JPH02299424A - Trouble restoring operation for electric power system - Google Patents
Trouble restoring operation for electric power systemInfo
- Publication number
- JPH02299424A JPH02299424A JP1116446A JP11644689A JPH02299424A JP H02299424 A JPH02299424 A JP H02299424A JP 1116446 A JP1116446 A JP 1116446A JP 11644689 A JP11644689 A JP 11644689A JP H02299424 A JPH02299424 A JP H02299424A
- Authority
- JP
- Japan
- Prior art keywords
- power
- accident
- equipment
- restoration
- trouble
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
本発明は、広域的な電力系統の事故発生時に復旧対処す
るための電力系統の事故復旧操作方法に関するものであ
る。TECHNICAL FIELD The present invention relates to a power system fault recovery operation method for dealing with recovery when a wide-area power system fault occurs.
第2図は、例えば糟谷、小田他電学論B、109巻4号
、平成元年「地方供給系統における事故時 −復旧操作
方式の開発Jに示された従来の電力系統の事故時自動復
旧操作方法の概念図であり、図において、■は電子計算
機、2は電力系統の基本構成データ、3はオンライン入
力データ、4は電子計算機1によって出力された系統事
故時の復旧操作である復旧手順データである。
次に動作について説明する。まず、自動復旧制御システ
ムの中核となる電子計算機1は担当電力系統の基本構成
データ2とオンライン入力データ3を収集して復旧手順
データ4を出力する。電力系統の基本構成データ2とし
ては担当電力系統を構成するしゃ断器、断路器などの開
閉器類、送配電線路、変圧器、更に発電機などの設備名
称データ、それら設備群の隣接関係を示す結合データ、
送電線、母線、変圧器、電源などの設備群に許容される
電力容量データ等が用意される。
事故が発生すると、その電力系統事故発生時の復旧には
第3図に示す流れ図に従って変電システム計算機と給電
システム計算機の処理分担を行い、互いの計算機間を伝
送網を介して有機的に結合することにより指令と操作の
一体化を図っている。
まず、ステップSTIでは電力系統事故発生時、変電シ
ステムから入力された表示計測情報を基に事故発生を自
動検出すると共に、遮断器や保護リレー等の動作情報か
ら、充停電設備状態の判定および停電系統内の事故設備
の判定を行う。次にステップST2では事故設備判定結
果から、送電線が事故設備と判定された場合、給電再送
電の条件成立の可否判定を行う。可の場合には給電再送
電操作手順を作成し、変電システムへ指令の自動伝達を
行い、変電システムの操作実行後、表示計測情報から給
電再送電操作の結果を判定し事故設備の確定を行う。否
の場合は事故設備が事故設備判定結果どおりであると確
定する。また、ステップST3では、給電再送電処理後
も停電状態で残る系統を復旧対象系統として、事故時復
旧論理の展開を行い、過負荷を発生させずに実際に復旧
できる系統(以下、復旧決定系統と呼ぶ)を作成する。
さらに、ステップST4では事故後の現在系統と復旧決
定系統を比較し、現在系統から復旧決定系統の系統構成
にするための系統復旧指令手順を自動作成する。この系
統復旧指令手順は、給電再送電操作と同様に変電システ
ムへ給電指令として自動伝達し、変電システムが操作を
実行する。Figure 2 shows, for example, automatic restoration in the event of an accident in a conventional electric power system as shown in Kasuya, Oda et al.'s Electrical Engineering Theory B, Vol. 109, No. 4, 1989, "Accidents in Local Supply Systems - Development of Recovery Operation Methods J. This is a conceptual diagram of the operation method. In the figure, ■ is the computer, 2 is the basic configuration data of the electric power system, 3 is the online input data, and 4 is the recovery procedure that is the recovery operation in the event of a system failure output by the computer 1. Next, the operation will be explained. First, the electronic computer 1, which is the core of the automatic restoration control system, collects basic configuration data 2 and online input data 3 of the electric power system in charge, and outputs restoration procedure data 4. The basic configuration data 2 of the power system shows equipment name data such as circuit breakers, disconnectors, power transmission and distribution lines, transformers, generators, etc. that make up the power system in charge, and the adjacency relationship of these equipment groups. combined data,
Allowable power capacity data for equipment groups such as transmission lines, busbars, transformers, and power sources are prepared. When an accident occurs, in order to restore the power system when an accident occurs, the substation system computer and the power supply system computer share the processing according to the flowchart shown in Figure 3, and the computers are organically connected via the transmission network. This allows for the integration of commands and operations. First, in Step STI, when a power system accident occurs, it automatically detects the occurrence of the accident based on display measurement information input from the substation system, and also determines the status of charging and power outage equipment based on operation information of circuit breakers, protection relays, etc. Determine faulty equipment within the system. Next, in step ST2, if the power transmission line is determined to be an accidental equipment based on the accidental equipment determination result, it is determined whether the conditions for power retransmission are satisfied. If possible, create a power retransmission operation procedure, automatically transmit the command to the substation system, and after performing the operation of the substation system, determine the result of the power retransmission operation from the displayed measurement information and confirm the faulty equipment. . If not, it is determined that the accident equipment is in accordance with the accident equipment determination result. In addition, in step ST3, the system that remains in a power outage state even after the power supply retransmission process is set as the system to be restored, and the accident recovery logic is developed, and the system that can actually be restored without overloading (hereinafter referred to as the restoration decision system) is developed. ). Furthermore, in step ST4, the current system after the accident is compared with the restoration determined system, and a system restoration command procedure is automatically created to change the system configuration from the current system to the restoration determined system. Similar to the power retransmission operation, this system restoration command procedure is automatically transmitted to the substation system as a power supply command, and the substation system executes the operation.
従来の電力系統の事故復旧操作方法は以上のように実行
されているので、送電線に事故が発生した時には給電再
送電操作の結果を判定する作業の事故設備の確定が行わ
れるまでの間、次の事故時復旧論理を展開することがで
きないため、給電再送電処理後も停電状態で未処理の系
統に対する系統復旧指令手順の作成が遅れることになり
迅速な電力系統の復旧が行えないという課題があった。
この発明は上記のような課題を解消するためになされた
もので、給電再送電操作の実行結果を待たずに並行して
送電線の仮事故設備を設定し事故時復旧論理を展開する
ことで、迅速に系統復旧指令手順を作成し、電力系統の
復旧を行うことのできる電力系統の事故復旧操作方法を
得ることを目的とする。The conventional power system accident recovery operation method is carried out as described above, so when an accident occurs on a power transmission line, until the faulty equipment is determined during the work to determine the result of the power retransmission operation, Since it is not possible to develop the next fault recovery logic, there is a delay in creating a system recovery command procedure for a grid that is in a power outage state and has not yet been processed even after the power retransmission process, making it impossible to quickly restore the power system. was there. This invention was made in order to solve the above-mentioned problems, and it is possible to set temporary fault equipment on the power transmission line in parallel without waiting for the execution result of the power retransmission operation, and to develop the fault recovery logic. The purpose of this study is to obtain a power system accident recovery operation method that can quickly create a system restoration command procedure and restore the power system.
この発明に係る電力系統の事故復旧操作方法は事故検出
・停電設備判定、事故設備判定処理群を実行して事故設
備を判定した後に、給電再送電手順作成・実行処理群の
実行と並行して、判定された事故設備が確定した事故設
備であると仮定した場合の事故時復旧論理と、該事故設
備が確定した事故設備でないと仮定した場合の事故時復
旧論理とを同時に展開し、夫々の系統復旧指令手順の作
成完了後に前記給電再送電操作完了後の結果と作成され
た前記系統復旧指令手順とを関連動作させて電力系統の
事故を復旧させるようにしたものである。The power system accident recovery operation method according to the present invention executes the accident detection/power outage equipment judgment and faulty equipment judgment processing group to determine the faulty equipment, and then, in parallel with the execution of the power retransmission procedure creation/execution processing group. , we simultaneously develop the accident recovery logic when it is assumed that the equipment that has been judged to have had an accident is a confirmed accident equipment, and the accident recovery logic when it is assumed that the accident equipment is not a confirmed accident equipment. After the creation of the system restoration command procedure is completed, the result after the completion of the power supply retransmission operation and the created system restoration command procedure are operated in conjunction with each other to restore the power system from an accident.
この発明における電力系統の事故復旧操作方法は事故検
出・停電設備判定、事故設備判定処理群実行後に給電再
送電手順作成・実行処理群の結果を待たずに、仮事故設
備と事故でない設備の2つの事故時復旧論理を並行処理
させることによって系統復旧指令手順を迅速に作成し、
系統復旧指令実行が行えるようにする。The power system accident recovery operation method according to the present invention is based on the fault detection/power outage equipment determination and failure equipment determination processing group, without waiting for the results of the power supply retransmission procedure creation/execution processing group, and detecting the temporary accidental equipment and non-accident equipment. By processing two accident recovery logics in parallel, grid recovery command procedures can be quickly created.
Enables system restoration command execution.
以下、この発明の一実施例を図について説明する。図中
、第3図と同一の部分は同一の符号をもって図示した第
1図において、変電システム部については従来技術と動
作が同一であるので説明は省略する。
図中、ステップSTIは事故検出・停電設備判定、事故
設備判定処理群、ステップST2は給電再送電手順作成
・実行処理群、ステップST3は事故時復旧論理処理、
ステップST4は系統復旧指令手順作成・実行処理群、
ステップST5は送電線事故発生時事故復旧論理・系統
復旧指令手順作成処理群およびステップST6は送電線
事故発生時系統復旧指令実行処理群である。
次に動作について説明する。まず、ステップST1の終
了後、事故設備判定の結果、送電線事故ではないと判定
された場合にはステップST3゜ステップST4の処理
を実行して終了する。Sr3、Sr1の動作については
、従来技術と同様なので説明を省略する。STIの終了
後、送電線事故と判定された場合には、ステップST2
とステップST5の両機能を並列動作させる。ステップ
ST2の動作については従来技術と同様のため省略する
。一方、ステップST5では、送電線を事故設備と事故
設備でない両ケースについて事故時復旧論理、系統復旧
指定手順の作成を行う。つまり、事故設備と判定された
送電線について、給電−再送電後も事故設備となったと
仮定した電力系統を復旧対象系統として事故時復旧論理
の展開を行う。そして、系統復旧指令手順の作成を行う
。事故時復旧論理の動作は従来技術のステップST3と
同様であり、系統復旧指令手順作成の動作はステップS
T4と同様である。上記処理と並行して、以下の処理を
並列動作させる。事故設備と判定された送電線が給電再
送電後に復旧する(送電線が事故設備ではない)と仮定
した電力系統を復旧対象系統として事故時復旧論理の展
開を行い、その後、系統復旧指令手順の作成を行う。次
にステップST6では、ステップST2の事故設備確定
で得られた該送電線が事故設備か否かの結果をもとに、
送電線が事故設備と確定した場合は、ステップST5で
仮に事故設備として事故時復旧論理を展開して作成した
系統復旧指令手順を正式に系統復旧指令手順として採用
する。
また、事故設備でないと確定した場合には、ステップS
T、5で仮に事故設備でないとして事故時復旧論理を展
開して作成した系統復旧指令手順を採用する。以上のよ
うに採用した手順をもとに系統復旧指令実行を行う。系
統復旧指令実行の動作については従来技術のステップS
T4と同様である。
なお、上記実施例では送電線事故時の給電再送電操作の
実施ケースについて述べたが、再閉路装置を用いた再送
電機能による復旧の場合についても全く同様で第1図の
ステップST2を再閉路装置による復旧成功又は失敗確
定機能と置換することにより、再送電成功又は失敗の判
定を待たずにステップST5を並行して実行することで
同様の効果を奏する。
さらに、上記実施例の各機能の並列動作については、マ
ルチCPU等の負荷分散システムを構築することで電力
系統の復旧のより一層の迅速化を図ることができる。An embodiment of the present invention will be described below with reference to the drawings. In FIG. 1, the same parts as in FIG. 3 are designated by the same reference numerals, and since the operation of the substation system section is the same as that of the prior art, the explanation will be omitted. In the figure, step STI is an accident detection/power outage equipment determination, accident equipment determination processing group, step ST2 is a power retransmission procedure creation/execution processing group, step ST3 is an accident recovery logic process,
Step ST4 is a system restoration command procedure creation/execution processing group;
Step ST5 is a processing group for creating an accident recovery logic/system restoration command procedure when an accident occurs on a power transmission line, and step ST6 is a processing group for executing a system restoration command when an accident occurs on a power transmission line. Next, the operation will be explained. First, after completing step ST1, if it is determined that there is no power transmission line accident as a result of the accident equipment determination, steps ST3 and ST4 are executed, and the process ends. The operations of Sr3 and Sr1 are the same as those in the prior art, so the explanation will be omitted. After the STI ends, if it is determined that a power transmission line accident has occurred, proceed to step ST2.
and step ST5 are operated in parallel. The operation of step ST2 is the same as that of the prior art, and will therefore be omitted. On the other hand, in step ST5, accident recovery logic and system recovery designation procedures are created for both the cases where the transmission line is an accidental equipment and a case where the transmission line is not an accidental equipment. In other words, for a power transmission line that has been determined to be a faulty facility, fault recovery logic is developed using a power system that is assumed to be a faulty facility even after power supply and retransmission as a restoration target system. Then, create a system restoration command procedure. The operation of the accident recovery logic is the same as step ST3 of the conventional technology, and the operation of creating the system recovery command procedure is step S.
It is similar to T4. In parallel with the above processing, the following processing is performed in parallel. We develop accident recovery logic using the power system as a recovery target system, assuming that the transmission line determined to be the faulty equipment will be restored after power is retransmitted (the transmission line is not the faulty equipment), and then we will develop the fault recovery logic in the system to be restored. Create. Next, in step ST6, based on the result of determining whether the power transmission line is an accidental equipment obtained in step ST2 in determining the accidental equipment,
If the power transmission line is determined to be the faulty equipment, in step ST5, the grid restoration command procedure created by developing the accident recovery logic for the faulty equipment is officially adopted as the grid restoration command procedure. In addition, if it is determined that it is not the equipment that caused the accident, step S
In T.5, assuming that the equipment is not in an accident, adopt the system restoration command procedure created by developing the accident recovery logic. The system restoration command is executed based on the procedure adopted as described above. Regarding the operation of executing the grid restoration command, step S of the conventional technology is used.
It is similar to T4. In the above embodiment, a case was described in which a power supply retransmission operation was performed in the event of a power transmission line fault, but the same applies to the case of restoration using a power retransmission function using a reclosing device, and step ST2 in FIG. By replacing the function with the function of determining success or failure of restoration by the device, the same effect can be achieved by executing step ST5 in parallel without waiting for determination of success or failure of power retransmission. Furthermore, regarding the parallel operation of each function in the above embodiments, it is possible to further speed up the recovery of the power system by constructing a load distribution system such as a multi-CPU.
以上のように、この発明によれば、給電再送電等の再送
電操作の実行を待たずに、並列処理によって事故時復旧
論理を夫々の該当設備について展開し系統復旧指令手順
の作成を行えるように構成したので、系統復旧指令手順
を迅速に作成することができて電力系統の事故発生によ
る供給支障時間の短縮化を図ることができる効果がある
。As described above, according to the present invention, it is possible to develop the accident recovery logic for each applicable equipment and create a system recovery command procedure using parallel processing without waiting for the execution of power retransmission operations such as power retransmission. Since the system is configured as follows, it is possible to quickly create a system restoration command procedure, which has the effect of shortening the time during which supply is interrupted due to the occurrence of an accident in the power system.
第1図はこの発明の一実施例による電力系統の事故復旧
操作方法を示すフローチャート、第2図は従来の電力系
統の事故復旧操作方法の概念図、第3図は従来の事故復
旧操作方法を示すフローチャートである。
図において、1は電子計算機、2は電力系統の基本構成
データ、3はオンライン入力データ、4は復旧手順デー
タ、STIは事故検出・停電設備判定、事故設備判定処
理群、Sr1は給電再送電手順作成・実行処理群、Sr
5は送電線事故発生時事故時復旧論理・系統復旧指令手
順作成処理群、Sr1は送電線事故発生時系統復旧指令
実行処理群である・。
なお、図中、同一符号は同一または相当部分を示す。FIG. 1 is a flowchart showing a power system accident recovery operation method according to an embodiment of the present invention, FIG. 2 is a conceptual diagram of a conventional power system accident recovery operation method, and FIG. 3 is a flowchart showing a conventional power system accident recovery operation method. FIG. In the figure, 1 is a computer, 2 is basic configuration data of the power system, 3 is online input data, 4 is recovery procedure data, STI is accident detection / power outage equipment judgment, faulty equipment judgment processing group, Sr1 is power retransmission procedure Creation/execution processing group, Sr
5 is a processing group for creating an accident recovery logic/system restoration command procedure when a transmission line accident occurs, and Sr1 is a processing group for executing a system restoration command when a transmission line accident occurs. In addition, in the figures, the same reference numerals indicate the same or corresponding parts.
Claims (1)
ンライン入力データとを電子計算機に入力し、該系統事
故に起因して接続状態が変化した事故直後の系統につい
て停電設備を判定し、かつ該停電設備の中より事故設備
を判定し、該停電設備と該事故設備との情報より電力系
統を自動復旧する復旧手順データを出力して実行する電
力系統の事故復旧操作方法において、前記電力系統内の
送電線事故発生時に事故検出・停電設備判定、事故設備
判定処理群を実行して事故設備を判定し、給電再送電手
順作成・実行処理群を実行して給電再送電後の事故設備
を確定し、前記給電再送電手順作成・実行処理群の実行
と並行して、判定された前記事故設備が前記給電再送電
後も事故設備である場合と事故設備でない場合とについ
て系統復旧指令手順を作成する送電線事故発生時事故時
復旧論理・系統復旧指令手順作成処理群を実行し、前記
系統復旧指令手順作成の完了時に前記給電再送電手順作
成・実行処理群を実行して得られた結果に従って前記系
統復旧指令手順を選択して系統復旧指令の実行を行うこ
とを特徴とする電力系統の事故復旧操作方法。When an accident occurs in a power system, the basic configuration data and online input data of the power system are input into a computer, and the power outage equipment is determined for the system immediately after the accident, where the connection state has changed due to the power outage, and In the power system accident recovery operation method, which outputs and executes recovery procedure data for automatically restoring the power system based on the information of the power outage equipment and the accident equipment, determining the faulty equipment among the equipment, When an accident occurs on a power transmission line, execute the accident detection/outage equipment determination and faulty equipment determination processing groups to determine the faulty equipment, and execute the power retransmission procedure creation/execution processing group to determine the faulty equipment after power retransmission. , In parallel with the execution of the power supply retransmission procedure creation/execution processing group, a system restoration command procedure is created for cases in which the determined faulty equipment remains the faulty equipment even after the power supply retransmission, and cases in which the faulty equipment is not the faulty facility. When a power transmission line accident occurs, execute the accident recovery logic/grid restoration command procedure creation processing group, and upon completion of the grid restoration command procedure creation, execute the power retransmission procedure creation/execution processing group and perform the above operations according to the results obtained. 1. A power system accident recovery operation method, comprising selecting a system recovery command procedure and executing the system restoration command.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1116446A JPH02299424A (en) | 1989-05-10 | 1989-05-10 | Trouble restoring operation for electric power system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1116446A JPH02299424A (en) | 1989-05-10 | 1989-05-10 | Trouble restoring operation for electric power system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH02299424A true JPH02299424A (en) | 1990-12-11 |
Family
ID=14687317
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1116446A Pending JPH02299424A (en) | 1989-05-10 | 1989-05-10 | Trouble restoring operation for electric power system |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH02299424A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0311945A (en) * | 1989-06-08 | 1991-01-21 | Hitachi Ltd | Supervisory control method and device for power system |
| KR100380657B1 (en) * | 2000-05-10 | 2003-04-18 | 한국수력원자력 주식회사 | Automatic Power Restoration Method |
| JP2008099534A (en) * | 2006-10-16 | 2008-04-24 | Chugoku Electric Power Co Inc:The | Monitoring control unit having automatic reclosed circuit function |
-
1989
- 1989-05-10 JP JP1116446A patent/JPH02299424A/en active Pending
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0311945A (en) * | 1989-06-08 | 1991-01-21 | Hitachi Ltd | Supervisory control method and device for power system |
| KR100380657B1 (en) * | 2000-05-10 | 2003-04-18 | 한국수력원자력 주식회사 | Automatic Power Restoration Method |
| JP2008099534A (en) * | 2006-10-16 | 2008-04-24 | Chugoku Electric Power Co Inc:The | Monitoring control unit having automatic reclosed circuit function |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101911421B (en) | Method for electric power rehabilitation in electric power distribution systems | |
| Hotta et al. | Implementation of a real-time expert system for a restoration guide in a dispatching center | |
| CN110166483B (en) | Power grid fault and network attack identification method, device and equipment | |
| CN104778632A (en) | Intelligent decision making aiding method and system for transfer power supply | |
| CN111786383A (en) | Spare power automatic switching device and method for realizing mutual backup of multiple power incoming lines | |
| Wan et al. | Multi‐agent application of substation protection coordination with distributed generators | |
| CN118040666A (en) | A distribution automation fault self-healing method and system | |
| CN113612228B (en) | Multi-dimensional information fusion-based feeder automation active fault processing system, method and readable storage medium | |
| JPH02299424A (en) | Trouble restoring operation for electric power system | |
| CN113991835A (en) | Control method for seamless switching of double power supplies based on spare power automatic switching device | |
| JPH02299425A (en) | Trouble restoration operation of electric power system | |
| CN109861203B (en) | Spare power automatic switching locking checking method | |
| JP2577392B2 (en) | Pre-accident grid status creation method for automatic recovery in the event of a power grid accident | |
| JPH1115515A (en) | Simulator | |
| CN114629075B (en) | A power restoration method, apparatus, equipment and medium based on power distribution network | |
| JPS60144116A (en) | Power system simulator | |
| JP2921034B2 (en) | System failure section judgment device | |
| JPH06165378A (en) | System restoration operation procedure creation system | |
| JP2778741B2 (en) | Power system accident recovery support device | |
| JPH0417525A (en) | Supporting method for power system operation | |
| JP2618905B2 (en) | Automatic creation of system operation procedure in power system | |
| Cirio et al. | Application of an Advanced Transient stability assessment and control method to a realistic power system | |
| JP2925238B2 (en) | Power system accident recovery support device | |
| JP3177701B2 (en) | Accident recovery inference method at substation | |
| JPH067731B2 (en) | Automatic creation method of system operation command procedure in electric power system |