ES8307319A1 - Layered placing of upright or sloping dam cores - Google Patents

Layered placing of upright or sloping dam cores

Info

Publication number
ES8307319A1
ES8307319A1 ES510567A ES510567A ES8307319A1 ES 8307319 A1 ES8307319 A1 ES 8307319A1 ES 510567 A ES510567 A ES 510567A ES 510567 A ES510567 A ES 510567A ES 8307319 A1 ES8307319 A1 ES 8307319A1
Authority
ES
Spain
Prior art keywords
core
transitional
machine
dam
core material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
ES510567A
Other languages
Spanish (es)
Other versions
ES510567A0 (en
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bitumarin BV
Original Assignee
Bitumarin BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bitumarin BV filed Critical Bitumarin BV
Priority to ES510567A priority Critical patent/ES8307319A1/en
Publication of ES510567A0 publication Critical patent/ES510567A0/en
Publication of ES8307319A1 publication Critical patent/ES8307319A1/en
Expired legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)

Abstract

EP--59515 A The upright or sloping dam cores of bitumen and/or plastics and/or a natural binder are placed in a constant or upward-tapering thickness. The core material is placed from a silo (2) on a travelling machine. Transitional material is at the same time placed against the core material from the machine silos (5). - The dam core is formed with the aid of a sliding formwork, which gives lateral support while the transitional material is placed. The core material is pre-compacted (4) vertically and laterally before the transitional material is placed. Subsequently both core and transitional material are further compacted (9). (1/3) EPAB- EP--59515 B The upright or sloping dam cores of bitumen and/or plastics and/or a natural binder are placed in a constant or upward-tapering thickness. The core material is placed from a silo (2) on a travelling machine. Transitional material is at the same time placed against the core material from the machine silos (5). - The dam core is formed with the aid of a sliding formwork, which gives lateral support while the transitional material is placed. The core material is pre-compacted (4) vertically and laterally before the transitional material is placed. Subsequently both core and transitional material are further compacted (9). (13pp Dwg.No.1/3) - EP--59515 B Machine suitable for the layered placing of upright or sloping dam cores of materials bound with bitumen and/or plastic and/or natural binder, in a constant or upward-tapering thickness for dams such as barrage dams, and of adjacent transitional material, comprising a) a sliding formwork to form the dam core, and containing compacting elements (4) for precompaction of the dam core, b) travelling elements (10) to move the machine while placing the dam, characterised in that it moreover comprises: c) a silo (2) from which the core material is placed in the sliding formwork, d) one or more silos (5) from which the transitional material is placed alongside and against theplaced core material, e) vibrating plates (4), which are located on or in the sliding formwork, for pre-compaction of the core material both vertically and laterally immediately after it has been placed and before the transitional material is placed, f) vibrating plates (9), which are located at the rear of the machine, for further compaction of the core material and the simultaneous comapcting of the transitional material, the sliding formwork still protecting the formed core until and while the placing of the transitional material from the silo(s) (5). (7pp) USAB- US4508471 A The method is for the layered placing of upright or sloping dam cores of material bound with bitumen and/or plastic and/or a natural binder in a constant or upward-tapering thickness for dams such as barrage dams. The core material is placed from a silo of a travelling machine and at the same time transitional material is placed, from one or more silos of that machine, alongside and against the placed core material. - The dam core is formed with the aid of a sliding formwork located on the machine to give lateral support to the core until while the transitional material is placed. The core material, immediately after it has been placed and before the transitional material is placed, is pre-compacted both vertically and laterally. Subsequently the core material and the transitional material are (further) compacted. (5pp)i
ES510567A 1982-03-18 1982-03-18 Layered placing of upright or sloping dam cores Expired ES8307319A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ES510567A ES8307319A1 (en) 1982-03-18 1982-03-18 Layered placing of upright or sloping dam cores

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
ES510567A ES8307319A1 (en) 1982-03-18 1982-03-18 Layered placing of upright or sloping dam cores

Publications (2)

Publication Number Publication Date
ES510567A0 ES510567A0 (en) 1983-06-16
ES8307319A1 true ES8307319A1 (en) 1983-06-16

Family

ID=8483852

Family Applications (1)

Application Number Title Priority Date Filing Date
ES510567A Expired ES8307319A1 (en) 1982-03-18 1982-03-18 Layered placing of upright or sloping dam cores

Country Status (1)

Country Link
ES (1) ES8307319A1 (en)

Also Published As

Publication number Publication date
ES510567A0 (en) 1983-06-16

Similar Documents

Publication Publication Date Title
FR2607160B1 (en) ARTICLES OF COMPACT MATERIALS COMPRISING FILL MIXTURE WITH HYDRAULIC BINDER AND METHODS AND MACHINES FOR CONSTRUCTING THEM BY COMPACTING SLOPES
GB1134554A (en) Improvements relating to the production of lightweight constructional plates
GR3025165T3 (en) A method for reinforcing a covering layer on ground
IT8422360A0 (en) EQUIPMENT FOR CRUSHING COMPACTED PARTICULATE MATERIAL IN STORAGE TANKS.
DE69230802D1 (en) METHOD AND DEVICE FOR PRODUCING BUILDING BLOCKS FROM A HYDRAULIC BINDING AGENT LIKE PLASTER, AN INERT MATERIAL LIKE SAND AND WATER
ES8307319A1 (en) Layered placing of upright or sloping dam cores
GR3015935T3 (en) Fire-resistant or fireproof laminate.
GB2061178B (en) Process and device for production of concrete pipe by filling and compaction of fresh concrete in an upright form
DK78789A (en) METHOD AND APPARATUS FOR PRODUCING ROOF PLATES
PL244155A1 (en) Apparatus for compacting granular mpulding materials
ATE134163T1 (en) CONCRETE KNEADING METHOD AND APPARATUS THEREOF
ZA837937B (en) Device for compacting granular molding materials
GB2034591B (en) Compacting device for particulate material
GB2006311A (en) Concrete Extrusion Machine
YU105484A (en) Device for compacting form cast material using compressed gas
JPS56150210A (en) Construction method and apparatus for asphalt water- shield wall
JPS5785885A (en) Apparatus for compact-briquetting raw coal for coke
SU587904A1 (en) Device for compacting fibrous material in a hopper
JPH0472008B2 (en)
UA33155A (en) Method of stack formation
GB1343953A (en) Apparatus for compacting the placement material in road building
SU622677A1 (en) Device for moulding laminated reinforced-concrete articles
GB2086783B (en) Process for compacting granular materials
JPS59158210A (en) Manufacture of cement shape
RU94021319A (en) METHOD OF FORMING SELF-NECK PRODUCTS

Legal Events

Date Code Title Description
MM4A Patent lapsed

Effective date: 19960506