ES2493722B1 - Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained - Google Patents
Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained Download PDFInfo
- Publication number
- ES2493722B1 ES2493722B1 ES201330349A ES201330349A ES2493722B1 ES 2493722 B1 ES2493722 B1 ES 2493722B1 ES 201330349 A ES201330349 A ES 201330349A ES 201330349 A ES201330349 A ES 201330349A ES 2493722 B1 ES2493722 B1 ES 2493722B1
- Authority
- ES
- Spain
- Prior art keywords
- wind turbine
- foundation
- wind
- upgrade
- execution procedure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title abstract 3
- 238000004873 anchoring Methods 0.000 abstract 2
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2292—Holders used for protection, repair or reinforcement of the post or pole
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
Abstract
Procedimiento de ejecución de un aerogenerador para repotenciar un parque eólico existente y aerogenerador obtenido, donde el procedimiento comprende:#- desmontar las palas, la turbina y la torre del aerogenerador a reemplazar, conservando la primera cimentación (1) y los elementos de cimentación (6) embebidos en ella,#- ejecutar una segunda cimentación (2) circunscrita y en contacto con la primera cimentación (1),#- proporcionar elementos de anclaje (3) en la segunda cimentación (2),#- fijar la primera cimentación (1) a la segunda cimentación (2) mediante unos medios de fijación,#- anclar un primer tramo (9) de la torre del nuevo aerogenerador a los elementos de anclaje (3) provistos en la segunda cimentación (2),#- instalar una turbina y unas palas y el resto de la torre sobre el primer tramo (9) de la misma para obtener un nuevo aerogenerador funcional.Execution procedure of a wind turbine to repower an existing wind farm and wind turbine obtained, where the procedure includes: # - disassemble the blades, the turbine and the wind turbine tower to be replaced, keeping the first foundation (1) and the foundation elements ( 6) embedded in it, # - execute a second foundation (2) circumscribed and in contact with the first foundation (1), # - provide anchoring elements (3) in the second foundation (2), # - fix the first foundation (1) to the second foundation (2) by means of fixing means, # - anchor a first section (9) of the new wind turbine tower to the anchoring elements (3) provided in the second foundation (2), # - install a turbine and some blades and the rest of the tower on the first section (9) of the same to obtain a new functional wind turbine.
Description
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ES201330349A ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ES201330349A ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| ES2493722A1 ES2493722A1 (en) | 2014-09-12 |
| ES2493722B1 true ES2493722B1 (en) | 2015-07-20 |
Family
ID=51492699
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| ES201330349A Expired - Fee Related ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Country Status (1)
| Country | Link |
|---|---|
| ES (1) | ES2493722B1 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP3165680A4 (en) * | 2014-07-03 | 2018-04-11 | GRI Renewable Industries, S.L. | Method for installing a wind turbine to upgrade an existing wind farm and wind turbine obtained |
| ES2894337B2 (en) * | 2020-08-07 | 2022-08-19 | Hws Concrete Towers S L | FOUNDATION EXTENSION PROCEDURE IN WIND FARMS |
| ES2999374B2 (en) | 2023-08-25 | 2025-08-08 | Ingenieria Zero S L | Expandable modular foundation and construction procedure |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6453636B1 (en) * | 2000-04-24 | 2002-09-24 | Charles D. Ritz | Method and apparatus for increasing the capacity and stability of a single-pole tower |
| US20020056250A1 (en) * | 2000-04-24 | 2002-05-16 | Cash David W. | Method and apparatus for increasing the capacity and stability of a single-pole tower |
| FR2910038B1 (en) * | 2006-12-18 | 2009-03-06 | Transel Etude De Construction | METHOD FOR REPLACING A POST AND INSTALLATION COMPRISING A POST |
| US8734705B2 (en) * | 2008-06-13 | 2014-05-27 | Tindall Corporation | Method for fabrication of structures used in construction of tower base supports |
-
2013
- 2013-03-12 ES ES201330349A patent/ES2493722B1/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| ES2493722A1 (en) | 2014-09-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| ES2472306B1 (en) | Mold for the manufacture of precast concrete | |
| CL2018000551A1 (en) | Tower segment and method using a segmented bearing plate | |
| CL2016001325A1 (en) | Wind power installation comprising a foundation that has a tower socket and a tower with a plurality of tower segments; the base has at least two segments and a tower segment is specially braced on the base by means of tensioning elements | |
| DK3060385T3 (en) | WIND TURBINE BLADES | |
| ES2401648R1 (en) | PROCEDURE FOR ACCESS TO THE OUTSIDE SURFACE OF AEROGENERATOR TOWERS AND USE DEVICE WITH THE SAME | |
| EP2972038A4 (en) | COOLING TOWER WITH INDIRECT HEAT EXCHANGER | |
| DK2929182T3 (en) | The wind turbine tower assembly | |
| DK3049668T3 (en) | Liquid wind turbine carrier system. | |
| DK2841766T3 (en) | WIND TURBLE PARK WITH FIXED LOCAL REACTIVE POWER MANAGEMENT | |
| BR112015002954A2 (en) | integrated cooling system for a wind turbine nacelle | |
| DK2354541T3 (en) | Wind park power management based on a matrix showing a power load distribution between individual wind turbines | |
| DK2906817T3 (en) | SECURING AN OPERATING PERSON DURING MAINTENANCE OF A WIND POWER PLANT | |
| EP2899111A4 (en) | METHOD FOR ASSEMBLING FLOATING WIND POWER GENERATION DEVICE, AND FLOATING WIND POWER GENERATION DEVICE | |
| DK2855924T3 (en) | METHOD AND MEANS FOR ESTABLISHING ACCESS TO THE MAIN PARTS IN THE NACELLE ON A WIND TURBINE. | |
| DK3527820T3 (en) | Wind turbine cooling device | |
| ES2549586T3 (en) | Solar energy system with weather vane | |
| DK3690234T3 (en) | Wind turbine management | |
| ITUA20163710A1 (en) | WIND TURBINE WITH VERTICAL AXIS WITH MOBILE BLADES | |
| EP3724494C0 (en) | WIND TURBINE NACELLE COOLING | |
| DK2808544T3 (en) | Device for detecting aerodynamic conditions in wind turbine blades | |
| ES2493722B1 (en) | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained | |
| DK3307954T3 (en) | MONOPILE FOUNDATION FOR AN OFFSHORE TOWER CONSTRUCTION | |
| EP4010592C0 (en) | WIND TURBINE COOLING SYSTEM | |
| CL2014001314A1 (en) | Processing device for processing an upper segment edge of a tower segment of a concrete tower comprising a processing means and a support device for securing in the area of the segment edge for the movable support and the guide of the means of processing processing medium; process; formwork; segment of a tower; wind power installation. | |
| ES2440666B1 (en) | SYSTEM AND METHOD TO SUPERVISE THE HEALTH OF HELIOSTATES |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FG2A | Definitive protection |
Ref document number: 2493722 Country of ref document: ES Kind code of ref document: B1 Effective date: 20150720 |
|
| PC2A | Transfer of patent |
Owner name: GRI RENEWABLE INDUSTRIES, S.L. Effective date: 20170605 |
|
| FD2A | Announcement of lapse in spain |
Effective date: 20211004 |