ES8307319A1 - Layered placing of upright or sloping dam cores - Google Patents
Layered placing of upright or sloping dam coresInfo
- Publication number
- ES8307319A1 ES8307319A1 ES510567A ES510567A ES8307319A1 ES 8307319 A1 ES8307319 A1 ES 8307319A1 ES 510567 A ES510567 A ES 510567A ES 510567 A ES510567 A ES 510567A ES 8307319 A1 ES8307319 A1 ES 8307319A1
- Authority
- ES
- Spain
- Prior art keywords
- core
- transitional
- machine
- dam
- core material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Road Paving Machines (AREA)
Abstract
EP--59515 A The upright or sloping dam cores of bitumen and/or plastics and/or a natural binder are placed in a constant or upward-tapering thickness. The core material is placed from a silo (2) on a travelling machine. Transitional material is at the same time placed against the core material from the machine silos (5). - The dam core is formed with the aid of a sliding formwork, which gives lateral support while the transitional material is placed. The core material is pre-compacted (4) vertically and laterally before the transitional material is placed. Subsequently both core and transitional material are further compacted (9). (1/3) EPAB- EP--59515 B The upright or sloping dam cores of bitumen and/or plastics and/or a natural binder are placed in a constant or upward-tapering thickness. The core material is placed from a silo (2) on a travelling machine. Transitional material is at the same time placed against the core material from the machine silos (5). - The dam core is formed with the aid of a sliding formwork, which gives lateral support while the transitional material is placed. The core material is pre-compacted (4) vertically and laterally before the transitional material is placed. Subsequently both core and transitional material are further compacted (9). (13pp Dwg.No.1/3) - EP--59515 B Machine suitable for the layered placing of upright or sloping dam cores of materials bound with bitumen and/or plastic and/or natural binder, in a constant or upward-tapering thickness for dams such as barrage dams, and of adjacent transitional material, comprising a) a sliding formwork to form the dam core, and containing compacting elements (4) for precompaction of the dam core, b) travelling elements (10) to move the machine while placing the dam, characterised in that it moreover comprises: c) a silo (2) from which the core material is placed in the sliding formwork, d) one or more silos (5) from which the transitional material is placed alongside and against theplaced core material, e) vibrating plates (4), which are located on or in the sliding formwork, for pre-compaction of the core material both vertically and laterally immediately after it has been placed and before the transitional material is placed, f) vibrating plates (9), which are located at the rear of the machine, for further compaction of the core material and the simultaneous comapcting of the transitional material, the sliding formwork still protecting the formed core until and while the placing of the transitional material from the silo(s) (5). (7pp) USAB- US4508471 A The method is for the layered placing of upright or sloping dam cores of material bound with bitumen and/or plastic and/or a natural binder in a constant or upward-tapering thickness for dams such as barrage dams. The core material is placed from a silo of a travelling machine and at the same time transitional material is placed, from one or more silos of that machine, alongside and against the placed core material. - The dam core is formed with the aid of a sliding formwork located on the machine to give lateral support to the core until while the transitional material is placed. The core material, immediately after it has been placed and before the transitional material is placed, is pre-compacted both vertically and laterally. Subsequently the core material and the transitional material are (further) compacted. (5pp)i
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ES510567A ES8307319A1 (en) | 1982-03-18 | 1982-03-18 | Layered placing of upright or sloping dam cores |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| ES510567A ES8307319A1 (en) | 1982-03-18 | 1982-03-18 | Layered placing of upright or sloping dam cores |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| ES510567A0 ES510567A0 (en) | 1983-06-16 |
| ES8307319A1 true ES8307319A1 (en) | 1983-06-16 |
Family
ID=8483852
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| ES510567A Expired ES8307319A1 (en) | 1982-03-18 | 1982-03-18 | Layered placing of upright or sloping dam cores |
Country Status (1)
| Country | Link |
|---|---|
| ES (1) | ES8307319A1 (en) |
-
1982
- 1982-03-18 ES ES510567A patent/ES8307319A1/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| ES510567A0 (en) | 1983-06-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| FR2607160B1 (en) | ARTICLES OF COMPACT MATERIALS COMPRISING FILL MIXTURE WITH HYDRAULIC BINDER AND METHODS AND MACHINES FOR CONSTRUCTING THEM BY COMPACTING SLOPES | |
| GB1134554A (en) | Improvements relating to the production of lightweight constructional plates | |
| GR3025165T3 (en) | A method for reinforcing a covering layer on ground | |
| IT8422360A0 (en) | EQUIPMENT FOR CRUSHING COMPACTED PARTICULATE MATERIAL IN STORAGE TANKS. | |
| DE69230802D1 (en) | METHOD AND DEVICE FOR PRODUCING BUILDING BLOCKS FROM A HYDRAULIC BINDING AGENT LIKE PLASTER, AN INERT MATERIAL LIKE SAND AND WATER | |
| ES8307319A1 (en) | Layered placing of upright or sloping dam cores | |
| GR3015935T3 (en) | Fire-resistant or fireproof laminate. | |
| GB2061178B (en) | Process and device for production of concrete pipe by filling and compaction of fresh concrete in an upright form | |
| DK78789A (en) | METHOD AND APPARATUS FOR PRODUCING ROOF PLATES | |
| PL244155A1 (en) | Apparatus for compacting granular mpulding materials | |
| ATE134163T1 (en) | CONCRETE KNEADING METHOD AND APPARATUS THEREOF | |
| ZA837937B (en) | Device for compacting granular molding materials | |
| GB2034591B (en) | Compacting device for particulate material | |
| GB2006311A (en) | Concrete Extrusion Machine | |
| YU105484A (en) | Device for compacting form cast material using compressed gas | |
| JPS56150210A (en) | Construction method and apparatus for asphalt water- shield wall | |
| JPS5785885A (en) | Apparatus for compact-briquetting raw coal for coke | |
| SU587904A1 (en) | Device for compacting fibrous material in a hopper | |
| JPH0472008B2 (en) | ||
| UA33155A (en) | Method of stack formation | |
| GB1343953A (en) | Apparatus for compacting the placement material in road building | |
| SU622677A1 (en) | Device for moulding laminated reinforced-concrete articles | |
| GB2086783B (en) | Process for compacting granular materials | |
| JPS59158210A (en) | Manufacture of cement shape | |
| RU94021319A (en) | METHOD OF FORMING SELF-NECK PRODUCTS |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| MM4A | Patent lapsed |