JPH01287366A - Construction of reinforced concrete structure - Google Patents
Construction of reinforced concrete structureInfo
- Publication number
- JPH01287366A JPH01287366A JP11627088A JP11627088A JPH01287366A JP H01287366 A JPH01287366 A JP H01287366A JP 11627088 A JP11627088 A JP 11627088A JP 11627088 A JP11627088 A JP 11627088A JP H01287366 A JPH01287366 A JP H01287366A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- mortar
- steel
- plates
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011150 reinforced concrete Substances 0.000 title abstract description 3
- 238000010276 construction Methods 0.000 title 1
- 239000004567 concrete Substances 0.000 claims abstract description 54
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 24
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 17
- 239000010959 steel Substances 0.000 claims abstract description 17
- 238000000034 method Methods 0.000 claims abstract description 9
- 238000009415 formwork Methods 0.000 claims description 21
- 238000005266 casting Methods 0.000 claims description 7
- 239000004568 cement Substances 0.000 abstract 2
- 239000011083 cement mortar Substances 0.000 abstract 2
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
【発明の詳細な説明】
(a)、産業上の利用分野
本発明は梁、柱等の構築に際して適用することの出来る
鉄骨コンクリート構造物の構築方法に関する。DETAILED DESCRIPTION OF THE INVENTION (a) Field of Industrial Application The present invention relates to a method for constructing a steel concrete structure that can be applied to constructing beams, columns, etc.
(b)、従来の技術
従来、H形鋼等の形鋼を平行に設置し、該設置された形
鋼の間にコンクリート・モルタル(本明細書において、
「コンクリート・モルタル」とは、「コンクリート」又
は「モルタル」の意)を打設して梁等を構築する方法が
知られている。(b), Prior Art Conventionally, section steels such as H section steels are installed in parallel, and between the installed section steels, concrete mortar (in this specification,
BACKGROUND ART A method of constructing beams, etc. by pouring "concrete mortar" (meaning "concrete" or "mortar") is known.
こうした方法では、形鋼内部に打設されるコンクリート
・モルタルと形鋼との間の付着をとる必要から、形鋼の
コンクリート・モルタルの打設される側にスタッドを植
設することが行われている。In these methods, studs are installed on the side of the section steel where the concrete and mortar will be poured, since it is necessary to maintain adhesion between the concrete and mortar placed inside the section steel. ing.
(C)8発明が解決しようとする問題点しかし、これで
は、スタッドの植設作業に多くの手間が必要となる不都
合が有った。(C) 8 Problems to be Solved by the Invention However, this method has the disadvantage that a lot of effort is required to install the studs.
本発明は、前述の欠点を解消すべく、スタッドの植設作
業を不要とする鉄骨コンクリート構造物の構築方法を提
供することを目的とするものである。SUMMARY OF THE INVENTION In order to eliminate the above-mentioned drawbacks, the present invention aims to provide a method for constructing a steel-framed concrete structure that does not require the work of installing studs.
(d)0問題点を解決するための手段
即ち、本発明は、コンクリート・モルタル打設面側に凹
凸(3d)が多数形成された型枠ブレ−ト(3)を対向
する形で設置してコンクリート打設空間(7)を形成し
、該コンクリート打設空間(7)内にコンクリート・モ
ルタル(9)を打設するようにして構成される。(d) Means for solving the zero problem, that is, the present invention installs formwork plates (3) facing each other, each having a large number of irregularities (3d) formed on the concrete/mortar pouring surface side. to form a concrete placement space (7), and concrete mortar (9) is placed within the concrete placement space (7).
なお、括弧内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下のr (el
、作用」の欄についても同様である。Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions on the drawings. The following r (el
The same applies to the column ``, action''.
(e)0作用
即ち、本発明は、型枠プレート(3)に形成された凹凸
(3d)が、コンクリート・モルタルと型枠プレート(
3)との間の付着を取るように作用する。(e) 0 action, that is, the present invention is such that the unevenness (3d) formed on the formwork plate (3) is different from the concrete mortar and the formwork plate (
3) It acts to remove the adhesion between.
(f)、実施例 以下、本発明の実施例を図面に基づき説明する。(f), Example Embodiments of the present invention will be described below based on the drawings.
第1図は本発明による鉄骨コンクリート構造物の構築方
法の一実施例が適用された鉄骨コンクリート梁の一例を
示す断面図である。FIG. 1 is a sectional view showing an example of a steel-framed concrete beam to which an embodiment of the method for constructing a steel-framed concrete structure according to the present invention is applied.
鉄骨コンクリート構造物としての鉄骨コンクリート梁l
は、第1図に示すように、上層スラブ2の下面に設けら
れており、鉄骨コンクリート梁1は鋼製の型枠プレート
3.3を有している。型枠プレート3.3は互いに対向
する形で、紙面と直角方向に伸延する形で設けられてお
り、該型枠プレート3は、上下に設けられたフランジ部
3a。Steel concrete beams as steel concrete structures
As shown in FIG. 1, is provided on the lower surface of the upper slab 2, and the steel concrete beam 1 has a steel formwork plate 3.3. The formwork plates 3.3 are provided to face each other and extend in a direction perpendicular to the plane of the paper, and the formwork plates 3 have flange portions 3a provided above and below.
3aを有している。フランジ部3a13a間にはリブ鋼
板等からなるウェブ部3bが両者を接続する形で設けら
れており、ウェブ部3bのコンクリート・モルタルの打
設されろ側の表面には凹凸3dが多数形成されている。3a. A web portion 3b made of a ribbed steel plate or the like is provided between the flange portions 3a13a to connect the two, and a large number of irregularities 3d are formed on the surface of the web portion 3b on the side where concrete/mortar is to be poured. There is.
図中上方のフランジ部3aの上面には、該型枠プレート
3とスラブ2を接続するスタッド3Cが多数、紙面と直
角方向に所定の間隔で植設されており、更に型枠プレー
ト3.3の下方のフランジ部3a、3a間には、敷プレ
ート6が両者の間に生じる間隙5を閉塞する形で設けら
れている。また、型枠プレート3.3、敷プレート6及
びスラブ2下面の間で形成されるコンクリート打設空間
7内にはコンクリート・モルタル9が打設されている。On the upper surface of the flange portion 3a in the upper part of the figure, a large number of studs 3C for connecting the formwork plate 3 and the slab 2 are planted at predetermined intervals in the direction perpendicular to the plane of the paper, and the formwork plate 3.3 A bottom plate 6 is provided between the lower flange portions 3a, 3a so as to close the gap 5 created between the two. Further, concrete mortar 9 is placed in a concrete placement space 7 formed between the formwork plate 3.3, the bed plate 6, and the lower surface of the slab 2.
鉄骨コンクリート梁1は以上のような構成を有するので
、該梁を構築する際には、まず型枠プレート3を、該型
枠プレート3を構成するフランジ部3a、3aと凹凸3
dの形成されたウェブ部3bを溶接接続することにまり
製作する。凹凸3dの形成されたウェブ部3bを構成す
る鋼板は、リブ鋼板等として市販されているので、型枠
プレート3は簡単に製作することが出来る。こうして型
枠プレート3を製作したところで、第1rEiに示すよ
うに、型枠プレート3.3を互いに対向する形でスラブ
2下方に配置しくなお、この時点で、スラブ2の部分に
はコンクリート・モルタルは打設されておらず、スラブ
2部分のコンクリート・モルタルの打設は、梁1に対す
る打設と同時に行われる)、更に型枠プレート3.3の
間に敷プレート6を設置する。すると、該敷プレート6
、型枠プレート3.3によりコンクリート打設空間7が
形成されるので、該コンクリート打設空間7内に、コン
クリート・モルタル9を、上層スラブ2部分と共に打設
し、鉄骨コンクリート梁1の構築を完了させる。こうし
て、打設凝固したコンクリート・モルタル9と型枠プレ
ート3との間の付着は、型枠プレート3のウェブ部3b
に形成された凹凸3dにより、良好な状態に生成される
。Since the steel-framed concrete beam 1 has the above-mentioned configuration, when constructing the beam, first the formwork plate 3 is assembled with the flanges 3a, 3a and the unevenness 3 constituting the formwork plate 3.
The web portion 3b formed in d is welded and connected. Since the steel plate constituting the web portion 3b having the unevenness 3d is commercially available as a rib steel plate or the like, the formwork plate 3 can be easily manufactured. After forming the form plate 3 in this way, as shown in 1rEi, the form plate 3.3 is placed below the slab 2 so as to face each other. At this point, the slab 2 is covered with concrete and mortar. (The concrete and mortar for the slab 2 portion is placed at the same time as the pouring for the beam 1), and a paving plate 6 is installed between the formwork plates 3.3. Then, the floor plate 6
Since a concrete casting space 7 is formed by the formwork plate 3.3, concrete mortar 9 is poured into the concrete casting space 7 together with the upper slab 2 portion, and the steel-framed concrete beam 1 is constructed. complete it. In this way, the adhesion between the poured and solidified concrete mortar 9 and the formwork plate 3 is maintained at the web portion 3b of the formwork plate 3.
Due to the unevenness 3d formed on the surface, it is generated in a good condition.
なお、上述の実施例は、本発明を鉄骨コンクリート梁1
を構築する際に適用した場合ついて述べたが、本発明は
鉄骨コンクリート梁1に限ること無く、型枠プレートに
よりコンクリート打設空間を形成し、該コンクリート打
設空間内にコンクリート・モルタルを打設する限り、柱
等、各種の鉄筋コンクリート構造に適用することが出来
ることは勿論である。Note that the above-mentioned embodiments describe the present invention as a steel-framed concrete beam 1.
Although the present invention is not limited to the steel-framed concrete beam 1, it can also be applied to forming a concrete casting space using a formwork plate, and pouring concrete and mortar into the concrete casting space. It goes without saying that it can be applied to various types of reinforced concrete structures such as columns.
(g)0発明の効果
以上、説明したように、本発明によれば、コンクリート
・モルタル打設面側に凹凸3dが多数形成された型枠プ
レート3を対向する形で設置してコンクリート打設空間
7を形成し、該コンクリート打設空間7内にコンクリー
ト・モルタル9を打設するようにして構成したので、型
枠プレート3とコンクリート・モルタルとの間の付着は
、凹凸3dを介して取ることが出来、わざわざスタッド
等を植設する手間を無くすことが可能となる。(g) 0 Effects of the Invention As explained above, according to the present invention, concrete is poured by installing formwork plates 3 facing each other, each having a large number of unevenness 3d formed on the concrete/mortar pouring surface side. Since the space 7 is formed and the concrete/mortar 9 is placed in the concrete placing space 7, the adhesion between the formwork plate 3 and the concrete/mortar is achieved through the unevenness 3d. This makes it possible to eliminate the trouble of installing studs, etc.
第1図は本発明による鉄骨コンクリート構造物の構築方
法の一実施例が適用された鉄骨コンクリート梁の一例を
示す断面図である。
1・・・・・・鉄骨コンクリート構造物(鉄骨コンクリ
ート梁)
3・・・・・・型枠プレート
3d・・・・・・凹凸
7・・・・・・コンクリート打設空間FIG. 1 is a sectional view showing an example of a steel-framed concrete beam to which an embodiment of the method for constructing a steel-framed concrete structure according to the present invention is applied. 1... Steel concrete structure (steel concrete beam) 3... Formwork plate 3d... Unevenness 7... Concrete pouring space
Claims (1)
れた型枠プレートを対向する形で設置してコンクリート
打設空間を形成し、 該コンクリート打設空間内にコンクリート ・モルタルを打設するようにして構成した鉄骨コンクリ
ート構造物の構築方法。[Scope of Claims] A concrete casting space is formed by installing formwork plates having a large number of unevenness formed on the concrete/mortar casting surface so as to face each other, and concrete/mortar is placed within the concrete casting space. A method of constructing a steel concrete structure constructed by pouring.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63116270A JPH0749708B2 (en) | 1988-05-13 | 1988-05-13 | Form plate and method for constructing steel-concrete beam using the same |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63116270A JPH0749708B2 (en) | 1988-05-13 | 1988-05-13 | Form plate and method for constructing steel-concrete beam using the same |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01287366A true JPH01287366A (en) | 1989-11-20 |
| JPH0749708B2 JPH0749708B2 (en) | 1995-05-31 |
Family
ID=14682921
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63116270A Expired - Lifetime JPH0749708B2 (en) | 1988-05-13 | 1988-05-13 | Form plate and method for constructing steel-concrete beam using the same |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0749708B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104563392B (en) * | 2014-10-31 | 2016-08-24 | 华南理工大学 | The regenerative mixed beam of a kind of built-in box shaped steel and construction technology thereof |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5390612A (en) * | 1977-01-20 | 1978-08-09 | Kajima Corp | Building frame construction |
| JPS6145042A (en) * | 1984-08-06 | 1986-03-04 | 清水建設株式会社 | Mold frame for casting concrete |
-
1988
- 1988-05-13 JP JP63116270A patent/JPH0749708B2/en not_active Expired - Lifetime
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5390612A (en) * | 1977-01-20 | 1978-08-09 | Kajima Corp | Building frame construction |
| JPS6145042A (en) * | 1984-08-06 | 1986-03-04 | 清水建設株式会社 | Mold frame for casting concrete |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0749708B2 (en) | 1995-05-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH01287366A (en) | Construction of reinforced concrete structure | |
| JP2002038420A (en) | Corrugated steel plate for bridge | |
| JP2004116059A (en) | Construction method of corrugated steel web bridge | |
| JPH083928A (en) | Connection material structure of precast floor slab | |
| JP3026058B2 (en) | PC composite floor slab | |
| US2268822A (en) | Ceiling construction | |
| JP2776216B2 (en) | Architectural frame | |
| JPH0334963Y2 (en) | ||
| JPH026901B2 (en) | ||
| JP2864905B2 (en) | Precast wall joining method | |
| JP6630776B2 (en) | Construction method of slab structure | |
| JPS583848Y2 (en) | Prestressed concrete girder for road bridge | |
| JPH0528294B2 (en) | ||
| JPS6025590B2 (en) | Method for joining old and new concrete using studded plates | |
| JP2857815B2 (en) | Joining method for heterogeneous structural members | |
| JP2536250Y2 (en) | Steel foundation beam | |
| JPH0113122Y2 (en) | ||
| JPH086383B2 (en) | Floor construction method | |
| JP3028422U (en) | Flat slab column support structure | |
| JPH0218088Y2 (en) | ||
| JP2917433B2 (en) | Precast beam formwork and beam construction method | |
| JPH04343952A (en) | Floor slab, pc floor board, and constructing method of floor slab | |
| JPH0634491Y2 (en) | Formwork and floor slab | |
| JPH1181485A (en) | Artificial land and its construction method | |
| JPS597365Y2 (en) | Edge structure of concrete slab at road joint |