JPH02140329A - Prefabricated underground structure - Google Patents
Prefabricated underground structureInfo
- Publication number
- JPH02140329A JPH02140329A JP1262637A JP26263789A JPH02140329A JP H02140329 A JPH02140329 A JP H02140329A JP 1262637 A JP1262637 A JP 1262637A JP 26263789 A JP26263789 A JP 26263789A JP H02140329 A JPH02140329 A JP H02140329A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- block
- screwed
- steel
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は立坑等の潜函地下構造物、特に山留工法と、そ
の後の現場施工を必要とする地下構造物をプレハブ化し
た製品を用いて施工する工法及びそれに使用するプレハ
ブ地下構造物に関する。[Detailed Description of the Invention] [Industrial Field of Application] The present invention is directed to the use of prefabricated products for underground underground structures such as vertical shafts, especially underground structures that require the pile construction method and subsequent on-site construction. Concerning construction methods and prefabricated underground structures used therein.
〔従来の技術]
立坑やピア等の地下躯体構造物は、潜函工法によって埋
没されることが多い。[Prior Art] Underground structures such as shafts and piers are often buried using the underground box construction method.
ここで潜函工法とは、構造物自体を地上で構築し、ある
いはプレハブ化した製品を所定の構造に組立てた後に地
下に沈埋させる工法をいう。Here, the submerged box construction method refers to a construction method in which the structure itself is built above ground, or prefabricated products are assembled into a predetermined structure and then buried underground.
ところで潜函掘削地盤の土質によっては、安全性との関
連もあって、失板、コルゲート又は連続壁工法等によっ
て周辺地盤を保護し、更に盤周辺の弛みや理水等の防止
対策が必要となる。これ等の対策には、地盤改良、排水
歪場、ウェルポイント、及びアンダーピニング等の施工
が工事の進行に伴って必要となり、経済性、安全性、迅
速性等に問題点を併発する。By the way, depending on the soil quality of the ground where the submersible is excavated, it is necessary to protect the surrounding ground by using board loss, corrugated or continuous wall construction methods, etc., and also to take preventive measures such as loosening around the board and water removal. . These countermeasures require construction such as ground improvement, drainage strain field, well points, and underpinning as the construction progresses, which creates problems in terms of economy, safety, speed, etc.
また躯体沈埋後の基礎構造は後打ち現場施工の鉄筋コン
クリート構造等とする必要があり、埋設後の底版鉄筋コ
ンクリートの施工中の湧水処理は、通常、地下水面下に
おける地下構造物の内部で施工するようになるため、十
分な管理の下でコンクリート打込みが行えず、水密性に
欠けるコンクリートの施工となり、漏水等の欠陥を生ず
るおそれを残す。該工事を矢板工法等と併用する場合に
は本躯体と矢板、中梁等の所要幅を加えた敷地面積を必
要とし、加えて路上での工事に際しては交通上のため復
興板を仮置して施工を進める必要があり、復興板の路上
での使用は交通の円滑を欠くので、短時間の工事完成が
要請されている。In addition, the foundation structure after the building frame is buried must be a reinforced concrete structure that is constructed on-site afterwards, and spring water treatment during the construction of the reinforced concrete bottom plate after burial is usually carried out inside the underground structure below the groundwater table. As a result, concrete cannot be poured under sufficient supervision, resulting in concrete that lacks watertightness, leaving the risk of defects such as water leakage. If this construction is used in conjunction with the sheet pile construction method, etc., a site area that includes the main frame and the required width of the sheet piles, center beams, etc. will be required, and in addition, when construction is carried out on the street, reconstruction boards will be temporarily placed for traffic reasons. It is necessary to proceed with the construction, and since using reconstruction boards on the road will hinder smooth traffic flow, it is requested that the construction be completed in a short time.
本発明は上記した欠点を補い安全で経済的でしかも迅速
なる作業が行えるプレハブ地下構造物を提供することを
目的とする。SUMMARY OF THE INVENTION It is an object of the present invention to provide a prefabricated underground structure that overcomes the above-mentioned drawbacks and allows for safe, economical, and quick work.
本発明は前記した目的を達成せんとするもので、その手
段は、少なくとも四隅に連通孔が形成されたプレハブ側
塊と、上記プレハブ側塊の連通孔と連通される連通孔に
定着金具が埋没された最下部側塊と、積重ね状態におけ
る側塊の上記連通孔の内の少なくとも2つ以上の連通孔
内に挿入され、下端が上記定着金具に螺合され、上端が
最上部側塊より突出されナツトが螺合されて側塊を一体
化するPC鋼棒と、積重ね状態における側塊の上記連通
孔の上記PC銅棒が挿入されていな上記連通孔内に挿入
され、下端が上記定着金具に螺合され、上端が最上部側
塊より突出されて排水管及びグラウト管として利用され
る鋼管ととを具備したプレハブ地下構造物を要旨とする
ものである。The present invention aims to achieve the above-mentioned object, and its means include a prefabricated block having communicating holes formed in at least four corners, and a fixing fitting embedded in the communicating hole communicating with the communicating hole of the prefabricated block. inserted into at least two or more of the communication holes of the side blocks in the stacked state, the lower end is screwed to the fixing metal fitting, and the upper end protrudes from the uppermost side block. A PC steel rod with a nut screwed together to integrate the side blocks, and a PC copper rod in the communication hole of the side block in the stacked state are inserted into the communication hole in which the PC copper rod is not inserted, and the lower end is connected to the fixing metal fitting. The gist of this is a prefabricated underground structure comprising a steel pipe which is screwed together with a steel pipe whose upper end protrudes from the uppermost block and is used as a drainage pipe and a grout pipe.
以下、実施例を図面と共に説明するに第1.2図におい
て1〜4は平面形状が四角形若しくは多角形に形成され
たプレハブコンクリート製の側塊にして、最下部側塊l
上に上部側塊2.3.4を順次積重したものである。Hereinafter, the embodiment will be explained with reference to the drawings. In Fig. 1.2, 1 to 4 are side blocks made of prefabricated concrete having a rectangular or polygonal planar shape.
The upper side blocks 2.3.4 are stacked one after another on top.
そして、最上部側塊4にはマンホール出入口孔5aを有
する床版塊5が載架されている。A floor slab block 5 having a manhole entrance/exit hole 5a is mounted on the uppermost block 4.
6は底版コンクリートにして、潜函工法により最下部側
塊1等が沈下した後、現場にて施工される。6 will be made of concrete bottom slab and will be constructed on site after the lowest block 1 has settled using the submerged box construction method.
なお、最下部側塊1は、潜函工法による沈下時に側塊周
辺の土壌によるIY擦低抵抗緩和させ、沈下を容易にす
るために他の側塊2〜4よりも外壁面に段差をつけ、土
砂と側塊との摩擦力の低減を図っている。In addition, the lowermost side block 1 is provided with a step on the outer wall surface compared to the other side blocks 2 to 4 in order to reduce IY friction resistance due to the soil around the side block and to facilitate settlement during subsidence by the submerged box construction method. Efforts are being made to reduce the frictional force between the earth and sand and the side blocks.
また、各側塊1〜4の各水平接合面には、全周に亘って
段部1a、2a、3aが形成され、これに可W性ゴム7
やエポキシ樹脂を含浸したスポンジ8を配置し、側塊間
の接着効果と漏水防止を図っている。In addition, stepped portions 1a, 2a, and 3a are formed around the entire circumference on each horizontal joint surface of each of the side blocks 1 to 4, and a W flexible rubber 7 is formed on the stepped portions 1a, 2a, and 3a.
A sponge 8 impregnated with epoxy resin is placed to provide adhesion between the side blocks and prevent water leakage.
さらに、各側塊2〜4及び床版塊5の少なくとも四隅に
は垂直な連通孔1b、2b、3b、4b5bが形成され
ると共に最下部側塊1には最下部に近い点で外側に開口
を有する外通孔1cが形成され、この外通孔1cに定着
金具9.9′が形成されている。Furthermore, vertical communication holes 1b, 2b, 3b, 4b5b are formed in at least the four corners of each of the side blocks 2 to 4 and the slab block 5, and the lowest side block 1 has an opening outward at a point near the bottom. An external through hole 1c is formed, and a fixing fitting 9.9' is formed in this external through hole 1c.
なお、定着金具9,9′は実施例として、第45図に示
すものがあり、第4回においては′P梨型状ものが、又
第5図においては箱状のものが夫々コンクリート内に埋
没されている。Examples of the fixing metal fittings 9 and 9' are shown in Fig. 45; in the fourth article, a pear-shaped one was used, and in Fig. 5, a box-shaped one was installed in the concrete. It is buried.
次に施工法(本実施例では地下マンホールの場合)につ
いて説明する。Next, the construction method (in the case of an underground manhole in this example) will be explained.
先ず、地上において、側塊1〜4を上記した如く可塑性
ゴム7やスポンジ8を介在させながら順次積重ねる。こ
の時、各側塊1〜4の各連通孔1b〜4bは各々1本の
孔として連通される。First, on the ground, the side blocks 1 to 4 are sequentially stacked with the plastic rubber 7 or sponge 8 interposed therebetween as described above. At this time, each of the communication holes 1b to 4b of each of the side blocks 1 to 4 is communicated as one hole.
次いで最下部側塊4の各連通孔4bから鋼管10を定着
金具9まで貫通し、該鋼管10の下端螺子部を螺合する
と共に、定着金具9の内部側にプラグ20を螺合せしめ
る。Next, the steel pipe 10 is passed through each communication hole 4b of the lowermost block 4 to the fixing fitting 9, and the lower end threaded portion of the steel pipe 10 is screwed together, and the plug 20 is screwed into the inside of the fixing fitting 9.
また、残りの連通孔にはPC鋼棒10′を定着金具9′
まで貫通し、該PC鋼棒10′の下端螺合部にナンド1
1を螺合し、その後、モルタル等の固着剤12によって
十分な水密性を保って密閉する。In addition, the PC steel rod 10' is attached to the fixing metal fitting 9' in the remaining communication hole.
The NAND 1 is inserted into the threaded portion of the lower end of the PC steel bar
1 are screwed together, and then sealed with a fixing agent 12 such as mortar to maintain sufficient watertightness.
そして、定着金具9に連通ずる外通孔1c、あるいは定
着金具9′からソケ71□ 22を介して連通ずる外通
孔1この外側に開口された部分には、フィルター13を
外側から装着する。そして、側塊の全てが積重ねられて
から最上部側塊4の連通孔4bから突出した鋼管10及
びPC鋼棒10′にナツト14をもって仮締固定し、こ
れにより側塊1〜4を一体化する。なお、鋼管1oにナ
ツト14を螺合する際には定着板19も一体に固定され
る。A filter 13 is attached from the outside to the external through hole 1c that communicates with the fixing metal fitting 9 or the external through hole 1 that communicates with the fixing metal fitting 9' via the socket 71□22. After all of the side blocks are stacked, the steel pipe 10 and PC steel bar 10' protruding from the communication hole 4b of the uppermost side block 4 are temporarily tightened with nuts 14, thereby integrating the side blocks 1 to 4. do. Note that when screwing the nut 14 onto the steel pipe 1o, the fixing plate 19 is also fixed integrally.
次ニ、PC鋼棒10′の上部にセンターホール油圧ジヤ
ツキを挿入し、鋼管引張り強度の許容応力度範囲でPC
鋼棒10′の緊張を行い、ナンド14をもって本締めを
なす。Next, insert a center hole hydraulic jack into the upper part of the PC steel bar 10', and set the PC in the allowable stress range of the steel pipe tensile strength.
The steel rod 10' is tensioned and finally tightened using the Nand 14.
鋼管10にナツト14で締め付けられる定着板19はグ
ラウト穴21を有し鋼管1oの周囲の充填に役立てる効
果と銅管10を固定する役目を併用する。尚、グラウト
・穴にはナツト2ビ締めも可能である(第4図)。また
、第5図に示す12′もグラウト穴であるが、このプラ
ウ1−穴12’は−F−ルタルで塞いだ中に細いフレキ
シブルなビニル若しくはゴム製の管を介してモルタル注
入を行次いで、最下部側塊1に対せん断鉄筋を配置しコ
ンクリート打ち作業を行うのであるが、ここで、地盤周
辺の弛みや湧水が生じると、十分な水密性コンクリート
打ちが行えない。The fixing plate 19, which is fastened to the steel pipe 10 with a nut 14, has a grout hole 21 and serves both of the effect of filling the surrounding area of the steel pipe 1o and the role of fixing the copper pipe 10. Note that it is also possible to tighten the grout/hole with two nuts (Figure 4). Further, 12' shown in Fig. 5 is also a grout hole, but this plow 1 hole 12' is filled with -F-rutar and mortar is injected through a thin flexible vinyl or rubber pipe. , Concreting work is performed by placing shear reinforcing bars on the lowermost block 1, but if loosening or spring water occurs around the ground, sufficient water-tight concrete casting cannot be performed.
そこで本発明にあっては、上記した鋼管1oの突出先端
に真空ポンプを接続し、湧水を吸引する方法をとる。こ
の吸引排水にはフィルター13が働き鋼管10内がつま
るようなことはない。これにより、配筋やコンクリート
打ちを、地下水位下の場所においても通常の地上作業と
同じような状態の中で行うことができ、従って所定の構
造物の精度、品質、能率及び安全性を高めることができ
る。Therefore, in the present invention, a method is adopted in which a vacuum pump is connected to the protruding tip of the above-mentioned steel pipe 1o to suck spring water. A filter 13 acts on this suction waste water so that the inside of the steel pipe 10 is not clogged. This allows reinforcing and concreting to be carried out under conditions similar to normal surface work, even below the groundwater table, thus increasing the accuracy, quality, efficiency and safety of a given structure. be able to.
そして、上記のような手段によって底版のコンクリート
打ちの終了後で所定の強度が得られてから、吸引排水管
として使用した鋼管1oの突出先端を真空ポンプから外
し、今度はグラウトポンプに接続し、モルタルミルク等
のグラウト注入を行う。この時、フィルター13はグラ
ウトの圧力によって外通孔1cより排出され、グラウト
は外通孔ICの開口部周囲に流出される。Then, after completing the concreting of the bottom slab and obtaining the desired strength by the above-mentioned means, the protruding tip of the steel pipe 1o used as the suction and drainage pipe was removed from the vacuum pump, and this time it was connected to the grout pump. Inject grout using mortar milk, etc. At this time, the filter 13 is discharged from the external hole 1c by the pressure of the grout, and the grout flows out around the opening of the external hole IC.
従って最下部側塊Iの周囲及び底版底面への地盤の弛み
はグラウトによりフッパクト効果を得て、地盤周囲を改
良させ地盤沈下を十分に防止することができる。Therefore, the loosening of the ground around the lowermost mass I and the bottom of the bottom slab can be affected by grouting, improving the surroundings of the ground and sufficiently preventing ground subsidence.
次に床版塊5を最上部側塊4の上に乗せ、上記鋼管10
を利用し、ナンドで螺合し固定する。床版塊5には下部
側塊に対応する連通穴が設けられてあり、上記固定後、
耐腐蝕物キャンプを用いて末端処理を施す。Next, the floor slab block 5 is placed on top of the uppermost side block 4, and the steel pipe 10
Use a screwdriver to secure it by screwing it together. The floor slab mass 5 is provided with a communication hole corresponding to the lower side mass, and after the above-mentioned fixation,
Perform terminal treatment using corrosion-resistant camp.
床版埋土は通常、人孔凹環をもって地上と接する。地下
構造物が立坑等の場合、中梁や腹起し等の横架材を必要
とすることな(、そのまま横穴作業若しくは推進管作業
の開始が可能である。作業終了後は構造物自体がマンホ
ール躯体として利用し得るので、上記床版塊及び人孔凹
環の設置をもって工事を終了させることができる。Filled slabs usually come into contact with the ground through a manhole concave ring. If the underground structure is a vertical shaft, etc., there is no need for horizontal members such as center beams or uprights (it is possible to start horizontal tunnel work or propulsion pipe work as is. After the work is completed, the structure itself Since it can be used as a manhole frame, the construction work can be completed with the installation of the floor slab mass and manhole concave ring.
なお、側塊の施工目的が推進坑である場合には吸引排水
は推進管施工中にも続行することが可能である。後で行
うグラウト注入は、推進管周囲の地盤沈下若しくは不動
沈下の防止に寄与する。In addition, if the purpose of construction of the side block is a propulsion shaft, suction and drainage can be continued even during the construction of the propulsion pipe. The grouting performed later contributes to preventing ground subsidence or immobility settlement around the propulsion pipe.
〔発明の効果]
本発明は上記したように、積重ねた側塊の連通孔に鋼管
とP(Jl棒を挿入固定したので、特に、PC鋼棒によ
って各側塊を一体化することができると共に、鋼管を利
用して地下湧水を排水することができるので、耐圧板と
しての底版コンクリート工事が確実、かつ迅速に行え、
排水作業完了後は上記鋼管を介してグラウト注入を行い
地盤改良を為し得るので、排水やグラウトを別個の工事
として行うよりも作業時間の短縮や作業敷地面積を最少
限度の範囲で施工を容易にし、路上での交通混乱を大幅
に改善することができる。[Effects of the Invention] As described above, the present invention inserts and fixes the steel pipe and P (Jl bar) into the communication holes of the stacked side blocks, so that in particular, each side block can be integrated with the PC steel rod, and Since underground spring water can be drained using steel pipes, construction of the bottom slab concrete as a pressure plate can be done reliably and quickly.
After the drainage work is completed, grout can be injected through the steel pipes mentioned above to improve the ground, so it is easier to do the work by shortening the work time and minimizing the work site area, compared to doing drainage and grouting as separate works. This can greatly reduce traffic confusion on the roads.
実施例では40立方米の地下マンボールで、躯体設置開
始から48時間で床版塊まで完了させており、通常1力
月乃至2力月を要するとされる開削工事に比較して極め
て顕著な迅速性の効果を有する。In this example, in a 40 cubic meter underground man-hole, construction was completed from the start of the frame installation to the slab block within 48 hours, which is extremely fast compared to excavation work which normally takes 1 to 2 months. It has a sexual effect.
図は本発明に係る実施例を示し、第1図は平面図、第2
図は同上のn−n線断面図、第3図は第1図のI−II
I線断面図、第4.5図は定着金具部分の拡大図、第6
図は施工状態を示す半断面図である。
1〜4−側塊、lb、2b、3b、4b、5b連通孔、
9.9′一定着金具、10−鋼管、■OPC鋼棒。The figures show an embodiment according to the present invention, with the first figure being a plan view and the second figure being a plan view.
The figure is a sectional view taken along the line nn of the same as above, and Figure 3 is the I-II line in Figure 1.
I-line sectional view, Figure 4.5 is an enlarged view of the fixing metal part, Figure 6
The figure is a half-sectional view showing the construction state. 1 to 4-side mass, lb, 2b, 3b, 4b, 5b communicating hole,
9. 9′ fixed fitting, 10-steel pipe, ■OPC steel bar.
Claims (1)
具が埋没された最下部側塊と、 積重ね状態における側塊の上記連通孔の内の少なくとも
2つ以上の連通孔内に挿入され、下端が上記定着金具に
螺合され、上端が最上部側塊より突出されナットが螺合
されて側塊を一体化するPC鋼棒と、 積重ね状態における側塊の上記連通孔の上記PC鋼棒が
挿入されていな上記連通孔内に挿入され、下端が上記定
着金具に螺合され、上端が最上部側塊より突出されて排
水管及びグラウト管として利用される鋼管と、 とを具備したことを特徴とするプレハブ地下構造物。[Scope of Claims] A prefabricated block having communicating holes formed in at least four corners; a lowermost block having a fixing fitting embedded in a communicating hole that communicates with the communicating hole of the prefabricated block; and a side in a stacked state. It is inserted into at least two or more of the communicating holes of the block, the lower end is screwed to the fixing metal fitting, the upper end is protruded from the uppermost side block, and a nut is screwed together to integrate the side blocks. The PC steel rods are inserted into the communication holes of the side blocks in the stacked state where the PC steel rods are not inserted, the lower ends are screwed into the fixing fittings, and the upper ends are connected to the uppermost side blocks. A prefabricated underground structure characterized by comprising: a protruding steel pipe used as a drainage pipe and a grout pipe;
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1262637A JPH02140329A (en) | 1989-10-07 | 1989-10-07 | Prefabricated underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1262637A JPH02140329A (en) | 1989-10-07 | 1989-10-07 | Prefabricated underground structure |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP57233891A Division JPS59122629A (en) | 1982-12-28 | 1982-12-28 | Construction of prefabricated underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH02140329A true JPH02140329A (en) | 1990-05-30 |
| JPH0262652B2 JPH0262652B2 (en) | 1990-12-26 |
Family
ID=17378552
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1262637A Granted JPH02140329A (en) | 1989-10-07 | 1989-10-07 | Prefabricated underground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH02140329A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006097429A (en) * | 2004-09-30 | 2006-04-13 | Cti Engineering Co Ltd | Structure |
| US20130055650A1 (en) * | 2010-11-17 | 2013-03-07 | Udo Hartmann | Modular Integrated Underground Utilities Enclosure and Distribution System |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| TW314298U (en) * | 1991-12-06 | 1997-08-21 | Samsung Electronic Devices | Deflection yoke with leaking magnetic field prevention coils |
-
1989
- 1989-10-07 JP JP1262637A patent/JPH02140329A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006097429A (en) * | 2004-09-30 | 2006-04-13 | Cti Engineering Co Ltd | Structure |
| US20130055650A1 (en) * | 2010-11-17 | 2013-03-07 | Udo Hartmann | Modular Integrated Underground Utilities Enclosure and Distribution System |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0262652B2 (en) | 1990-12-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
| JP2009084919A (en) | Ground excavation method | |
| AU2001277141A1 (en) | Integrated footings | |
| CN118110193A (en) | The whole process construction method of large diameter caisson in complex geological conditions | |
| CN114837088A (en) | A kind of construction method of bearing platform on highway | |
| CN116289677B (en) | Drainage box culvert construction technology | |
| KR102190480B1 (en) | Implant pile pressing apparatus in architecture foundation system and a universal implant piling method | |
| JP4440497B2 (en) | Construction method of underground continuous wall and construction method of underground structure | |
| JPH0219252B2 (en) | ||
| CN116556374A (en) | Frame prestressed zigzag anchor plate support system | |
| JPH0262652B2 (en) | ||
| JP4695623B2 (en) | Retaining wall reinforcing structure and construction method thereof | |
| JPH07197473A (en) | Open caisson structure | |
| CN114232601A (en) | Construction method for wall of enclosing structure under pipeline | |
| JP4332651B2 (en) | Foundation reinforcement device and foundation construction method | |
| JPH0525821A (en) | Continuous underground wall and its construction method | |
| JPH0474489B2 (en) | ||
| CN119663895B (en) | But miniature steel-pipe pile assembled L type barricade structure of slip casting | |
| JP3168197B2 (en) | Caisson anchor structure and construction method | |
| JP2908764B2 (en) | Repair method around concrete structures | |
| JP2004036086A (en) | Seismic isolation structuring method from existing building ground | |
| JP3384990B2 (en) | Septic tank protection structure and construction method | |
| JP2581602B2 (en) | Waste treatment method | |
| US20080008538A1 (en) | Foundation system | |
| JP3050729U (en) | Seismic cistern |