JPH0216817B2 - - Google Patents
Info
- Publication number
- JPH0216817B2 JPH0216817B2 JP21238584A JP21238584A JPH0216817B2 JP H0216817 B2 JPH0216817 B2 JP H0216817B2 JP 21238584 A JP21238584 A JP 21238584A JP 21238584 A JP21238584 A JP 21238584A JP H0216817 B2 JPH0216817 B2 JP H0216817B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- ground
- retaining wall
- concrete frame
- earthen
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000000034 method Methods 0.000 claims description 13
- 238000009412 basement excavation Methods 0.000 claims description 6
- 239000011162 core material Substances 0.000 claims description 4
- 238000010276 construction Methods 0.000 description 11
- 230000003014 reinforcing effect Effects 0.000 description 7
- 238000009415 formwork Methods 0.000 description 5
- 239000004576 sand Substances 0.000 description 4
- 239000004570 mortar (masonry) Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 206010042008 Stereotypy Diseases 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0283—Retaining or protecting walls characterised by constructional features of mixed type
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
「産業上の利用分野」
本発明は、擁壁を構築する方法に係わり、特
に、構築に必要な用地が狭く、かつ、施工中およ
び施工後における擁壁の安定性が良好な擁壁の構
築方法に関するものである。Detailed Description of the Invention "Field of Industrial Application" The present invention relates to a method of constructing a retaining wall, and in particular, to a method for constructing a retaining wall in which the land required for construction is narrow and the stability of the retaining wall during and after construction. This article concerns how to construct a good retaining wall.
「従来の技術」
一般に、傾斜地等に道路やその他の構築物を築
く場合、傾斜地盤を掘削して(切り崩して)平地
化することが行なわれるが、このような地盤の掘
削時に形成される土壁を崩壊から守るための一手
段として、土壁を覆うようにコンクリート製の擁
壁を設けることが行なわれる。"Conventional technology" Generally, when building roads or other structures on sloped land, the sloped ground is excavated (cut down) and leveled. As a way to protect earthen walls from collapse, concrete retaining walls are installed to cover the earthen walls.
従来、このような擁壁を構築する方法として
は、例えば、第14図に示すように地盤1を線か
ら実線の如く最終レベルの深さまで一度に掘削し
た後、この掘削によつて形成された土壁2に対し
て間隔をおいた位置に、第15図実線から二点鎖
線で示す如く擁壁3を構成するコンクリート躯体
4を下から順に積み上げるように打設していき、
全てのコンクリート躯体4の打設が終了した後
に、土壁2と擁壁3との間を第15図一点鎖線の
レベルまで埋め戻す、いわゆる順巻工法が知られ
ている。 Conventionally, the method of constructing such a retaining wall is, for example, as shown in Fig. 14, after excavating the ground 1 at once from the line to the depth of the final level as shown by the solid line, Concrete frames 4 constituting the retaining wall 3 are placed at a distance from the earthen wall 2 in a stacked manner from the bottom, as shown from the solid line to the two-dot chain line in Figure 15.
A so-called sequential construction method is known in which the space between the earthen wall 2 and the retaining wall 3 is backfilled to the level indicated by the dashed-dotted line in FIG. 15 after all the concrete structures 4 have been placed.
「発明が解決しようとする問題点」
しかしながら、前述したような順巻工法では施
工中における土壁2の崩壊を防止するために、土
壁面を充分な傾斜をもつた法面に形成しなければ
ならず、この法面を形成する分だけ、すなわち、
第15図符号Wで示す幅だけ、擁壁3を構築する
ための用地が広く必要であるという難点がある。
つまり、擁壁3の構築予定地の近くに、宅地その
他の既存構造物等が存在して用地が限定される場
合には、構築作業が極めて困難になる。そして、
このような用地の問題は、地盤が軟弱で法面の勾
配が緩くなるほど、また、岩質地盤であつても風
化されて自立不能な状態となつているほど助長さ
れるからこのような地盤に擁壁3を築く場合には
何らかの解決策が必要とされている。``Problems to be solved by the invention'' However, in the above-mentioned sequential construction method, in order to prevent the earth wall 2 from collapsing during construction, the earth wall surface must be formed into a slope with a sufficient slope. However, only the amount that forms this slope, that is,
There is a drawback that the site for constructing the retaining wall 3 needs to be wide by the width indicated by the symbol W in FIG. 15.
In other words, if there is a residential lot or other existing structure near the site where the retaining wall 3 is planned to be constructed, and the land is limited, construction work becomes extremely difficult. and,
Problems like this are exacerbated as the ground becomes softer and the slope slope becomes gentler, and even if the ground is rocky, it becomes weathered and cannot stand on its own. When constructing the retaining wall 3, some kind of solution is required.
「問題点を解決するための手段」
本発明は、前記問題点を解決するために、掘削
前の地盤に支柱を埋設した後、この支柱を含む地
盤を単位深さずつ掘削しながら、掘削のたびに露
出した支柱を芯材として土壁を覆うコンクリート
躯体を打設することにより、擁壁を逆巻きするよ
うにした方法である。``Means for Solving the Problems'' In order to solve the above-mentioned problems, the present invention buries a support in the ground before excavation, and then excavates the ground including the support by a unit depth. In this method, the retaining wall is rolled backwards by placing a concrete frame covering the earthen wall using the exposed pillars as core material.
「作 法」
本発明によれば、施工中に土壁の上部がコンク
リート躯体によつて押えられるとともに、コンク
リート躯体の重量が支柱によつて支えられるた
め、土壁の法面勾配をきつくすることができる。"Mannerism" According to the present invention, the upper part of the earthen wall is held down by the concrete frame during construction, and the weight of the concrete body is supported by the supports, so that the slope slope of the earthen wall can be made steeper. Can be done.
「実施例」
以下本発明の一実施例を第1図〜第13図に基
づいて説明すれば、まず、掘削すべき地盤1にボ
ーリング孔を開け、このボーリング孔に第1図の
如く支柱(例えば鋼管等)5を建込んで支柱5と
ボーリング孔との隙間にモルタル6を充填すると
により、複数本の支柱5を水平方向(紙面と駄交
する方向)に間隔をおいて垂直状態に埋設する。
次いで、第2図に示すように
(イ) 支柱5を含む地盤1を支柱5の長さより短か
い単位深さlだけ掘削して、垂直な壁面を有す
る土壁7を形成するとともに、この土壁7に対
向する位置に支柱5の一部を露出させる。``Embodiment'' An embodiment of the present invention will be described below with reference to FIGS. 1 to 13. First, a borehole is drilled in the ground 1 to be excavated, and a support column ( For example, by erecting steel pipes (such as steel pipes) 5 and filling the gap between the pillars 5 and the borehole with mortar 6, multiple pillars 5 are buried vertically at intervals in the horizontal direction (direction that intersects with the plane of the paper). do.
Next, as shown in Fig. 2, (a) the ground 1 including the pillars 5 is excavated by a unit depth l shorter than the length of the pillars 5 to form a soil wall 7 having a vertical wall surface, and this soil A part of the support column 5 is exposed at a position facing the wall 7.
次に、第3図に示すように
(ロ) 露出した支柱5を芯材として擁壁の一部をな
すコンクリート躯体8を打設し、土壁7の壁面
をコンクリート躯体8によつて覆う。 Next, as shown in FIG. 3, (b) a concrete frame 8 forming a part of the retaining wall is cast using the exposed pillars 5 as core materials, and the wall surface of the earthen wall 7 is covered with the concrete frame 8.
そして、コンクリート躯体8が硬化したら、再
び前記(イ)の工程と同様の工程を行うことにより、
第4図の如く前記コンクリート躯体8の下の地盤
1を掘削し、さらに、前記(ロ)の工程と同様の工程
を行なうことにより、第5図の如く前記コンクリ
ート躯体8の下に新たなコンクリート躯体8を打
設する。このように(イ)、(ロ)の工程を交互に繰り返
すことにより、上から下に向かつて順次、複数の
コンクリート躯体8を連結していき、最後に、第
6図に示す如く土台となる幅の大きいコンクリー
ト躯体8を打設して擁壁9が完成する。 Then, once the concrete frame 8 has hardened, the same process as in step (a) above is performed again.
By excavating the ground 1 under the concrete frame 8 as shown in Fig. 4, and performing the same process as the step (b) above, new concrete is added under the concrete frame 8 as shown in Fig. 5. Pour the frame 8. By repeating steps (a) and (b) alternately in this way, a plurality of concrete frames 8 are successively connected from top to bottom, and finally a foundation is formed as shown in Figure 6. A retaining wall 9 is completed by pouring a wide concrete frame 8.
ここで、(ロ)の工程、すなわちコンクリート躯体
8を打設する工程について詳述すれば、第7図の
ように単位深さ分の掘削作業が終了した後、第8
図の如く、土壁7にほぼ水平状態にロツクボルト
(あるいはアースアンカー)10を埋め込んで、
壁面から突出させ、土壁7との隙間にモルタル6
を充填して固定する。次いで、第9図の如く、前
回打設したコンクリート躯体8の下側に垂直方向
および水平方向(紙面と直交する方向)に沿う鉄
筋11を配し、垂直方向の鉄筋11を前回打設し
たコンクリート躯体8の下面から突出する鉄筋1
1に、圧接部11aにおいて圧接する。しかる後
に、第10図の如く、土壁7との間で、支柱5お
よび鉄筋11を挾むように型枠12を配し、前記
ロツクボルト10にナツト13を用いて固定す
る。続いて、第11図の如く型枠12の内側に、
垂直方向の鉄筋11の下部が隠れる程の量の砂1
4を投入し、この砂の上面をならしてから、型枠
12内にコンクリートを流し込んで第12図の如
くコンクリート躯体8を打設する。そして、コン
クリートが硬化してから型枠12を取り外せば第
13図の如く一単位のコンクリート躯体8が完成
するものである。なお、前記砂14は、この後、
地盤1をさらに掘削することにより取り除かれ
て、コンクリート躯体8の下面に鉄筋11の下部
が露出する。 Here, to explain in detail the process (b), that is, the process of pouring the concrete frame 8, after the excavation work for the unit depth is completed as shown in Fig. 7,
As shown in the figure, a lock bolt (or earth anchor) 10 is embedded in the earth wall 7 in an almost horizontal state,
Mortar 6 is made to protrude from the wall surface and placed in the gap between it and the earthen wall 7.
Fill and fix. Next, as shown in Fig. 9, reinforcing bars 11 are placed in the vertical and horizontal directions (direction perpendicular to the page) below the previously cast concrete frame 8, and the vertical reinforcing bars 11 are placed under the previously cast concrete frame 8. Reinforcing bars 1 protruding from the lower surface of the frame 8
1 at the pressure contact portion 11a. Thereafter, as shown in FIG. 10, a formwork 12 is arranged between the earthen wall 7 and the pillar 5 and the reinforcing bars 11, and fixed to the lock bolt 10 using nuts 13. Next, as shown in Fig. 11, inside the formwork 12,
An amount of sand 1 that covers the bottom of the vertical reinforcing bars 11
4, and after leveling the top surface of the sand, concrete is poured into the formwork 12 and a concrete frame 8 is cast as shown in FIG. 12. When the formwork 12 is removed after the concrete has hardened, one unit of concrete frame 8 is completed as shown in FIG. 13. Note that the sand 14 is then
The ground 1 is further excavated and removed, and the lower part of the reinforcing bars 11 is exposed on the lower surface of the concrete frame 8.
このように本発明にあつては、掘削する先から
土壁7を押えつけつつ、掘削を進めていくので、
施工中に土壁7が崩れない。しかも、打設したコ
ンクリート躯体8は支柱5によつてその重量が支
えられるからコンクリート躯体8の下の地盤を掘
削する際にも安定性が良好である。従つて、第1
図〜第5図の如く、土壁7の壁面を垂直にした状
態で、すなわち、法面勾配を90゜にした状態で地
盤1を掘削することができる。 In this way, in the present invention, since the excavation proceeds while pressing down the earth wall 7 from the excavation point,
The earth wall 7 does not collapse during construction. Furthermore, since the weight of the cast concrete frame 8 is supported by the supports 5, stability is good even when the ground beneath the concrete frame 8 is excavated. Therefore, the first
As shown in Figures 5 to 5, the ground 1 can be excavated with the earth wall 7 vertical, that is, with the slope slope at 90°.
ちなみに、第6図に示すような全体が5個のコ
ンクリート躯体8からなり擁壁9について荷重条
件が最も厳しい最下段のコンクリート躯体打設前
の応力状態を調べた結果、支柱5に作用する4個
のコンクリート躯体8の重量は、支柱5の許容支
持力および支柱5とコンクリート躯体との許容付
着力の両者を下まわり、また、支柱5に生じる軸
応力も、支柱5の許容応力を下まわつた。さら
に、完成時の安定性については、ロツクボルトの
支持力を無視した状態においても常時、地震時共
に安定状態を確保できる調査結果が得られた。 By the way, as shown in Fig. 6, the entire structure consists of five concrete frames 8, and as a result of examining the stress state of the retaining wall 9 before placing the lowest concrete frame, which has the most severe load conditions, we found that The weight of each concrete frame 8 is lower than both the allowable supporting force of the column 5 and the allowable adhesive force between the column 5 and the concrete frame, and the axial stress generated in the column 5 is also lower than the allowable stress of the column 5. Ivy. Furthermore, regarding the stability upon completion, the investigation results showed that even when the supporting capacity of the rock bolts was ignored, a stable state could be ensured both at all times and during earthquakes.
「発明の効果」
以上説明したように本発明によれば、地盤に支
柱を埋設し、この支柱を含む地盤を単位深さずつ
掘削しながら露出した支柱を芯材として、擁壁を
逆巻きしていくので、次のような優れた効果を得
ることができる。"Effects of the Invention" As explained above, according to the present invention, a support is buried in the ground, and while excavating the ground containing the support in unit depths, the exposed support is used as a core material and a retaining wall is wound backwards. As a result, you can obtain the following excellent effects.
土壁面を垂直に形成できるため、擁壁の構築
に必要な用地が狭くてすみ、急斜面、岩質地盤
等に構築物を築く際の擁壁の構築法として好適
である。 Since the earth wall surface can be formed vertically, the land required for constructing the retaining wall is small, and it is suitable as a method for constructing retaining walls when constructing structures on steep slopes, rocky ground, etc.
地盤の掘削量が少なく、また、埋め戻し等の
作業が不要である。 The amount of ground excavation is small, and there is no need for backfilling or other work.
支柱によつてコンクリート躯体を支持するの
で、施工中および施工後における擁壁の安定性
が良好であり、かつ、施工中における安全性を
確保することができる。 Since the concrete frame is supported by the pillars, the stability of the retaining wall during and after construction is good, and safety during construction can be ensured.
第1図〜第6図は本発明の一実施例を工程順に
説明する垂直断面図、第7図〜第13図は本発明
におけるコンクリート躯体の打設工程の一例を説
明する拡大垂直断面図、第14図および第15図
は、従来の擁壁の構築方法を説明する垂直断面図
である。
1……地盤、5……支柱、6……モルタル、7
……土壁、8……コンクリート躯体、9……擁
壁、10……ロツクボルト、11……鉄筋、12
……型枠、14……砂。
FIGS. 1 to 6 are vertical sectional views illustrating an embodiment of the present invention in the order of steps; FIGS. 7 to 13 are enlarged vertical sectional views illustrating an example of the concrete frame casting process of the present invention; FIGS. 14 and 15 are vertical sectional views illustrating a conventional retaining wall construction method. 1... Ground, 5... Support, 6... Mortar, 7
...Earth wall, 8...Concrete frame, 9...Retaining wall, 10...Rock bolt, 11...Reinforcing bar, 12
...Formwork, 14...Sand.
Claims (1)
対し、この土壁を保護する擁壁を構築する方法に
おいて、 掘削前の地盤に支柱を埋設した後、 (イ) この支柱を含む地盤を単位深さ分掘削して土
壁に対向する位置に支柱の一部を露出させる工
程と、 (ロ) 露出した支柱を芯材として土壁を覆うコンク
リート躯体を打設する工程と、 を交互に繰り返すことにより、擁壁を上部から下
部に向けて単位長さずつ順次構築することを特徴
とする擁壁の構築方法。[Claims] 1. In a method for constructing a retaining wall to protect an earthen wall formed by excavating the ground, after burying a support in the ground before excavation, (a) this A process of excavating the ground containing the pillars to a unit depth to expose a part of the pillars at a position facing the earthen wall, and (b) a process of pouring a concrete frame to cover the earthen walls using the exposed pillars as core material. A method for constructing a retaining wall, characterized in that the retaining wall is constructed sequentially from the top to the bottom, unit length by unit length, by repeating and alternately.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21238584A JPS6192217A (en) | 1984-10-09 | 1984-10-09 | How to build a retaining wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21238584A JPS6192217A (en) | 1984-10-09 | 1984-10-09 | How to build a retaining wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6192217A JPS6192217A (en) | 1986-05-10 |
| JPH0216817B2 true JPH0216817B2 (en) | 1990-04-18 |
Family
ID=16621702
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP21238584A Granted JPS6192217A (en) | 1984-10-09 | 1984-10-09 | How to build a retaining wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6192217A (en) |
-
1984
- 1984-10-09 JP JP21238584A patent/JPS6192217A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6192217A (en) | 1986-05-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2837128B2 (en) | Construction method of cast-in-place concrete pile | |
| KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
| JP6860895B2 (en) | Retaining wall and its construction method | |
| JPH0960028A (en) | Strengthening method of existing steel pipe pile | |
| JP2868651B2 (en) | Earth retaining method above existing underground structure | |
| JP2000257088A (en) | Earth retaining wall and its construction method | |
| JPS5829922A (en) | Constructing method for underground outer wall | |
| JP3057466B2 (en) | How to build underground structures | |
| JPH0721196B2 (en) | Reverse construction method of underground structure | |
| JPS6018769B2 (en) | Construction method of underground structure | |
| JP2599299B2 (en) | Retaining wall and retaining method in soft ground | |
| JPS5851092B2 (en) | Earth retaining installation method using advance shoring frame | |
| JPH0726569A (en) | Pile foundation construction method for structures subjected to uneven earth pressure | |
| JP2657671B2 (en) | Reconstruction method for existing structures | |
| JP2811436B2 (en) | Construction method of earth retaining or fence and concrete block used in the method | |
| JP2797066B2 (en) | Solid foundation method with stabilizer | |
| JPH0790863A (en) | Retaining wall for embankment | |
| JP2506978Y2 (en) | Synthetic retaining wall | |
| JP3162654B2 (en) | Construction method of floor slab support structure in building structure using pile as pillar | |
| JP2001059228A (en) | Mat foundation structure for detached house and its constructing method | |
| JPS59233028A (en) | Residential land formation work on sloped ground | |
| JPS6024249B2 (en) | How to build a basement | |
| JPH08226126A (en) | Construction method for earth retaining wall and construction material therefor | |
| JPS6350491B2 (en) | ||
| JPH0748848A (en) | Construction method of underground skeleton by reverse construction method |