JP2000257006A - Artificial ground structure and its construction method - Google Patents

Artificial ground structure and its construction method

Info

Publication number
JP2000257006A
JP2000257006A JP11056732A JP5673299A JP2000257006A JP 2000257006 A JP2000257006 A JP 2000257006A JP 11056732 A JP11056732 A JP 11056732A JP 5673299 A JP5673299 A JP 5673299A JP 2000257006 A JP2000257006 A JP 2000257006A
Authority
JP
Japan
Prior art keywords
foundation pile
pile
artificial ground
steel pipe
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11056732A
Other languages
Japanese (ja)
Inventor
Takuzo Katsura
拓造 葛
Masataka Kinoshita
雅敬 木下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP11056732A priority Critical patent/JP2000257006A/en
Publication of JP2000257006A publication Critical patent/JP2000257006A/en
Pending legal-status Critical Current

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00—Adapting or protecting infrastructure or their operation
    • Y02A30/60—Planning or developing urban green infrastructure

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Road Paving Structures (AREA)

Abstract

(57)【要約】 【課題】 斜面上へ道路や公園等をつくる人工地盤構造
において、施工簡略化・工期短縮化し、かつ自然破壊を
極力抑制することができる人工地盤構造を提供する。 【解決手段】 基礎杭4を打設後、基礎杭径以上で基礎
杭4の施工誤差を吸収できる直径を有し、基礎杭径以上
の長さを有するソケットの鋼管9と鋼製の梁部材5との
連結部材とかるなるソケット部材13を基礎杭4の頭部
に被せ、基礎杭4とソケット部材13の鋼管9との間隙
にコンクリート等の充填材を充填することにより基礎杭
4と梁5の接合部を構築し、梁部材の上に床版6を固定
して、斜面部等に人工地盤を構築することを特徴とす
る。
(57) [Summary] [PROBLEMS] To provide an artificial ground structure that can simplify construction, shorten construction period, and suppress natural destruction as much as possible in an artificial ground structure for creating roads and parks on slopes. SOLUTION: After placing a foundation pile 4, a steel pipe member 9 and a steel beam member of a socket having a diameter greater than the foundation pile diameter and capable of absorbing a construction error of the foundation pile 4, and having a length greater than the foundation pile diameter. 5 is covered with the head member of the foundation pile 4 and the gap between the foundation pile 4 and the steel pipe 9 of the socket member 13 is filled with a filler such as concrete to form a beam between the foundation pile 4 and the beam. 5 is constructed, a floor slab 6 is fixed on a beam member, and an artificial ground is constructed on a slope or the like.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、土木建築分野にお
ける公園・駅舎等を、山岳部の斜面等に設ける人工地盤
構造や、道路・鉄道といった高架構造を対象とした人工
地盤構造と構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an artificial ground structure for constructing parks and station buildings in the field of civil engineering and construction on slopes of mountainous areas, and an artificial ground structure for elevated structures such as roads and railways, and a construction method. .

【0002】[0002]

【従来の技術】従来、山岳部の斜面等における人工地盤
の構築には、斜面に打設される基礎杭の施工誤差が大き
いため、梁や床版部には、基礎杭と梁や床版部との接合
部で基礎杭の施工誤差の吸収を図るために、鉄筋コンク
リート構造を現場施工により構築する場合が多い。
2. Description of the Related Art Conventionally, when constructing artificial ground on a slope in a mountainous area or the like, there is a large construction error in a foundation pile cast on a slope. Reinforced concrete structures are often constructed by on-site construction in order to absorb construction errors in foundation piles at the joints with the sections.

【0003】しかし、この様な鉄筋コンクリート工事
は、建設材料や建設機器の運搬が困難、施工時に基礎杭
の間に架設の支柱を立設したり、基礎杭間に鋼製梁を設
置し、該支柱や鋼製梁で支持して梁や床版用の型枠を組
立て、この型枠の中に鉄筋を組立てた後、コンクリート
を打設して鉄筋コンクリートの梁を構築する必要があ
り、工事が複雑で施工工期が長くなり、建設コストが高
い、施工条件がわるく品質の確保が困難である、上部構
造の自重が大きくなり、耐震設計を確保するためには基
礎構造にも高い耐震性能が要求され不経済である、とい
った問題があった。
However, in such reinforced concrete construction, it is difficult to transport construction materials and construction equipment, and at the time of construction, erection columns are erected between foundation piles or steel beams are installed between foundation piles. It is necessary to assemble a formwork for beams and floor slabs supported by columns and steel beams, and to assemble the rebar in this formwork, then cast concrete to build a reinforced concrete beam. Complicated, construction period is long, construction cost is high, construction conditions are poor, quality is difficult to secure, the weight of the upper structure is large, and high seismic performance is required for the foundation structure to secure the seismic design And was uneconomical.

【0004】また、斜面部への人工地盤の構築におい
て、上記鉄筋コンクリート構造を用いた場合は足場・支
保工の設置や多量の建設資材や建設機器の搬入のための
スペース確保が必要、法面を掘削により人工地盤を構築
する場合は斜面の掘削により山岳部の自然破壊が大きい
といった問題があった。
In the construction of artificial ground on a slope, when the above-mentioned reinforced concrete structure is used, it is necessary to secure scaffolds and supports and secure a space for carrying a large amount of construction materials and construction equipment. In the case of constructing artificial ground by excavation, there is a problem that excavation of a slope causes great natural destruction in a mountainous area.

【0005】一方、上部構造に軽量で工場にて予め、製
作が可能な鋼製の梁部材を用いることによって、上部構
造の自重を軽減し基礎の仕様を落し経済性を高めたり梁
部の施工を簡略化しようとすると、これまでのボルト接
合や溶接接合では基礎杭の施工誤差が大きいため予め製
作した梁部材では接合部での施工が困難であった。ま
た、杭打設後寸法を測定した後、梁部材を構築すること
も可能であるが、工期がかかるとともに、施工精度や加
工精度の高い精度管理が必要で施工の管理が大変であっ
た。
On the other hand, by using a lightweight steel beam member which can be manufactured in advance at a factory for the upper structure, the weight of the upper structure can be reduced, the specification of the foundation can be reduced, and the economic efficiency can be improved. In order to simplify the above, it has been difficult to construct the joints with the beam members manufactured in advance because the construction error of the foundation pile is large in the conventional bolt joining and welding joining. It is also possible to construct a beam member after measuring the dimensions after pile driving, but it takes a lot of time to construct and requires high precision control of construction precision and processing precision, and it is difficult to control construction.

【0006】この様な人工地盤の改良発明として提案さ
れた、「鋼管杭と鋼製桁よりなる構造物の構築方法なら
びにこれに使用する測定用定規」(特開平5−1409
56)では、鋼管杭と鋼製桁を用いて杭の施工誤差を吸
収し、杭と鋼製桁を迅速かつ確実に結合する方法を開示
している。
A method for constructing a structure comprising a steel pipe pile and a steel girder and a measuring ruler used for the same have been proposed as an improvement of such an artificial ground (Japanese Patent Laid-Open No. 5-1409).
No. 56) discloses a method for quickly and reliably connecting a pile and a steel girder by using a steel pipe pile and a steel girder to absorb construction errors of the pile.

【0007】しかし、この方法では、鋼管杭の打設後鋼
管杭の施工誤差を測定し、鋼製桁と仕口部材からなる接
合部材を鋼管杭の施工誤差を打ち消すことができる様に
製作し鋼管杭に溶接接合する必要があり、施工誤差の測
定および接合部材の製作には工期がかかるとともに、接
合部材と鋼管杭の連結には現場溶接が必要となるため施
工が大変であり建設コストも高くなり、また、現場溶接
での品質の確保が困難といった問題があった。
However, in this method, after the steel pipe pile is driven, the construction error of the steel pipe pile is measured, and a joining member composed of a steel girder and a connection member is manufactured so as to cancel the construction error of the steel pipe pile. It is necessary to weld to steel pipe piles, and it takes a lot of time to measure the construction error and manufacture the joint members.In addition, the connection between the joint members and the steel pipe piles requires on-site welding, which makes construction difficult and reduces construction costs. However, there is a problem that it is difficult to secure the quality in the field welding.

【0008】[0008]

【発明が解決しようとしている課題】本発明は、経済
性、工期、施工手間省略、高耐震性、自然破壊抑制、高
品質の面での改良を解決課題としている。すなわち、従
来の鉄筋コンクリート構造の梁を用いる人工地盤や高架
構造の構築では、斜面上での鉄筋組・型枠設置等の複雑
な現場作業が多く工期・工費がかかるとともに、上部構
造の自重が大きくなり不経済であり、施工のための型枠
・足場等の設置や高重量・高容積の資材の搬入や置き場
の確保は多大な自然破壊を発生させていた。
SUMMARY OF THE INVENTION It is an object of the present invention to provide an improvement in terms of economy, construction period, elimination of labor for construction, high earthquake resistance, suppression of natural destruction, and high quality. In other words, in the construction of artificial ground or elevated structures using conventional reinforced concrete beams, complicated on-site work such as reinforcing bar assembly and formwork installation on slopes requires a lot of construction time and cost, and the weight of the upper structure is large. The installation of formwork and scaffolding for construction, the loading of high-weight and high-volume materials, and the securing of a storage place caused a great deal of natural destruction.

【0009】また、この様な人工地盤は、長期にわたり
機能を発揮することが期待される重量構造物であり、ま
た維持管理が極めて困難な山岳部斜面等で多用されるも
のである。従って、この様な人工地盤に鋼製梁、床版や
鋼管杭を用いた場合、錆の発生に対して、斜面部の作業
を行ないにくい場所での点検やメンテナンスが必要とな
り、メンテナンスコストがかかるという問題があった。
本発明では、接合部材を杭頭部に設置したのち基礎杭と
梁部とを簡単に接合することにより、大幅な工期短縮・
工費削減・高品質また自然に害を与えないで人工地盤構
造の構築を可能とする。また、高い耐久性を有する鋼材
を用いることによって極力メンテナンスを省略すること
ができる。
Such artificial ground is a heavy structure expected to exhibit its function for a long period of time, and is often used on mountain slopes where maintenance and management are extremely difficult. Therefore, when steel beams, floor slabs, or steel pipe piles are used for such artificial ground, inspection and maintenance are required in places where it is difficult to work on slopes, and maintenance costs are incurred. There was a problem.
According to the present invention, the joint member is installed at the pile head, and then the foundation pile and the beam are easily joined to greatly shorten the construction period.
It enables construction of artificial ground structures with low construction cost, high quality and no harm to nature. Further, by using a steel material having high durability, maintenance can be omitted as much as possible.

【0010】[0010]

【課題を解決するための手段】前記の目的を達成するた
め、本発明の請求項1に係る人工地盤構造は、下部構造
を基礎杭構造とし、上部構造に梁や床版を設けることに
よって、鉄道、道路、公園や住宅を構築する人工地盤構
造において、前記基礎杭の直径より大きな直径を有し、
前記杭の直径以上の長さの鋼管を具備したソケット部材
と、縦方向や横方向の鋼製梁部材とからなる上部構造部
材を、前記ソケット部材の鋼管が基礎杭の杭頭部を覆う
様に設置し、基礎杭とソケット部材の鋼管の間隙にコン
クリートやモルタル等を充填することによりソケット部
材と基礎杭を一体化し、基礎杭と梁部の接合部を構築す
ることを特徴とする。本発明の請求項2は、請求項1に
示した人工地盤構造において、前記基礎杭として鋼管杭
が用いられて斜面に打設され、当該鋼管杭の施工誤差が
その直径の1/10程度生じることを前提として、ソケ
ット部材には鋼管杭の直径に対し20%以上大きな直径
を有する鋼管を用いることを特徴とする。本発明の請求
項3は、請求項1または2に記載の人工地盤の構造にお
いて、基礎杭、ソケット部材、鋼製梁、床版のいずれか
に耐食性の高い鋼材を用いて、形成されたことを特徴と
する。本発明の請求項4は、前記耐食性の高い鋼材とし
て、ソケット部材、鋼製梁や床版には耐候性鋼材あるい
は表面が金属被覆された鋼材を用い、また、基礎杭に
は、ポリエチレン被覆、ウレタン被覆、金属被覆等の工
場で事前に防食被覆された鋼管および耐候性鋼材による
鋼管を用いて形成されたことを特徴とする。本発明の請
求項5は、 請求項1ないし4のいずれかに記載の人工
地盤の構造において、前記ソケット部材と梁部材は別々
に製作し、個々のソケット部材を基礎杭の杭頭に設置
後、ソケット部材の間に梁部材を設置・連結することに
よって上部構造を構築することを特徴とする。
According to a first aspect of the present invention, there is provided an artificial ground structure according to the first aspect of the present invention, wherein the lower structure is a foundation pile structure, and the upper structure is provided with beams or floor slabs. In the artificial ground structure for building railways, roads, parks and houses, having a diameter larger than the diameter of the foundation pile,
An upper structural member consisting of a socket member provided with a steel pipe having a length equal to or greater than the diameter of the pile and a vertical or horizontal steel beam member is provided so that the steel pipe of the socket member covers the pile head of the foundation pile. It is characterized in that the socket member is integrated with the foundation pile by filling concrete or mortar or the like into the gap between the steel pipe of the foundation pile and the socket member, and the joint between the foundation pile and the beam is constructed. According to a second aspect of the present invention, in the artificial ground structure according to the first aspect, a steel pipe pile is used as the foundation pile and is driven into a slope, and a construction error of the steel pipe pile occurs about 1/10 of its diameter. On the premise of this, a steel pipe having a diameter that is at least 20% larger than the diameter of the steel pipe pile is used as the socket member. According to a third aspect of the present invention, in the structure of the artificial ground according to the first or second aspect, any of the foundation pile, the socket member, the steel beam, and the floor slab is formed using a highly corrosion-resistant steel material. It is characterized by. Claim 4 of the present invention uses, as the corrosion-resistant steel material, a socket member, a steel beam or a slab, a weather-resistant steel material or a steel material whose surface is coated with metal, and a foundation pile is coated with polyethylene. It is characterized by being formed using a steel pipe coated in advance with anticorrosion and a steel pipe made of weather-resistant steel at a factory such as urethane coating and metal coating. According to a fifth aspect of the present invention, in the artificial ground structure according to any one of the first to fourth aspects, the socket member and the beam member are separately manufactured, and each socket member is installed on a pile head of a foundation pile. The upper structure is constructed by installing and connecting a beam member between the socket members.

【0011】[0011]

【作用】基礎杭の打設後、上部に設置する梁構造を予め
製作し杭頭部で連結する場合、基礎杭の施工誤差が大き
いため、接合部で連結することが困難であり、梁部の製
作は基礎杭打設後、現場施工の鉄筋コンクリート構造を
用いることによって施工誤差を吸収する必要があった。
しかるに、本発明では、基礎杭の施工誤差の吸収が可能
な様に、基礎杭より大きな直径を有し、前記直径以上の
長さを有する鋼管と、鋼製梁との円滑な荷重伝達が可能
なダイアフラムを有するソケット部材と鋼製の梁部材と
からなる上部構造部材を、該ソケット部材の鋼管が基礎
杭の杭頭部を覆う様に設置し、ソケット部材の鋼管と基
礎杭の間隙にコンクリートやモルタル等を充填すること
によって梁部材と基礎杭の接合部を構築し荷重伝達を行
なう。ソケット部材の鋼管は、杭鋼管の施工誤差を吸収
できる様に充分大きな直径を有するものを用いることに
よって、基礎杭の施工誤差を吸収できる。本発明の人工
地盤構造を用いることによって、杭鋼管の施工誤差が生
じた場合においても、予め製作した鋼製の梁部材を用い
て施工することができるため、上部構造が軽量化でき基
礎の経済性を高めることができるとともに、大幅な工期
短縮・工費削減・高品質を実現し、自然の害を与えるこ
となく人工地盤構造の構築することを可能とする。ま
た、耐候性鋼材や防食被覆された鋼管を用いることによ
って、通常のメンテナンス期間よりも長くメンテナンス
を行なわないで使用することができ、山岳部の急斜面で
のメンテナンスを大幅に省力できる。
[Function] When a beam structure to be installed on the upper part is pre-fabricated after connecting the foundation pile and connected by the pile head, it is difficult to connect at the joint because the construction error of the foundation pile is large. It was necessary to absorb the construction error by using a reinforced concrete structure constructed on site after the foundation pile was put in place.
However, in the present invention, a smooth load transmission between a steel pipe having a diameter larger than that of the foundation pile and having a length equal to or greater than the diameter and a steel beam is possible so that construction errors of the foundation pile can be absorbed. An upper structural member consisting of a socket member having a flexible diaphragm and a steel beam member is installed such that the steel pipe of the socket member covers the pile head of the foundation pile, and concrete is placed in the gap between the steel pipe of the socket member and the foundation pile. The joint between the beam member and the foundation pile is constructed by filling with mortar or the like, and the load is transmitted. By using a steel pipe of the socket member having a diameter large enough to absorb the construction error of the pile steel pipe, the construction error of the foundation pile can be absorbed. By using the artificial ground structure of the present invention, even when a construction error occurs in a pile steel pipe, the pile can be constructed using a steel beam member manufactured in advance. In addition to being able to increase the efficiency, it is possible to significantly shorten the construction period, reduce construction costs and achieve high quality, and to construct an artificial ground structure without harming nature. In addition, by using a weather-resistant steel material or a steel pipe coated with anti-corrosion, it can be used without performing maintenance for a longer period than a normal maintenance period, and maintenance on steep slopes in mountainous areas can be greatly reduced.

【0012】[0012]

【発明の実施の形態】本発明に係る高架構造などの人工
地盤構造は、基礎杭の施工誤差を吸収できるよう、基礎
杭径よりも大きな直径を有する鋼管と梁との接合部に、
適切な荷重伝達を行なうことができるダイアフラム等を
取付けたソケット部材と鋼製の梁部材からなる上部構造
を、基礎杭の杭頭部を鋼管が覆うように設置した後、基
礎杭と鋼管の間隙にコンクリートやモルタル等を充填す
ることによって固定して接合部を構成し、上部に床版等
を設置する。耐候性鋼材としては、Ni,Cr,Cuな
どを含有する鋼材が適用でき、防錆被覆としては、ステ
ンレス、モネル、チタン等の板による被覆、あるいは亜
鉛、アルミ等のめっきもしくは溶射による被覆を適用す
ることができる。
BEST MODE FOR CARRYING OUT THE INVENTION An artificial ground structure such as an elevated structure according to the present invention has a joint portion between a steel pipe having a diameter larger than the diameter of a foundation pile and a beam so as to absorb a construction error of the foundation pile.
After installing the upper structure consisting of a socket member with a diaphragm etc. that can transmit appropriate load and a steel beam member so that the steel pipe covers the pile head of the foundation pile, the gap between the foundation pile and the steel pipe The joints are fixed by filling concrete, mortar, etc. into the joints, and a floor slab, etc. is installed on the upper part. As the weather-resistant steel material, a steel material containing Ni, Cr, Cu, etc. can be applied. As the rust preventive coating, coating with a plate of stainless steel, monel, titanium, or the like, or coating with plating or thermal spraying of zinc, aluminum, or the like is applied. can do.

【0013】[0013]

【実施例】以下、本発明の実施例を図を参照して説明す
る。図1、図2および図3に示すとおり、人工地盤1
は、斜面2上に設けられる1つ以上のブロック3からな
り、基礎杭4、鋼製梁5、および、床版6等から構成さ
れる。後述する各実施例1、2および3では、基礎杭4
が山岳部の斜面2の地中7に打設されており、人工地盤
1の1ブロック3の構造およびその構築方法を示してい
る。但し、各実施例で人工地盤1のブロック3の配置
や、基礎杭4や鋼製梁5の配置は、代表的な人工地盤の
例について示したもので、この配置によって本発明が限
定されるものではない。また各実施例は、基礎杭として
鋼管杭を用いた場合について示すが、本発明が鋼管杭に
限定されるものではない。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below with reference to the drawings. As shown in FIGS. 1, 2 and 3, the artificial ground 1
Consists of one or more blocks 3 provided on the slope 2 and comprises a foundation pile 4, a steel beam 5, a floor slab 6, and the like. In each of Examples 1, 2 and 3 described later, the foundation pile 4
Is installed in the underground 7 on the slope 2 of the mountainous area, and shows the structure of one block 3 of the artificial ground 1 and a construction method thereof. However, in each embodiment, the arrangement of the blocks 3 of the artificial ground 1 and the arrangement of the foundation piles 4 and the steel beams 5 show examples of typical artificial ground, and the present invention is limited by this arrangement. Not something. Further, although each embodiment shows a case where a steel pipe pile is used as a foundation pile, the present invention is not limited to a steel pipe pile.

【0014】[実施例1]実施例1を図3〜図10に示
す。図3は実施例1の人工地盤1の1ブロック3の斜面
直角方向からみた側面図、図4は要部斜視図、図5は要
部分解斜視図を示す。また、図6〜図8は杭頭部8およ
びソケット部材18を示し、図9、図10は人工地盤1
の1ブロック3の斜面直角方向と斜面方向から見た側断
面図を示す。実施例1の鋼管杭よりなる基礎杭4は、斜
面2の山側および谷側の2列に、下端部が斜面2の地中
7に固定される様に設置された直杭からなり、鋼製梁5
は、杭頭部8で隣り合う杭の上端部を連結する様に配置
されており、床版6が鋼製梁5の上部に設置されてい
る。
Embodiment 1 Embodiment 1 is shown in FIGS. 3 is a side view of one block 3 of the artificial ground 1 according to the first embodiment viewed from a direction perpendicular to the slope, FIG. 4 is a perspective view of a main part, and FIG. 5 is an exploded perspective view of a main part. 6 to 8 show the pile head 8 and the socket member 18, and FIGS. 9 and 10 show the artificial ground 1.
1 is a side sectional view of one block 3 viewed from a direction perpendicular to the slope and a direction of the slope. The foundation pile 4 made of the steel pipe pile of the first embodiment is a straight pile which is installed in two rows on the hill side and the valley side of the slope 2 so that the lower end is fixed to the underground 7 of the slope 2. Beam 5
Are arranged so as to connect the upper ends of adjacent piles with the pile head 8, and the floor slab 6 is installed above the steel beam 5.

【0015】人工地盤1の1ブロック3の構築は基礎杭
4を打設後、杭頭部8の位置が所定の高さになる様に切
断したのち、ソケット鋼管9との重なり部に、必要に応
じて杭鋼管の外側にずれ止め10を所定量設置し、基礎
杭の内側にコンクリート11を充填する。
To construct one block 3 of the artificial ground 1, after the foundation pile 4 has been driven, the pile head 8 is cut so that the position of the pile head 8 is at a predetermined height, and then the pile 3 is required to be overlapped with the socket steel pipe 9. A predetermined amount of the slip stopper 10 is installed on the outside of the pile steel pipe according to the above condition, and the concrete 11 is filled inside the foundation pile.

【0016】次に、予め工場で製作したソケットの鋼管
9と鋼製梁5との連結用ダイアフラム12からなるソケ
ット部材13と鋼製梁5を地上で組立てた後、ソケット
部材13の鋼管9が、基礎杭4の杭頭部8を覆う様に設
置する。このとき、ソケット部材13の鋼管9には、基
礎杭4の径よりも十分大きな直径を有し、前記直径以上
の長さを有する鋼管を使用し、所定の施工位置であり、
かつ、基礎杭4の施工誤差を吸収できる様に、また、杭
頭部8を覆った後コンクリート等の充填材14を充填で
きる間隙が保持できる様に設置する。
Next, after assembling the socket member 13 and the steel beam 5 comprising the diaphragm 12 for connecting the steel tube 9 of the socket and the steel beam 5 manufactured in the factory in advance, the steel tube 9 of the socket member 13 is assembled. , So as to cover the pile head 8 of the foundation pile 4. At this time, for the steel pipe 9 of the socket member 13, a steel pipe having a diameter sufficiently larger than the diameter of the foundation pile 4 and having a length equal to or larger than the diameter is used, and is a predetermined construction position.
The pile 4 is installed so as to absorb a construction error of the foundation pile 4 and to maintain a gap for covering the pile head 8 with a filler 14 such as concrete after covering the pile head 8.

【0017】その後、ソケット部材の鋼管9と基礎杭4
の間隙にコンクリート等の充填材14を打設し鋼製梁5
を固定する。鋼製梁5の上に、場所打ちコンクリート、
プレキャストコンクリートや合成床版、鋼製床版等によ
り製作される床版6を設置し、表層コンクリート、アス
ファルトや土砂等の表面仕上げ材15を設置し人工地盤
構造を完成させる。図示例において、表面仕上げ材15
の側部には、地覆部19と欄干20が設けられている。
また、基礎杭4の内外面および鋼管9の内面には、必要
に応じて適量のずれ止め10を取付けるか突起付き鋼管
を用いる。
After that, the steel pipe 9 of the socket member and the foundation pile 4
A filler 14 such as concrete is poured into the gap between the steel beams 5.
Is fixed. Cast-in-place concrete on steel beam 5,
A slab 6 made of precast concrete, a composite slab, a steel slab, or the like is installed, and a surface finishing material 15 such as surface concrete, asphalt, earth and sand, and the like, and an artificial ground structure is completed. In the illustrated example, the surface finishing material 15
A ground cover 19 and a balustrade 20 are provided on the sides of the.
Further, on the inner and outer surfaces of the foundation pile 4 and the inner surface of the steel pipe 9, an appropriate amount of a slip stopper 10 is attached or a steel pipe with a projection is used as necessary.

【0018】[実施例2]実施例2を図11〜図17に
示す。図11,図12は要部斜視図と要部分解斜視図を
示す。、また、図13〜図15は杭頭部8およびソケッ
ト部材13を示し、図16,図17は実施例2の人工地
盤1の1ブロック3の斜面直角方向から見た側断面図と
斜面側から見た側断面図を示す。実施例2の人工地盤構
築方法は、実施例1とほぼ同様であるが、ソケット部材
13と鋼製梁5を別々に施工する点が相違している。実
施例2の鋼管杭よりなる基礎杭4は、斜面2の山側およ
び谷側の2列に、下端部が斜面2の地中7に固定される
様に設置された基礎杭からなり、鋼製梁5は、杭頭部8
で隣り合う杭の上端部を連結する様に配置されており、
床版6が鋼製梁5の上部に設置されている。
[Embodiment 2] Embodiment 2 is shown in FIGS. 11 and 12 show a perspective view of a main part and an exploded perspective view of a main part. 13 to 15 show the pile head 8 and the socket member 13, and FIGS. 16 and 17 are side sectional views and the slope side of one block 3 of the artificial ground 1 according to the second embodiment viewed from a direction perpendicular to the slope. FIG. The artificial ground construction method of the second embodiment is substantially the same as that of the first embodiment, except that the socket member 13 and the steel beam 5 are separately constructed. The foundation pile 4 made of the steel pipe pile of the embodiment 2 is composed of a foundation pile installed in two rows on the hill side and the valley side of the slope 2 so that the lower end is fixed to the underground 7 of the slope 2. Beam 5 is pile head 8
It is arranged to connect the upper ends of adjacent piles with
A floor slab 6 is installed above the steel beam 5.

【0019】実施例2も実施例1と同様に人工地盤1の
1ブロック3の構築は、基礎杭4を打設後、杭頭部8の
位置が所定の高さになる様に切断したのち、ソケットの
鋼管9との重なり部に、必要に応じて杭鋼管の外側にず
れ止め10を所定量設置し、基礎杭4の内側にコンクリ
ート11を充填する。
In the second embodiment, as in the first embodiment, the construction of one block 3 of the artificial ground 1 is performed after the foundation pile 4 is driven and then cut so that the position of the pile head 8 is at a predetermined height. Then, a predetermined amount of a slip stopper 10 is installed outside the pile steel pipe as necessary at the overlapping portion of the socket with the steel pipe 9, and concrete 11 is filled inside the foundation pile 4.

【0020】次に、基礎杭4と梁部間で荷重伝達を図る
ためのソケットの鋼管9とダイアフラム12および、鋼
製梁5とボルト16で連結する梁接続部材17からなる
ソケット部材13を予め工場で製作し、全杭頭部8にソ
ケット部材13の鋼管9が、基礎杭5の杭頭部8を覆う
様に設置する。このとき、ソケット部材13の鋼管9に
は十分大きな直径を有する鋼管を使用し、所定の施工位
置であり、かつ、基礎杭4の施工誤差を吸収できる様
に、また、杭頭部9を覆った後コンクリート等の充填材
14を充填できる間隙が保持できる様に設置する。
Next, a socket member 13 consisting of a steel pipe 9 and a diaphragm 12 of a socket for transmitting a load between the foundation pile 4 and the beam portion and a beam connecting member 17 connected to the steel beam 5 by bolts 16 are previously prepared. Manufactured in a factory, the steel pipe 9 of the socket member 13 is installed on the entire pile head 8 so as to cover the pile head 8 of the foundation pile 5. At this time, a steel pipe having a sufficiently large diameter is used for the steel pipe 9 of the socket member 13, the steel pipe 9 is located at a predetermined construction position, and the pile head 9 is covered so that construction errors of the foundation pile 4 can be absorbed. After that, it is installed so that a gap that can be filled with the filler 14 such as concrete can be maintained.

【0021】その後、ソケット部材13の鋼管9と基礎
杭4の間隙にコンクリート等の充填材14を打設しソケ
ット部材13を固定する。
Thereafter, a filler 14 such as concrete is poured into the gap between the steel pipe 9 of the socket member 13 and the foundation pile 4 to fix the socket member 13.

【0022】ソケット部材13を杭頭部8に固定後、鋼
製梁5をボルト(や溶接)16により梁接続部材17に
連結し、その後、鋼製梁5の上に、場所打ちコンクリー
ト、プレキャストコンクリートや合成床版、鋼製床版等
により製作される床版6を設置し表層コンクリート、ア
スファルトや土砂等の表面仕上げ材15を設置し、人工
地盤構造を完成させる。また、基礎杭4の内外面および
鋼管9の内面には、必要に応じて適量のずれ止め10を
取付けるか突起付き鋼管を用いる。
After fixing the socket member 13 to the pile head 8, the steel beam 5 is connected to the beam connecting member 17 by bolts (or welding) 16, and then cast-in-place concrete or precast on the steel beam 5. A floor slab 6 made of concrete, a composite slab, a steel slab, or the like is installed, and a surface finishing material 15 such as surface concrete, asphalt, earth and sand, and the like, and an artificial ground structure is completed. Further, on the inner and outer surfaces of the foundation pile 4 and the inner surface of the steel pipe 9, an appropriate amount of a slip stopper 10 is attached or a steel pipe with a projection is used as necessary.

【0023】[実施例3]実施例3を図18〜図20に
示す。図18は、人工地盤の側断面図を、図19は、ソ
ケット部材13とブレース材18の接合部の斜視図を、
図20は、鋼管杭とブレース材18の取付部の斜視図を
示す。実施例3の人工地盤構造は、実施例2とほぼ同様
であるが、ソケット部材13および梁部材5を設置後、
鋼管杭4に補強リング24とガセットプレート21を有
する外鋼管23を充填材14を介して取付け、上部と下
部のガセップレート21を介してソケット部材13と外
鋼管23とをブレース材18で連結することによって、
人工地盤の変形や、揺れなど構造全体の強度、耐震性を
高めた事例である。
Third Embodiment FIGS. 18 to 20 show a third embodiment. FIG. 18 is a side sectional view of the artificial ground, and FIG. 19 is a perspective view of a joint between the socket member 13 and the brace material 18.
FIG. 20 shows a perspective view of a mounting portion between the steel pipe pile and the brace material 18. The artificial ground structure of the third embodiment is almost the same as that of the second embodiment, except that the socket member 13 and the beam member 5 are installed.
The outer steel pipe 23 having the reinforcing ring 24 and the gusset plate 21 is attached to the steel pipe pile 4 via the filler 14, and the socket member 13 and the outer steel pipe 23 are connected with the brace material 18 via the upper and lower gusset plates 21. By
This is an example of increasing the strength and seismic resistance of the entire structure such as deformation and shaking of the artificial ground.

【0024】[0024]

【発明の効果】本発明は、斜面上へ道路や公園等をつく
る人工地盤構造において、基礎杭と鋼製梁の接合部に鋼
管等からなるソケット部材とコンクリートやモルタル等
の充填材を介在させた接合法を用いることにより現場で
の基礎杭の施工誤差を吸収し接合できるため、上部構造
に予め工場製作した軽量な鋼製部材を用いることがで
き、耐震性および基礎杭の経済性高めるとともに、足場
や支保工を省力することによって、施工簡略化・工期短
縮・自然破壊を極力抑制することができる。
According to the present invention, in an artificial ground structure for forming a road or a park on a slope, a socket member made of a steel pipe or the like and a filler such as concrete or mortar are interposed at a joint between a foundation pile and a steel beam. By using the new joining method, it is possible to absorb the construction error of the foundation pile at the site and join it, so it is possible to use a lightweight steel member manufactured in advance for the superstructure, and to improve the seismic resistance and the economic efficiency of the foundation pile In addition, simplification of construction, shortening of construction period, and natural destruction can be suppressed as much as possible by omitting scaffolding and support works.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例を示す人工地盤の平面図。FIG. 1 is a plan view of an artificial ground showing an embodiment of the present invention.

【図2】本発明の実施例を示す人工地盤の側面図。FIG. 2 is a side view of the artificial ground showing the embodiment of the present invention.

【図3】本発明の実施例を示す人工地盤の側面図。FIG. 3 is a side view of the artificial ground showing the embodiment of the present invention.

【図4】本発明の実施例1を示す人工地盤の一部破断要
部斜視図。
FIG. 4 is a partially broken perspective view of a part of the artificial ground showing the first embodiment of the present invention.

【図5】本発明の実施例1を示す人工地盤の分解斜視
図。
FIG. 5 is an exploded perspective view of the artificial ground showing the first embodiment of the present invention.

【図6】本発明の実施例1を示す基礎杭と鋼製梁部材の
杭頭接合部の斜視図。
FIG. 6 is a perspective view of a pile head joint between a foundation pile and a steel beam member according to the first embodiment of the present invention.

【図7】本発明の実施例1を示すソケット部材の側断面
図。
FIG. 7 is a side sectional view of the socket member showing the first embodiment of the present invention.

【図8】(A),(B),(C)は図7のA−A,B−
B,C−C線に沿う図。
8 (A), (B), and (C) show AA, B- in FIG.
The figure which follows the B, CC line.

【図9】本発明の実施例1を示す人工地盤の1ブロック
の斜面と直角方向から見た側断面図。
FIG. 9 is a side sectional view of one block of the artificial ground according to the first embodiment of the present invention, viewed from a direction perpendicular to a slope.

【図10】本発明の実施例1を示す人工地盤の1ブロッ
クの斜面方向から見た側断面図。
FIG. 10 is a side sectional view of one block of the artificial ground according to the first embodiment of the present invention, as viewed from a slope direction.

【図11】本発明の実施例2を示す人工地盤の一部破断
要部斜視図。
FIG. 11 is a partially cutaway perspective view of a principal portion of an artificial ground according to a second embodiment of the present invention.

【図12】本発明の実施例2を示す人工地盤の要部分解
斜視図。
FIG. 12 is an exploded perspective view of a main part of an artificial ground according to a second embodiment of the present invention.

【図13】本発明の実施例2を示す基礎杭と鋼製梁部材
の杭頭接合部の斜視図。
FIG. 13 is a perspective view of a pile head joint between a foundation pile and a steel beam member according to a second embodiment of the present invention.

【図14】本発明の実施例2を示すソケット部材の側断
面図。
FIG. 14 is a side sectional view of a socket member showing the second embodiment of the present invention.

【図15】(A),(B),(C)は図14のD−D,
E−E,F−F線に沿う図。
15 (A), (B) and (C) are DD, FIG.
The figure which follows the EE and FF line.

【図16】本発明の実施例2を示す人工地盤の1ブロッ
クの斜面と直角方向から見た側断面図。
FIG. 16 is a side sectional view of one block of the artificial ground according to the second embodiment of the present invention as viewed from a direction perpendicular to a slope.

【図17】本発明の実施例2を示す人工地盤の1ブロッ
クの斜面方向から見た側断面図。
FIG. 17 is a side sectional view of one block of the artificial ground according to the second embodiment of the present invention as viewed from a slope direction.

【図18】本発明の実施例3を示す人工地盤の1ブロッ
クの斜面と直角方向から見た側断面図。
FIG. 18 is a side cross-sectional view of one block of an artificial ground according to a third embodiment of the present invention viewed from a direction perpendicular to a slope.

【図19】本発明の実施例3を示すブレース材とソケッ
ト部材の接合部の斜視図。
FIG. 19 is a perspective view of a joint between a brace member and a socket member, showing Embodiment 3 of the present invention.

【図20】本発明の実施例3を示すブレース材と鋼管杭
の接合部の斜視図。
FIG. 20 is a perspective view of a joint between a brace material and a steel pipe pile, showing a third embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1…人工地盤構造 2…斜面 3…人工地盤構造の1ブロック 4…基礎杭 5…鋼製梁 5a…梁フランジ 5b…梁ウェブ 6…床版 7…地中 8…杭頭部 9…ソケットの鋼管 10…ズレ止め 11…充填コンクリート 12…ダイアフラム 13…ソケット部材 14…充填材 15…表面仕上げ材 16…ボルト又は溶接接合部 17…梁接続部材 18…ブレース 19…地覆部 20…欄干 21…ガセットプレート 22…ピン 23…外鋼管 24…補強リング DESCRIPTION OF SYMBOLS 1 ... Artificial ground structure 2 ... Slope 3 ... 1 block of artificial ground structure 4 ... Foundation pile 5 ... Steel beam 5a ... Beam flange 5b ... Beam web 6 ... Floor slab 7 ... Underground 8 ... Pile head 9 ... Socket Steel pipe 10 ... Preventing displacement 11 ... Filled concrete 12 ... Diaphragm 13 ... Socket member 14 ... Filling material 15 ... Surface finishing material 16 ... Bolt or welded joint 17 ... Beam connecting member 18 ... Brace 19 ... Gusset plate 22 ... Pin 23 ... Outer steel pipe 24 ... Reinforcing ring

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 下部構造を基礎杭構造とし、上部構造に
梁や床版を設けることによって、鉄道、道路、公園や住
宅を構築する人工地盤構造において、前記基礎杭の直径
より大きな直径を有し、前記杭の直径以上の長さの鋼管
を具備したソケット部材と、縦方向や横方向の鋼製梁部
材とからなる上部構造部材を、前記ソケット部材の鋼管
が基礎杭の杭頭部を覆う様に設置し、基礎杭とソケット
部材の鋼管の間隙にコンクリートやモルタル等を充填す
ることによりソケット部材と基礎杭を一体化し、基礎杭
と梁部の接合部を構築することを特徴とする人工地盤構
造。
1. An artificial ground structure for constructing railways, roads, parks and houses by providing a lower structure as a foundation pile structure and providing beams and floor slabs in the upper structure to have a diameter larger than the diameter of the foundation pile. Then, a socket member having a steel pipe having a length equal to or larger than the diameter of the pile, and an upper structural member including a vertical or horizontal steel beam member, and the steel pipe of the socket member forms a pile head of a foundation pile. It is installed so as to cover, and the socket member and the foundation pile are integrated by filling concrete or mortar etc. into the gap between the steel pipe of the foundation pile and the socket member, and the joint between the foundation pile and the beam is constructed. Artificial ground structure.
【請求項2】 請求項1に記載の人工地盤構造におい
て、前記基礎杭として鋼管杭が用いられて斜面に打設さ
れ、当該鋼管杭の施工誤差がその直径の1/10程度生
じることを前提として、ソケット部材には鋼管杭の直径
に対し20%以上大きな直径を有する鋼管を用いること
を特徴とする人工地盤構造。
2. The artificial ground structure according to claim 1, wherein a steel pipe pile is used as the foundation pile and is cast on a slope, and a construction error of the steel pipe pile occurs about 1/10 of its diameter. An artificial ground structure characterized by using a steel pipe having a diameter larger than a diameter of a steel pipe pile by 20% or more as a socket member.
【請求項3】 請求項1または2に記載の人工地盤の構
造において、前記基礎杭、ソケット部材、鋼製梁、およ
び床版のいずれかに耐食性の高い鋼材を用いて形成され
たことを特徴とする人口地盤構造。
3. The artificial ground structure according to claim 1, wherein the foundation pile, the socket member, the steel beam, and the floor slab are formed using a highly corrosion-resistant steel material. And the artificial ground structure.
【請求項4】 前記耐食性の高い鋼材として、ソケット
部材、鋼製梁や床版には耐候性鋼材あるいは表面が金属
被覆された鋼材を用い、また、基礎杭には、ポリエチレ
ン被覆、ウレタン被覆、金属被覆等の工場で事前に防食
被覆された鋼管および耐候性鋼材による鋼管を用いて形
成されたことを特徴とする請求項3記載の人工地盤構
造。
4. As the steel material having high corrosion resistance, a weather-resistant steel material or a steel material whose surface is metal-coated is used for a socket member, a steel beam and a floor slab, and a polyethylene coating, a urethane coating is used for a foundation pile, The artificial ground structure according to claim 3, wherein the artificial ground structure is formed using a steel pipe that has been subjected to anticorrosion coating in a factory such as a metal coating and a steel pipe made of a weather-resistant steel material.
【請求項5】 請求項1ないし4のいずれかに記載の人
工地盤の構造において、前記ソケット部材と梁部材は別
々に製作し、個々のソケット部材を基礎杭の杭頭に設置
後、ソケット部材の間に梁部材を設置・連結することに
よって上部構造を構築する人工地盤の構築方法。
5. The artificial ground structure according to claim 1, wherein said socket member and said beam member are manufactured separately, and said socket member is installed on a pile head of a foundation pile. A method of constructing an artificial ground in which an upper structure is constructed by installing and connecting beam members between the members.
JP11056732A 1999-03-04 1999-03-04 Artificial ground structure and its construction method Pending JP2000257006A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11056732A JP2000257006A (en) 1999-03-04 1999-03-04 Artificial ground structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11056732A JP2000257006A (en) 1999-03-04 1999-03-04 Artificial ground structure and its construction method

Publications (1)

Publication Number Publication Date
JP2000257006A true JP2000257006A (en) 2000-09-19

Family

ID=13035695

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11056732A Pending JP2000257006A (en) 1999-03-04 1999-03-04 Artificial ground structure and its construction method

Country Status (1)

Country Link
JP (1) JP2000257006A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353273A (en) * 2003-05-29 2004-12-16 Daiwa House Ind Co Ltd Foundation structure
JP2005068951A (en) * 2003-08-28 2005-03-17 Nippon Steel Corp Cylindrical foundation structure
JP2006207306A (en) * 2005-01-31 2006-08-10 Taisei Corp Frame structure and connection structure of frame body and pile
JP2010059743A (en) * 2008-09-05 2010-03-18 Jfe Civil Engineering & Construction Corp Construction method of pier-type road
KR101054741B1 (en) * 2010-11-22 2011-08-08 주식회사 오케이컨설턴트 Bicycle road construction method using two-point support of lateral support and bottom plate
JP2012207516A (en) * 2011-09-20 2012-10-25 Kouchi Marutaka:Kk Manufacturing method of superstructure for bridge, bridge and superstructure for bridge
KR101222161B1 (en) 2012-10-25 2013-01-22 (주) 태평양지질 Independent type girder bridge using pipe support
CN103397656A (en) * 2013-08-19 2013-11-20 铁道第三勘察设计院集团有限公司 Embedded type joist pile plank structure
JP2014005652A (en) * 2012-06-25 2014-01-16 Nippon Juuki Kensetsu Kk Construction method for pile type pier
WO2016001997A1 (en) * 2014-06-30 2016-01-07 株式会社高知丸高 Bridge construction method and bridge structure
KR20160099863A (en) * 2015-02-13 2016-08-23 정제평 Extended footbridge with continuous steel socket on slope
JP2016217000A (en) * 2015-05-20 2016-12-22 株式会社技研製作所 Elevated structure and construction method thereof
JP2023070286A (en) * 2021-11-09 2023-05-19 Jfeスチール株式会社 Temporary work tool, construction method of artificial ground using temporary work tool
JP7430842B1 (en) 2022-08-05 2024-02-13 Jfeシビル株式会社 artificial ground structure
JP2024022158A (en) * 2022-08-05 2024-02-16 Jfeシビル株式会社 Artificial ground structures and drone ports
CN119663825A (en) * 2025-01-02 2025-03-21 中交二航局第一工程有限公司 Construction method and construction platform for step-by-step bored pile

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353273A (en) * 2003-05-29 2004-12-16 Daiwa House Ind Co Ltd Foundation structure
JP2005068951A (en) * 2003-08-28 2005-03-17 Nippon Steel Corp Cylindrical foundation structure
JP2006207306A (en) * 2005-01-31 2006-08-10 Taisei Corp Frame structure and connection structure of frame body and pile
JP2010059743A (en) * 2008-09-05 2010-03-18 Jfe Civil Engineering & Construction Corp Construction method of pier-type road
KR101054741B1 (en) * 2010-11-22 2011-08-08 주식회사 오케이컨설턴트 Bicycle road construction method using two-point support of lateral support and bottom plate
JP2012207516A (en) * 2011-09-20 2012-10-25 Kouchi Marutaka:Kk Manufacturing method of superstructure for bridge, bridge and superstructure for bridge
JP2014005652A (en) * 2012-06-25 2014-01-16 Nippon Juuki Kensetsu Kk Construction method for pile type pier
KR101222161B1 (en) 2012-10-25 2013-01-22 (주) 태평양지질 Independent type girder bridge using pipe support
CN103397656A (en) * 2013-08-19 2013-11-20 铁道第三勘察设计院集团有限公司 Embedded type joist pile plank structure
WO2016001997A1 (en) * 2014-06-30 2016-01-07 株式会社高知丸高 Bridge construction method and bridge structure
KR20160099863A (en) * 2015-02-13 2016-08-23 정제평 Extended footbridge with continuous steel socket on slope
KR101673070B1 (en) * 2015-02-13 2016-11-04 정제평 Extended footbridge with continuous steel socket on slope
JP2016217000A (en) * 2015-05-20 2016-12-22 株式会社技研製作所 Elevated structure and construction method thereof
JP2023070286A (en) * 2021-11-09 2023-05-19 Jfeスチール株式会社 Temporary work tool, construction method of artificial ground using temporary work tool
JP7463331B2 (en) 2021-11-09 2024-04-08 Jfeスチール株式会社 Temporary jig and method for constructing artificial ground using said temporary jig
JP7430842B1 (en) 2022-08-05 2024-02-13 Jfeシビル株式会社 artificial ground structure
JP2024022158A (en) * 2022-08-05 2024-02-16 Jfeシビル株式会社 Artificial ground structures and drone ports
JP2024023169A (en) * 2022-08-05 2024-02-21 Jfeシビル株式会社 artificial ground structure
JP7850393B2 (en) 2022-08-05 2026-04-23 Jfeシビル株式会社 Artificial ground structures and drone ports
CN119663825A (en) * 2025-01-02 2025-03-21 中交二航局第一工程有限公司 Construction method and construction platform for step-by-step bored pile

Similar Documents

Publication Publication Date Title
JP5693140B2 (en) Artificial ground such as road and its construction method
US4282619A (en) Truss structure
CN109339229B (en) Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor
JP2000248526A (en) Pier structure and its construction method
KR100839439B1 (en) Steel structure of ramen bridge that combines substructure and superstructure prefabricated and construction method of ramen bridge using the same
JP2001159140A (en) Landslide prevention structure
KR101631447B1 (en) Top-Down method of underground structure using the CFT and the Composite Beam
JP2004263467A (en) Reconstruction method using existing underground structure
CN110106772A (en) A kind of highway clod wash U-shaped composite beam bridge and its construction method
JP2831909B2 (en) Connection structure of steel columns, piles and foundation beams
KR200381589Y1 (en) A pile head reinforcement structure of precastconcrete pile
JP3106881B2 (en) Mixed structure of reinforced concrete columns and steel beams
JP2002206209A (en) Bridge with upper and lower integrated structure and its construction method
JP2012207516A (en) Manufacturing method of superstructure for bridge, bridge and superstructure for bridge
JP2007297861A (en) Junction structure between pier and pile
JP2004285823A (en) Slab bridge and slab unit
JPH05340031A (en) Prestressed concrete girder and its manufacture
JP2021031926A (en) Steel structure Pile-column joint integrated column base structure without underground beams
JP3081833B1 (en) Three-dimensional rigid frame high bridge structure
JPH08120638A (en) Joint structure of pile and beam and construction method of structure using it
JP2000087504A (en) Girder structure of steel frame
CN212506737U (en) Assembled beam column node
KR200383309Y1 (en) Form system for construction of underground slab
KR102583155B1 (en) The continuous rahmen bridge constructed by the hybrid sections that made 2-girder & panel, and constructing method thereof
JP3981688B2 (en) Joint structure and composite structure of steel beam and reinforced concrete column

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050913

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070911

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070918

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080212

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080624