JPH01250524A - Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction method - Google Patents
Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction methodInfo
- Publication number
- JPH01250524A JPH01250524A JP8050288A JP8050288A JPH01250524A JP H01250524 A JPH01250524 A JP H01250524A JP 8050288 A JP8050288 A JP 8050288A JP 8050288 A JP8050288 A JP 8050288A JP H01250524 A JPH01250524 A JP H01250524A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe pile
- construction method
- concrete layer
- soil cement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は地盤に縦孔を形成し、その縦孔に形成したソイ
ルセメント柱の内部に鋼管杭を配設したソイルセメント
合成鋼管杭の施設工法、及び、その工法に使用する鋼管
杭に関する。[Detailed Description of the Invention] [Field of Industrial Application] The present invention provides a soil cement composite steel pipe pile facility in which a vertical hole is formed in the ground and a steel pipe pile is arranged inside a soil cement column formed in the vertical hole. Concerning construction methods and steel pipe piles used in the construction methods.
従来、上記の如きソイルセメント合成鋼管杭の施設工法
において、抗頭部の補強のために、鋼管抗頭部における
内部ソイルセメントを排除し、それに置換させる状態で
鋼管抗頭部の内部にコンクリートを充填するものがあっ
た(例えば特公昭61−22089号参照)。Conventionally, in the construction method for soil-cement composite steel pipe piles as described above, in order to reinforce the head of the steel pipe pile, the internal soil cement in the head of the steel pipe pile is removed and concrete is poured inside the head of the steel pipe pile to replace it. There was a method for filling (for example, see Japanese Patent Publication No. 61-22089).
しかし、上述従来工法では、補強用充填コンクリート層
の断面積を鋼管杭の開口断面積と等しい面積しか得られ
ないために、補強強度が制約され、未だ十分な補強を達
成し得ない問題があった。However, in the conventional method described above, the cross-sectional area of the reinforcing filled concrete layer is only equal to the opening cross-sectional area of the steel pipe pile, which limits the reinforcement strength, and there is still a problem that sufficient reinforcement cannot be achieved. Ta.
本発明の目的は、合理的な改良により杭頭部の補強をよ
り確実にする点にある。An object of the present invention is to more reliably reinforce the pile head through rational improvements.
本発明によるソイルセメント合成鋼管杭の施設工法の特
徴手段は、地盤に縦孔を形成し、その縦孔に形成したソ
イルセメント柱の内部に鋼管杭を配設する基本手段に対
し、前記縦孔の上端部において、前記ソイルセメント柱
の上端に連ねる状態で前記鋼管杭の外周部に環状コンク
リート層を付設することにあり、その作用・効果は次の
通りである。The characteristic means of the soil cement synthetic steel pipe pile construction method according to the present invention is that, in contrast to the basic method of forming a vertical hole in the ground and arranging the steel pipe pile inside the soil cement column formed in the vertical hole, the vertical hole is An annular concrete layer is attached to the outer periphery of the steel pipe pile at the upper end so as to be connected to the upper end of the soil cement column, and its functions and effects are as follows.
つまり、補強用コンクリート層を鋼管杭の外周部に付設
形成するから、鋼管杭の内部にコンクリート層を形成す
るに比して、補強用コンクリート層の断面積を制限なく
大きく確保できる。That is, since the reinforcing concrete layer is attached and formed on the outer periphery of the steel pipe pile, the cross-sectional area of the reinforcing concrete layer can be secured to be larger without any limit, compared to forming a concrete layer inside the steel pipe pile.
その結果、ソイルセメント合成鋼管杭における抗頭部の
補強強度を十分にすることができ、地震等に対する杭の
強度を大巾に向上し得るに至った。As a result, the reinforcement strength of the head of the soil-cement synthetic steel pipe pile could be made sufficient, and the strength of the pile against earthquakes and the like could be greatly improved.
又、杭上端における強度部分の断面積を大きく確保でき
ることで上部構造体に対する支持強度をも合せ向上し得
るに至った。In addition, by ensuring a large cross-sectional area of the strong portion at the upper end of the pile, the support strength for the upper structure can also be improved.
しかも、従来工法であれば鋼管杭を細くすると補強強度
も低下して杭強度が大巾に低下してしまうが、本発明工
法によれば補強強度を十分に確保しながら鋼管杭を細く
することもでき、その点、鋼管杭の細径孔によるコスト
ダウンを図る上でも有利である。Furthermore, with conventional construction methods, when the steel pipe pile is made thinner, the reinforcement strength also decreases, resulting in a significant drop in pile strength, but with the construction method of the present invention, the steel pipe pile can be made thinner while ensuring sufficient reinforcement strength. In this respect, it is also advantageous in terms of cost reduction due to the small diameter holes of steel pipe piles.
〔第1実施例〕 次に第1実施例を説明する。[First example] Next, a first embodiment will be described.
第1図は種々の地上構造物の基礎とするソイルセメント
合成鋼管杭を示し、(1)は鋼管杭、(2)はソイルセ
メント柱、(3)は補強用のコンクリート層である。Figure 1 shows soil-cement synthetic steel pipe piles used as the foundations of various above-ground structures, where (1) is a steel pipe pile, (2) is a soil-cement column, and (3) is a reinforcing concrete layer.
施設工法としては、先ずオーガにより地盤(4)に縦孔
を削孔しながらセメントミルクを注入して、その縦孔に
ソイルセメント柱(2)を形成し、そのソイルセメント
柱(2)が硬化する前にソイルセメント柱(2)の内部
に鋼管杭(1)を同芯状に挿入設置する。As for the facility construction method, first, cement milk is injected while drilling a vertical hole in the ground (4) with an auger, a soil cement column (2) is formed in the vertical hole, and the soil cement column (2) is hardened. Before this, the steel pipe piles (1) are inserted and installed concentrically inside the soil cement columns (2).
その後、縦孔の上端部において、環状に形成された既成
のコンクリート層(3)を、ソイルセメント柱(2)の
上端に載置する状態で鋼管杭(1)頭部に対し外嵌状に
配置し、そして、コンクリート層(3)と鋼管杭(1)
との間にモルタルやコンクリート(5)を充填して両者
を一体化する。After that, at the upper end of the vertical hole, the ring-shaped ready-made concrete layer (3) is placed on the upper end of the soil cement column (2) and fitted over the head of the steel pipe pile (1). Place and then concrete layer (3) and steel pipe pile (1)
Fill the gap with mortar or concrete (5) to integrate the two.
尚、既成コンクリート層(3)には、pc鋼棒等を用い
てプレストレスを与えたものを使用するのが好しい。In addition, it is preferable to use a pre-formed concrete layer (3) that has been prestressed using a PC steel rod or the like.
又、鋼管杭(1)の頭部には、その外周に多数のリプ(
6)を付設しておき、これによって、モルタル・コンク
リート充填によるコンクリート層(3)と鋼管杭(1)
との一体化をより確実にする。In addition, the head of the steel pipe pile (1) has many lips (
6) is attached, and with this, the concrete layer (3) filled with mortar and concrete and the steel pipe pile (1)
to ensure greater integration with the
〔第2実施例〕 次に第2実施例を説明する。[Second example] Next, a second embodiment will be explained.
第2図は同じくソイルセメント合成鋼管杭を示すが、こ
のものの施設工法としては、ソイルセメント柱(2)の
内部に鋼管杭(1)を挿入設置した後、縦孔の上端部に
おいて鋼管杭(1)頭部の外周部にコンクリートを充填
して補強用の環状コンクリート層(3)を現場で形成す
る。Figure 2 also shows a soil cement synthetic steel pipe pile, but the construction method for this facility is to insert and install the steel pipe pile (1) inside the soil cement column (2), and then install the steel pipe pile (1) at the upper end of the vertical hole. 1) Fill the outer periphery of the head with concrete to form a reinforcing annular concrete layer (3) on site.
尚、鋼管杭(1)頭部の外周面には、多数のリブ(6)
を付設しておくと共に、複数のpc鋼棒(7)を立てた
フランジ(8)をコンクリート層(3)の下部に対応す
る位置に予め付設しておき、そして、コンクリート層(
3)の形成後、コンクリート層(3)の上端面に載置し
たフランジ(9)を反力支点としてpc鋼棒(7)に引
上げ荷重を付与し、それによって補強用コンクリート層
(3)にプレストレスを与える。In addition, there are many ribs (6) on the outer peripheral surface of the head of the steel pipe pile (1).
At the same time, a flange (8) with a plurality of PC steel rods (7) erected thereon is attached in advance at a position corresponding to the bottom of the concrete layer (3).
After forming 3), a lifting load is applied to the PC steel bar (7) using the flange (9) placed on the upper end surface of the concrete layer (3) as a reaction force fulcrum, thereby causing the reinforcing concrete layer (3) to Gives prestress.
次にその他の実施例を列記する。 Next, other examples will be listed.
(イ)本発明によるソイルセメント合成鋼管杭の施設工
法を実施するに、補強用の環状コンクリート層(3)を
予め一体付設した鋼管杭(1)を用いるようにしても良
い。(a) When carrying out the soil cement synthetic steel pipe pile construction method according to the present invention, a steel pipe pile (1) to which a reinforcing annular concrete layer (3) is attached in advance may be used.
(0) fal管抗(1)とコンクリート層(3)との
具体的一体化構造は種々の改良が可能である。(0) Various improvements can be made to the specific integrated structure of the fal pipe shaft (1) and the concrete layer (3).
(ハ)コンクリート層(3)にプレストレスを付与して
おく場合、その具体的手段及びプレストレス付与構造は
種々の改良が可能である。(c) When applying prestress to the concrete layer (3), various improvements can be made to the specific means and structure for applying prestress.
(=)鋼管杭(1)の内部にもソイルセメントを充填し
ても良い。又、その場合、抗頭部において、鋼管杭(1
)の外周部のみならず内部にも補強用コンクリート層を
形成するようにしても良い。(=) Soil cement may also be filled inside the steel pipe pile (1). In that case, steel pipe piles (1
) may be formed with a reinforcing concrete layer not only on the outer periphery but also on the inside.
(ネ)補強用コンクリート層(3)の径は必要に応じて
適宜決定すれば良く、又、上下長さ寸法は、鋼管杭(1
)における曲げモーメントの分布特性等を考慮して適宜
決定すれば良い。(n) The diameter of the reinforcing concrete layer (3) may be determined as necessary, and the vertical length dimension of the steel pipe pile (1
) may be determined as appropriate, taking into consideration the distribution characteristics of the bending moment.
尚、特許請求の範囲の項に図面との対照を便利にするた
めに符号を記すが、該記入により本発明は添付図面の施
設形態に限定されるものではない。Incidentally, although reference numerals are written in the claims section for convenient comparison with the drawings, the present invention is not limited to the facility form shown in the accompanying drawings.
第1図は本発明の第1実施例を示す断面図であり、第2
図は本発明の第2実施例を示す断面図である。
(1)・・・・・・鋼管杭、(2)・・・・・・ソイル
セメント柱、(3)・・・・・・コンクリート層。FIG. 1 is a sectional view showing a first embodiment of the present invention, and a second embodiment of the present invention is shown in FIG.
The figure is a sectional view showing a second embodiment of the present invention. (1)... Steel pipe pile, (2)... Soil cement column, (3)... Concrete layer.
Claims (1)
イルセメント柱(2)の内部に鋼管杭(1)を配設した
ソイルセメント合成鋼管杭の施設工法であって、前記縦
孔の上端部において、前記ソイルセメント柱(2)の上
端に連ねる状態で前記鋼管杭(1)の外周部に環状コン
クリート層(3)を付設するソイルセメント合成鋼管杭
の施設工法。 2、前記環状コンクリート層(3)を前記鋼管杭(1)
に予め一体付設してある請求項1記載のソイルセメント
合成鋼管杭の施設工法に使用する鋼管杭。[Claims] 1. A soil cement composite steel pipe pile facility in which a vertical hole is formed in the ground (4) and a steel pipe pile (1) is arranged inside a soil cement column (2) formed in the vertical hole. A soil-cement composite steel pipe pile, which is a construction method in which a ring-shaped concrete layer (3) is attached to the outer periphery of the steel pipe pile (1) in a state that it is connected to the top end of the soil-cement column (2) at the top end of the vertical hole. facility construction method. 2. The annular concrete layer (3) is attached to the steel pipe pile (1)
A steel pipe pile for use in a facility construction method for a soil cement synthetic steel pipe pile according to claim 1, wherein the steel pipe pile is integrally attached in advance to the soil cement synthetic steel pipe pile.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8050288A JPH01250524A (en) | 1988-03-31 | 1988-03-31 | Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8050288A JPH01250524A (en) | 1988-03-31 | 1988-03-31 | Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH01250524A true JPH01250524A (en) | 1989-10-05 |
Family
ID=13720084
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8050288A Pending JPH01250524A (en) | 1988-03-31 | 1988-03-31 | Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH01250524A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH07259084A (en) * | 1994-03-15 | 1995-10-09 | Giken Seisakusho Co Ltd | Pile, pile wall, and constructing method for pile wall |
-
1988
- 1988-03-31 JP JP8050288A patent/JPH01250524A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH07259084A (en) * | 1994-03-15 | 1995-10-09 | Giken Seisakusho Co Ltd | Pile, pile wall, and constructing method for pile wall |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5826387A (en) | Pier foundation under high unit compression | |
| JP3689840B2 (en) | Seismic reinforcement method for existing structure foundation | |
| JP7381781B2 (en) | pile foundation structure | |
| JPH02232416A (en) | Foundation pile structure | |
| JP2000265484A (en) | Construction method of underground structure by PCa pile ground wall | |
| JP3603130B2 (en) | Root-wound reinforcement structure for column bases such as steel columns | |
| KR20190077888A (en) | Composite phc pile for soil retaining wall | |
| JPH01250524A (en) | Facility construction method for soil cement synthetic steel pipe piles and steel pipe piles used in the construction method | |
| JP3943527B2 (en) | Concrete storage tank and its construction method | |
| JP4612422B2 (en) | Construction method of structure and foundation structure used for it | |
| JP5008683B2 (en) | Pile head reinforcement member and pile head reinforcement structure using it | |
| JPH0291315A (en) | Method for reinforcing the pile head of a cylindrical pile | |
| CN210562273U (en) | Foundation for bearing assembly type elevator | |
| JPH0314483Y2 (en) | ||
| JPH0232417B2 (en) | ||
| JPS62268423A (en) | Construction work of underground pile used in common for earth anchor | |
| JP2903873B2 (en) | Beam joint structure of centrifugally formed hollow PC column | |
| JP2000297480A (en) | Reinforcing method for steel-pipe structure column base section | |
| JPH0562161B2 (en) | ||
| JPH0243848B2 (en) | ||
| JP2005105812A (en) | Pile head reinforcement member and pile head reinforcement structure using it | |
| JPH0452320A (en) | Pedestal | |
| JP2006009258A (en) | Column-beam joining structure, construction method of column-beam joining structure, construction method of underground structure and building | |
| JPH07150554A (en) | Steel pipe pile and steel pipe pile installation method | |
| JPH0726569A (en) | Pile foundation construction method for structures subjected to uneven earth pressure |