JPH02194227A - Jointing method for precast concrete pillar with pillar beam - Google Patents

Jointing method for precast concrete pillar with pillar beam

Info

Publication number
JPH02194227A
JPH02194227A JP1191989A JP1191989A JPH02194227A JP H02194227 A JPH02194227 A JP H02194227A JP 1191989 A JP1191989 A JP 1191989A JP 1191989 A JP1191989 A JP 1191989A JP H02194227 A JPH02194227 A JP H02194227A
Authority
JP
Japan
Prior art keywords
column
reinforcement
main
precast concrete
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1191989A
Other languages
Japanese (ja)
Inventor
Takeo Seguchi
瀬口 健夫
Riichi Kobayashi
小林 理市
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP1191989A priority Critical patent/JPH02194227A/en
Publication of JPH02194227A publication Critical patent/JPH02194227A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はプレキャストコンクリート柱(以下PC柱とい
う)と、半プレキャストコンクリート梁(以下半PC梁
という)との接合工法、及び同工法に使用されるPC柱
に係るものである。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is a method for joining a precast concrete column (hereinafter referred to as a PC column) and a semi-precast concrete beam (hereinafter referred to as a semi-PC beam), and a method used in the same method. This is related to the PC pillar.

(従来の技術) 従来、PC柱は柱脚部より梁下端までを工場で製作して
これを現場で建込み、同PC柱の柱頭部にPC梁の端部
を載せ、パネルゾーン内に梁主筋及び剪断補強筋を配筋
したのち、パネルゾーン形成のための外側型枠を取付け
、コンクリートを打設してPC柱梁を接合していた。
(Prior technology) Conventionally, PC columns were manufactured in a factory from the column base to the bottom end of the beam, and then erected on site. After placing the main reinforcement and shear reinforcing bars, the outer formwork for forming the panel zone was installed, concrete was poured, and the PC columns and beams were connected.

(発明が解決しようとする課題) しかしながら前記従来の工法では次のような問題点があ
った。
(Problems to be Solved by the Invention) However, the conventional construction method has the following problems.

i)パネルゾーン内のみでは梁主筋に必要な定着長が確
保できない。
i) It is not possible to secure the necessary anchorage length for the beam main reinforcement only within the panel zone.

li)パネルゾーンで梁が交叉するような場合では、P
C梁及びPC柱の各主筋は打込まれて固定されているた
め、パネルゾーン内での梁主筋の納まり、及びフープの
納まり等の面で、現場での作業は非常に困難となってい
た。
li) In cases where beams intersect in the panel zone, P
The main reinforcements of the C-beams and PC columns were driven and fixed, so it was extremely difficult to work on site in terms of fitting the beam main reinforcements and hoops within the panel zone. .

1i)パネルゾーンにおける現場でのコンクリート打設
は、鉄筋が密集している部分での作業であるため、十分
に密実なコンクリートの打設は困難となり、欠陥が生起
し易い。
1i) Since on-site concrete placement in the panel zone is work in areas where reinforcing bars are densely packed, it is difficult to place concrete densely enough and defects are likely to occur.

iv)パネルゾーンを形成する外側型枠は、柱の4隅部
分のみであり、型枠を固定するに当り、困難な点があっ
た。
iv) The outer formwork forming the panel zone was only at the four corners of the pillars, and it was difficult to fix the formwork.

本発明は前記従来技術の有する問題点に鑑みて堤案され
たもので、その目的とする処は、施工が簡単且つ確実に
行なわれ、構造的に信軌性の高いPC柱梁の接合工法、
及び同工法に適用されるPC柱を提供する点にある。
The present invention has been proposed in view of the problems of the prior art, and its purpose is to provide a method for joining PC columns and beams that is easy and reliable in construction and has high structural reliability. ,
and to provide PC pillars that can be applied to the same construction method.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係るPC柱梁の接
合工法は、柱主筋及び剪断補強筋を内蔵し、梁接合位置
に上下梁主筋を各一端部が柱面より突出するように定着
してなるプレキャストコンクリート柱を所定位置に立設
し、次いで半プレキャストコンクリート梁を建込み、同
梁の梁下端筋の突出端部及び現場で配設される梁上端筋
と、前記下部梁主筋及び上部梁主筋の各柱面突出端部と
を夫々接合するとともに、柱梁接合部に梁肋筋を配設し
たのち、柱梁接合コンクリートを打設することを特徴と
するものである。
(Means for Solving the Problems) In order to achieve the above object, the PC column and beam joining method according to the present invention incorporates column main reinforcement and shear reinforcement, and connects upper and lower beam main reinforcement at one end of each at the beam joining position. A precast concrete column is erected in a predetermined position so as to protrude from the column surface, and then a semi-precast concrete beam is erected, and the protruding end of the beam bottom reinforcement of the beam and the beam installed at the site are After joining the upper end reinforcement and the column surface protruding ends of the lower main beam reinforcement and the upper main beam reinforcement, respectively, and placing beam reinforcing bars at the column-beam joint, pour the column-beam joint concrete. This is a characteristic feature.

との場合、前記上下梁主筋の柱内に埋設される端部には
定着力を増大させるため、定着端部を曲成することが望
ましい。
In this case, it is desirable that the anchoring end portions of the upper and lower beam main reinforcements buried in the columns be curved in order to increase the anchoring force.

また前記PC柱梁の接合工法を円滑に遂行させるため、
本発明に係るPC柱は、柱主筋及び剪断補強筋を内蔵し
、梁接合位置に上下梁主筋を定着し、同各梁主筋の端部
を柱面より突出せしめて構成されるものである。
In addition, in order to smoothly carry out the joining method of the PC columns and beams,
The PC column according to the present invention is constructed by incorporating column main reinforcements and shear reinforcing bars, fixing the upper and lower beam main reinforcements at the beam joining position, and making the ends of each of the beam main reinforcements protrude from the column surface.

(作用) 本発明によれば、柱主筋及び剪断補強筋が内蔵され、且
つ梁接合位置に上下社主筋を各一端部が柱面より突出す
るように定着したPC柱を所定位置に立設し、次いで半
PC梁を建込んで同梁の梁下端筋の突出端部と前記PC
柱に定着された下部梁主筋の柱面からの突出端部、及び
現場で配設される梁上端筋と前記PC柱に定着された上
部梁主筋の柱面からの突出端部を夫々接合し、柱梁接合
部に梁肋筋を配筋したのち、同接合部に接合コンクリー
トを打設することによって、梁主筋に十分な定着長が確
保されたPC柱梁の接合部が構成される。またパネルゾ
ーン内の配筋が現場で行なわれず、工場で行なわれるの
で配筋が確実に行なわれ、コンクリートの打設も容易に
且つ確実に行なわれる。
(Function) According to the present invention, a PC column is erected at a predetermined position, which has a built-in column main reinforcement and a shear reinforcing bar, and has upper and lower main reinforcements fixed at the beam joining position so that one end of each is protruded from the column surface. Then, a half PC beam is erected and the protruding end of the beam bottom reinforcement of the same beam and the PC
The protruding end from the column surface of the lower beam main reinforcement fixed to the column, and the protruding end from the column surface of the beam upper end reinforcement installed on the site and the upper beam main reinforcement fixed to the PC column are respectively connected. After arranging beam reinforcing bars at the column-beam joint, a joint concrete is placed at the joint, thereby creating a PC-column-beam joint in which sufficient anchorage length is secured for the beam main reinforcement. Further, since reinforcement within the panel zone is not done on site but in a factory, reinforcement can be reliably arranged and concrete can be placed easily and reliably.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

(A)はPC柱で、その長さは床上面部から上階の床上
面部までに至る1層分の階高に等しい。
(A) is a PC column whose length is equal to the height of one floor from the floor top to the floor top of the upper floor.

社主筋(1)は脚部においてスプライススリーブ(2)
等の接合用金物が取付けられ、柱頭部においては上階の
PC柱(A)のスプライススリーブ(2)に接続するの
に必要な長さが突出されている。また前記柱主筋(1)
間には剪断補強筋(3)が配筋されている。
The main bar (1) has a splice sleeve (2) at the leg.
Connecting hardware such as these are attached, and a length necessary to connect to the splice sleeve (2) of the PC column (A) on the upper floor protrudes from the column head. In addition, the main column reinforcement (1)
Shear reinforcing bars (3) are arranged between them.

一方、パネルゾーン内には、上部梁主筋(4)及び下部
梁主筋(5)におけるフック状に曲成された定着基端部
(4a) (5a)が埋設され、所要の定着長さが確保
されており、同各梁主筋(4)(5)の先端部が柱面よ
りPC梁の梁筋と接合するのに必要な長さ突出されてい
る。
On the other hand, in the panel zone, the hook-shaped anchor base ends (4a) and (5a) of the upper main beam reinforcement (4) and the lower main beam reinforcement (5) are buried to ensure the required anchorage length. The tips of the main beam reinforcements (4) and (5) protrude from the column surface by a length necessary to connect with the beam reinforcement of the PC beam.

前記PC柱(A)は工場で製作され、PC柱成型用柱型
枠に柱主筋(1)剪断補強筋(3)、スプライススリー
ブ(2)及びパネルゾーン内の上下梁主筋(4)(5)
をセットし、コンクリートを打設することによって製作
される。
The PC column (A) is manufactured in a factory, and the column main reinforcement (1), shear reinforcement (3), splice sleeve (2), and upper and lower beam main reinforcement (4) (5) in the panel zone are installed in the column formwork for forming the PC column. )
It is manufactured by setting and pouring concrete.

この場合、パネルゾーン内の配筋は、梁主筋が比較的短
かく、その他の鉄筋も比較的自由に移動できるので、配
筋作業が容易に行なわれる。
In this case, the reinforcing bars in the panel zone can be easily arranged because the beam main reinforcements are relatively short and the other reinforcing bars can move relatively freely.

(B)は半PC梁で梁下端筋(6)が梁端部より突出さ
れ、肋筋(7)の一部が梁上面より突設され、更に梁端
面にはコツター(8)が配設されている。
(B) is a half-PC beam with the beam bottom reinforcement (6) protruding from the beam end, a part of the cost reinforcement (7) protruding from the top of the beam, and a cotter (8) installed on the beam end. has been done.

而して前記PC柱(A)を所定位置に立設し、次いで前
記半PC粱(B)を建込みサポート(9)によって支持
し、現場で梁上端筋0ωを配筋し、同梁上端筋01lD
及び前記梁下端筋(6)の突出端部と、PC柱(^)に
おける下部梁主筋(4)及び下部梁主筋(5)の各突出
端部とを溶接(@)またはスリーブ等で接合し、柱梁接
合部において前記各梁筋(4)(6)(5)間に梁肋筋
(10を配筋したのち、柱梁接合部分の梁型枠を取付け
、柱梁接合コンクリート(C)を打設して、前記PC柱
梁(A) (B)を接合するものである。
Then, the PC column (A) is erected at a predetermined position, and then the half PC column (B) is supported by the erection support (9), and the beam top end reinforcement 0ω is arranged on site, and the top end of the beam is Muscle 01lD
And the protruding end of the beam lower end reinforcement (6) and each protruding end of the lower main beam reinforcement (4) and the lower main beam reinforcement (5) in the PC column (^) are connected by welding (@) or a sleeve, etc. , After placing beam reinforcing bars (10) between each of the beam reinforcements (4), (6), and (5) at the column-beam joint, the beam formwork for the column-beam joint is installed, and the column-beam joint concrete (C) is created. The PC beams (A) and (B) are joined by pouring the concrete.

(発明の効果) 本発明によれば前記したように、柱主筋及び剪断補強筋
を内蔵したPC柱における柱梁接合位置に、上下梁主筋
を各一端部が柱面より突出するように定着したことによ
って、梁主筋の定着長さが容易に確保され、柱梁接合部
の強度の向上が図られる。
(Effects of the Invention) According to the present invention, as described above, the upper and lower beam main reinforcements are fixed at the column-beam joint position of a PC column having built-in column main reinforcements and shear reinforcing bars so that one end of each of them protrudes from the column surface. By doing so, the anchoring length of the main beam reinforcement can be easily ensured, and the strength of the beam-column joint can be improved.

本発明によれば前記したように構成されたPC柱を所定
位置に立設したのち、半PC梁を建込み、同半PC梁の
梁下端部突出端部、及び現場で配筋される梁上端筋と、
前記PC柱における下部梁主筋及び上部梁主筋の各突出
端部とを夫々接合するとともに、柱梁接合部に梁肋筋を
配筋したのち、柱梁接合コンクリートを打設し、PC柱
梁を一体に接合するものであり、この際、パネルゾーン
内の複雑な配筋作業は現場で行なわれず、工場で行なわ
れることによって、配筋作業が容易に且つ確実に行なわ
れるものである。
According to the present invention, after the PC column configured as described above is erected at a predetermined position, a half-PC beam is erected, and the protruding end of the lower end of the beam of the half-PC beam and the beam to be reinforced on site are The upper end muscle,
After connecting the protruding ends of the lower main beam reinforcement and the upper main beam reinforcement of the PC column, and placing beam reinforcing bars at the column-beam joint, column-beam joint concrete is poured, and the PC column and beam are connected. They are joined together as one piece, and in this case, the complicated reinforcing work within the panel zone is not done on site, but is done in the factory, so that the reinforcing work can be done easily and reliably.

またパネルゾーン内の複雑に配筋された部分のコンクリ
ート打設は現場で行なう場合、設備やコンクリート打設
方法の面で制約があるため、コンクリートの充填性に問
題があるが、本発明の方法によればこのような問題は解
消される。
In addition, when concrete is placed on site in areas with complex reinforcement within the panel zone, there are restrictions in terms of equipment and concrete placement methods, so there is a problem with the filling properties of the concrete, but the method of the present invention According to this, this problem will be resolved.

請求項2の発明は、前記PC柱の上下梁主筋の社内に埋
設される端部に定着部を曲成したことによって、同各梁
主筋のパネルゾーンにおける定着力を増大せしめたもの
である。
According to the second aspect of the present invention, anchoring portions are curved at the ends of the upper and lower beam main reinforcements of the PC column to be buried within the company, thereby increasing the anchoring force of each of the beam main reinforcements in the panel zone.

請求項3の発明は、PC柱に柱主筋及び剪断補強筋を内
蔵するとともに、梁接合位置に上下梁主筋を定着し、同
各梁主筋の端部を柱面より突出せしめ、同PC柱によっ
て前記PC柱梁接合工法を円滑に遂行しうるようにした
ものである。
The invention of claim 3 incorporates column main reinforcements and shear reinforcing bars in the PC column, fixes upper and lower beam main reinforcements at the beam joining position, makes the ends of each of the beam main reinforcements protrude from the column surface, and uses the PC column to This allows the PC column beam joining method to be carried out smoothly.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係るプレキャストコンクリート柱梁の
接合工法の一実施例の実施状況を示す縦断面図、第2図
は本発明に係るプレキャストコンクリート柱の縦断面図
、第3図は半プレキャストコンクリート梁の部分斜視図
である。 (^)・・・PC柱     (B)・・・半PC梁(
C)・・・柱梁接合コンクリート (+)・・・社主筋       (3)・・・剪断補
強筋(4)・・・上部梁主筋     (5)・・・下
部梁主筋(6)・・・梁肋筋       OI・・・
梁上梁筋01)・・・梁肋筋 第3図 第1回
Fig. 1 is a longitudinal cross-sectional view showing the implementation status of one embodiment of the precast concrete column and beam joining method according to the present invention, Fig. 2 is a longitudinal cross-sectional view of the precast concrete column according to the present invention, and Fig. 3 is a semi-precast concrete column. It is a partial perspective view of a concrete beam. (^)...PC column (B)...Semi-PC beam (
C)... Column-beam joint concrete (+)... Main reinforcement (3)... Shear reinforcement (4)... Upper beam main reinforcement (5)... Lower beam main reinforcement (6)... Beam rib OI...
Beam reinforcement on beam 01)...Beam rib Fig. 3 Part 1

Claims (3)

【特許請求の範囲】[Claims] (1)柱主筋及び剪断補強筋を内蔵し、梁接合位置に上
下梁主筋を各一端部が柱面より突出するように定着して
なるプレキャストコンクリート柱を所定位置に立設し、
次いで半プレキャストコンクリート梁を建込み、同梁の
梁下端筋の突出端部及び現場で配設される梁上端部と、
前記下部梁主筋及び上部梁主筋の各柱面突出端部とを夫
々接合するとともに、柱梁接合部に梁肋筋を配設したの
ち、柱梁接合コンクリートを打設することを特徴とする
プレキャストコンクリート柱梁の接合工法。
(1) A precast concrete column with built-in column main reinforcement and shear reinforcing reinforcement, and with upper and lower beam main reinforcement fixed at the beam joint position so that one end of each protrudes from the column surface, is erected at a predetermined position,
Next, a semi-precast concrete beam is erected, and the protruding end of the beam bottom reinforcement of the beam and the beam top end placed on site,
Precasting characterized in that the column surface protruding ends of the lower beam main reinforcement and the upper beam main reinforcement are respectively connected, and beam ribs are placed at the column-beam joint, and then column-beam joint concrete is poured. Connection method for concrete columns and beams.
(2)前記上下梁主筋の柱内に埋設される端部には、定
着部が曲成された請求項1記載のプレキャストコンクリ
ート柱梁の接合工法。
(2) The method for joining precast concrete columns and beams according to claim 1, wherein anchoring portions are curved at the ends of the main reinforcements of the upper and lower beams to be buried in the columns.
(3)柱主筋及び剪断補強筋を内蔵し、梁接合位置に上
下梁主筋を定着し、同各梁主筋の端部を柱面より突出せ
しめてなることを特徴とするプレキャストコンクリート
柱。
(3) A precast concrete column having a built-in column main reinforcement and shear reinforcing bars, upper and lower beam main reinforcements fixed at the beam joining position, and the ends of each of the beam main reinforcements protruding from the column surface.
JP1191989A 1989-01-23 1989-01-23 Jointing method for precast concrete pillar with pillar beam Pending JPH02194227A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1191989A JPH02194227A (en) 1989-01-23 1989-01-23 Jointing method for precast concrete pillar with pillar beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1191989A JPH02194227A (en) 1989-01-23 1989-01-23 Jointing method for precast concrete pillar with pillar beam

Publications (1)

Publication Number Publication Date
JPH02194227A true JPH02194227A (en) 1990-07-31

Family

ID=11791104

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1191989A Pending JPH02194227A (en) 1989-01-23 1989-01-23 Jointing method for precast concrete pillar with pillar beam

Country Status (1)

Country Link
JP (1) JPH02194227A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010097758A (en) * 2000-04-26 2001-11-08 정란 Precast Corbel Structure, and Contructuring Method thereof
JP2013011105A (en) * 2011-06-29 2013-01-17 Okumura Corp Junction structure of beam member and vertical member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010097758A (en) * 2000-04-26 2001-11-08 정란 Precast Corbel Structure, and Contructuring Method thereof
JP2013011105A (en) * 2011-06-29 2013-01-17 Okumura Corp Junction structure of beam member and vertical member

Similar Documents

Publication Publication Date Title
KR100652896B1 (en) Precast beam-column connection system using head rebar
JP3039295B2 (en) Manufacturing method of prefabricated member of mixed structure
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JPH0396544A (en) Jointing method for precast steel frame reinforced concrete column having beam steel frame
JP2893406B2 (en) Precast concrete beam-column joining method
JP2005002585A (en) Capital member and RCFT pillar construction method using the same
JP2516808B2 (en) Construction method of ramen type precast concrete structure
JPS6312987B2 (en)
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPH0459426B2 (en)
JP2998450B2 (en) Connection method between PC beam and column
JPS6367347A (en) Method for connecting precast concrete pillar
JP2656175B2 (en) Column-beam joint structure
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JPH0261238A (en) Steel plate concrete method
JP2901889B2 (en) Beam main bar anchorage device at the connection between column and beam
JPH07310368A (en) Reinforced concrete frame and its construction method
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JPS5846970B2 (en) Connection method between RC columns, Pca girders in the column direction, and cast-in-place girders in the span direction
JPS626034A (en) Construction of concrete structure
JPS61109842A (en) Column/beam connection method
JPH04265349A (en) Precast beam and construction method of beam
JPH10231559A (en) Center pillar provided with beam steel frame, and construction method for mixed structure using same
JPH05112947A (en) Execution method of foundation