JPH02210120A - Underground beam structure - Google Patents

Underground beam structure

Info

Publication number
JPH02210120A
JPH02210120A JP3067089A JP3067089A JPH02210120A JP H02210120 A JPH02210120 A JP H02210120A JP 3067089 A JP3067089 A JP 3067089A JP 3067089 A JP3067089 A JP 3067089A JP H02210120 A JPH02210120 A JP H02210120A
Authority
JP
Japan
Prior art keywords
column
underground beam
underground
foundation
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3067089A
Other languages
Japanese (ja)
Inventor
Fumio Ishikawa
石川 二巳穂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP3067089A priority Critical patent/JPH02210120A/en
Publication of JPH02210120A publication Critical patent/JPH02210120A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は建築物の地中梁の構造に係り、とくに、建築物
の柱が鉄骨造である場合の地中梁の接続部における構造
に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to the structure of underground beams in buildings, and particularly relates to the structure at the joints of underground beams when the pillars of the building are made of steel. It is something.

[従来の技術] 建築物の主架橋における地中梁は柱脚部間に架設されて
柱脚モーメントを処理する重要な部材であるが、全体が
地中にあるために、一般には鉄筋コンクリート造で構成
され、基礎のコンクリートと同時に打設されることが多
い。一般に、公知の基礎構造では、基礎と地中梁との鉄
筋コンクリート工事が先行し、コンクリートの硬化をま
って基礎上に柱が立設される。また、地中梁が底盤の周
辺に配置されて、底盤下面の支持圧を負担するときには
、その成も大きくなって、補強鉄筋の配筋、その後のコ
ンクリート打設工事には、多くの仮設資材と施工労力を
必要とする。
[Prior art] Underground beams in main bridges of buildings are installed between column bases and are important members for handling column base moments, but because they are entirely underground, they are generally not constructed of reinforced concrete. It is often poured at the same time as the foundation concrete. Generally, in known foundation structures, reinforced concrete work for the foundation and underground beams is first performed, and columns are erected on the foundation after the concrete has hardened. In addition, when underground beams are placed around the base and bear the support pressure on the underside of the base, their size increases, and many temporary materials are required for reinforcing reinforcing bars and subsequent concrete pouring work. and construction labor.

一方、最近の建設業界では、施工期間が短縮される傾向
にあり、構造躯体が鉄骨造で構成されることが多くなっ
ている。他面、労務事情も悪化する一方であって、こと
に、施工現場における型枠大工ならびに鉄筋工の確保が
困麹になっている。
On the other hand, in recent years in the construction industry, construction periods have tended to be shortened, and structural frames are increasingly constructed of steel frames. On the other hand, the labor situation is worsening, and it is particularly difficult to secure formwork carpenters and reinforcing bar workers at construction sites.

[発明が解決しようとする課運] 従来の地中梁の施工方法では、地中梁が鉄筋コンクリー
ト造であるために、基礎の鉄筋コンクリートと同時に施
工され、その後に柱が立設されるため、コンクリートの
硬化の時期を待つ必要があり、しかもアンカーボルトの
正確な設置には多大の配慮が必要である。さらに、柱脚
部における地中梁の鉄筋の定着が錯綜せざるを得ない。
[Issues to be solved by the invention] In the conventional construction method for underground beams, since the underground beams are made of reinforced concrete, they are constructed at the same time as the reinforced concrete of the foundation, and then the columns are erected. It is necessary to wait for the anchor bolt to harden, and moreover, a great deal of consideration is required for accurate installation of the anchor bolt. Furthermore, fixing the reinforcing bars of the underground beams at the column bases becomes complicated.

一方、地中梁の成が大きい時には、それに応じた鉄筋足
場を使用する。また、その構築に際しても、コンクリー
トの型枠工事が全く別種の工程を要し、いずれの施工に
も資材とその架は払しの技能工の労力、施工期間が必要
であり、このような従来の地中梁はごく通常の構造であ
りながら、とくに着目されることがなく、それらの解決
が課題となっていた。
On the other hand, if the underground beams are large, appropriate reinforced scaffolding will be used. In addition, when constructing it, the concrete formwork work requires a completely different process, and each type of construction requires the labor of skilled workers to remove materials and the frame, and the construction period. Although underground beams have a very ordinary structure, they have not received much attention, and their solution has been an issue.

[課題を解決するための手段] 本発明は、上述のような課題の解決を図るために創案さ
れたものであって、鉄骨造の柱を基礎杭の上端に立設し
、その下端部に架設される地中梁をプレキャストコンク
リート造で形成し、該地中梁の両端部に鉄骨製の接続部
材を接続部を突出させて埋設し、鉄骨柱と直接剛接合し
てなることを特徴とする地中梁の構造を提供することを
目的とするものである。この発明によれば、地中梁の施
工に際して、地中梁を予めプレキャストコンクリート造
で形成し、端部に設置した鉄骨造の接続部材を介して鉄
骨の柱脚間に直接架設することによって、地中梁自体の
製作工程を短縮し、鉄筋足場や型枠の仮設工事を不要と
して現場における労力を減少させるとともに、鉄筋コン
クリートに関する工期を大幅に短縮させることに成功し
たものである。
[Means for Solving the Problems] The present invention was devised to solve the above-mentioned problems, and consists of installing steel columns at the upper ends of foundation piles, The underground beam to be erected is formed of precast concrete, and steel connecting members are buried at both ends of the underground beam with the connecting parts protruding, and are directly rigidly connected to the steel column. The purpose of this project is to provide a structure for underground beams. According to this invention, when constructing an underground beam, the underground beam is formed in advance from precast concrete and is directly erected between the steel column bases via the connecting member of the steel frame installed at the end. This has succeeded in shortening the manufacturing process for the underground beam itself, eliminating the need for temporary construction of reinforced scaffolding and formwork, reducing on-site labor, and significantly shortening the construction period for reinforced concrete.

[実施例] 本発明の地中梁の構造を実施例の図面に基づいて詳細に
説明する。第1図は建築物の一部を示す平面図、第2図
は柱1スパン分の断面架構図、第3図は柱脚部の斜視図
である。図において、1は鉄骨造の柱、2はその基礎、
3は柱1の脚部を固定する地中梁であり、4は底盤、5
は基礎2の下面を支持する基礎杭である。
[Example] The structure of the underground beam of the present invention will be explained in detail based on the drawings of the example. Fig. 1 is a plan view of a part of the building, Fig. 2 is a cross-sectional view of the frame for one span of a column, and Fig. 3 is a perspective view of the column base. In the figure, 1 is a steel frame column, 2 is its foundation,
3 is an underground beam that fixes the legs of column 1, 4 is a bottom plate, and 5 is
is a foundation pile that supports the lower surface of foundation 2.

地中梁3は、適宜のプレキャストコンクリート工場にお
いて、プレキャストの鉄筋コンクリート部材として製作
され、その両端部に接続部材31としての鉄骨が、接続
用の端部32を突出させて所定の長さに製作される。接
続部材31は、基端部33の上下面に、スタッドボルト
34を植設し、地中梁3の製作時に、端部32を接続部
として突出させてコンクリート内に埋設されている。3
5は地中梁3の上下の主筋であり、両端の接続部材31
のフランジ36に支持されて、通常のスタラップ37を
組付け、プレキャストコンクリート梁が形成されている
The underground beam 3 is manufactured as a precast reinforced concrete member at an appropriate precast concrete factory, and a steel frame serving as a connecting member 31 is attached to both ends of the beam 3, and the connecting end 32 is made to protrude to a predetermined length. Ru. The connecting member 31 has stud bolts 34 planted on the upper and lower surfaces of the base end portion 33, and is buried in concrete with the end portion 32 protruding as a connecting portion when the underground beam 3 is manufactured. 3
5 is the main reinforcement at the top and bottom of the underground beam 3, and the connecting members 31 at both ends
A precast concrete beam is formed by supporting the flange 36 of the beam and attaching an ordinary stirrup 37 thereto.

一方、柱1は、基礎杭5上に立設され、柱脚部11の周
辺には、接続用フランジ12が固着されており、その位
置は上記地中梁3の接続部材31のフランジ36の位置
に対応して、このフランジ12と接続部材31とを接続
することによって、地中梁3を柱1の下部に架設しであ
る。
On the other hand, the column 1 is erected on the foundation pile 5, and a connecting flange 12 is fixed to the periphery of the column base 11, and its position is in line with the flange 36 of the connecting member 31 of the underground beam 3. The underground beam 3 is constructed under the column 1 by connecting the flange 12 and the connecting member 31 according to the position.

[作 用コ 本発明の地中梁の構造の作用を図面に示す一実施例の施
工工程に基づいて詳細に説明する。第2図において、ま
ず、基礎杭5が構築され、その上面に1通常柱1に先付
けされているベースプレート13を載置し、基礎杭5に
植設したアンカーボルト14によって固定して、柱1が
立設される。
[Function] The function of the underground beam structure of the present invention will be explained in detail based on the construction process of an embodiment shown in the drawings. In FIG. 2, first, the foundation pile 5 is constructed, and the base plate 13, which is normally attached to the column 1, is placed on the top surface of the foundation pile 5, and is fixed with the anchor bolt 14 installed in the foundation pile 5. will be erected.

この時点で、基礎2の鉄筋を配筋し、柱脚部11と地中
梁3の接続部分を除く基礎2のフーティング21部分を
構築してもよい。
At this point, the reinforcing bars of the foundation 2 may be arranged, and the footing 21 portion of the foundation 2 excluding the connection portion between the column base 11 and the underground beam 3 may be constructed.

一方、前記したような地中梁3がコンクリート工場にお
いて製作され、施工現場に搬入されて、柱1の柱脚部1
1間に架設される。この架設は地中梁3の端部に突出し
ている接続部材31の端部32を接続部として、柱1の
接続用フランジ12に溶接することによって剛接合し、
柱1と地中梁3とが直接結合される。ついで、基礎2の
全体。
On the other hand, the above-mentioned underground beam 3 is manufactured at a concrete factory, transported to the construction site, and the column base 1 of the column 1 is
It will be constructed between 1 and 2. In this construction, the end 32 of the connecting member 31 protruding from the end of the underground beam 3 is used as a connecting part, and is rigidly connected by welding to the connecting flange 12 of the column 1.
Column 1 and underground beam 3 are directly connected. Next, the whole of Basic 2.

またはフーティング21の除外部分に後打ちコンクリー
ト22を打設して基礎2を構築し、柱脚部11と基礎2
とを一体化させる。この作業によって地中梁3は柱1の
柱脚部11に固着され、柱1と地中梁3との架構が完成
する。従って、アンカーボルト14による柱1の立設は
、鉄筋コンクリート工事に先行して工期を短縮すること
ができるだけでなく、柱1の固定度が向上し、柱脚部1
1上下の諸鋼材が節減される。
Alternatively, post-cast concrete 22 is poured in the excluded part of the footing 21 to construct the foundation 2, and the column base 11 and the foundation 2 are
and integrate them. Through this work, the underground beam 3 is fixed to the column base 11 of the column 1, and the frame of the column 1 and the underground beam 3 is completed. Therefore, erecting the column 1 using the anchor bolt 14 not only shortens the construction period in advance of reinforced concrete construction, but also improves the degree of fixation of the column 1 and improves the stability of the column base.
1. Various steel materials on the upper and lower sides are saved.

[発明の効果コ 本発明は、鉄骨造の柱を基礎杭の上端に立設し、その下
端部に架設される地中梁をプレキャストコンクリート造
で形成し、該地中梁の両端部に鉄骨製の接続部材を接続
部を突出させて埋設し、鉄骨柱と直接剛接合してなるも
のであるから、まず。
[Effects of the Invention] The present invention erects a steel frame column at the upper end of the foundation pile, forms an underground beam constructed from precast concrete at the lower end thereof, and installs steel frames at both ends of the underground beam. First of all, it is made by burying the connecting member made of steel with the connecting part protruding and directly rigidly joining it to the steel column.

地中梁がかなり大規模のものであっても、プレキャスト
コンクリート梁として省力化して製作され、その製作に
要する工期も大幅に削減することができ、しかも、施工
現場における取付けが、既製部材同志の接続であるから
、工期が短縮される。また、柱の鉄骨と、地中梁との接
続も、鉄骨製の接続部材と鉄骨柱との溶接によって直接
剛に接続され、柱脚部の固定度が簡易な構造によって十
分確保されるばかりでなく、鉄筋コンクリート工事に先
行して施工されるから、コンクリートの硬化に左右され
ずに工期が短縮される。さらに、後打ちコンクリートに
よって基礎と一体化されるから。
Even if the underground beam is quite large, it can be produced labor-savingly as a precast concrete beam, and the construction period required for its production can be significantly reduced.Moreover, installation at the construction site is much easier than with ready-made members. Because it is a connection, the construction period is shortened. In addition, the steel frame of the column and the underground beam are directly and rigidly connected by welding the steel connection member and the steel column, and the stability of the column base is sufficiently ensured by the simple structure. Since it is constructed before the reinforced concrete construction, the construction period is shortened without being affected by the hardening of the concrete. Furthermore, it is integrated with the foundation using post-cast concrete.

格別の固定手段などを必要とせず、安価な構築が可能で
ある等、地中梁の施工方法の改善に画期的効果をもたら
す発明というべきである。
This invention should be said to have a revolutionary effect on improving underground beam construction methods, as it does not require special fixing means and can be constructed at low cost.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の地中梁の施工方法を採用した実施例を示
す図面であって、第1図は建築物の一部を示す床伏せ平
面図、第2図は柱1スパン分の立面図、第3図は柱脚部
の斜視図である。 1・・・柱、2・・・基礎、3・・・地中梁、4・・・
底盤、5・・・基礎杭、11・・・柱脚部、12・・・
フランジ、13・・・ベースプレート、14・・・アン
カーボルト、21・・・フーティング、22・・・後打
ちコンクリート、31・・・接続部材、32・・・端部
、接続部、33・・・基端部、34・・・スタッドボル
ト、35・・・主筋、36・・・フランジ、37・・・
スタラップ。 第1図 第2図
The drawings are drawings showing an example in which the underground beam construction method of the present invention is adopted, in which Fig. 1 is a floor plan showing a part of the building, and Fig. 2 is an elevation view of one column span. FIG. 3 is a perspective view of the column base. 1...Column, 2...Foundation, 3...Underground beam, 4...
Bottom plate, 5... Foundation pile, 11... Column base, 12...
Flange, 13... Base plate, 14... Anchor bolt, 21... Footing, 22... Post-cast concrete, 31... Connection member, 32... End, connection part, 33...・Base end, 34... Stud bolt, 35... Main reinforcement, 36... Flange, 37...
Stirrup. Figure 1 Figure 2

Claims (1)

【特許請求の範囲】[Claims] 鉄骨造の柱を基礎杭の上端に立設し、その下端部に架設
される地中梁をプレキャストコンクリート造で形成し、
該地中梁の両端部に鉄骨製の接続部材を接続部を突出さ
せて埋設し、鉄骨柱と直接剛接合してなることを特徴と
する地中梁の構造。
A steel column is erected at the upper end of the foundation pile, and an underground beam erected at the lower end is made of precast concrete.
An underground beam structure characterized in that steel frame connecting members are buried at both ends of the underground beam with their connecting parts protruding, and are directly and rigidly connected to a steel column.
JP3067089A 1989-02-09 1989-02-09 Underground beam structure Pending JPH02210120A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3067089A JPH02210120A (en) 1989-02-09 1989-02-09 Underground beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3067089A JPH02210120A (en) 1989-02-09 1989-02-09 Underground beam structure

Publications (1)

Publication Number Publication Date
JPH02210120A true JPH02210120A (en) 1990-08-21

Family

ID=12310165

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3067089A Pending JPH02210120A (en) 1989-02-09 1989-02-09 Underground beam structure

Country Status (1)

Country Link
JP (1) JPH02210120A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5096008A (en) * 1973-12-26 1975-07-30

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5096008A (en) * 1973-12-26 1975-07-30

Similar Documents

Publication Publication Date Title
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP3039295B2 (en) Manufacturing method of prefabricated member of mixed structure
JP2537330B2 (en) Precast reinforced concrete columns
JPH07247557A (en) Foundation, column mold, and underground beam made of precast reinforced concrete
JP2000160687A (en) Construction method of mixed structure and precast concrete column
JPH0533351A (en) Steel column base of steel structure and its construction method
JPH02210120A (en) Underground beam structure
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPS6195136A (en) Construction of multistoried building skeletal by precast reinforced concrete unit
JP2784450B2 (en) Reinforced concrete foundation
JPH11181807A (en) Construction method for underground story
JP2614000B2 (en) Basics of steel frame
JP2000192664A (en) Method for construction of building
JPH06220869A (en) Drop-in type steel frame bridge pier and process of construction thereof
JPH04128430A (en) concrete foundation
JP2025122529A (en) Building construction method and joint members used therein
JPS63125743A (en) Construction of building
JPS6375231A (en) Building housing
JPH0765368B2 (en) Precast concrete half flat slab
JP2715162B2 (en) Reinforcement method for joints between piles and foundations
JPH0588331B2 (en)
JPH0782817A (en) Building wall structure and construction method
WO2020261342A1 (en) Plant frame structure
JPH08326310A (en) Timbering for assembling foundation beam reinforcement