JPH02491B2 - - Google Patents
Info
- Publication number
- JPH02491B2 JPH02491B2 JP51061370A JP6137076A JPH02491B2 JP H02491 B2 JPH02491 B2 JP H02491B2 JP 51061370 A JP51061370 A JP 51061370A JP 6137076 A JP6137076 A JP 6137076A JP H02491 B2 JPH02491 B2 JP H02491B2
- Authority
- JP
- Japan
- Prior art keywords
- injection
- ground
- soft
- soil
- liquid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Soil Conditioners And Soil-Stabilizing Materials (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【発明の詳細な説明】
この発明はセメントミルク主体液の地盤注入に
よる軟弱粘性土地盤の改良工法とその工法に使用
される装置に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for improving soft and viscous soil by injecting a cement milk-based liquid into the ground, and an apparatus used in the method.
セメントミルクを主体とした注入液を用いた地
盤注入によつて軟弱な粘性土地盤が破壊されて亀
裂を形成することは既に実験的に確認し得たとこ
ろであり、また、モール・クーロンの破壊理論に
よつても理論的に証明することができるが、この
発明はこれらの理論と実際を発展的に応用して(イ)
軟弱粘性土地盤を改良する工法と(ロ)改良基準の判
定装置をかねた軟弱粘性土地盤改良工法用セメン
トミルク主体液の注入装置である。 It has already been experimentally confirmed that the soft and viscous soil is destroyed and cracks are formed by injecting the ground using an injection liquid mainly composed of cement milk, and the Mohr-Coulomb failure theory Although it can be theoretically proven by
This is a method for improving soft and viscous soil, and (b) an injection device for a cement milk-based liquid for a method of improving soft and viscous soil, which also serves as a determination device for improvement standards.
軟弱粘性土地盤の改良工法として、これまで一
般的に採用されてきている工法としては置換工法
と脱水圧密工法に大別され、それぞれの工法につ
いてもいくつかの種類と特徴がある。後者につい
て言えば、たとえば、プレローデイング工法、サ
ンドドレーン工法、ペーパードレーン工法等であ
つて、各々一長一短があるが、これらに共通して
いるのは、一般にかなり長期間にわたる工期をと
ることと、載荷物を必要とすることである。軟弱
粘性土地盤を対象とした土木工事では新しく造ら
れる道路や堤防盛土等の場合でも、またこうした
土構造物が辷り破壊や地震等で被害をうけて早急
に復旧しなければならないような場合でも、現在
の社会構造では長期間の工期は大きな障害とな
る。ある場合には、載荷物を用いられないような
條件もあるし、手もどり等で経済的に不利となる
場合もでてくる。 The methods that have been generally used to improve soft and cohesive soil are broadly divided into replacement methods and dehydration consolidation methods, and each method has several types and characteristics. Regarding the latter, for example, there are pre-loading methods, sand drain methods, paper drain methods, etc., each of which has its advantages and disadvantages, but what they all have in common is that they generally take a fairly long construction period; It is necessary to carry cargo. In civil engineering work that targets soft and cohesive soil, it is useful even when constructing a new road or embankment, or when such earth structures have been damaged by sliding or earthquakes and must be quickly restored. , In the current social structure, a long construction period is a major obstacle. In some cases, there are conditions that make it impossible to use loaded cargo, and there are also cases where it is economically disadvantageous to have to go back.
この発明は以上述べたようなこれまでの工法の
欠点を除去することによつて、短期間に安全に施
工できて、しかもより経済的な軟弱粘性土地盤の
改良工法とその装置を提供するを目的とする。 The present invention aims to provide an improved construction method and equipment for soft and viscous soil that can be constructed safely in a short period of time and is more economical by eliminating the drawbacks of the conventional construction methods as described above. purpose.
次にこの発明の構成を説明する。 Next, the configuration of this invention will be explained.
まず、本願の全体の構成として本願の地盤改良
の原理を第4図及び第5図を参照しながら説明す
る。 First, the principle of ground improvement of the present application will be explained as the overall structure of the present application with reference to FIGS. 4 and 5.
第4図は従来技術で先端コーンを用いて軟弱地
盤の貫入抵抗値を測定する場合の模式図である。
すなわち、1は施工地盤のある深度に貫入装置を
セツトした状態を示したものであるが、先端部だ
けの貫入抵抗値を測定しようとすれば接続するロ
ツドの周面に作用する摩擦抵抗を除かなければな
らないから、図のように2重管式の構造にしてお
く必要がある。この時、2のように機械力または
人為的な力によつて与えられる圧力pをロツド頭
部に加えると先端コーンは地盤中に貫入する。こ
の場合、先端コーンを地盤に貫入させる条件とし
て圧力pが地盤の強度qよりも大きいことが必要
であつてp>qの関係が成立しなければ対象地盤
を破壊させることができない。 FIG. 4 is a schematic diagram of measuring the penetration resistance value of soft ground using a tip cone according to the prior art.
In other words, 1 shows the state in which the penetration device is set at a certain depth in the construction ground, but if you want to measure the penetration resistance value only at the tip, it is necessary to remove the frictional resistance acting on the circumferential surface of the connecting rod. Therefore, it is necessary to have a double pipe structure as shown in the diagram. At this time, if pressure p is applied to the rod head by mechanical or artificial force as shown in step 2, the tip cone penetrates into the ground. In this case, the condition for penetrating the tip cone into the ground is that the pressure p must be greater than the strength q of the ground, and unless the relationship p>q holds, the target ground cannot be destroyed.
本願では、以上述べた原理を応用して、圧力p
のかわりに(イ)注入液の密度と注入パイプの高さで
決まる液圧および(ロ)圧送圧をある一定の関係に調
整して得られる圧力(注入圧力)をp′とした場
合、p′の条件をp′>qとすれば第5図に示したよ
うに地盤注入によつて対象地盤を破壊させること
ができる。 In this application, by applying the principles described above, the pressure p
Instead, if p′ is the pressure (injection pressure) obtained by adjusting (a) the liquid pressure determined by the density of the injected liquid and the height of the injection pipe, and (b) the pumping pressure to a certain relationship, then p If the condition for ' is p'> q, the target ground can be destroyed by ground injection as shown in Figure 5.
第4図の場合は、地盤強度を連続的に測定しよ
うとすると、外管の圧入→先端コーンの貫入の操
作をくりかえさなければならないが、第5図の場
合はp′の破壊条件をかえないならば破壊はそのま
ま連続して進行することになるから、この過程に
ある注入液は流動していることになり、注入液に
よる流動体を形成してp′=qとなるまで注入液に
よる破壊領域が広がることになる。そして施工時
における地盤強度qよりも大きい強度q′が得られ
るように注入地盤を改良強化しようとする場合に
は新たな破壊条件p″を設定してp″>q′となるよう
な管理注入を行う。 In the case of Fig. 4, if you want to measure the ground strength continuously, you have to repeat the operation of pressing in the outer tube and inserting the tip cone, but in the case of Fig. 5, the failure condition of p' does not change. In this case, since the destruction continues to proceed as it is, the injection liquid in this process is flowing, and the injection liquid forms a fluid and the destruction by the injection liquid continues until p′ = q. The area will expand. When attempting to improve and strengthen the poured ground so as to obtain a strength q' that is greater than the ground strength q at the time of construction, a new failure condition p'' is set and controlled injection is performed so that p''>q'. I do.
第5図について、実験を行つたすべての結果か
ら、このようにして形成される注入体は注入中か
ら固結するまでの間に鉛直方向または斜鉛直方向
に層状の流動体をつくることが確認された。 Regarding Figure 5, all the experimental results confirmed that the injection body formed in this way creates a layered fluid in the vertical or oblique vertical direction from the time of injection until solidification. It was done.
この場合、地盤改良計画に基づいて主として、
注入箇所より上向きの鉛直方向に改良域を設定す
る場合と下向きの場合に大別される。一般の場合
は、注入液の注入箇所より下方向に改良域が拡が
るが、改良計画の一定深度から上方を改良強化し
ようとする場合には、軽量の注入材料を用いて、
注入装置を第1図ロにセツトして高圧注入を行
う。いづれの場合も、ほぼ鉛直に近い層状の流動
体が形成される。 In this case, mainly based on the ground improvement plan,
There are two main types: cases in which the improvement area is set vertically upward from the injection point and cases in which the improvement area is set downward. In general, the improvement area expands downward from the injection point of the injection liquid, but when trying to improve and strengthen the area above a certain depth of the improvement plan, using a lightweight injection material,
The injection device is set as shown in Fig. 1B, and high-pressure injection is performed. In either case, a nearly vertical layered fluid is formed.
以上に述べた原理と注入のメカニズムによつ
て、地盤注入が進行し、破壊領域が拡大するとと
もに次々と流動体が形成されて量的、質的に成長
する。完全に飽和された軟弱粘性土地盤に注入材
料が注入されるということは、地盤を構成してい
る間隙部が注入材料と置き換わることである。し
たがつて、その過程では、注入中絶えず両者のバ
ランスが維持されていることになるから、同一条
件で注入が継続している限り初期の注入圧が失わ
れることはない。つまり、一定の改良範囲に関し
ては、初期圧力がそのまま続いている状態から次
第に注入圧が増加し、それとともに改良度が増大
していくことになる。一方、一定範囲内で目的と
する改良が終了して最終的な管理圧力を超せば流
動体は対象範囲外に拡大するため、この場合は当
然に最終管理圧力以下の注入圧となる。 According to the principle and injection mechanism described above, the ground injection progresses, the fracture area expands, and fluids are formed one after another, growing quantitatively and qualitatively. When the injection material is injected into the completely saturated soft and viscous ground, the gap that makes up the ground is replaced with the injection material. Therefore, in this process, the balance between the two is constantly maintained during injection, so as long as injection continues under the same conditions, the initial injection pressure will not be lost. In other words, within a certain improvement range, the injection pressure gradually increases from a state where the initial pressure continues as it is, and the degree of improvement increases accordingly. On the other hand, if the intended improvement is completed within a certain range and the final control pressure is exceeded, the fluid will expand outside the target range, so in this case, the injection pressure will naturally be less than the final control pressure.
尚、注入圧は第6図に示したように注入液の密
度と注入点の注入高さLで決まる液圧とグラウト
ポンプから注入地点までの圧送圧の和で表わされ
る。第6図中、21はセメントミルク主体液圧送
用高圧ゴムホース、22はスイベル(回り継手)、
23は先端コーンの位置を設定する調整装置であ
る。 Incidentally, as shown in FIG. 6, the injection pressure is expressed as the sum of the liquid pressure determined by the density of the injection liquid and the injection height L of the injection point, and the pumping pressure from the grout pump to the injection point. In Fig. 6, 21 is a high-pressure rubber hose for pumping the cement milk main liquid, 22 is a swivel (swivel joint),
23 is an adjustment device for setting the position of the tip cone.
このように、注入液が目的とする対象範囲外に
逃げないようにするために、実際上は、図面第2
図Bと第3図に示したように(1)矢板等の仮設物を
用いてあらかじめ障壁の構造を仮設するか、また
は、(2)施工範囲の複数の注入点の中で、まず外側
の注入点の注入を先行して周壁の構造をつくつた
上で次に内側の注入にかかる方法が採られる。 In this way, in order to prevent the injection liquid from escaping outside the intended target area, in practice,
As shown in Figure B and Figure 3, (1) the barrier structure is constructed in advance using temporary materials such as sheet piles, or (2) the barrier structure is first constructed at the outside of the multiple injection points in the construction area. A method is adopted in which the structure of the peripheral wall is created by first injecting the injection points, and then the inner part is injected.
以上について、本願工法によつて達成される効
果を要約すると、本願工法の特徴は、(1)原位置急
速載荷効果、(2)原位置急速脱水効果、(5)原位置ド
レーン(排水)効果、(4)原位置固結効果、(5)原位
置置換効果のすべての効果が同一工程においてほ
ぼ同時に得られることである。この場合は、これ
らの効果全部に関与するのは、注入液(セメント
ミルク主体液)である。この中で(1)〜(3)までの効
果のメカニズムについて述べれば、注入液は(1)〜
(2)については加圧脱水材、(3)についてはドレーン
材としての機能を果たし、ここまでのプロセスは
あらかじめ設定した改良計画の下で、決められた
注入液によつて地盤注入が継続されていることが
本願工法の条件であつて、従来技術にない画期的
な発明である。したがつて、一般用語の注入液、
グラウト(注入材料)などでは、以上述べた特徴
を表現することができないので、発明用語として
「流動体」を用いた。また、地盤注入で注入中(1)
〜(3)の効果が得られた後、注入液(セメントミル
ク主体液)は約24時間以内に注入されたそのまま
の位置即ち原位置で固結するため、この約24時間
以後の効果が(4)の原位置固結効果と(5)の原位置置
換効果である。つまり、(1)〜(3)の効果は約24時間
以内に作用するので、この間に圧密脱水と排水が
終了する。 Regarding the above, to summarize the effects achieved by the present construction method, the characteristics of the present construction method are (1) in-situ rapid loading effect, (2) in-situ rapid dewatering effect, and (5) in-situ drain effect. , (4) in-situ consolidation effect, and (5) in-situ substitution effect can all be obtained almost simultaneously in the same process. In this case, it is the injection liquid (cement milk-based liquid) that is responsible for all of these effects. Among these, if we talk about the mechanisms of effects (1) to (3), the injection solution is
(2) functions as a pressurized dewatering material, and (3) functions as a drain material, and the process up to this point continues to be injected into the ground with a predetermined injection liquid under a preset improvement plan. This is a condition of the present construction method, and is an epoch-making invention not found in the prior art. Hence the general term infusion,
Since grout (pouring material) and the like cannot express the above-mentioned characteristics, "fluid" was used as the invention term. Also being injected into the ground (1)
After the effect of (3) is obtained, the injection liquid (cement milk-based liquid) solidifies at the same position where it was injected within about 24 hours, so the effect after about 24 hours is ( (4) in-situ consolidation effect and (5) in-situ displacement effect. In other words, the effects (1) to (3) take effect within about 24 hours, so the consolidation dewatering and drainage are completed during this time.
従来技術で、軟弱粘性土地盤を改良する工法に
はいろいろな工法があるが、圧密脱水を改良原理
とする代表例は盛土などの載荷重を用いた「脱水
圧密」工法と圧密を促進するために砂柱をドレー
ン材として使用した「サンドドレーン」工法であ
る。 There are various methods to improve soft and cohesive soil using conventional technology, but the typical example that uses consolidation and dewatering as the improvement principle is the "dewatering consolidation" method that uses loading such as embankment, and the method to promote consolidation. This is a ``sand drain'' construction method that uses sand pillars as drain material.
原理は同じであつても、このような従来技術の
「脱水圧密」の機構と本願による「脱水圧密」の
機構を比較すると次のようになる。 Even though the principles are the same, a comparison between the "dehydration consolidation" mechanism of the prior art and the "dehydration consolidation" mechanism of the present application is as follows.
第7図は盛土の載荷重のみで脱水圧密を行う機
構であり、第8図はサンドドレーンなどのドレー
ン材を用いて脱水圧密を促進する機構で縦線がそ
のドレーン材であることを示してある。このよう
に従来技術では、軟弱粘性土層が厚い場合には、
載荷重は地表面にしか載荷できないので、なかな
か下層部まで応力が伝わりにくいから圧密時間が
長期間かかるとともに、実際上、どれだけの時間
に、どの範囲に、どれだけの圧密度が得られるか
どうかをいちいち確認することが極めて困難であ
つて、一定時間(期間)ごとに確認する以外に方
法がなかつた。また、事前の予測としては、ある
程度まで圧密理論によつて予測できるが、現在の
技術をもつてしても理論と実際の施工との間に相
当の差がある。 Figure 7 shows a mechanism that performs dewatering and consolidation using only the loading load of the embankment, and Figure 8 shows a mechanism that promotes dewatering and consolidation using a drain material such as a sand drain, and the vertical lines indicate the drain material. be. In this way, with the conventional technology, when the soft cohesive soil layer is thick,
Since the load can only be applied to the ground surface, it is difficult for the stress to be transmitted to the lower layers, so consolidation time takes a long time, and in reality, it is difficult to achieve how much consolidation density can be achieved in what time, in what area, and in what area. It was extremely difficult to check each time, and there was no other way than to check at regular intervals (periods). In addition, advance predictions can be made to some extent based on consolidation theory, but even with current technology there is a considerable difference between theory and actual construction.
以上述べたことから従来技術の欠点は圧密理論
が成立するために必要とされる次の3点が満足さ
れていないことによるものである。即ち、
(1) 圧密の速度は目的とする改良範囲(深度や拡
がり)に影響を与える排水の距離が短かければ
短かい程、最も有効に短時間で進行する。 As stated above, the drawbacks of the prior art are due to the fact that the following three points required for the consolidation theory to hold true are not satisfied. That is, (1) The speed of consolidation is most effective and progresses in a short time, the shorter the distance of drainage that affects the target improvement area (depth and spread).
(2) 同時に(1)と関連して(1)の範囲に作用する載荷
重の大きさが大きければ大きい程、圧密の速度
が速くなる。(2) At the same time, in relation to (1), the greater the magnitude of the applied load acting on the range of (1), the faster the consolidation speed.
(3) (1)と(2)が同一時間で原位置の同一箇所で同時
に作用しなければ圧密の効果が少なくなる。(3) If (1) and (2) do not act at the same time and at the same location at the same time, the consolidation effect will be reduced.
以上の3点を同時に解決しようとしたのが本願
工法の最も基本的な特徴の一つであり、in situ
(原位置)の技術思想を導入したものである。 One of the most basic features of the proposed method is that it attempted to solve the above three points at the same time.
(in-situ) technical philosophy was introduced.
本願の脱水圧密の機構は、第11図に示したよ
うに、地盤注入によつて注入中に形成される鉛直
方向または斜鉛直方向の層状の流動体が載荷面で
あつて従来技術の盛土に相当する。したがつて、
本願工法では従来技術の必要条件である盛土を必
要としない(第9図点線部分がそれに相当する)
ことと、複数の載荷面を有する地盤注入中に注入
圧が載荷重となり、しかも、この載荷重は、従来
技術の盛土荷重のように限定されたものではな
く、改良目的によつて自由に調整できるようにな
つている。 As shown in FIG. 11, the mechanism of dewatering consolidation of the present application is that the layered fluid in the vertical or oblique vertical direction formed during the ground injection is the loading surface, and the embankment of the prior art is Equivalent to. Therefore,
The proposed construction method does not require embankment, which is a necessary condition of the conventional technology (the dotted line in Figure 9 corresponds to this).
In addition, the injection pressure becomes a loading load during ground injection with multiple loading surfaces, and this loading load is not limited like the embankment load of conventional technology, but can be freely adjusted according to the purpose of improvement. I'm starting to be able to do it.
また、第9図の縦線に示したように、注入液に
よつてほぼ鉛直方向に形成される流動体間の距離
が本願工法の場合の排水距離Dに相当する。した
がつて、第7図と第8図に示した従来技術の排水
距離Dと比較して大巾に短縮できる。 Further, as shown by the vertical lines in FIG. 9, the distance between the fluid bodies formed by the injection liquid in the substantially vertical direction corresponds to the drainage distance D in the method of the present application. Therefore, compared to the drainage distance D of the prior art shown in FIGS. 7 and 8, it can be greatly shortened.
尚、第7図乃至第9図の符号Bは盛土を示し、
符号Hは圧密層の厚さを示し、その下方部分の符
号Sは非圧密層(砂質土層)を示すものである。 In addition, the symbol B in FIGS. 7 to 9 indicates embankment,
The symbol H indicates the thickness of the consolidated layer, and the symbol S below it indicates the unconsolidated layer (sandy soil layer).
ここで、限定されたものという意味は、一つに
は予め盛土できる高さが技術的、人為的に限定さ
れるということと、一つには盛土による辷り破壊
の防止と盛土の周囲に対する地盤変状(盛上り、
沈下など)を避けなければならないということで
あつて、本願工法では地盤破壊や地盤変状を起こ
さないように十分に管理できることと、また、改
良設計を満足する最適載荷重を事前に決め、施工
中の管理もできるものである。従つて、注入液
は、地盤注入中は、調整可能な加圧材の機能を有
するものであつて、注入中の流動体の全域にわた
つて、ほぼ同じ物理量で作用する。即ち、注入さ
れたそのままの位置(原位置)で作用する点にお
いて、従来技術の圧密機構と全く異なるものであ
つて、本願の圧密機構の最大の利点は目的に従つ
て時間的、量的に調整可能な原位置載荷である。 Here, the meaning of "limited" means that, on the one hand, the height of the embankment is technically or artificially limited, and on the other hand, it means that the height of the embankment is technically or artificially limited, and on the other hand, it is necessary to prevent sliding damage caused by the embankment, and to prevent the ground from collapsing around the embankment. Deformation (swelling,
This means that the proposed construction method can be sufficiently controlled to prevent ground destruction or deformation, and that the optimum load that satisfies the improvement design must be determined in advance and the construction method must be avoided. You can also manage the inside. Therefore, the injection liquid has the function of an adjustable pressurizing material during ground injection, and acts in substantially the same physical amount over the entire area of the fluid being injected. In other words, it is completely different from the consolidation mechanism of the prior art in that it works at the same position (in-situ) as it is injected, and the greatest advantage of the consolidation mechanism of the present application is that it works in the same position (in situ) as it is injected. Adjustable in-situ loading.
次に脱水の機構について述べる。完全に飽和し
た軟弱粘性土地盤の場合は、間隙水とガス成分に
よつて占められる間隙部分と土粒子部から構成さ
れており、圧密(圧縮)現象とはこの間隙部分が
減少していく過程である。従つて、一般の地盤の
場合は、ガス成分は無視できるので、間隙水が地
盤から脱水されて改良しようとする対象地盤外に
排出されることであり、逆に脱水して排出されな
ければ圧密(圧縮)現象は起こらない。従来技術
で第10図の圧密に長時間を要するのは、間隙水
の脱水と排水が容易に起こりにくいからである。 Next, we will discuss the dehydration mechanism. In the case of a completely saturated soft and viscous soil, it is composed of pores occupied by pore water and gas components and soil particles, and consolidation (compression) is a process in which these pores decrease. It is. Therefore, in the case of ordinary ground, the gas component can be ignored, so pore water is dehydrated from the ground and discharged outside the ground to be improved; conversely, if it is not dehydrated and discharged, it will not be consolidated. (compression) phenomenon does not occur. The reason why the consolidation shown in FIG. 10 takes a long time in the prior art is that pore water is not easily dehydrated and drained.
圧密現象に限つた場合、この間隙水の脱水と排
水を極く短時間の間に可能にする方法は(1)自然地
盤のもとの位置でそのまま載荷重を加えること
(原位置載荷)と、(2)そのままの位置(原位置)
に排水路を造つて載荷重で脱水された間隙水を地
盤外に排水する以外に方法はない。しかも(1)と(2)
が同一時間に同一空間に同時に作用することが必
要条件である。 In the case of consolidation phenomena, the methods to make it possible to dehydrate and drain this pore water in a very short period of time are (1) applying a load to the natural ground at its original location (in-situ loading); , (2) Same position (original position)
There is no other way than to build a drainage channel and drain the pore water dewatered by the applied load out of the ground. Moreover, (1) and (2)
The necessary condition is that they act simultaneously on the same space at the same time.
注入液は、単なる注入液ではなく、以上の必要
条件を満足する機能を有するものであつて、本願
では、先に述べた意味に加えてこのような意味で
「流動体」とした。したがつて、流動体と流動体
の間に挾まれた範囲のみが脱水されるのではな
く、注入によつて形成される流動体自体とそのま
ま原位置で置き換えられるのが脱水である。 The injection liquid is not just an injection liquid, but has a function that satisfies the above-mentioned requirements, and in this application, the term "fluid" is used in this sense in addition to the above-mentioned meaning. Therefore, dehydration does not involve dehydrating only the area sandwiched between the fluids, but instead replaces the fluid itself formed by injection in situ.
次に排水の機構について述べる。 Next, we will discuss the drainage mechanism.
流動体は注入中、常に設計上必要な注入圧で管
理されている。また、注入液はセメントを主体材
料とする複数の注入材料で組成された特定の配合
でつくられており、注入後約24時間以内で固結す
るようになつている。この両者を合理的に調整し
て目的に合つた適切な地盤改良計画が設計され
る。 During injection, the fluid is always controlled at the injection pressure required by design. In addition, the injection liquid is made with a specific composition of multiple injection materials, mainly cement, and is designed to solidify within about 24 hours after injection. By rationally adjusting these two factors, an appropriate ground improvement plan that meets the purpose is designed.
注入液が対象地盤に注入されて流動体を形成す
るためには、対象地盤の中の間隙水が脱水されて
地盤外に排出されることが条件である。 In order for the injection liquid to be injected into the target ground to form a fluid, it is necessary that the pore water in the target ground be dehydrated and discharged to the outside of the ground.
具体的な排水のメカニズムは次のようになる。 The specific drainage mechanism is as follows.
地盤中の間隙水が脱水される過程を考えてみる
と、(1)地盤の透水性がよいかどうか、(2)透水が静
的に行われるか動的に行われるか、(3)荷重の大き
さ、(4)排水距離が脱水の関連因子である。 When considering the process by which pore water in the ground is dehydrated, there are several factors to consider: (1) whether the ground has good permeability, (2) whether water permeation occurs statically or dynamically, and (3) the load. and (4) drainage distance are factors related to dehydration.
(1)〜(2)との関連で静的に行われる場合は圧縮さ
れて過剰間隙水圧が発生することが必要であり、
動的な場合は動水勾配を与えること、即ち流動が
条件となる。従来技術では、例えば盛土だけの荷
重を加えて脱水させるのは(1)の透水性の問題であ
り、少しでも脱水を早くするためにサンドドレー
ンなどのドレーン材が使用されている。また(1)と
(2)をより効果的に機能させるためには、(3)載荷重
の大きさと(4)排水距離が問題となる。しかしなが
ら、実際の載荷重は大部分が盛土の荷重であるか
ら、その大きさは現実的に大きな制約がある。つ
まり、(イ)一度に急速に盛土すれば、盛土地盤の破
壊や、盛土地盤の周辺の沈下や盛り上がりなどが
発生するので、段階的に盛土しなければならない
ことと(ロ)軟弱層が厚い場合には軟弱層全体に荷重
が伝わりにくい。これはドレーンを施工した場合
についてもいえることである。 In connection with (1) to (2), if it is performed statically, it is necessary to compress and generate excess pore water pressure.
In the dynamic case, the condition is to provide a hydraulic gradient, that is, flow. In the conventional technology, for example, dewatering by applying the load of only the embankment is a problem of water permeability (1), and drain materials such as sand drains are used to speed up dewatering as much as possible. Also (1)
In order to make (2) work more effectively, (3) the size of the applied load and (4) the drainage distance become issues. However, since most of the actual load is the load of the embankment, there are realistic restrictions on its size. In other words, (a) if the embankment is carried out rapidly all at once, the embankment base will be destroyed, and the area around the embankment base will sink or swell, so the embankment must be done in stages; and (b) the soft layer is thick. In some cases, it is difficult for the load to be transmitted to the entire soft layer. This also applies when drains are installed.
動水勾配を与える従来の方法は、サンドドレー
ンを通して脱水された間隙水を揚水ポンプでくみ
上げるなどの方法もあるが、広域にわたつて地盤
沈下を生じたりするので現在ではほとんど用いら
れていない。 Conventional methods for creating a hydraulic gradient include pumping dewatered pore water through sand drains using lift pumps, but these methods cause ground subsidence over a wide area, so they are rarely used today.
これに対して、本願工法の場合は、(1)について
は、従来技術と本願工法に共通の地盤条件であつ
て軟弱粘性土地盤の透水性は、透水係数で表わす
とすれば、10-7cm/sec以上のオーダーである。
(2)については、静的な場合でも、本願工法は、原
位置載荷と原位置脱水を主体工法とする技術であ
るから、従来技術の載荷重と比較すれば格段の大
きさの差がある。また、動的な手段については従
来技術では上述の通り現実的に適用できる可能性
は限られるが、本願工法では、注入中の注入液が
流動体であるために原位置排水が最も効率的に行
われるから、従来技術のサンドドレーンが極めて
小さい動水勾配の排水路とすれば、本願工法の排
水機構はいわば動水勾配が非常に大きい排水路に
相当する。 On the other hand, in the case of the present construction method, regarding (1), the permeability of the soft and weakly viscous soil, which is a ground condition common to the conventional technology and the present construction method, is 10 -7 if expressed in terms of permeability coefficient. It is on the order of cm/sec or more.
Regarding (2), even in a static case, the proposed construction method is a technology that mainly uses in-situ loading and in-situ dewatering, so there is a significant difference when compared to the loading of conventional technology. . In addition, with regard to dynamic means, the possibility of practical application is limited as described above in the conventional technology, but in the present construction method, in-situ drainage is the most efficient method because the injected liquid is a fluid. Therefore, if the sand drain of the prior art is a drainage channel with an extremely small hydraulic gradient, the drainage mechanism of the present method corresponds to a drainage channel with an extremely large hydraulic gradient.
上述したことを基礎として、「排水」のメカニ
ズムを詳述すると以下のようになる。 Based on the above, the mechanism of "drainage" is detailed as follows.
本願工法については、(1)注入によつて脱水され
る間隙水は、注入直後の瞬間的な状態でとらえれ
ば、流動体にとり込まれて注入液が希釈される。
このことは、流動体が地表にリークする場合、水
(間隙水)→薄い(希釈された)セメントミルク
主体液→原液のセメントミルク主体液という順序
で流出することなどから実験的に明らかである。
即ち、次々と連続的に注入されてくるセメントミ
ルク主体液がおよぶ範囲つまり破壊領域の末端部
では、最も注入液の希釈度が高くなるため、破壊
範囲(破壊条件)が限界となり、それ以上破壊を
起こすことができない(流動体の成長が止まる)
ので注入液は逆流し、地表にリークする。また、
対象地盤中に砂質土層などの排水層が存在すれば
この排水層に排出される。(2)実際注入が継続して
いる場合は次のようなメカニズムによるものであ
つて、実験でも確認されている。即ち、第11図
に示したように注入中の流動体の断面で考えれ
ば、流動体の中心部は原液のセメントミルク主体
液で占められているが、注入地盤と接する部分つ
まり流動体の外側の部分が中心部から離れるにつ
れて原液から希釈されたセメントミルク主体液→
水(間隙水)となつているので、流動体と注入地
盤に接する部分が排水路の役割りを果たしてお
り、本願工法の最も基本的な圧密−脱水−排水の
メカニズムである。 Regarding the construction method of the present application, (1) If the pore water dehydrated by injection is captured in an instantaneous state immediately after injection, it will be incorporated into the fluid and the injection liquid will be diluted.
This is experimentally clear from the fact that when fluid leaks to the ground surface, it flows out in the following order: water (pore water) → thin (diluted) cement milk-based liquid → undiluted cement milk-based liquid. .
In other words, in the area covered by the cement milk-based liquid that is continuously injected one after another, that is, at the end of the destruction area, the degree of dilution of the injected liquid is highest, so the failure range (destruction condition) becomes the limit, and no further failure will occur. cannot occur (fluid growth stops)
Therefore, the injected liquid flows backwards and leaks to the ground. Also,
If a drainage layer such as a sandy soil layer exists in the target ground, the water will be discharged into this drainage layer. (2) If the injection actually continues, it is due to the following mechanism, which has been confirmed through experiments. In other words, if we consider the cross section of the fluid being injected as shown in Figure 11, the center of the fluid is occupied by the undiluted cement milk solution, but the part in contact with the injected ground, that is, the outside of the fluid, Cement milk-based liquid diluted from the original solution as the part moves away from the center →
Since it is water (pore water), the part where the fluid comes into contact with the injection ground plays the role of a drainage channel, which is the most basic consolidation-dewatering-drainage mechanism of the present method.
この外にも、真空作用による脱水があるが、こ
のことは、地盤注入中に、注入を一旦停止して、
注入孔の孔口を閉塞すると、閉塞物が孔内に引込
まれる現象で確認されているが、これは副次的な
脱水機構の一部と考えられる。 In addition to this, there is also dehydration due to vacuum action, but this can be done by temporarily stopping the injection during ground injection.
It has been confirmed that when the injection hole is blocked, the blockage is drawn into the hole, and this is thought to be part of the secondary dehydration mechanism.
以上の工程を繰り返すことによつて各段階の粘
性土の強度は段階的に増加し、結果として軟弱粘
性土地盤が合目的的に改良できることになる。 By repeating the above steps, the strength of the clayey soil at each stage increases step by step, and as a result, the soft clayey soil can be purposefully improved.
この発明の第2の発明即ち軟弱粘性土地盤改良
装置は軟弱粘性土地盤中に鉛直に挿入する注入管
の先端に二重管装置にしたコーンを取付けて、内
管を圧入することによつて、あらかじめ目的とす
る改良範囲の地盤強度を判定し、直ちに地盤改良
計画の基準(注入液の配合−種類、濃度、注入
圧、注入深度、注入方向等)を決定できる装置で
あり同時にこの装置は前記地盤改良計画の基準の
決定に従つて注入圧、注入方法を調整する注入装
置をもかねるようになつている。 The second invention of this invention, that is, the soft and viscous soil improvement device, is achieved by attaching a cone made of a double tube device to the tip of an injection pipe that is vertically inserted into the soft and viscous soil, and press-fitting the inner tube. This device can determine the ground strength of the target improvement area in advance and immediately determine the criteria for the soil improvement plan (mixture of injection liquid - type, concentration, injection pressure, injection depth, injection direction, etc.). It also serves as an injection device that adjusts the injection pressure and injection method in accordance with the criteria determined for the ground improvement plan.
以下この発明の実施例を例示図面により説明す
る。 Embodiments of the present invention will be described below with reference to illustrative drawings.
第1図はこの発明の地盤改良判定装置および注
入装置の主部の断面図を示すものである。まず、
軟弱粘性土地盤の改良を行うために注入深度の位
置、注入方向、セメントミルク主体液(たとえ
ば、セメントミルクの水・セメント比、セメント
ミルクとフライアツシユまたはプラスチツク等の
粉体あるいは細粒固体との混合液の混合の比率
等)の調整等を決める必要があり、それには第1
に対象地盤の特性(主として地盤強度)を把握す
る必要がある。そこで、第1図Aはその装置を示
したものであり、1は地盤強度判定に用いられる
内管であつて先端にコーン(尖頭状の金具)を取
付けてある。2は注入用パイプであつて前記先端
コーン付内管1の保護パイプを兼ねている。これ
は、地盤強度を判定する場合保護パイプがないと
周面摩擦抵抗が加わるので注入深度における正確
な強度を示さないから先端抵抗のみを分離して測
定するためである。次に第1図Bに示すようにA
の装置を測定しようとする地盤のある深度にセツ
トして注入用パイプ2を固定しておいて先端コー
ン付き内管1のみをそのまゝ静かに10〜20cm圧入
しその時の圧入強度P(Kg/cm2)を地上で読みと
る。しかして、コーンの貫入長さにおける圧入強
度の平均値をとつて地盤改良判定基準値としてセ
メントミルク主体液を調整し、この調整液にした
がつて注入長さ(地盤面からの深度+地上のパイ
プ長さ)、注入液の流動方向3(上向きか下向き
かの方向)、注入圧(ポンプの送圧)を決定する。
この場合、第2図の実施例に示したように調整
液、注入圧と先端コーンの位置関係により選択さ
れる注入方法としては3通りの方法があるが注入
装置を大別すれば第1図のC、D図のようにな
る。すなわち、第1図Cはセツトした深度から下
の範囲に注入しようとする場合であり、D図は同
様にしてセツトした深度から上の範囲に注入しよ
うとする場合の装置を示したものである。なお、
地盤構成は必ずしも均質であるとは限らず、むし
ろ不均質な地盤が普通であるから、各装置に共通
した注入方法としては、地盤強度のもつとも弱い
部分から改良できるようにするため注入用パイプ
2をゆつくり回転させながら注入を行う。 FIG. 1 shows a sectional view of the main parts of the soil improvement determination device and injection device of the present invention. first,
In order to improve soft and viscous soil, the position of injection depth, injection direction, cement milk-based liquid (e.g. water/cement ratio of cement milk, mixing of cement milk with powder or fine solids such as fly ash or plastic), etc. It is necessary to decide on adjustments such as the mixing ratio of liquids, etc.
It is necessary to understand the characteristics of the target ground (mainly ground strength). Therefore, FIG. 1A shows the apparatus, and numeral 1 is an inner tube used for determining the strength of the ground, and a cone (pointed metal fitting) is attached to the tip. Reference numeral 2 denotes an injection pipe which also serves as a protection pipe for the inner tube 1 with a tip cone. This is because when determining the ground strength, without the protective pipe, circumferential frictional resistance is added, which does not indicate accurate strength at the depth of injection, so only the tip resistance is measured separately. Next, as shown in Figure 1B,
Set the device at a certain depth in the ground to be measured, fix the injection pipe 2, and gently press in only the inner tube 1 with the tip cone for 10 to 20 cm, then measure the press-fit strength P (Kg). /cm 2 ) is read on the ground. Therefore, the cement milk-based liquid was adjusted by taking the average value of the injection strength at the penetration length of the cone and used as the ground improvement judgment reference value, and the injection length (depth from the ground surface + ground level) was adjusted according to this adjusted liquid. Determine the pipe length), flow direction 3 of the injection liquid (upward or downward direction), and injection pressure (pump pressure).
In this case, as shown in the example in Figure 2, there are three injection methods that can be selected depending on the positional relationship between the adjustment liquid, injection pressure, and tip cone. It will look like Figures C and D. That is, Fig. 1C shows a case in which injection is to be performed in a range below the set depth, and Fig. 1 shows a device in which injection is to be performed in a similar manner in a range above the set depth. . In addition,
Since the ground composition is not necessarily homogeneous, and rather, heterogeneous ground is common, the injection method common to each device is to use an injection pipe 2 to improve the soil strength starting from weak areas. Inject while rotating slowly.
第2図は第1図のC、D図を用いた施工例を示
したものである。第2図のAはそのもつとも一般
的な施工法であつて上部より下向きに注入する例
であるが(第1図C図に示す装置と工法を使用)
掘削と盛土を施工するような場合には比較的容易
に必要とする範囲を改良することができる。この
例では改良地盤の最上限6から最下限7の範囲に
流動範囲を制限する注入方式である。(第1図の
CまたはD図に示す装置と工法を使用)この場
合、横方向の一方の側のみに改良範囲が限られる
場合は、片側に矢板等の仮設物8を仮設して区切
るかまたは第3図及び第4図に示すように第一次
注入で予め必要範囲(改良範囲)の外周を地下壁
9により囲い外数の注入パイプ1の注入孔10よ
り地下壁9の範囲内にセメントミルク主体液を注
入して障壁11を形成する。次いで第2次注入で
障壁11内の注入パイプ1より改良範囲12の内
側に注入するのが第3図に示す2段式の施工例で
ある。この場合障壁11内での1次施行において
は、各注入孔10より注入されるセメントミルク
主体液の量は注入圧等による調整がされて主とし
て同心円上の一定距離内に注入される。この例で
はA図の場合と同様改良地盤の最下限7から最上
限6の順に調整する。また、地盤條件によつては
目的とする改良範囲に対して軟弱層の長さが著し
く厚かつたり、または軟弱層の厚層の中間部を改
良しようとする場合がある。このような場合に
は、もつとも比重の小さい調整液を用いたとして
も地表からの注入長さが長すぎるため、上述した
注入方法を採用したのでは改良を必要とする範囲
外にも流動範囲が拡大して極めて不経済なものと
なる。したがつて、このような例では第2図Cに
示すように地盤のある深度に一つたん調整液の仮
設タンク4を設け、この仮設タンク4の深度から
注入長さをとつて液圧を少くする。この場合の注
入方法は第1図のD図の装置を用いて高圧注入を
行い逆向き(上向き)の方向に注入する。 FIG. 2 shows an example of construction using diagrams C and D in FIG. 1. A in Figure 2 is a common construction method, and is an example of pouring downward from the top (using the equipment and construction method shown in Figure 1 C).
In cases such as excavation and embankment construction, it is relatively easy to improve the required area. In this example, the injection method is to limit the flow range to the range from the upper limit 6 to the lower limit 7 of the improved ground. (Using the equipment and construction method shown in Figure 1 C or D) In this case, if the improvement range is limited to only one side in the horizontal direction, it may be separated by temporarily installing a temporary structure 8 such as a sheet pile on one side. Or, as shown in Figures 3 and 4, in the first injection, the outer periphery of the necessary range (improved range) is covered by the underground wall 9, and the injection holes 10 of the injection pipes 1, which are not included in the enclosure, are placed within the range of the underground wall 9. The barrier 11 is formed by injecting the cement milk main liquid. In the two-stage construction example shown in FIG. 3, the second injection is performed from the injection pipe 1 inside the barrier 11 to the inside of the improved area 12. In this case, in the primary application within the barrier 11, the amount of the cement milk main liquid injected from each injection hole 10 is adjusted by injection pressure, etc., and is mainly injected within a certain distance on a concentric circle. In this example, as in the case of Figure A, the improved ground is adjusted in order from the lowest limit 7 to the highest limit 6. Furthermore, depending on the ground conditions, the length of the soft layer may be significantly thicker than the intended improvement range, or the middle part of the thick layer of the soft layer may be attempted to be improved. In such cases, even if a regulating liquid with a low specific gravity is used, the length of injection from the ground surface is too long, and if the injection method described above is adopted, the flow range will extend beyond the range that requires improvement. This will expand and become extremely uneconomical. Therefore, in such an example, as shown in FIG. Make less. The injection method in this case is to perform high-pressure injection using the apparatus shown in Fig. 1D and inject in the opposite (upward) direction.
この発明は以上に述べたように、従来技術の盛
土などの載荷物を用いる脱水圧密工法、或いは脱
水圧密を促進する補助工法としてサンドドレーン
またはペーパードレーンなどのドレーン工法との
組合せを用いる工法に比較して、本願の工法は単
独の工法でありながら、盛土を必要とせず、極く
短時間の間に軟弱地盤を計画的に安全に軟弱地盤
を改良することができること、また、従来技術で
は圧密理論と実際の施工との間に大変な隔たりが
あつたが本願工法はこれを的確な改良設計に基づ
いて合理的、経済的に施工できること、そして本
願工法は大型の設備を必要としないので地形的環
境的に制約された諸条件のため従来技術の工法を
適用できない地盤も極めて容易に改良強化するこ
とができる。 As described above, this invention is superior to the conventional dewatering consolidation method using loads such as embankments, or the construction method using a combination with a drain method such as sand drain or paper drain as an auxiliary method to promote dewatering consolidation. Therefore, although the method of the present application is a stand-alone construction method, it does not require embankment and can improve soft ground systematically and safely in an extremely short period of time. Although there was a huge gap between theory and actual construction, the proposed construction method can be constructed rationally and economically based on an accurate improved design, and since the proposed construction method does not require large-scale equipment, it is suitable for terrain. Grounds to which conventional construction methods cannot be applied due to environmentally restricted conditions can be improved and strengthened very easily.
また、本願工法の効果は注入されるセメントミ
ルク主体液の地盤注入によつて軟弱粘性土地盤の
軟弱度に応じて設計管理されて軟弱地盤全体が目
的とする改良地盤に均質化するものである。この
場合、注入されるセメントミルク主体液は、注入
中はほぼ鉛直層状の流動体を形成し、その層状の
流動体は注入の経過とともに質的、量的に増大す
ると共に、その過程で特に複数の該流動体層によ
つて挾まれた軟弱層部分は、急激に圧縮されるの
でセメントミルク主体液は軟弱地盤に対して横方
向に作用する原位置載荷物として機能し、即効的
な脱水圧密を行つて脱水・排水の連鎖効果により
対象地盤が急速に圧密されて高密度化し、地盤強
度が増加するだけでなく、固結後はそれ自体が軟
弱地盤の固化骨核体を形成するものである。即
ち、このような特定の注入液と施工目的によつて
選定または調整される注入装置を用いてセメント
ミルク主体液の地盤注入によつて次々と対象地盤
の中に拡がつて行く流動体は注入中は、それぞれ
の流動径路とその成長過程において各破壊面に接
する地盤に対して原位置で急速載荷作用を強制す
るため、対象地盤の間隙水を脱水させると同時に
この間隙水を直ちに注入液の流動体自体の中に排
水させる機能を果すものである。そして注入液の
流動体は、注入後は速効的に固結化が進み、原位
置置換固化体として対象地盤の中に骨核構造体を
造り、脱水圧密で圧縮されて強化された部分とと
もに軟弱地盤全体を複合地盤として一体化し、安
定した地盤構造に改良強化することができる。従
つて、この発明による注入材料は圧密・脱水と排
水・固化・置換の各作用を一工程で施工できて即
時的に全部の効果を得ることができるように機能
し、軟弱粘性土地盤を施工目的に合わせて改良強
化するものである。 In addition, the effect of the present method is that by injecting the cement milk-based liquid into the ground, the design is managed according to the degree of softness of the soft and viscous ground, and the entire soft ground is homogenized into the desired improved ground. . In this case, the cement milk-based liquid to be injected forms a nearly vertical layered fluid during injection, and the layered fluid increases qualitatively and quantitatively as the injection progresses, and in the process, especially Since the soft layer sandwiched by the fluid layer is rapidly compressed, the cement milk-based liquid acts as an in-situ load acting laterally on the soft ground, resulting in immediate dewatering and consolidation. Through this process, the target ground is rapidly consolidated and densified due to the chain effect of dewatering and drainage, which not only increases the strength of the ground, but also forms a solidified bone core of the soft ground after consolidation. be. In other words, by injecting the cement milk-based liquid into the ground using a specific injection liquid and an injection device selected or adjusted depending on the purpose of construction, the fluid that spreads into the target ground one after another is injected. In order to force rapid loading action in situ on the ground in contact with each fracture surface during each flow path and its growth process, the pore water in the target ground is dehydrated and at the same time this pore water is immediately injected with the injection liquid. It functions to drain water into the fluid itself. After injection, the fluid injected solidifies quickly, creating a bone core structure in the target ground as an in-situ solidified body, and softens the part that has been compressed and strengthened by dehydration consolidation. It is possible to integrate the entire ground into a composite ground and improve and strengthen it into a stable ground structure. Therefore, the injection material according to the present invention functions to perform the functions of consolidation, dewatering, drainage, solidification, and replacement in one step, and can obtain all the effects immediately, and is effective in constructing soft and cohesive soil. It is intended to be improved and strengthened according to the purpose.
図面はこの発明の一実施例を示すものであつ
て、第1図A,B,C,Dはこの発明方法に使用
する軟弱粘性土地盤改良用セメントミルク主体液
注入装置および改良基準判定装置の主部を示す断
面図、第2図A,B,C、第1図の注入装置を用
いて軟弱粘性土地盤の地盤改良を行う場合の施工
方法をしめす断面図、第3図は同上平面図であ
る。第4図は従来技術で先端コーンを用いて軟弱
地盤の貫入抵抗値を測定する場合の模式図、第5
図は本発明の工法による注入液の地盤注入により
対象地盤の破壊状況を示す模式図、第6図は注入
圧説明図、第7図は盛土の載荷重のみで脱水圧密
を行う機構の説明図、第8図は各種のドレーン材
を用いて圧密を促進する機構の説明図、第9図は
本発明の脱水圧密を行う機構の説明図、第10図
は従来技術の脱水圧密及び排水の態様説明図、第
11図は本発明の脱水圧密及び排水の態様説明図
である。
1……先端コーン(尖頭状金具)付き内管、2
……注入用パイプ、3……注入液の流動方向、4
……注入する調整液の仮設タンク、5……改良を
要する地盤、6……改良地盤の最上限、7……改
良地盤の最下限、8……矢板等の仮設物、9……
地下壁、10……一次注入孔、10′……二次注
入孔、11……障壁、12……改良範囲、13…
…コーン(尖頭状金具)。
The drawings show an embodiment of the present invention, and FIGS. 1A, B, C, and D show a cement milk-based liquid injection device for improving soft and weak viscous soil soil and an improvement standard determining device used in the method of this invention. A cross-sectional view showing the main part, Figures 2A, B, and C, a cross-sectional view showing the construction method for soil improvement of soft and viscous soil using the injection device shown in Figure 1, and Figure 3 is a plan view of the same. It is. Figure 4 is a schematic diagram of measuring the penetration resistance value of soft ground using a tip cone using the conventional technology.
The figure is a schematic diagram showing the state of destruction of the target ground by injecting liquid into the ground using the construction method of the present invention, Figure 6 is an explanatory diagram of the injection pressure, and Figure 7 is an explanatory diagram of the mechanism that performs dewatering and consolidation using only the loading load of the embankment. , FIG. 8 is an explanatory diagram of a mechanism for promoting consolidation using various drain materials, FIG. 9 is an explanatory diagram of a mechanism for dehydration consolidation of the present invention, and FIG. 10 is an embodiment of dehydration consolidation and drainage in the prior art. The explanatory diagram, FIG. 11, is an explanatory diagram of aspects of dewatering consolidation and drainage according to the present invention. 1... Inner tube with tip cone (pointed metal fitting), 2
... Injection pipe, 3 ... Flow direction of injection liquid, 4
...Temporary tank for adjusting liquid to be injected, 5...Ground that requires improvement, 6...Maximum limit of improved ground, 7...Lowest limit of improved ground, 8...Temporary construction such as sheet piles, 9...
Basement wall, 10...Primary injection hole, 10'...Secondary injection hole, 11...Barrier, 12...Improvement range, 13...
...Cone (pointed metal fitting).
Claims (1)
注入することにより、注入されたそのままの位置
即ち原位置において強制脱水・急速圧密をもたせ
て、注入中のセメントミルク主体液の流動体を介
して即時的に排水させることによつて、極めて短
時間に軟弱粘性土地盤を圧縮し、地盤強度を増加
させるとともに注入液をそのまま原位置で固結・
置換せしめて軟弱粘性土地盤の骨核構造となし、
軟弱粘性土地盤全体を一体化して安定した地盤に
改良強化することを特徴とする軟弱粘性土地盤の
改良工法。 2 軟弱粘性土地盤に鉛直に挿入する注入用パイ
プ内に先端にコーンを有する内管を挿通し、地盤
強度の判定装置と地盤改良基準判定装置として用
いるとともにそれがそのまま地盤注入装置として
使用できることを特徴とする軟弱粘性土地盤の改
良装置。[Claims] 1. By injecting the cement milk-based liquid into the soft and viscous soil, forced dehydration and rapid consolidation are performed at the same position where it is injected, that is, at the original position, and the cement milk-based liquid being poured is Immediate drainage via fluid compresses the soft and viscous soil in an extremely short time, increasing the strength of the ground and solidifying the injected liquid in situ.
Replace the bone core structure of the soft and viscous soil,
A method for improving soft and viscous soil, which is characterized by integrating the entire soft and viscous soil to improve and strengthen it into a stable foundation. 2. An inner tube with a cone at the tip is inserted into an injection pipe that is vertically inserted into soft and viscous soil, and is used as a soil strength determination device and a soil improvement standard determination device, as well as being able to be used as is as a soil injection device. A device for improving soft and viscous soil.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6137076A JPS52144109A (en) | 1976-05-27 | 1976-05-27 | Method of and apparatus for improving soft and sticky subsoil by impregnating subsoil with liquid mainl6y comprising cement milk |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6137076A JPS52144109A (en) | 1976-05-27 | 1976-05-27 | Method of and apparatus for improving soft and sticky subsoil by impregnating subsoil with liquid mainl6y comprising cement milk |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS52144109A JPS52144109A (en) | 1977-12-01 |
| JPH02491B2 true JPH02491B2 (en) | 1990-01-08 |
Family
ID=13169205
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP6137076A Granted JPS52144109A (en) | 1976-05-27 | 1976-05-27 | Method of and apparatus for improving soft and sticky subsoil by impregnating subsoil with liquid mainl6y comprising cement milk |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS52144109A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3168301D1 (en) * | 1980-07-29 | 1985-02-28 | Becker Bau Gmbh & Co Kg | Method for soil stabilisation |
| JP4678018B2 (en) * | 2006-10-10 | 2011-04-27 | 株式会社大北耕商事 | Ground survey device, ground survey method, and ground improvement method |
-
1976
- 1976-05-27 JP JP6137076A patent/JPS52144109A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS52144109A (en) | 1977-12-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS6248009B2 (en) | ||
| CN107417182B (en) | Intumescent high polymer cement slurry, grouting reinforcement device and grouting reinforcement method | |
| CN114108597A (en) | Vacuum drainage grouting method | |
| CN111379253A (en) | Construction method of composite foundation of high-speed railway with expanded cement slurry after grouting | |
| KR20020022446A (en) | Repairing method of earth-fill dam | |
| JPH09137444A (en) | Preventive method of disaster caused by liquefaction phenomena generating in loose sand or sandy ground in earthquake, and restoration work of damaged ground | |
| CN112160313B (en) | Undisturbed Q4Loess or remolded Q4Loess reinforcing method | |
| JPH02491B2 (en) | ||
| CN113548840A (en) | Water guide grouting material, preparation method thereof and water guide grouting stone body | |
| CN218116337U (en) | Be used for permeating earth and rockfill dam and widen seepage prevention structure | |
| US4981399A (en) | Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall | |
| US20120163923A1 (en) | Structure supporting system | |
| JP2019100083A (en) | Ground reinforcing method and injection pipe device | |
| US11884860B2 (en) | Fluidized sand and method of density control | |
| CN114960555A (en) | Widened seepage-proofing structure for penetrated earth-rock dam and construction method | |
| Ibragimov | Design and implementation of soil stabilization by grout injection using hydrofracking technology | |
| CN106759284A (en) | Gradual change type permeable concrete-broken stone pile, ground, building and method | |
| Khan et al. | Performance Evaluation of Cement Grouting by Universal Testing Machine to Improve the Bearing Capacity of Sandy Soil | |
| CN214993745U (en) | Be applicable to artifical hole digging pile foundation pile week slip casting and consolidate subassembly | |
| JP3935259B2 (en) | On-site concrete pile construction method | |
| KR100554364B1 (en) | Method for increasing the bearing capacity of foundation soils for buildings | |
| JP2832204B2 (en) | Liquefaction prevention method and liquefaction prevention structure | |
| CN109137950A (en) | Highly permeable karst strata major diameter manually digging hole foundation pile water-stopping method | |
| JPH04336116A (en) | Executing method for cast-in-place concrete pile | |
| JP2927612B2 (en) | Foundation method |