Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Butsems Y Cia S R C
Original Assignee
Butsems Y Cia S R C
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Butsems Y Cia S R CfiledCriticalButsems Y Cia S R C
Priority to ES232575ApriorityCriticalpatent/ES232575A1/en
Publication of ES232575A1publicationCriticalpatent/ES232575A1/en
A system for the construction of ceilings, which is characterized by the combination of two prefabricated elements constituted, the first, by a precompressed and trapezoidal concrete joist, whose sides constitute the start or abutment of a flat arch, being the second element formed by a piece of ceramic, cement or similar material, which forms the voussoir itself and bears a notch for coupling the beam guide, leaving the appropriate clearance to correct the differences that occur in its coupling; once this clearance is filled with cement mortar or other resistant material, the arc is constituted. (Machine-translation by Google Translate, not legally binding)
ES232575A1956-12-201956-12-20A system for roofing ceilings (Machine-translation by Google Translate, not legally binding)
ExpiredES232575A1
(en)
A procedure for the construction of ceilings and floors with beams and prefabricated trapezoid blocks (Machine-translation by Google Translate, not legally binding)
Procedure for the construction of forged through the coupling of prefabricated pieces in which the resistant element and the cielorraso are a single piece on which the square is placed directly (Machine-translation by Google Translate, not legally binding)
A procedure for construction of floors and covers of armed or mixed concrete for assembly and pretension (Machine-translation by Google Translate, not legally binding)