material Substances 0.000 title abstract 3
- 238000010276 construction Methods 0.000 title 1
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract 6
- 239000004567 concrete Substances 0.000 abstract 3
- 229910052742 iron Inorganic materials 0.000 abstract 3
- 229910000831 Steel Inorganic materials 0.000 abstract 2
- 239000004574 high-performance concrete Substances 0.000 abstract 2
- 238000009417 prefabrication Methods 0.000 abstract 2
- 239000010959 steel Substances 0.000 abstract 2
- 230000000977 initiatory effect Effects 0.000 abstract 1
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 239000000463 material Substances 0.000 abstract 1
- 238000000465 moulding Methods 0.000 abstract 1
- 230000002787 reinforcement Effects 0.000 abstract 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/29—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
- E04C3/293—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
- E04C3/294—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete of concrete combined with a girder-like structure extending laterally outside the element
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
- B28B23/04—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
- B28B23/06—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed for the production of elongated articles
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49616—Structural member making
- Y10T29/49623—Static structure, e.g., a building component
- Y10T29/49634—Beam or girder
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Manufacturing & Machinery (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Composite Materials (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
- Bridges Or Land Bridges (AREA)
- Analysing Materials By The Use Of Radiation (AREA)
- Superconductors And Manufacturing Methods Therefor (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
SE PRESENTA UN METODO PARA MANUFACTURAR UNA VIGA COMPUESTA (11) QUE COMPRENDE UNO O MAS NUCLEOS VERTICALES DE PLANCHA DE ACERO, ASOCIADOS Y QUE COOPERAN CON UNA O MAS LOSAS (13, 4) O ALAS HORIZONTALES DE HORMIGON. AL MENOS UNA DE LAS LOSAS O ALAS HORIZONTALES ESTA HECHA DE HORMIGON DE ALTO RENDIMIENTO PARA PERMITIR QUE LAS FUERZAS MUTUAS O COACCIONES SEAN CARGADAS ENTRE LOS DIFERENTES COMPONENTES DE LA VIGA QUE SON MUCHO MAS ALTOS/FUERTES QUE LAS FUERZAS MUTUAS/COACCIONES QUE PUEDEN SER CARGADAS POR MEDIO DE OTROS METODOS Y MATERIALES. SI LA VIGA COMPUESTA ESTA AL MENOS PARCIALMENTE MANUFACTURADA EN LA FABRICA DE PREFABRICACION, DE ACUERDO CON EL METODO, EL ELEMENTO INICIADOR SERA UNA VIGA EN I (12) PREDOBLADA O INFLEXADA CON MEDIOS DE CONEXION SOLDADOS (15). LA VIGA EN I SE POSICIONARA SOBRE EL BANCO DE PREFABRICACION IMPONIENDO LAS LIGADURAS DE FORMA QUE SE REFUERCE LA VIGA, ENTONCES SE INSTALAN CABLES DE ACERO DE POSICIONAMIENTO (16) PRETENSADOS ENTRE LOS PUNTOS DE ANCLAJE EXTERNOS (17),Y SE LLEVA A CABO EL MOLDEADO DEL HORMIGON EN UN ALA (13) EN LA CUAL LOS CABLES (16) ESTAN ASOCIADOS CON HORMIGON DE ALTO RENDIMIENTO. DE ACUERDO CON EL METODO DE LA INVENCION, DESPUES DE QUE SE COMPLETA EL ENDURECIMIENTO, SE CORTAN Y SE QUITAN LAS LIGADURAS AUXILIARES. DE ESTA FORMA, EL HORMIGON AHORA ENDURECIDO, HACIENDOSE INTEGRAL CON LA VIGA DE HIERRO (12) GRACIAS A LOS ELEMENTOS DE REFUERZO DEL HIERRO Y A LOS MEDIOS DE CONEXION SOLDADOS (15) Y CON LOS CABLES (16) MEDIANTE ADHESION, PROVOCA QUE LOS DIFERENTES COMPONENTES COOPEREN MECANICAMENTE Y QUE LA VIGA COMPUESTA ESTE DOTADA DE CARACTERISTICAS MUCHO MEJORES QUE LAS DE LAS VIGAS YA CONOCIDAS.
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| IT96MI000426A IT1283189B1 (it) | 1996-03-05 | 1996-03-05 | Metodo per la realizzazione di una trave composita e trave cosi' realizzata |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| ES2176608T3 true ES2176608T3 (es) | 2002-12-01 |
Family
ID=11373503
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| ES97200608T Expired - Lifetime ES2176608T3 (es) | 1996-03-05 | 1997-03-04 | Procedimiento para la construccion de una viga compuesta y viga asi construida. |
Country Status (6)
| Country | Link |
|---|---|
| US (1) | US5852905A (es) |
| EP (1) | EP0794042B1 (es) |
| AT (1) | ATE217243T1 (es) |
| DE (1) | DE69712394D1 (es) |
| ES (1) | ES2176608T3 (es) |
| IT (1) | IT1283189B1 (es) |
Families Citing this family (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| AU746805B2 (en) * | 1999-12-15 | 2002-05-02 | Abergeldie G Beam Pty Ltd | A structural element |
| KR100401671B1 (ko) * | 2000-09-16 | 2003-10-11 | (주) 동양구조안전기술 | 프리스트레스트 프리캐스트 콘크리트 패널을 이용한 합성보 |
| KR100396855B1 (ko) * | 2000-11-10 | 2003-09-02 | (주)금화산업 | 축방향 하중을 이용한 프리플렉스 파일의 제작공법 |
| HRP20000906B1 (hr) * | 2000-12-28 | 2009-05-31 | Mara-Institut D.O.O. | Dvostruko prednapregnuta, kompozitna, krovno-stropna konstrukcija s ravnim podgledom za gradnju hala |
| KR100427405B1 (ko) * | 2001-03-07 | 2004-04-17 | 박재만 | 피에스에스씨 합성거더 |
| KR20030012015A (ko) * | 2001-07-30 | 2003-02-12 | 이형훈 | 강바닥판 및 프리플렉스거더 복합형 교량구조 |
| KR20030012014A (ko) * | 2001-07-30 | 2003-02-12 | 이형훈 | 플레이트거더 설치방식을 이용한 프리플렉스교량구조 |
| KR100439470B1 (ko) * | 2001-11-19 | 2004-07-09 | 신성건설 주식회사 | 교량용 합성빔 |
| DE10259584A1 (de) * | 2002-04-04 | 2004-07-15 | Gerhards, Karl, Dipl.-Ing. | Konstruktionen und Verfahren zur Erhöhung der Tragfähigkeit von Biegeträgern |
| KR100501487B1 (ko) * | 2002-05-28 | 2005-07-18 | 이형훈 | 가로보 및 주형(프리플렉스 빔)을 이용한 연속교 시공방법 |
| US20050056822A1 (en) * | 2003-09-12 | 2005-03-17 | Linford Paul M. | Apparatus and method for reinforcing a vinyl beam |
| US20090249742A1 (en) * | 2007-05-11 | 2009-10-08 | International Contractors Services Llc | Composite construction beam |
| EP2324952A1 (de) * | 2008-03-12 | 2011-05-25 | Homag Holzbearbeitungssysteme AG | Bearbeitungsvorrichtung mit Grundkörper aus Beton |
| CN102296751B (zh) * | 2011-06-01 | 2013-03-20 | 马人乐 | 预应力抗疲劳钢梁 |
| DK177889B1 (en) | 2012-11-23 | 2014-11-17 | Kim Illner Breuning | System and Method for biaxial semi-prefabricated lightweight concrete slab |
| CN104358356B (zh) * | 2014-09-17 | 2016-10-05 | 华南理工大学 | 内设局部约束的高强化再生混合钢管砼抗震柱及施工工艺 |
| EP3327200B1 (en) * | 2016-11-29 | 2019-05-15 | Vistal Gdynia S.A. | Prefabricated bridge girder |
| US10576658B2 (en) * | 2017-05-15 | 2020-03-03 | Morton Buildings, Inc. | System and method for embedding substrate in concrete structure |
| CN108058267A (zh) * | 2017-12-14 | 2018-05-22 | 山西路桥第二工程有限公司 | 预制t梁槽钢底座施工方法 |
| CN114108944B (zh) * | 2020-08-25 | 2023-01-03 | 赖政兴 | 具破坏警示功能的非对称断面金属梁 |
| US20240060253A1 (en) * | 2021-09-24 | 2024-02-22 | Pramod Kumar Singh | Composite rcc deck and prestressed parabolic bottom chord underslung open web steel girder bridge superstructure |
| CN115897370B (zh) * | 2022-12-09 | 2023-09-15 | 深圳大学 | 一种复合钢板剪力连接的全装配式钢-砼组合梁桥 |
Family Cites Families (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB842739A (en) * | 1957-07-24 | 1960-07-27 | Felix Louis James Samuely | Improvements in structural steel sections, trusses and the like |
| CH623879A5 (es) * | 1977-10-14 | 1981-06-30 | Emil Peter | |
| BE861444A (fr) * | 1977-12-02 | 1978-03-31 | Cerfontaine Jacques E E | Procede de realisation d'une poutre mixte preflechie en acier-beton |
| JP2844211B2 (ja) * | 1989-04-21 | 1999-01-06 | 日本コンクリート工業株式会社 | 超高強度コンクリート硬化体及び超高強度コンクリート配合物の混練方法 |
| JP2618366B2 (ja) * | 1989-10-16 | 1997-06-11 | 日本セメント株式会社 | 水硬性硬化体の製造方法 |
| US5305572A (en) * | 1991-05-31 | 1994-04-26 | Yee Alfred A | Long span post-tensioned steel/concrete truss and method of making same |
| JPH07116790B2 (ja) * | 1991-07-03 | 1995-12-18 | オリエンタル建設株式会社 | プレキャストコンクリート梁 |
| JPH05302398A (ja) * | 1991-07-03 | 1993-11-16 | Oriental Kensetsu Kk | プレキャストコンクリート梁 |
| FR2681592B1 (fr) * | 1991-09-25 | 1994-07-29 | Saret France | Beton, notamment du type a hautes performances, et procede pour sa preparation. |
| FI92089C (fi) * | 1993-01-13 | 1994-09-26 | Deltatek Oy | Esivalmistettu teräs-betoni-liittopalkki |
| US5471812A (en) * | 1993-07-13 | 1995-12-05 | Muller; Jean | Method for fabricating pretensioned concrete structures |
| DE4328187C2 (de) * | 1993-08-21 | 1995-06-22 | Ekkehart Mitschke | Verfahren zur Herstellung eines Verbundträgers und Verbundträger |
| JP2667129B2 (ja) * | 1995-04-07 | 1997-10-27 | 株式会社ピー・エス | 鋼・コンクリート複合桁 |
-
1996
- 1996-03-05 IT IT96MI000426A patent/IT1283189B1/it active IP Right Grant
-
1997
- 1997-03-04 AT AT97200608T patent/ATE217243T1/de not_active IP Right Cessation
- 1997-03-04 ES ES97200608T patent/ES2176608T3/es not_active Expired - Lifetime
- 1997-03-04 DE DE69712394T patent/DE69712394D1/de not_active Expired - Lifetime
- 1997-03-04 EP EP97200608A patent/EP0794042B1/en not_active Expired - Lifetime
- 1997-03-05 US US08/811,974 patent/US5852905A/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| ITMI960426A0 (es) | 1996-03-05 |
| DE69712394D1 (de) | 2002-06-13 |
| EP0794042B1 (en) | 2002-05-08 |
| ATE217243T1 (de) | 2002-05-15 |
| IT1283189B1 (it) | 1998-04-16 |
| EP0794042A3 (en) | 1999-06-23 |
| US5852905A (en) | 1998-12-29 |
| ITMI960426A1 (it) | 1997-09-05 |
| EP0794042A2 (en) | 1997-09-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| ES2176608T3 (es) | Procedimiento para la construccion de una viga compuesta y viga asi construida. | |
| KR102003670B1 (ko) | 텍스타일 그리드 고정장치를 이용한 텍스타일 보강 콘크리트 구조물 및 그 시공방법 | |
| Abdelrahman | Serviceability of concrete beams prestressed by fibre reinforced plastic tendons | |
| KR100554408B1 (ko) | 교량용 합성거더 및 이를 이용한 시공방법 | |
| KR101723847B1 (ko) | 가설중 프리스트레스를 도입한 강합성 교량 시공 방법 | |
| JPH09158126A (ja) | 既存pc構造物の切断工法 | |
| JPH1025997A (ja) | トンネル壁の補修方法 | |
| JPH0711897A (ja) | トンネル構造 | |
| KR100370939B1 (ko) | 교량용 합성 빔 | |
| KR100403505B1 (ko) | 교량의 보강공법 및 그 구조 | |
| KR20000030231A (ko) | 교량용 합성 빔 | |
| SE9301051D0 (sv) | Bjaelklag omfattande prefabricerade bjaelklagselement | |
| KR102160062B1 (ko) | 기설 교량용 방음터널 및 그 시공 방법 | |
| KR102273716B1 (ko) | 기설 교량용 방음터널 및 그 시공 방법 | |
| KR102462655B1 (ko) | 상부슬래브의 휨모멘트를 완화시킨 조립식 교량 | |
| KR20010097760A (ko) | 포스트 텐션 보강방식 코오벨 구조물 및 그 시공방법 | |
| KR20050000676A (ko) | 거푸집을 사용하지 않은 강합성 교량 및 그 시공방법 | |
| KR20100047962A (ko) | 섬유강화 복합소재로 구성된 조립 부재를 이용한 터널 라이닝 공법 및 이에 사용되는 조립 부재 | |
| US3273295A (en) | Split-beam prestressing | |
| KR200301034Y1 (ko) | 전신주용 지지구조물의 보강 구조 | |
| KR101050168B1 (ko) | 예비 바닥판이 구비되는 연속교의 건설방법 | |
| DK179455B1 (en) | A prefabricated water control sluice system and a method of segregating a body of water with a prefabricated water control sluice system | |
| KR20240084251A (ko) | 섬유강화 플라스틱 로드를 이용한 프리캐스트 콘크리트 부재의 접합 구조 및 그 방법 | |
| GR890100754A (el) | Ελασματοποιημενη κατασκευη φερουσα οπλισμενο σκυροδεμα,μεθοδος υλοποιησεως της καθως και ετοιμο τμημα οπλισμενου σκυροδεματος,παγκος καλουπωματος και μεθοδος κατασκευης ετοιμων οπλισμενου σκυροδεματος π.χ. κασσετοειδων ετοιμων τμηματων με διδυμες πλακες. | |
| JP2024040986A (ja) | プレキャスト部材及びプレキャスト部材の吊り上げ構造 |