JP4986068B2 - Self-sustained operation system for distributed power supply - Google Patents

Self-sustained operation system for distributed power supply Download PDF

Info

Publication number
JP4986068B2
JP4986068B2 JP2008058336A JP2008058336A JP4986068B2 JP 4986068 B2 JP4986068 B2 JP 4986068B2 JP 2008058336 A JP2008058336 A JP 2008058336A JP 2008058336 A JP2008058336 A JP 2008058336A JP 4986068 B2 JP4986068 B2 JP 4986068B2
Authority
JP
Japan
Prior art keywords
power supply
abnormality detection
signal
control
circuit breaker
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2008058336A
Other languages
Japanese (ja)
Other versions
JP2009219204A (en
Inventor
俊博 山根
茂生 沼田
仁夫 森野
英介 下田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2008058336A priority Critical patent/JP4986068B2/en
Publication of JP2009219204A publication Critical patent/JP2009219204A/en
Application granted granted Critical
Publication of JP4986068B2 publication Critical patent/JP4986068B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Stand-By Power Supply Arrangements (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Description

本発明は、分散型電源の自立運転システムに関する。   The present invention relates to a self-sustained operation system for a distributed power source.

近年、分散型電源の負荷追従運転によって商用系統への負担を軽減する「マイクログリッド」への取り組みが活発化している。マイクログリッドの思想を取り込んだ分散型電源によるエネルギー供給システム(以下、単にマイクログリッドという)では、通常時は系統連系により商用系統からの買電量が一定となるように発電量を制御する連係運転を行い、停電等の非常時はマイクログリッド系統内に高品質な(電圧・周波数の変動が小さい)電力を供給する自立運転を行う負荷追従運転が求められている。   In recent years, efforts to “microgrid” to reduce the burden on the commercial system by load following operation of distributed power sources have become active. In an energy supply system using a distributed power source that incorporates the idea of a microgrid (hereinafter simply referred to as a microgrid), a linked operation that controls the amount of power generated so that the amount of power purchased from a commercial system is kept constant by grid connection. In the event of an emergency such as a power outage, load follow-up operation is required to perform autonomous operation to supply high-quality (voltage and frequency fluctuation is small) power in the microgrid system.

建物の利便性を考慮すると、停電等の非常時に連系運転から自立運転へ高品質な電力供給を保ったまま無瞬断で移行するシステムを構築することが望ましい。これにより、例えばコンピュータのような電力品質(電圧・周波数の変動)に比較的敏感な機器を含め、マイクログリッド系統内では外部の停電の影響を全く受けることなく建物の継続運用が可能となる。   In consideration of the convenience of the building, it is desirable to construct a system that makes an uninterrupted transition while maintaining a high-quality power supply from interconnected operation to independent operation in the event of an emergency such as a power failure. As a result, the building can be operated continuously without being affected by an external power failure in the microgrid system, including devices that are relatively sensitive to power quality (voltage and frequency fluctuations) such as a computer.

連系運転から無瞬断で自立運転へ移行する先行技術として、特許文献1や特許文献2等に記載の無瞬断自立移行発電システムが知られている。このシステムを図3を参照して簡単に説明する。このシステムは、回転機系発電機6と燃料電池7の2種類の電源構成となっており、計測器31、41、51、61、71によって計測された計測データや制御部1から出力される制御信号の通信には例えばアナログ信号線のような高速な信号線を利用している。   As a prior art that shifts from a grid operation to a self-sustained operation without instantaneous interruption, there is known an uninterruptible self-sustaining transition power generation system described in Patent Literature 1, Patent Literature 2, and the like. This system will be briefly described with reference to FIG. This system has two types of power supply configurations, that is, a rotating machine generator 6 and a fuel cell 7, and is output from measurement data measured by the measuring instruments 31, 41, 51, 61, 71 and the control unit 1. A high-speed signal line such as an analog signal line is used for control signal communication.

自立運転時は回転機系発電機6を定電圧制御とすることにより、マイクログリッド系統内の電圧変動の抑制を行う。回転機系発電機6の定電圧制御は、負荷3、4、5において高速な負荷変動があった場合、供給電力の電圧が変動してしまうため、このシステムでは燃料電池7を用いて高速な負荷変動補償を行い、回転機系発電機6には非常に緩やかな負荷変動のみを補償させることで、供給する電力の電圧変動を抑制している。また、自立運転移行は、商用系統2の異常を検出する系統異常検出部9の検出信号を遮断器8へ高速な信号線で送信するともに、各電源(回転機系発電機6と燃料電池7)に対して制御部1を経由して高速な信号線で制御信号を送信することにより、遮断器8の開放と各電源の自立運転時の制御への移行を瞬時に行うことで無瞬断化を実現している。   During the self-sustained operation, the voltage fluctuation in the microgrid system is suppressed by controlling the rotating machine generator 6 with constant voltage control. In the constant voltage control of the rotating machine generator 6, when the load 3, 4, 5 has a high speed load fluctuation, the voltage of the supplied power fluctuates. By performing load variation compensation, the rotating machine generator 6 is compensated for only very gradual load variation, thereby suppressing voltage variation of the supplied power. In addition, in the autonomous operation transition, a detection signal of the system abnormality detection unit 9 that detects an abnormality of the commercial system 2 is transmitted to the circuit breaker 8 through a high-speed signal line, and each power source (the rotating machine generator 6 and the fuel cell 7). ) By transmitting a control signal via a high-speed signal line via the control unit 1 to instantaneously switch off the circuit breaker 8 and shift to control during independent operation of each power source. Has been realized.

ただし、図3に示すシステム構成においては、全ての信号の受け渡しに高速信号線を使用しているため、信号線の埋設費用等のコストアップになるという問題を有している。このような問題を解決するために、図3のシステム構成の変形例として、例えばLAN回線のような既存の低速な信号線を利用したシステム構成が考えられる。図4に示すように、系統異常検出部9と遮断器8との信号線S1のみを高速な信号伝送を行うことができる信号線とし、他の信号線に低速の信号線を用いることで、信号線の埋設費用等のコストアップを抑制することが可能となる。
特開2002−135982号公報 特開2002−171671号公報
However, since the system configuration shown in FIG. 3 uses high-speed signal lines for transferring all signals, there is a problem that the cost for embedding signal lines increases. In order to solve such a problem, a system configuration using an existing low-speed signal line such as a LAN line can be considered as a modification of the system configuration in FIG. As shown in FIG. 4, by using only the signal line S1 between the system abnormality detection unit 9 and the circuit breaker 8 as a signal line capable of performing high-speed signal transmission, and using a low-speed signal line for the other signal lines, It becomes possible to suppress the cost increase such as the burying cost of the signal line.
JP 2002-135982 A JP 2002-171671 A

しかしながら、特許文献1、2に示す無瞬断自立移行発電システム装置(図3)にあっては、自立運転移行時において、燃料電池の運転モードを定電力制御から定電圧制御へ切り替えて系統電圧の維持のみを行う制御であるため、自立運転時のマイクログリッド系統周波数の維持が困難であるという問題がある。また、電源となる回転機系発電機と燃料電池は双方ともに発電原理に起因した発電最低出力が存在するため、自立運転時のマイクログリッド系統内の負荷合計値が各発電機の最低出力合計値以下の場合は電力供給が停止してしまうという問題もある。   However, in the non-instantaneous self-sustaining transition power generation system apparatus shown in Patent Literatures 1 and 2 (FIG. 3), the system voltage is switched by switching the operation mode of the fuel cell from constant power control to constant voltage control at the time of self-sustaining operation transition Therefore, there is a problem that it is difficult to maintain the microgrid system frequency during the independent operation. In addition, since both the power generator and the fuel cell have a power generation minimum output due to the power generation principle, the total load value in the microgrid system during independent operation is the minimum output total value of each generator. There is also a problem that the power supply stops in the following cases.

また、図4に示すシステム構成のように、既設の低速な信号線としてLAN回線を用いた場合、データの収受には数秒オーダーの時間遅れが生じるため、自立運転中に、低速な信号線による時間遅れにより数秒オーダー以下の高速な負荷変動に対しては燃料電池が補償することができず、供給電力品質が悪化してしまうという問題もある。また、自立運転移行時、遮断器潮流によっては低速な信号線による時間遅れの間に回転機系発電機が補償する負荷がステップ状(非常に高速)に変動し、電力品質が悪化してしまうという問題がある。   In addition, when a LAN line is used as an existing low-speed signal line as in the system configuration shown in FIG. 4, there is a time delay of several seconds on the receipt of data. There is also a problem that the fuel cell cannot compensate for a fast load fluctuation of several seconds or less due to a time delay, and the supplied power quality deteriorates. Also, when shifting to independent operation, depending on the circuit breaker flow, the load compensated by the rotary generator during a time delay due to a low-speed signal line fluctuates stepwise (very high speed), and power quality deteriorates. There is a problem.

本発明は、このような事情に鑑みてなされたもので、分散型電源の自立運転移行時の瞬断を発生させることなく、供給電力品質を維持することができる分散型電源の自立運転システムを提供することを目的とする。   The present invention has been made in view of such circumstances, and a self-sustained operation system for a distributed power source that can maintain the power supply quality without causing a momentary interruption at the time of transition to the self-sustained operation of the distributed power source. The purpose is to provide.

本発明は、回転機系発電機を備える分散型電源の負荷追従運転によって商用系統への負担を軽減する分散型電源の自立運転システムであって、前記商用系統の異常を検出した場合に、異常検出信号を出力する系統異常検出手段と、前記系統異常検出手段から前記異常検出信号が入力された場合に前記商用系統の電力供給を遮断する遮断器と、前記遮断器が遮断状態になったことを検出した場合に遮断器状態信号を出力する状態検出手段と、前記遮断器状態信号が入力された場合に、電力供給を開始することにより、前記遮断器によって商用系統の電力が遮断されてから前記回転機系発電機が自立運転制御の運転に移行するまでの間の負荷変動を補償する蓄電装置とを有し、前記異常検出信号及び前記遮断器状態信号は、前記回転機系発電機に制御系信号を伝送する信号線より高速な信号線によって伝送されることを特徴とする。 The present invention is a self-sustained operation system for a distributed power source that reduces the burden on the commercial system by load following operation of the distributed power source equipped with a rotating machine power generator. A system abnormality detecting means for outputting a detection signal; a circuit breaker for interrupting power supply to the commercial system when the abnormality detection signal is input from the system abnormality detecting means; and the circuit breaker is in a disconnected state. When the circuit breaker state signal is input, the state detection means that outputs a circuit breaker state signal when the circuit breaker is detected, and when the circuit breaker state signal is input, the power supply is started to cut off the commercial system power by the circuit breaker. and a power storage device wherein the rotating machine system generator to compensate for load variation until the transition to the operation of the self-sustaining operation control, the abnormality detection signal and the breaker status signal, the rotating machine system generator Characterized in that it is transmitted by the high-speed signal line from the signal line for transmitting a control system signal.

本発明は、前記系統異常検出手段から異常検出信号を受信すると前記自立運転システムを連係運転から自立運転へ移行する制御手段を有し、前記系統異常検出手段は、前記異常検出信号を前記高速な信号線によって前記遮断器に出力するとともに、前記制御手段に前記高速な信号線よりも低速な信号線を介して出力し、前記遮断器状態信号は、前記制御手段を介することなく前記蓄電装置に伝送されることを特徴とする。 The present invention has control means for shifting the autonomous operation system from linked operation to autonomous operation when an abnormality detection signal is received from the system abnormality detection means, and the system abnormality detection means sends the abnormality detection signal to the high-speed operation signal. The signal line is output to the circuit breaker, and is output to the control unit via a signal line that is slower than the high-speed signal line, and the circuit breaker state signal is transmitted to the power storage device without the control unit. It is transmitted .

本発明は、前記蓄電装置は、前記遮断器状態信号が入力された場合に、自己の供給電力量を計測し、計測した供給電力量に基づいて、予め決められた制御値になるように運転制御を行うことを特徴とする。   According to the present invention, when the circuit breaker state signal is input, the power storage device measures its own power supply amount and operates so as to have a predetermined control value based on the measured power supply amount. Control is performed.

本発明によれば、商用系統からの電力供給が遮断された場合に、高速な負荷追従が可能な蓄電装置によって電力供給を開始することにより、商用系統の電力が遮断されてから回転機系発電機が自立運転制御の運転に移行するまでの間の負荷変動を補償するようにしたため、分散型電源の自立運転移行時の瞬断を発生させることなく、供給電力品質を維持することができるという効果が得られる。   According to the present invention, when power supply from the commercial system is interrupted, the power supply is started by the power storage device capable of high-speed load follow-up, so that the rotating machine power generation is performed after the commercial system power is interrupted. Because the load fluctuation until the machine shifts to the operation of the autonomous operation control is compensated, the supply power quality can be maintained without causing the instantaneous interruption at the time of the autonomous operation transition of the distributed power source. An effect is obtained.

以下、本発明の一実施形態による分散型電源の自立運転システムを図面を参照して説明する。図1は同実施形態の構成を示すブロック図である。この図において、図4に示すシステムと同一の部分には同一の符号を付し、その説明を省略する。この図に示す自立運転システムが図4示すシステムと異なる点は、燃料電池7に代えて、最も高速な負荷変動補償を行う蓄電装置(例えば、電気二重層キャパシタ)10と数秒オーダー以上(中速)の時間間隔で制御を行う蓄電装置(例えば、ニッケル水素電池)11の2種類の蓄電装置と、遮断器8の状態を検出する状態検出部81を設け、制御部1が3台の電源(回転機系発電機6、蓄電装置10及び蓄電装置11)の運転制御を行うようにした点である。   Hereinafter, a self-sustaining operation system for a distributed power source according to an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a block diagram showing the configuration of the embodiment. In this figure, the same parts as those in the system shown in FIG. The self-sustained operation system shown in this figure differs from the system shown in FIG. 4 in that, instead of the fuel cell 7, a power storage device (for example, an electric double layer capacitor) 10 that performs the fastest load fluctuation compensation and on the order of several seconds (medium speed) ) Two types of power storage devices (for example, nickel metal hydride batteries) 11 that perform control at time intervals and a state detection unit 81 that detects the state of the circuit breaker 8, and the control unit 1 includes three power sources ( The operation control of the rotating machine generator 6, the power storage device 10, and the power storage device 11) is performed.

次に、図1を参照して、図1に示す自立運転システムの動作を説明する。まず、系統異常検出部9は、商用系統2が供給する電力を監視し、商用系統に異常が検出された場合、異常検出信号を遮断器8と制御部1へ送信する。このとき、遮断器8へ送信する異常検出信号S1を伝送する信号線は、高速の信号線を用いる。遮断器8は、異常検出信号S1を受信すると、商用系統を遮断する(スイッチを開放する)。また、制御部1は、異常検出信号を受信すると、自立運転へ移行する。制御部1は、自立運転時において、計測器31、41、51が出力する負荷3、4、5それぞれの負荷変動計測データと、計測器61、101、111が出力する回転機系発電機6、蓄電装置10及び蓄電装置11の供給電力計測データに基づいて、3つの電源(回転機系発電機6、蓄電装置10及び蓄電装置11)の運転制御を実施する。このとき、計測データの伝送と運転制御信号の伝送は低速の信号線を用いる。   Next, the operation of the self-sustaining operation system shown in FIG. 1 will be described with reference to FIG. First, the system abnormality detection unit 9 monitors the power supplied from the commercial system 2, and transmits an abnormality detection signal to the circuit breaker 8 and the control unit 1 when an abnormality is detected in the commercial system. At this time, a high-speed signal line is used as the signal line for transmitting the abnormality detection signal S1 to be transmitted to the circuit breaker 8. When receiving the abnormality detection signal S1, the circuit breaker 8 interrupts the commercial system (opens the switch). Moreover, the control part 1 will transfer to independent operation, if an abnormality detection signal is received. During the self-sustained operation, the control unit 1 includes load fluctuation measurement data for the loads 3, 4, and 5 output from the measuring devices 31, 41, and 51, and a rotating machine generator 6 output from the measuring devices 61, 101, and 111. Based on the supplied power measurement data of the power storage device 10 and the power storage device 11, operation control of the three power sources (the rotating machine generator 6, the power storage device 10, and the power storage device 11) is performed. At this time, low-speed signal lines are used for transmission of measurement data and transmission of operation control signals.

一方、状態検出部81は、遮断器8が遮断状態(スイッチ開放状態)になったことを検出すると、遮断状態になったことを示す遮断器状態信号を高速の信号線を経由して直接(制御部1を介すことなく)蓄電装置10へ送信する。これを受けて、蓄電装置10は、自立運転時の電力の供給の運転制御を開始する。自立運転時において、蓄電装置10は、計測器101の計測結果を高速な信号線により自己の供給電力量の計測データを受信し、この計測データをもとに予め決められた制御値になるように自己(蓄電装置10)の運転制御を行う(以下、この運転制御をローカル追従制御という)。これにより低速な信号線による時間遅れを解消し、高速な負荷変動を補償することが可能となる。   On the other hand, when the state detector 81 detects that the circuit breaker 8 is in a breaker state (switch open state), a state breaker state signal indicating the breaker state is directly transmitted via a high-speed signal line ( It transmits to the electrical storage apparatus 10 (without going through the control part 1). In response to this, the power storage device 10 starts operation control of power supply during the independent operation. During the self-sustained operation, the power storage device 10 receives the measurement data of the amount of power supplied from the measurement result of the measuring instrument 101 through a high-speed signal line, and takes a control value determined in advance based on the measurement data. The operation control of itself (power storage device 10) is performed (hereinafter, this operation control is referred to as local follow-up control). As a result, the time delay due to the low-speed signal line can be eliminated, and high-speed load fluctuation can be compensated.

このように、蓄電装置10は状態検出部81からの遮断器状態信号を高速な信号線で受信したことを受けて自立運転時の制御へ高速に移行することにより回転機系発電機6や蓄電装置11が自立運転時の制御に移行するまで間(低速な信号線による時間遅れの間)の非常に高速な負荷変動を補償することが可能となる。   As described above, the power storage device 10 receives the circuit breaker state signal from the state detection unit 81 through the high-speed signal line, and shifts to the control during the self-sustained operation at high speed. It is possible to compensate for a very high speed load fluctuation until the device 11 shifts to the control during the self-sustaining operation (during a time delay due to the low speed signal line).

なお、蓄電装置10における自立運転制御開始時の初期演算時間による時間遅れを防止するため、制御部1は、連系運転中にバックグラウンドで自立運転モードに移行した場合の制御値を常に演算しておき、蓄電装置10に対して所定のタイミングで送信しておくようにしてもよい。   In addition, in order to prevent a time delay due to the initial calculation time at the start of the autonomous operation control in the power storage device 10, the control unit 1 always calculates the control value when shifting to the autonomous operation mode in the background during the interconnection operation. In addition, it may be transmitted to the power storage device 10 at a predetermined timing.

また、図1においては、蓄電装置10、11がそれぞれ1台ずつの場合のシステム構成を示したが、蓄電装置10、11はそれぞれ複数台数備えていてもよい。また、蓄電装置11は省略し、蓄電装置10のみのシステム構成としてもよい。   1 shows a system configuration in which one power storage device 10, 11 is provided, but a plurality of power storage devices 10, 11 may be provided. Further, the power storage device 11 may be omitted, and only the power storage device 10 may be configured.

次に、図2を参照して、本発明による自立運転移行時の電力品質について説明する。図2は、回転機系発電機6としてはガスエンジン350kW、蓄電装置11としてはニッケル水素電池400kWh、蓄電装置10としては電気二重層キャパシタ100kW×充放電2秒を利用した場合の自立運転移行時の1秒周期の測定結果を示している。ここで、ガスエンジン(回転機系発電機6)とニッケル水素電池(蓄電装置11)はLAN回線を介して制御部1からの制御を行い、電気二重層キャパシタ(蓄電装置10)はローカル追従制御を行った。本発明による自立運転システムでは自立運転移行直後を含めた自立運転時の電圧変動は本測定時の制御目標値である6.6kVに対して1%以下、周波数変動は制御目標値の50Hzに対して±0.1Hzと非常に高品質な電力供給を実現することができる。   Next, with reference to FIG. 2, the power quality at the time of transition to independent operation according to the present invention will be described. FIG. 2 shows a state where a gas engine 350 kW is used as the rotating machine generator 6, a nickel metal hydride battery 400 kWh is used as the power storage device 11, and an electric double layer capacitor 100 kW × charge / discharge 2 seconds is used as the power storage device 10. The measurement result of 1 second period is shown. Here, the gas engine (rotor generator 6) and the nickel hydrogen battery (power storage device 11) perform control from the control unit 1 via the LAN line, and the electric double layer capacitor (power storage device 10) performs local follow-up control. Went. In the self-sustained operation system according to the present invention, the voltage fluctuation during the self-sustaining operation including immediately after the transition to the self-sustaining operation is 1% or less with respect to the control target value of 6.6 kV at the time of the main measurement, and the frequency fluctuation is with respect to the control target value of 50 Hz Therefore, a very high quality power supply of ± 0.1 Hz can be realized.

以上説明したように、回転機系発電機6を定電圧定周波数制御で運転することで、マイクログリッド系統内の電力品質(電圧・周波数双方)の維持を行うとともに、充電することで電力の一時的な蓄積が可能な蓄電装置10、11を利用しているため、自立運転時においてマイクログリッド系統内の負荷合計値が回転機系発電機6の最低出力以下となった場合についても電力供給を維持することが可能となる。この本発明によるマイクログリッドの自立運転中の制御方法と自立運転移行制御方法を用いることにより、自立運転移行時を含めて高品質な電力供給を継続的に行うができ、この結果、万一の停電等の異常の際、マイクログリッド内施設への影響を防止することが可能となる。また、系統異常検出部9から遮断器8までと、遮断器8から蓄電装置10までと、計測器101から蓄電装置10までの信号線を高速通信が可能な信号線を用い、その他の信号線にLAN回線等の低速な信号線を用いるようにしたため、信号線の埋設費用等のコストアップを抑制することが可能となる。   As described above, by operating the rotating machine generator 6 with constant voltage and constant frequency control, the power quality (both voltage and frequency) in the microgrid system is maintained and the power is temporarily stored by charging. Since the power storage devices 10 and 11 that can be stored in a continuous manner are used, the power supply is performed even when the total load value in the microgrid system is less than the minimum output of the rotating machine generator 6 during the autonomous operation. Can be maintained. By using the control method during the self-sustained operation of the microgrid and the self-sustained operation transition control method according to the present invention, it is possible to continuously supply high-quality power including during the self-sustained operation transition. When an abnormality such as a power failure occurs, it is possible to prevent the influence on the facilities in the microgrid. Further, the signal lines from the system abnormality detection unit 9 to the circuit breaker 8, the circuit breaker 8 to the power storage device 10, and the signal lines from the measuring device 101 to the power storage device 10 are signal lines that can perform high-speed communication, and other signal lines In addition, since a low-speed signal line such as a LAN line is used, it is possible to suppress an increase in cost such as a burying cost of the signal line.

本発明の一実施形態の構成を示すブロック図である。It is a block diagram which shows the structure of one Embodiment of this invention. 本発明による自立運転システムの電力品質の一例を示す説明図である。It is explanatory drawing which shows an example of the electric power quality of the independent operation system by this invention. 従来技術による自立運転システムの構成を示すブロック図である。It is a block diagram which shows the structure of the independent operation system by a prior art. 図3に示す自立運転システムの改善策を講じたシステム構成を示すブロック図である。It is a block diagram which shows the system configuration | structure which took the improvement plan of the independent operation system shown in FIG.

符号の説明Explanation of symbols

1・・・制御部、2・・・商用系統、3、4、5・・・負荷、6・・・回転機系発電機、8・・・遮断器、81・・・状態検出部、9・・・系統異常検出部、10・・・蓄電装置(高速)、11・・・蓄電装置(中速)、31、41、51、61、101、111・・・計測器   DESCRIPTION OF SYMBOLS 1 ... Control part, 2 ... Commercial system 3, 4, 5 ... Load, 6 ... Rotating machine system generator, 8 ... Circuit breaker, 81 ... State detection part, 9 ... System abnormality detection unit, 10 ... Power storage device (high speed), 11 ... Power storage device (medium speed), 31, 41, 51, 61, 101, 111 ... Measuring instrument

Claims (3)

回転機系発電機を備える分散型電源の負荷追従運転によって商用系統への負担を軽減する分散型電源の自立運転システムであって、
前記商用系統の異常を検出した場合に、異常検出信号を出力する系統異常検出手段と、
前記系統異常検出手段から前記異常検出信号が入力された場合に前記商用系統の電力供給を遮断する遮断器と、
前記遮断器が遮断状態になったことを検出した場合に遮断器状態信号を出力する状態検出手段と、
前記遮断器状態信号が入力された場合に、電力供給を開始することにより、前記遮断器によって商用系統の電力が遮断されてから前記回転機系発電機が自立運転制御の運転に移行するまでの間の負荷変動を補償する蓄電装置とを有し、
前記異常検出信号及び前記遮断器状態信号は、前記回転機系発電機に制御系信号を伝送する信号線より高速な信号線によって伝送されることを特徴とする分散型電源の自立運転システム。
A distributed power supply self-sustained operation system that reduces the burden on the commercial system by load following operation of the distributed power supply including a rotating machine generator,
A system abnormality detecting means for outputting an abnormality detection signal when an abnormality of the commercial system is detected;
A circuit breaker that cuts off the power supply of the commercial system when the abnormality detection signal is input from the system abnormality detection means;
State detecting means for outputting a breaker state signal when it is detected that the breaker is in a break state; and
When the circuit breaker state signal is input, by starting the power supply, the electric power of the commercial system is interrupted by the circuit breaker until the rotating machine generator shifts to the operation of the autonomous operation control. and a power storage device to compensate for load variations between,
The distributed power supply self-sustained operation system, wherein the abnormality detection signal and the breaker state signal are transmitted by a signal line faster than a signal line for transmitting a control system signal to the rotating machine generator .
前記系統異常検出手段から異常検出信号を受信すると前記自立運転システムを連係運転から自立運転へ移行する制御手段を有し、
前記系統異常検出手段は、前記異常検出信号を前記高速な信号線によって前記遮断器に出力するとともに、前記制御手段に前記高速な信号線よりも低速な信号線を介して出力し、
前記遮断器状態信号は、前記制御手段を介することなく前記蓄電装置に伝送されることを特徴とする請求項1に記載の分散型電源の自立運転システム。
Upon receipt of an abnormality detection signal from the system abnormality detection means, the autonomous operation system has a control means for shifting from linked operation to independent operation,
The system abnormality detection means outputs the abnormality detection signal to the circuit breaker through the high-speed signal line, and outputs to the control means via a signal line that is slower than the high-speed signal line,
2. The distributed power supply self-sustained operation system according to claim 1, wherein the breaker state signal is transmitted to the power storage device without passing through the control means .
前記蓄電装置は、前記遮断器状態信号が入力された場合に、自己の供給電力量を計測し、計測した供給電力量に基づいて、予め決められた制御値になるように運転制御を行うことを特徴とする請求項1または2に記載の分散型電源の自立運転システム。 When the circuit breaker state signal is input, the power storage device measures its own power supply amount and performs operation control so as to obtain a predetermined control value based on the measured power supply amount. The self-sustained operation system for a distributed power source according to claim 1 or 2.
JP2008058336A 2008-03-07 2008-03-07 Self-sustained operation system for distributed power supply Active JP4986068B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008058336A JP4986068B2 (en) 2008-03-07 2008-03-07 Self-sustained operation system for distributed power supply

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008058336A JP4986068B2 (en) 2008-03-07 2008-03-07 Self-sustained operation system for distributed power supply

Publications (2)

Publication Number Publication Date
JP2009219204A JP2009219204A (en) 2009-09-24
JP4986068B2 true JP4986068B2 (en) 2012-07-25

Family

ID=41190532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008058336A Active JP4986068B2 (en) 2008-03-07 2008-03-07 Self-sustained operation system for distributed power supply

Country Status (1)

Country Link
JP (1) JP4986068B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5583507B2 (en) * 2010-07-29 2014-09-03 株式会社日立製作所 Method and apparatus for monitoring and controlling smart grid
JP6119383B2 (en) * 2013-04-01 2017-04-26 新日鐵住金株式会社 Power supply system and power supply and demand adjustment method
DE102013210812A1 (en) * 2013-06-10 2014-12-11 Wobben Properties Gmbh Method for feeding electrical power into an electrical supply network
JP2019134497A (en) * 2016-03-30 2019-08-08 株式会社日立製作所 Power interconnection controller and method
EP3624304B1 (en) 2017-05-11 2023-04-05 Murata Manufacturing Co., Ltd. Power control device and power control method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06245410A (en) * 1993-02-18 1994-09-02 Meidensha Corp Mobile generation set to be switched without service interruption
JP4361470B2 (en) * 2004-01-28 2009-11-11 Tdkラムダ株式会社 Power supply system with lightning detection means
JP4360495B2 (en) * 2004-12-27 2009-11-11 本田技研工業株式会社 Cogeneration equipment

Also Published As

Publication number Publication date
JP2009219204A (en) 2009-09-24

Similar Documents

Publication Publication Date Title
WO2011016092A1 (en) Island operating system for distributed power source
US10156225B2 (en) Method for black starting wind turbine, wind farm, and restoring wind farm and wind turbine, wind farm using the same
JP5792824B2 (en) Power supply system, distributed power supply system, management device, and power supply control method
JP4986068B2 (en) Self-sustained operation system for distributed power supply
US10447075B2 (en) ASTS-less block redundant electrical topology with variable UPS walk-ins
JP2008278700A (en) Distributed power generator and power quality maintenance control method
JP2013121205A (en) Self-sustained operation system and method of distributed power supply
JPWO2020021925A1 (en) Power system
WO2013179357A1 (en) Controller and power distribution system
KR101859053B1 (en) Standby generator synchronizing operation of closed transition transfer switch
JP2005245136A (en) Reverse power flow prevention type grid interconnection system
JP3839643B2 (en) Uninterrupted self-sustained power generation system
WO2013179358A1 (en) Controller, battery control unit, and power distribution system
JP2002171671A (en) Instantaneous interruption independent transition power generation system
JP6021660B2 (en) Distributed power system
JP2010081751A (en) Power supply system
JP6289123B2 (en) Power generation system
JP6000144B2 (en) Distributed power system
JP4801109B2 (en) Power supply control system, power supply control device, and traffic information device
JP7113693B2 (en) power supply system
JP2009247210A (en) Method and apparatus for detecting individual operation of power generating facility
JP7815092B2 (en) Power supply system control device, power supply system, power supply system control method, and power supply system control program
JP2002135982A (en) Instantaneous interruption independent transition power generation system
JP5980100B2 (en) Emergency power generation system
JP2013141370A (en) Automatic generator voltage regulation apparatus

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100528

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111003

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111108

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120110

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120321

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120418

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4986068

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150511

Year of fee payment: 3