JPH01190878A JP1403488A JP1403488A JPH01190878A JP H01190878 A JPH01190878 A JP H01190878A JP 1403488 A JP1403488 A JP 1403488A JP 1403488 A JP1403488 A JP 1403488A JP H01190878 A JPH01190878 A JP H01190878A
Authority
JP
Japan
Prior art keywords
anchor hole
hole
anchor
opening
spacer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1403488A
Other languages
Japanese (ja)
Inventor
Naohiko Kobayashi
直彦 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP1403488A priority Critical patent/JPH01190878A/en
Publication of JPH01190878A publication Critical patent/JPH01190878A/en
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PURPOSE:To enable firm and reliable fixing of a filled reinforcing bar body, by a method wherein a reinforcing bar engage internally of a spacer is inserted in a bored hole the interior of which is spread than its opening so that it is positioned at a center, and the opening is sealed to fill it with chemicals. CONSTITUTION:An anchor hole 3 is formed in a shape, in which the inside is spread than an opening part 3', by using a drill the cutting blade mounting part of which is unfolded by exerting thrust during excavation. A reinforcing bar 10 engaged internally of a spacer 20 from which a plurality of leg pieces 21 are radially protruded is inserted in the anchole hole in a manner that a central axis approximately coincides with the center of the hole 3. After the opening part 3' is sealed with a cover piece 25 engaged internally of the reinforcing bar 10 and having an air bleed port 26 and a chemical injection port 27, chemicals 5 are injected by means of a chemical automatic injector 30 mounted to the chemical injection port 27. The hole 3 is filled with the chemicals 5 without forming a cavity, and curing thereof enables firm filling of the reinforcing bar 10.

Description

【発明の詳細な説明】 産業上の利用分野: 本発明は主として既設建造物の側壁部に、構造物を付加
する際の外付は鉄筋もしくは基礎ボルトなどを植設する
工法に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application: The present invention mainly relates to a method of installing external reinforcing bars or foundation bolts when adding a structure to the side wall of an existing building.

発明の背景: 構築物にあって、建物の増築や併設などで、既設の建造
物を基準にして、その横に新たな構造物を増設する場合
、通常既設側の一部に基礎となる部分を固定し、この基
礎材を基にして骨格を組付ける方法が採用される。特に
、構築物か、コンクリート建造物である場合には、その
既設側壁部にアンカー穴を穿設し、これにアンカーボル
トを植付けて、増設部分を構築するのであり、そのよう
な工法は多くの場所で行われている。
Background of the invention: When building a new structure next to an existing structure, such as by expanding or adding a building, it is common to build a foundation on a part of the existing structure. A method is adopted in which the structure is fixed and the framework is assembled based on this foundation material. In particular, in the case of a structure or a concrete building, an anchor hole is drilled in the existing side wall and an anchor bolt is planted in the hole to construct an extension.Such construction method is used in many places. It is being carried out in

しかし乍ら、このいわゆる外付けの増設工法では、既設
建造物の壁面を部分的に破壊して、既設側の骨組(鉄骨
部材・鉄筋など)を露出させ、この露出した骨組に対し
てアンカーボルトなどを溶接することにより、増設部の
基礎を構築するようになり、そのため既設建造物の強度
を弱めるおそれかある。
However, in this so-called external addition construction method, the walls of the existing building are partially destroyed to expose the existing framework (steel members, reinforcing bars, etc.), and anchor bolts are attached to the exposed framework. By welding, etc., the foundation for the extension will be constructed, which may weaken the strength of the existing building.

このような工法を採用している例として道路橋(高速道
路など)の橋脚梁を横に張出して道路増幅などを行う場
合がある。もちろん、これ以外に建物の一部に、増設す
る場合にも多く採用されている。
An example of this method is when the piers of a road bridge (such as an expressway) are extended laterally to amplify the road. Of course, in addition to this, it is also often used when adding parts to buildings.

解決しようとする課題: 従来実施されている既設建造物の側壁部などに外付は増
設するような場合、既設建造物に基礎を構築するため壁
部を一部破壊しなければならず、手数を多く要して、し
かも既設物を弱めることになる。特に部分的ではあって
もコンクリート構築部を広い面で掘削することになるの
で、必要個所以外にクラックを発生させて、その補修を
も必要となる等多くの問題点がある。
Issues to be solved: When adding an external attachment to the side wall of an existing building, which has been done in the past, it is necessary to partially destroy the wall in order to construct the foundation on the existing building, which is a hassle. This would require a lot of energy and weaken the existing structure. In particular, since the concrete construction part has to be excavated over a wide area, even if only partially, there are many problems, such as cracks occurring in areas other than the necessary areas, which also require repair.

また、既設建物で、その躯体外装の壁体を補強するよう
な場合、補強のために埋込む補強片は、一般にストレー
ト穴を穿ったあとに挿入して、接着剤で固定するような
処理をしているが、その埋込み穴と接着剤とによる固定
効果が長期にわたり安定性を保ち難い。
Additionally, when reinforcing the exterior walls of an existing building, the reinforcing pieces are generally inserted after drilling a straight hole and fixed with adhesive. However, the fixing effect of the embedded hole and the adhesive is difficult to maintain stability over a long period of time.

課題を解決する手段: 本発明は、上記したような課題を解決するため、建造物
の目的個所に、アンカー穴を穿設するに際し、コンクリ
ート躯体部に対して掘削内部で切削部が拡開する機能を
有した穿削ドリルを用いて、内部が深部に向って拡がる
ように穿孔し、植込み筋体(アンカーボルト・鉄筋等の
棒材以下同様)に併前記アンカー穴の内周面に対して局
部的に接触する脚がほぼ等分して放射状に備えた弾性材
にてなるスペーサーを外嵌して、アンカー穴に挿入し、
このアンカー穴の開口部には、エア抜き口と薬液注入口
とを備えた蓋片を、植込み筋体に外嵌した状態で取り付
けてシールし、この蓋片とスペーサーとによって植込み
筋体がアンカー穴の軸心線上にその軸心が沿うように支
持し、蓋片の薬泉注入口に加圧ポンプ式の薬液自動注入
器を取り付けて、接着性薬剤をアンカー穴内に注入充填
するのである。
Means for Solving the Problems: In order to solve the above-mentioned problems, the present invention provides a method in which, when drilling an anchor hole at a target location of a building, the cutting portion expands inside the excavation with respect to the concrete frame. Using a functional drilling drill, drill a hole so that the inside expands toward the deep part, and attach it to the implanted reinforcement body (same for bars such as anchor bolts and reinforcing bars) as well as to the inner peripheral surface of the anchor hole. A spacer made of an elastic material with locally contacting legs radially divided into approximately equal parts is fitted onto the outside, and inserted into the anchor hole.
A lid piece equipped with an air vent and a chemical injection port is attached to the opening of the anchor hole and sealed by fitting it onto the implanted muscle body, and the implanted muscle body is anchored by this lid piece and spacer. The anchor hole is supported so that its axis is aligned with the axis of the anchor hole, and a pressurized chemical liquid automatic injector is attached to the medicinal spring inlet of the lid piece to inject and fill the adhesive agent into the anchor hole.

本発明の工法で使用するスペーサーは合成樹脂製あるい
は金属薄板で形成したものであってよく、アンカー穴の
開口から挿入されるときには脚部が撓んで嵌挿可能で、
穴内部で脚部が拡開する内周面の任意の位置に弾性復帰
して均衡を保って筋体挿入位置か中心線上に軸心を合わ
せて保持できる弾性を備えたものが用いられる。
The spacer used in the construction method of the present invention may be made of synthetic resin or a thin metal plate, and when inserted through the opening of the anchor hole, the legs can be bent so that the spacer can be inserted.
An elastic member is used that can elastically return to any position on the inner circumferential surface where the leg part expands inside the hole, maintain balance, and maintain the axis at the muscle insertion position or on the center line.

本発明によれば、建物の外装壁を補強するために、補強
筋体を埋設して、躯体部と外装壁との浮き上がり防止な
どの処理をする埋設用穴を穿設するに際し、コンクリー
ト壁体部に対して掘削内部で拡開する機能を有するドリ
ルを用いて、掘削内部でテーパー礼状の拡開部を1以上
設け、埋設する補強ピンには前記埋設用穴の内周面に対
して局部的に接触する脚片を放射状に等分して備えた弾
性材にてなるスペーサーを外嵌して、これを埋設用穴に
挿入し、前記アンカー穴に対する植込み筋体の場合と同
要領で接着性薬剤を埋設用孔に注入し、補強ピンを埋設
用穴の中心に配して相互に遊離しない状態で埋設補強す
ることができる。
According to the present invention, in order to reinforce the exterior wall of a building, when drilling holes for burying reinforcing bars to prevent lifting of the building frame and exterior wall, the concrete wall Using a drill that has the function of expanding the area inside the excavation, one or more tapered expansion areas are provided inside the excavation, and the reinforcing pin to be buried has a local area with respect to the inner circumferential surface of the burial hole. Fit a spacer made of an elastic material made of radially equal parts of the legs that contact each other, insert it into the embedding hole, and glue it in the same way as for the implanted reinforcement body for the anchor hole. The sex drug can be injected into the embedding hole, and the reinforcing pin can be placed in the center of the embedding hole to reinforce the embedding in a state where they do not come apart from each other.

上記した薬液(接着性薬剤)の自動注入器としては、薬
液を注入容器に直接または間接的に入れたものに、内在
させた加圧力付勢機構(コイルバネ、ガス圧等)で自動
的に注入できるユニット型のものを使用する。
The automatic injector for the above-mentioned chemical solution (adhesive drug) automatically injects the drug solution directly or indirectly into an injection container using an internal pressure biasing mechanism (coil spring, gas pressure, etc.). Use a unit type that can be used.

作   用 : 本発明によれば、目的作業を行うコンクリート構造物の
作業面の所要個所に、推力を与えると先端の切削刃部が
拡開するような機能を備えたドリルを使用してアンカー
穴(または埋設補強用穴)を掘削し、まず壁部に内部で
開口部よりも広い部分を形成した穴を掘る。次にこのア
ンカー穴(または埋設補強用穴)に挿入する植設箔体(
アンカ−ボルト、植込み鉄筋、埋込み補強ピンないし補
強筋)には、挿入する穴内でそのほぼ中心線上に筋体が
保持されるようにする複数の脚片を周囲に備えたスペー
サーを外嵌して、開口部から挿入する。そのスペーサー
は弾性材で、脚部が復元容易な状態で変形するので開口
部からの穴挿入時には絞られて穴内に入り、穴内部では
該当位置で復元して筋体を支える。また予めアンカー穴
の開口部を閉じる蓋体も、この挿入動体に外嵌しておき
、所要深さに挿入動体を位置させた後、蓋体の周囲をシ
ールし、好ましくはエア抜き口が上になるようにして、
穴深部に開口部を配したエア抜きチューブを配しておき
、薬液注入口に加圧機構を備えたカプセル型の薬液注入
器を取り付け、この薬液注入器内に仕込んだ公知組成の
(主としてエポキシ樹脂系接着剤)薬液を、加圧機構の
ロックを解いて自動的に注入するように処置する。
Effect: According to the present invention, anchor holes are drilled at required locations on the work surface of a concrete structure where the intended work is to be performed using a drill equipped with a function in which the cutting edge portion at the tip expands when thrust is applied. (or a buried reinforcement hole), first dig a hole in the wall that is wider inside than the opening. Next, insert the embedded foil (
(anchor bolts, embedded reinforcing bars, embedded reinforcing pins or reinforcing bars) are fitted with a spacer having a plurality of legs around the circumference to keep the reinforcement approximately on its centerline within the hole into which it is inserted. , insert it through the opening. The spacer is made of an elastic material, and the legs are deformed so that they can be easily restored, so when the spacer is inserted into the hole through the opening, it is squeezed and goes into the hole, and inside the hole, it restores itself to the corresponding position and supports the muscle body. In addition, a lid body that closes the opening of the anchor hole is fitted onto the insertion body in advance, and after the insertion body is positioned at the required depth, the periphery of the lid body is sealed, preferably with the air vent opening at the top. so that
An air bleed tube with an opening deep in the hole is arranged, and a capsule-type chemical injector equipped with a pressure mechanism is attached to the chemical injection port. (Resin-based adhesive) Chemical solution is automatically injected by unlocking the pressure mechanism.

この状態で薬液の注入が行われると、穴内の空気はエア
ー抜きチューブを通って次第に排出され、挿入した筋体
はスペーサーによって穴内周面とほぼ一様に間隔を保っ
た状態で、薬液が注入充填される。もちろん、スペーサ
ーは薬液の移動を妨内に充填され、時間の経過によって
植込み筋体はアンカー穴に固定植設できる。この植込み
筋体はその外周面と薬液(接着剤)との密着性が高くな
る形状にしておくことで、植設後、アンカー穴の内部拡
大部による充填薬剤の穴に対する接着係止作用で確実に
固定され、既設構造物に対するアンカーとしての効果を
発揮する。
When the chemical solution is injected in this state, the air inside the hole is gradually discharged through the air release tube, and the inserted muscle body is maintained at an almost uniform distance from the inner peripheral surface of the hole by the spacer, and the chemical solution is injected. Filled. Of course, the spacer is filled in to prevent the movement of the drug solution, and over time the implanted muscle body can be fixedly implanted in the anchor hole. This implanted muscle body is designed to have a shape that increases the adhesion between its outer circumferential surface and the drug solution (adhesive), so that after implantation, the internal enlarged part of the anchor hole will securely lock the filled drug into the hole. It works as an anchor for existing structures.

したがって、上記した要領で多数本のアンカー穴を穿ち
、所要数のアンカーボルト、あるいは鉄筋を植設すれば
、既設側を破壊することなく合理的に増設基礎が形成で
きる。
Therefore, by drilling a large number of anchor holes as described above and planting the required number of anchor bolts or reinforcing bars, an additional foundation can be formed rationally without destroying the existing side.

外装壁の浮上り防止あるいは壁体の補修にあたっては、
補強ピンもしくは補強鉄筋を埋設するに際し、その埋設
深さにもよるが、複数の節状に穴の拡開部を形成し、ス
ペーサーを介在させて補強棒材を挿入し、前記と同要領
で薬液注入充填を行えばよい。
When preventing floating of exterior walls or repairing walls,
When burying reinforcing pins or reinforcing reinforcing bars, depending on the depth of embedding, the holes are expanded into multiple joints, and reinforcing bars are inserted with spacers in between, and the same method as above is used. All you have to do is inject and fill the drug.

実施例: 次に本発明工法を実施例について図面を参照して説明す
る。
Examples: Next, examples of the construction method of the present invention will be described with reference to the drawings.

第1図に示すのは、既設コンクリート建造物にアンカー
を取って側部に増設する際の鉄筋植込みの態様を表わし
ている。
Figure 1 shows the manner in which reinforcing bars are installed when adding anchors to the side of an existing concrete building.

たとえば既設のコンクリート建造物(1)の側面に、新
たな構造物を増設するために、増設部の骨組構成用鉄筋
00の基礎部となる基端Q6を植設するアンカー穴(3
)を穿設する。このアンカー穴(3)は建造物(1)の
側面(1′)からアンカーとして安定性が得られる深さ
に穿設するのであり、この穿孔に際しては、掘削途中で
推力を加えると切削刃01)取り付は部が芯金(6)に
よって拡開するような構造をもったドリルθO(第3図
参照)を用いて、先に下孔を穿削した後にこのドリルに
)を使用し、内部が開口部(3′)より拡がった形状に
穿孔する。このようなアンカー穴掘削用ドリル(40と
しては実開昭62−191405号公報によって知られ
たものが一例として挙げられる。
For example, in order to add a new structure to the side of an existing concrete building (1), an anchor hole (3
). This anchor hole (3) is drilled from the side surface (1') of the structure (1) to a depth that provides stability as an anchor. ) For installation, use a drill θO (see Figure 3) whose part is expanded by the core bar (6), first drill a pilot hole, and then use this drill). The hole is formed so that the inside thereof is wider than the opening (3'). An example of such an anchor hole drilling drill (40) is the one known from Japanese Utility Model Application Publication No. 191405/1983.

このような型式のドリルを使用して穿設したアンカー穴
(3)は、逆勾配になった内部拡開の構造になる。この
逆勾配の寸法形状などは、使用する前記ドリル00の切
削刃01)の拡開する程度によって決まる。
The anchor hole (3) drilled using this type of drill has an internally expanding structure with a reverse slope. The dimensions and shape of this reverse slope are determined by the extent to which the cutting blade 01) of the drill 00 used is expanded.

掘削されたアンカー穴(3)に植設する鉄筋αO(アン
カーボルト)には、スペーサー(1)を外嵌して、アン
カー穴(3)に挿入する。このスペーサー(イ)は第2
図に示すよう、放射状に複数の脚片(21)を突設した
、合成樹脂材で形成してあり、孔(イ)は鉄筋00が密
嵌する寸法にしてあり、脚片Q])はアンカー穴(3)
の開口部(3′)から挿入する際に容易に可撓なように
しである。
A spacer (1) is fitted onto the reinforcing bar αO (anchor bolt) to be planted in the excavated anchor hole (3), and the spacer (1) is inserted into the anchor hole (3). This spacer (a) is the second
As shown in the figure, it is made of a synthetic resin material with a plurality of radially protruding leg pieces (21), the hole (A) is sized to fit the reinforcing bar 00 tightly, and the leg piece Q) is Anchor hole (3)
It is designed so that it can be easily flexible when inserted through the opening (3').

また、アンカー穴(3)に挿入するに際して、アンカー
穴(3)の開口部(3′)を閉じる蓋片(ハ)を鉄筋α
Oに外嵌しておく。この蓋片(ハ)にはエアー抜き口翰
と薬液注入口(イ)とが設けてあり、エアー抜き口(ホ
)には第1図で示すようなエアー抜き用チューブ(ハ)
を、その終端がアンカー穴(3)の深部上側に位置する
ように配して、この蓋片(ハ)を開口部(イ)に嵌めて
閉じ、周囲を接着剤(4)によってシールする。
Also, when inserting into the anchor hole (3), attach the lid piece (c) that closes the opening (3') of the anchor hole (3) to the reinforcing steel α.
Fit it to O. This lid piece (C) is provided with an air vent hole and a chemical liquid inlet (A), and the air vent (E) is equipped with an air vent tube (C) as shown in Figure 1.
is arranged so that its terminal end is positioned above the deep part of the anchor hole (3), the lid piece (c) is fitted into the opening (a) to close it, and the periphery is sealed with adhesive (4).

この状態で鉄筋00はアンカー穴(3)にスペーサー(
イ)と蓋片(ハ)とにより保持される。そこで蓋片(ハ
)の薬液注入口(イ)のねじ部始に、公知の加圧ポンプ
式の薬液自動注入器(至)の取り付は注出管部0のをね
じ込んで取り付ける。予めこの薬液自動注入器(7)の
本体ケース0υ内に、公知組成(エポキシ樹脂系接着剤
)の薬液(5)を入れて、ピストン(ト)の背後とキャ
ップ(至)との間に介在させたコイルバネ(至)力を、
ピストンロッドiに付しである係止片(図示省略)で、
注入開始まではピストン(ハ)の推進を止めておき、準
備が整うと、その係止を解いてバネ(至)力による推力
をピストン(ハ)に与えると、注出部からアンカー穴(
3)に薬液(5)が注入される。この際アンカー穴(3
)内にあるエアーはチューブ(ハ)を通じてエア抜き口
(イ)から外部に排出され、アンカー穴(3)内にエア
ーが残留して空洞を形成することなく薬液が充填され、
鉄筋00はアンカー穴(3)にて薬液の硬化により強固
に固定される。
In this state, the reinforcing bar 00 is inserted into the anchor hole (3) with a spacer (
It is held by the lid piece (c) and the lid piece (c). Therefore, a known pressurized pump-type chemical liquid automatic injector (to) is attached to the threaded part of the chemical liquid inlet (a) of the lid piece (c) by screwing in the spouting pipe part 0. In advance, a chemical solution (5) of a known composition (epoxy resin adhesive) is put into the main body case 0υ of this automatic chemical injector (7), and inserted between the back of the piston (T) and the cap (To). The coil spring force is
A locking piece (not shown) attached to the piston rod i,
The piston (c) is not propelled until the injection starts, and when preparations are complete, the lock is released and thrust is applied to the piston (c) by the spring force, which causes the anchor hole (c) to flow from the spouting part.
The chemical solution (5) is injected into 3). At this time, the anchor hole (3
) is discharged to the outside from the air vent (a) through the tube (c), and the chemical solution is filled without air remaining in the anchor hole (3) and forming a cavity.
The reinforcing bar 00 is firmly fixed in the anchor hole (3) by hardening of the chemical solution.

力なアンカー効果が得られる。したがってこの峠−筋α
Oに増設物の骨組を付加して構築すればよい。
A strong anchor effect can be obtained. Therefore, this mountain pass-suji α
It can be constructed by adding the framework of the extension to O.

また、本発明工法にて、既設建物の側壁にアンカー穴を
上記のようにして穿設し、これにアンカーボルトを植設
すれば、このアンカーボルトを基準にして付設する骨組
の基部を締結して、増設することができる。
Furthermore, using the construction method of the present invention, if an anchor hole is drilled in the side wall of an existing building as described above and an anchor bolt is planted in it, the base of the frame to be attached can be fastened using the anchor bolt as a reference. can be expanded.

本発明の趣旨によれば、前記アンカーボルト等の植設手
段のほかに、たとえば既設建造物の外装壁が躯体から浮
き出したものをあるいは壁体部分を補強するための補強
棒の埋込みなどのような工法にも採用できる。
According to the gist of the present invention, in addition to the above-mentioned installation means such as anchor bolts, it is also possible to embed reinforcing rods for reinforcing the exterior wall of an existing building that protrudes from the frame or for reinforcing the wall portion. It can also be used in other construction methods.

この−例を図示すれば、第4図のように、既設コンクリ
ート躯体(IA)に、外装壁(IB)からアンカー穴(
3A)を穿設する際、前記実施例で使用したドリルにて
穴中開位置に拡開した節部(A5を形成し、埋込む補強
棒(11)にスペーサー翰を複数外嵌して、アンカー穴
(3A)内に挿入する。このようにすることで、補強棒
(1])はスペーサー(イ)によってほぼ中心線に沿っ
て支持される。アンカー穴(3A)の開口部(イ)にエ
ア抜き口(ハ)と薬液注入口(ハ)とを備えた蓋片iを
取り付け、前記実施例と同要領で薬液を注入することに
より、補強棒ODをアンカー穴(3A)内に接着性薬剤
(g)によって埋込み固定し、一体化することができる
To illustrate this example, as shown in Figure 4, anchor holes (
3A), use the drill used in the previous example to form a node (A5) expanded at the open position of the hole, and fit a plurality of spacer rods around the reinforcing rod (11) to be embedded. Insert into the anchor hole (3A).By doing this, the reinforcing rod (1]) is supported by the spacer (A) almost along the center line.The opening (A) of the anchor hole (3A) Attach a lid piece i equipped with an air vent (c) and a chemical liquid inlet (c) to the plate, and inject the chemical liquid in the same manner as in the previous example to adhere the reinforcing rod OD into the anchor hole (3A). It can be implanted and fixed with a sex agent (g) and integrated.

この補強棒01)の埋設によって躯体(IA)と外装壁
(IB)とを跨いで緊結状態を薬剤(5′)によって維
持され、強固に補強される。特にアンカー穴(3A)に
節部(A)が形成されて、ここに薬剤(5′)が充填さ
れているから、補強棒ODをくるんだ接着性薬剤(5′
)がアンカー穴(3A)穿設部と一体化し、緩むことな
く目的を達成できる。同様にして壁体単独での補強にも
採用できる。
By embedding this reinforcing rod 01), the bonded state is maintained across the frame (IA) and the exterior wall (IB) by the agent (5'), and the reinforcement is strongly reinforced. In particular, since the node (A) is formed in the anchor hole (3A) and filled with the agent (5'), the adhesive agent (5') surrounding the reinforcing rod OD is
) is integrated with the anchor hole (3A) drilling part, achieving the purpose without loosening. In the same way, it can also be used to reinforce a wall alone.

また、本発明の趣旨に基づけば、たとえば既設の床面上
にアンカー穴を穿設して、機械設備などの固定用アンカ
ーボルトを植設し、機械設備の据付けに役立て得る。
Furthermore, according to the spirit of the present invention, for example, anchor holes may be drilled on an existing floor surface and anchor bolts for fixing mechanical equipment or the like may be planted therein, thereby making it useful for installing mechanical equipment.

発明の効果: 本発明工法によれば、既設のコンクリート建造物を破損
することがなく、植設したあるいは埋込んだ部体に、開
口部より内部で拡開したアンカー穴と、充填した薬剤と
によって、その部体の軸線方向に作用する作用力が、強
固に保持され、抜は出すことなく固定でき、既設建造物
に過剰な加工を加えないで目的が達成でき、必要個所以
外にクラックを発生させることなく合理的にアンカーボ
ルトや補強筋体の植設ができる有用な工法であるといえ
る。
Effects of the invention: According to the construction method of the present invention, an existing concrete structure is not damaged, and an anchor hole enlarged inside from the opening and filled with a chemical can be formed in a planted or buried part. As a result, the force acting in the axial direction of the part is firmly held, it can be fixed without being pulled out, the purpose can be achieved without excessive machining of the existing structure, and cracks can be avoided in non-necessary areas. It can be said that this is a useful construction method that allows anchor bolts and reinforcing bars to be planted rationally without causing any damage.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法による鉄筋植設の態様を示す図、第
2図はスペーサー取り付は部の図、第3図はアンカー穴
穿設用のドリルの一例を示す図、第4図は外装壁の補強
における態様を示す図である。 (1)・・・建 造 物    (1′)・・・建造物
の側面(IA)・・・コンクリートの躯体 (IB)・
・・外装壁(3) (3A)・・・アンカー穴  (3
′)・・・開 口 部(3)・・・節   部    
(4)・シール用の接着剤(5)(5′)・・・薬液(
薬剤)   QO・・・鉄   筋06・・・基   
端    01)・・・補 強 棒翰・・・スペーサー
    (21)・・・脚片(イ)・・・  孔   
   (ハ)始・・・蓋  片(ハ)・・・エア抜き口
    (ハ)・・・薬液注入口(ハ)・・・エア抜き
用チューブ  (至)・・・薬液自動注入器01)・・
・本体ケース    0カ・・・取り付は注出管部(ト
)・・・ピストン     (ロ)・・・キャップ(至
)・・・コイルバネ
Fig. 1 is a diagram showing the aspect of reinforcing steel reinforcement according to the method of the present invention, Fig. 2 is a diagram of the spacer installation section, Fig. 3 is a diagram showing an example of a drill for drilling an anchor hole, and Fig. 4 is a diagram showing an example of a drill for drilling an anchor hole. It is a figure which shows the aspect in reinforcement of an exterior wall. (1)...Building (1')...Side surface of the building (IA)...Concrete frame (IB)
... Exterior wall (3) (3A) ... Anchor hole (3
')...Opening part (3)...Knot part
(4)・Adhesive for sealing (5) (5′)・・・Medical solution (
Drug) QO...Rebar 06...Group
End 01)... Reinforcement Rod... Spacer (21)... Leg piece (A)... Hole
(c) Start... Lid piece (c)... Air bleed port (c)... Chemical solution inlet (c)... Air vent tube (To)... Chemical solution automatic injector 01)・
・Body case 0 parts...Installation is the spout pipe part (G)...Piston (B)...Cap (to)...Coil spring

Claims (1)

【特許請求の範囲】 1 既設建造物のコンクリート躯体部に対して、掘削内
部で切削部が拡開する機能を有したドリルを用い、内部
が深部に向つて拡がるようなアンカー穴を穿設し、この
アンカー穴に植込む筋体には、放射状に複数の脚を備え
て弾性材にてなるスペーサーと、エア抜き口と薬液注入
口とを備えたアンカー穴開口部の蓋片とを外嵌して、ア
ンカー穴に挿入し、アンカー穴開口部に蓋片を取り付け
てシールし、この蓋片とスペーサーとによつて植込み筋
体がアンカー穴の軸心線上にその軸心が沿うように支持
し、蓋片の薬液注入口に加圧ポンプ式の薬液自動注入器
を取り付けて、接着性薬剤をアンカー穴に注入充填する
、ことを特徴とする既設建造物に対するアンカーボルト
等の植設工法。 2 特許請求の範囲第1項に記載の工法において、コン
クリート躯体部に対して穿孔するアンカー穴は、その深
部までの途中に拡開部を節状に形成し、かかるアンカー
穴内に、補強用棒を挿入し、蓋片で開口部を閉じて薬液
を注入充填し、既設建造物の壁部を補強することを特徴
とする既設建造物に対するアンカーボルト等の植設工法
[Claims] 1. Drilling an anchor hole in the concrete frame of an existing building so that the inside expands toward the depth using a drill that has a function of expanding the cutting part inside the excavation. The muscle body to be implanted in the anchor hole is fitted with a spacer made of an elastic material and having a plurality of radial legs, and a lid piece for the anchor hole opening that is equipped with an air vent and a chemical injection port. and insert it into the anchor hole, attach a lid piece to the anchor hole opening and seal it, and support the implanted muscle body so that its axis is aligned with the axis of the anchor hole by this lid piece and spacer. A method for planting anchor bolts, etc. in an existing structure, characterized by: attaching a pressure pump type chemical liquid automatic injector to the chemical liquid injection port of the lid piece, and injecting and filling an adhesive chemical into the anchor hole. 2. In the construction method described in claim 1, the anchor hole drilled into the concrete body has a node-like expanded part formed in the middle of the deep part of the anchor hole, and reinforcing rods are inserted into the anchor hole. A method for planting anchor bolts, etc. in an existing building, which is characterized by reinforcing the wall of the existing building by inserting the anchor bolt, closing the opening with a lid piece, and injecting and filling the chemical solution.
JP1403488A 1988-01-25 1988-01-25 Method of filling anchor bolt and the like in existing structure Pending JPH01190878A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1403488A JPH01190878A (en) 1988-01-25 1988-01-25 Method of filling anchor bolt and the like in existing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1403488A JPH01190878A (en) 1988-01-25 1988-01-25 Method of filling anchor bolt and the like in existing structure

Publications (1)

Publication Number Publication Date
JPH01190878A true JPH01190878A (en) 1989-07-31

Family

ID=11849858

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1403488A Pending JPH01190878A (en) 1988-01-25 1988-01-25 Method of filling anchor bolt and the like in existing structure

Country Status (1)

Country Link
JP (1) JPH01190878A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10205134A (en) * 1996-11-21 1998-08-04 Sansen Eng Kk Concrete structure reinforcing method and reinforcing structure obtained by it as well as cushion spacer used for it
JP2014005629A (en) * 2012-06-22 2014-01-16 Yahagi Construction Co Ltd Anchor installation construction method for steel framed reinforced concrete building
CN109025298A (en) * 2018-09-07 2018-12-18 科顺防水科技股份有限公司 A kind of node waterproof sealing compound brushing method and detection method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10205134A (en) * 1996-11-21 1998-08-04 Sansen Eng Kk Concrete structure reinforcing method and reinforcing structure obtained by it as well as cushion spacer used for it
JP2014005629A (en) * 2012-06-22 2014-01-16 Yahagi Construction Co Ltd Anchor installation construction method for steel framed reinforced concrete building
CN109025298A (en) * 2018-09-07 2018-12-18 科顺防水科技股份有限公司 A kind of node waterproof sealing compound brushing method and detection method

Similar Documents

Publication Publication Date Title
EP1375754B1 (en) A packing apparatus and method for soil nailing
JP2004027813A5 (en)
CN108360531B (en) A kind of adaptive prestressed anchor composite soil nailing wall and construction method
JP2002348859A (en) Prefabricated pile in which diameter can be expanded and its execution method
KR101864857B1 (en) Construction method of foundation pile with reinforced casing structure
JPH01190878A (en) Method of filling anchor bolt and the like in existing structure
WO1992020901A1 (en) Injection means
JP2003027462A (en) Construction method of underground continuous wall, and construction method of underground structure
JPH1077800A (en) Fixing material injection method and seal unit
JP4679966B2 (en) Boring hole closing method and equipment
JPH10184297A (en) Lock bolt installation method
KR20010001259A (en) Waterproofing method of concrete structure
JP2003055985A (en) Column and pile connection method
JPS5820850A (en) Embedding of anchor bolt
JPH038922A (en) Executing method for hollow foundation pile and pile head filling-in stuff
JP7678646B2 (en) Rock bolt structure and ground reinforcement structure
JPH10176483A (en) Reinforcement and reinforcing pipe, and reinforcing and repairing method for embedded body in underground by use of the pipe
JP2001152543A (en) Reinforcement structure and reinforcement method for existing underground structures
JPH02221515A (en) Earth anchor construction method using a water stop box
JPH03250114A (en) Construction method of cast-in-place concrete pile
JP3333478B2 (en) Construction method of concrete structure
JPH0579767B2 (en)
JP2789370B2 (en) Piling method
JPH0995943A (en) Construction method of earth anchors in steel pipe column retaining wall
JP2025178700A (en) Pole Construction Method