JPH0240835B2 - CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO - Google Patents

CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO

Info

Publication number
JPH0240835B2
JPH0240835B2 JP1546583A JP1546583A JPH0240835B2 JP H0240835 B2 JPH0240835 B2 JP H0240835B2 JP 1546583 A JP1546583 A JP 1546583A JP 1546583 A JP1546583 A JP 1546583A JP H0240835 B2 JPH0240835 B2 JP H0240835B2
Authority
JP
Japan
Prior art keywords
excavation
tunnel
ground
pipe
shoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1546583A
Other languages
Japanese (ja)
Other versions
JPS59141695A (en
Inventor
Kazuo Sasaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP1546583A priority Critical patent/JPH0240835B2/en
Publication of JPS59141695A publication Critical patent/JPS59141695A/en
Publication of JPH0240835B2 publication Critical patent/JPH0240835B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】 この発明は、地質不良地におけるトンネルの構
築工法に関し、特に二重管を用いることで地山の
崩落を防止することができる地質不良地における
トンネルの構築工法に関するものである。
[Detailed Description of the Invention] The present invention relates to a method for constructing a tunnel in a geologically poor land, and in particular to a method for constructing a tunnel in a geologically poor land in which collapse of the ground can be prevented by using double pipes. be.

従来、トンネルを構築する場合に、掘削したト
ンネル地山の崩落を防止するためアーチ状の鋼製
支保工を、所定の距離掘削するたびに構築する工
法が、地質が堅固な場合を除き一般的に採用され
ており、トンネルの掘削作業はダイナマイトで爆
破するか、機械で直接掘削し、ずり出しを行なつ
て前記支保工を構築するという一連のサイクルを
繰返して行なわれていた。
Conventionally, when constructing tunnels, arch-shaped steel supports were constructed every time a predetermined distance was excavated to prevent the excavated tunnel ground from collapsing, except in cases where the geology was solid. Tunnel excavation work was carried out repeatedly through a cycle of blasting with dynamite or direct excavation with a machine, offsetting, and constructing the support.

そして、特に不良地質個所に構築する場合に
は、支保工を構築するまでにトンネル地山が崩落
する危険性があるため、すでに構築された支保工
とトンネル地山の間に矢板を差し込み、矢先の地
山を切崩した分だけ矢板をたたき込むことでこれ
を防止する、いわゆる縫地、送り矢板工法等が採
用されていた。
Particularly when constructing in a location with poor geology, there is a risk that the tunnel ground may collapse before the shoring is constructed, so sheet piles are inserted between the already constructed shoring and the tunnel ground. In order to prevent this, the so-called sewn-up method and the feed sheet pile method were used to prevent this by driving in sheet piles to compensate for the amount of ground that had been cut down.

しかしながら、この工法を採用した場合には、
1次覆工としてトンネル地山にコンクリートの吹
付けを行なうと、矢板背面とトンネル地山間に空
隙を生じ、1次覆工としての機能が十分に発揮さ
れないという欠点があつた。
However, when this construction method is adopted,
When concrete is sprayed onto the tunnel ground as a primary lining, a gap is created between the back surface of the sheet pile and the tunnel ground, which has the disadvantage that the function as the primary lining cannot be fully demonstrated.

このため、掘削外周に向けてボルトやパイプを
打設する、いわゆる先行ロツクボルト工法、先行
パイプ工法が提案されているが、これらの工法に
おいては、ボルトやパイプのかなりの部分が掘削
範囲に入り、掘削廃棄されるため不経済となるだ
けでなく、打設作業は切羽で機械や足場を組んで
行なわなければならず、上記した一連の掘削サイ
クルにこの作業を組込むため掘削サイクルタイム
が延長されるという問題もあつた。
For this reason, the so-called pre-lock bolt method and pre-pipe method have been proposed, in which bolts and pipes are driven toward the outer circumference of the excavation, but in these methods, a large portion of the bolts and pipes fall within the excavation area. Not only is it uneconomical because the excavation is discarded, but the pouring work must be carried out using machinery and scaffolding at the face, and the excavation cycle time is extended because this work is incorporated into the series of excavation cycles described above. There was also this problem.

また、上記先行ロツクボルト工法等は、切羽か
ら斜め上方にボルト等を打設するため、ボルト等
の下部の地山は崩落し易くなり、その上掘削後の
トンネル面には、ボルト等が突出した状態で残存
するため、鋸歯状の余掘となり、吹付けコンクリ
ート量が増化するという問題もあつた。
In addition, in the above-mentioned advanced lock bolt construction method, etc., bolts are driven diagonally upward from the face, so the ground beneath the bolts is likely to collapse, and furthermore, the bolts, etc. protrude from the tunnel surface after excavation. There was also the problem that the excavation remained in a serrated state, resulting in an increase in the amount of shotcrete.

この発明は、このような従来の問題点に鑑みな
されたものであり、その目的とするところは、比
較的簡単な構成でもつて不良地質個所に安全に且
つ経済的にトンネルの構築を可能にする地質不良
地におけるトンネルの構築工法を提供するところ
にある。
This invention was made in view of these conventional problems, and its purpose is to make it possible to safely and economically construct tunnels in poor geological locations with a relatively simple configuration. The purpose is to provide a method for constructing tunnels in geologically poor areas.

この目的を達成するため、この発明は支保工を
用いるトンネルの構築工法において、支保工と掘
削後のトンネル地山の間に筒状の外管内に小径の
内管を収納した二重管を、掘削断面に沿つて且つ
これとほぼ直交するように複数本配設し前記支保
工に固定した後、掘削の進行に伴つてそれぞれの
内管を順次掘削面に沿つて掘削方向に延長するこ
とで地山の崩落を防止するようにしてなるという
特徴を有する。
In order to achieve this object, the present invention uses a double pipe, in which a small-diameter inner pipe is housed within a cylindrical outer pipe, between the shoring and the excavated tunnel ground in a tunnel construction method using shoring. After arranging a plurality of inner pipes along the excavation cross section and almost perpendicular thereto and fixing them to the shoring, each inner pipe is sequentially extended in the excavation direction along the excavation surface as the excavation progresses. It has the characteristic of preventing the collapse of the ground.

以下に、この発明の好適な実施例を添付図面を
参照して説明する。
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

第1図から第3図は、この発明に係る地質不良
地におけるトンネルの構築工法の一実施例を示す
ものである。
1 to 3 show an embodiment of the method for constructing a tunnel in a geologically poor area according to the present invention.

同図に示す構築工法は、アーチ状に形成された
H型鋼からなる支保工10,10′を、掘削され
たトンネル内に順次設置して、所定のトンネルを
構築する工法をメイン工法として採用し、地質不
良個所においてのみ本発明の工法を補助として採
用した場合を示すものである。
The main construction method shown in the figure is to construct a predetermined tunnel by sequentially installing supports 10 and 10' made of arch-shaped H-shaped steel into an excavated tunnel. , which shows the case where the construction method of the present invention is employed as an aid only in areas with poor geology.

地質不良個所は、トンネルの構築に当たつて綿
密な地質調査が行なわれるため、事前にこれを察
知することは比較的容易であり、地質不良個所ま
で工事が進行すると、先ず先行支保工10,1
0′と掘削後のトンネル地山12間に、円筒状の
外管14の内部に、この外管14より小径の円筒
状内管16を収納した二重管18を、第1図およ
び第2図に示すように先行支保工10,10′間
に掛け渡すように、掘削断面に沿つて且つこの掘
削断面とほぼ直交するように複数本配設し、、前
記外管14の両端をU字ボルト20でもつて前記
先行支保工10,10′のリブ10aに螺着固定
する。
It is relatively easy to detect areas with poor geology in advance because a thorough geological survey is carried out when constructing a tunnel.When construction progresses to an area with poor geology, the preliminary shoring 10, 1
0' and the tunnel ground 12 after excavation, a double pipe 18 is placed between a cylindrical outer pipe 14 and a cylindrical inner pipe 16 having a smaller diameter than the outer pipe 14, as shown in FIGS. 1 and 2. As shown in the figure, a plurality of pipes are arranged along the excavation cross section and almost perpendicular to the excavation cross section so as to span between the preceding shorings 10 and 10', and both ends of the outer pipe 14 are formed into a U shape. Bolts 20 are also screwed and fixed to the ribs 10a of the preceding shoring 10, 10'.

この場合好ましくは、前方の先行支保工10と
外管14との間に、楔形のキヤンバー22を介挿
させることで、第2図に示すように上記二重管1
8を傾斜させ地山に沿つた状態で、上記U字ボル
ト20で螺着することが、後述するように掘削の
進行に伴つて上記内管16を、掘削面側に延長さ
せた場合トンネル地山12に、より良好に密着し
地山12の崩落をより有効に防止できる。
In this case, preferably, a wedge-shaped camber 22 is inserted between the front preceding shoring 10 and the outer pipe 14, so that the double pipe 1
When the inner pipe 16 is extended toward the excavation surface side as the excavation progresses, as will be described later, screwing the U-shaped bolt 20 with the U-shaped bolt 20 in a state where the inner pipe 8 is inclined and follows the ground will cause the tunnel ground to fall. It can better adhere to the mountain 12 and prevent the rock 12 from collapsing more effectively.

そして、この後に上記先行支保工10の一部お
よび上記二重管18を埋め込むようにして、コン
クリート23の吹付けを行ない、これらと地山1
2とを固着する1次覆工となし、次いで地質不良
個所の掘削をするものであるが、この場合掘削の
進行に伴つて上記二重管18の内管16を掘削面
に沿つて掘削方向に延長しながら掘削を進めるこ
とで、内管16の外周面が掘削されたトンネル地
山12に当接し、先行支保工10上を支点する片
持梁として作用し、地山12の崩落を防止しつつ
掘削を進めることができる。
After this, concrete 23 is sprayed to embed a part of the preceding shoring 10 and the double pipe 18, and these and the ground 1
2 is used as the primary lining to secure it, and then excavation is performed in areas with poor geology. In this case, as the excavation progresses, the inner pipe 16 of the double pipe 18 is moved in the excavation direction along the excavation surface. By proceeding with the excavation while extending the inner pipe 16, the outer circumferential surface of the inner pipe 16 comes into contact with the excavated tunnel earth 12, and acts as a cantilever supporting the preceding shoring 10, thereby preventing the earth 12 from collapsing. excavation can proceed while

次いで、所定長掘削が終了すると上記先行支保
工10に隣接して後行支保工24を設置し、コン
クリートを吹付け1次覆工を行なうものである。
この場合、上記二重管18の延長した内管16と
トンル地山12間に、金鋼25を掘削面の全面を
覆うように配置しておくことは、内管16の間隙
部から小岩片の落下が防止されるとともに、外管
14および内管16同志の連結が補強されて地山
12の崩落に対し強度が増すことになり、望まし
いところである。
Next, when the predetermined length of excavation is completed, a trailing shoring 24 is installed adjacent to the preceding shoring 10, and a primary lining is performed by spraying concrete.
In this case, disposing the gold steel 25 between the extended inner pipe 16 of the double pipe 18 and the tunnel ground 12 so as to cover the entire excavated surface means that small pieces of rock can be removed from the gap of the inner pipe 16. This is desirable because it prevents the outer pipe 14 and the inner pipe 16 from falling, and the connection between the outer pipe 14 and the inner pipe 16 is reinforced, increasing the strength against the collapse of the ground 12.

また、上記実施例では上記二重管18を先行支
保工10,10′にU字ボルト20でもつて螺着
固定した後、コンクリート24の吹付けを行なつ
た後、上記内管16を延長させながら掘削をする
場合を示したが、このコンクリート24の吹付け
を行なわず、U字ボルト20でもつて螺着固定し
ただけで掘削作業を進行することも可能であり、
さらに、掘削後の地山12を上述のように内管1
6を片持梁として機能させた状態で順次掘削を進
行し、数区間を1度にまとめてコンクリート23
の吹付けを行ない11次覆工することも可能であ
る。
Further, in the above embodiment, after the double pipe 18 is screwed and fixed to the preceding shoring 10, 10' with U-shaped bolts 20, and after concrete 24 is sprayed, the inner pipe 16 is extended. Although we have shown the case where the concrete 24 is excavated, it is also possible to proceed with the excavation work by simply screwing and fixing the U-shaped bolts 20 without spraying the concrete 24.
Furthermore, the earth 12 after excavation is placed in the inner pipe 1 as described above.
6 is functioning as a cantilever beam, excavation progresses sequentially, and concrete 23 is added to several sections at once.
It is also possible to carry out the 11th lining by spraying.

さて、上述のような構成で地質不良地にトンネ
ルを構築した場合には、上記二重管18の支保工
10,10′への取付けは比較的簡単であること
と、この支保工10,10′間に配設する二重管
18は、従来の工法において支保工10,10′
間に配置されていた径間パイプに代替することが
可能であり、径間パイプを減少させるため、掘削
のサイクルタイムが先行ボルト工法等のように大
幅に延長されることはなく、逆に短縮することが
できる。
Now, when a tunnel is constructed in a geologically poor area with the above-mentioned configuration, it is relatively easy to attach the double pipe 18 to the supports 10, 10', and In the conventional construction method, the double pipe 18 placed between the shoring 10, 10'
It is possible to replace the span pipe that was placed in between, and because the number of span pipes is reduced, the excavation cycle time will not be significantly extended as in the advance bolt method, but on the contrary, it will be shortened. can do.

また、上記二重管18の取付けには、特別な足
場や機械は不要であり、さらにこの二重管18は
安価なため経済的効果は、上記サイクルタイムの
短縮と併せて極めて大きなものとなる。
Additionally, no special scaffolding or machinery is required to install the double pipe 18, and since the double pipe 18 is inexpensive, the economic effect is extremely large in addition to the shortened cycle time. .

さらに、1次覆工としてコンクリートの吹付け
を行なつた場合においても、従来の縫地、送り矢
板工法のように、矢板の背面に空隙を生ずる恐れ
は全くなく、1次覆工を完全なものとすることが
できるとともに、従来の先行ロツクボルト工法等
のように余掘が生じないため、吹付けコンクリー
ト量が増加することもない。
Furthermore, even when concrete is sprayed as the primary lining, there is no risk of creating voids on the back of the sheet piles, unlike in conventional seamed or fed sheet pile construction methods, and the primary lining can be completed completely. In addition, unlike the conventional pre-lock bolt construction method, no additional excavation is required, so the amount of shotcrete does not increase.

さらにまた、トンネル地山12の崩落は、金鋼
25を設けることで小崩落も防止できるため、見
た目に安全であるという心理的効果も加わり、切
羽作業は安心して行える。
Furthermore, since small collapses of the tunnel earth 12 can be prevented by providing the metal steel 25, the psychological effect of visual safety is added, and face work can be carried out with peace of mind.

なお、上記実施例においては、構築されるトン
ネルの特定個所に地質不良個所を有する場合につ
いて説明したが、地質不良個所がトンネルの全長
に亙る場合においても、本発明が適用できること
は勿論である。
In the above embodiments, a case has been described in which a tunnel to be constructed has a geological defect at a specific location, but the present invention is of course applicable even when the geological defect extends over the entire length of the tunnel.

以上実施例で詳細に説明したように、この発明
は支保工を使用するトンネルの構築工法におい
て、支保工とトンネル地山の間に二重管を複数配
置し、掘削の進行に伴つて内管を延長すること
で、掘削後の地山の崩落を防止しながらトンネル
の掘削作業を行なうものであり、地質不良地にお
いて地山の崩落を、比較的簡単な構成でもつて、
掘削サイクルタイムを延長することなく有効に防
止できるため、安全且つ経済的にトンネルを構築
することができる。
As explained in detail in the embodiments above, the present invention is a tunnel construction method using shoring, in which a plurality of double pipes are arranged between the shoring and the tunnel ground, and as excavation progresses, the inner pipes By extending the length of the tunnel, tunnel excavation work can be carried out while preventing the collapse of the ground after excavation.
Since this can be effectively prevented without prolonging the excavation cycle time, tunnels can be constructed safely and economically.

【図面の簡単な説明】[Brief explanation of drawings]

第1図から第3図は、この発明の一実施例を示
すもので、第1図は二重管の配置を示す説明図、
第2図は第1図の断面図、第3図は第1図の部分
拡大図である。 10,10′……先行支保工、10a……リブ、
12……トンネル地山、14……外管、16……
内管、18……二重管、20……U字ボルト、2
4……後行支保工。
1 to 3 show an embodiment of the present invention, and FIG. 1 is an explanatory diagram showing the arrangement of double pipes;
2 is a sectional view of FIG. 1, and FIG. 3 is a partially enlarged view of FIG. 1. 10, 10'...Advanced shoring, 10a...Rib,
12...Tunnel ground, 14...Outer tube, 16...
Inner pipe, 18...Double pipe, 20...U-shaped bolt, 2
4... Trailing shoring.

Claims (1)

【特許請求の範囲】[Claims] 1 掘削後のトンネル地山の崩落を防止するため
にトンネル内に順次支保工を設置してトンネルを
掘削する工法において、支保工と掘削後のトンネ
ル地山の間に筒状の外管内に該外管より小径の内
管を収納した二重管を掘削断面に沿つてほぼこれ
に直交するように複数本配設し該支保工と固定し
た後、掘削の進行にともなつてそれぞれの該内管
を順次掘削面に沿つて掘削方向に延長することで
掘削後の地山の崩落を防止するようにしてなるこ
とを特徴とする地質不良地におけるトンネルの構
築工法。
1. In a method of excavating a tunnel by sequentially installing supports inside the tunnel in order to prevent the tunnel ground from collapsing after excavation, there is a tunnel that falls between the support and the excavated tunnel ground within the cylindrical outer pipe. A plurality of double pipes containing inner pipes with a smaller diameter than the outer pipe are arranged along the excavation cross section so as to be almost perpendicular thereto, and are fixed to the shoring, and as the excavation progresses, each inner pipe is A method for constructing a tunnel in a geologically poor land, characterized in that the pipe is successively extended in the excavation direction along the excavation surface to prevent the collapse of the ground after excavation.
JP1546583A 1983-02-03 1983-02-03 CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO Expired - Lifetime JPH0240835B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1546583A JPH0240835B2 (en) 1983-02-03 1983-02-03 CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1546583A JPH0240835B2 (en) 1983-02-03 1983-02-03 CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO

Publications (2)

Publication Number Publication Date
JPS59141695A JPS59141695A (en) 1984-08-14
JPH0240835B2 true JPH0240835B2 (en) 1990-09-13

Family

ID=11889545

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1546583A Expired - Lifetime JPH0240835B2 (en) 1983-02-03 1983-02-03 CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO

Country Status (1)

Country Link
JP (1) JPH0240835B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0470459A (en) * 1990-07-10 1992-03-05 Tsutomu Honma Step stone and stair lighting system

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008248528A (en) * 2007-03-29 2008-10-16 Nippo Kk All-ground-fasten tunneling method
JP2010090608A (en) * 2008-10-08 2010-04-22 Taisei Corp Method for constructing underground space and structure of the underground space

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0470459A (en) * 1990-07-10 1992-03-05 Tsutomu Honma Step stone and stair lighting system

Also Published As

Publication number Publication date
JPS59141695A (en) 1984-08-14

Similar Documents

Publication Publication Date Title
JP3677699B2 (en) Construction method of tunnel junction
JPH0765455B2 (en) Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint
JP2788953B2 (en) Structure of tunnel structure
JPH0240835B2 (en) CHISHITSUFURYOCHINIOKERUTONNERUNOKOCHIKUKOHO
JPH0835391A (en) Preceding leg reinforcing type fore piling method by heading
JPH03202599A (en) Reinforced structure of twin tunnels
JP2884452B2 (en) Shaft construction method using segments
JPH07139300A (en) How to build an underground structure
JP2593356B2 (en) Tunnel construction method
JP3735411B2 (en) Tunnel lining method
JPH05280296A (en) Large scale underground structure and construction method thereof
JP3135495B2 (en) Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence
JPH0312633B2 (en)
JPS6216309B2 (en)
JP4867488B2 (en) Construction method of underground space, underground space constructed by this method, and underground structure constructed by this method
JP2681741B2 (en) Vertical shaft construction method and composite soil retaining material used for it
JP2700693B2 (en) How to build a large architectural space underground
CN212105885U (en) A preliminary bracing structure that is used for full section assembled lining in drilling and blasting method tunnel
JP3947363B2 (en) Tunnel support method and tunnel support method
JP7731022B1 (en) Launching equipment and launching method for tunneling machine
JP3450172B2 (en) Tunnel support structure
JP2725972B2 (en) Underground structure construction method and segment piece used therefor
CN215830516U (en) Underground concrete chamber supporting structure combining jet grouting pile and anchor rod
JP2987265B2 (en) Tunnel excavation method using belt-like reinforcement
CN211287718U (en) Supporting device for construction of main slope ramp of prospecting mine