JPH0268489A - Control method for deodorizing device in pre-heating scrap - Google Patents

Control method for deodorizing device in pre-heating scrap

Info

Publication number
JPH0268489A
JPH0268489A JP22078388A JP22078388A JPH0268489A JP H0268489 A JPH0268489 A JP H0268489A JP 22078388 A JP22078388 A JP 22078388A JP 22078388 A JP22078388 A JP 22078388A JP H0268489 A JPH0268489 A JP H0268489A
Authority
JP
Japan
Prior art keywords
deodorizing device
scrap
exhaust gas
preheating
amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP22078388A
Other languages
Japanese (ja)
Inventor
Toshiharu Furukawa
俊治 古川
Yukio Niwa
丹羽 幸雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daido Steel Co Ltd
Original Assignee
Daido Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daido Steel Co Ltd filed Critical Daido Steel Co Ltd
Priority to JP22078388A priority Critical patent/JPH0268489A/en
Publication of JPH0268489A publication Critical patent/JPH0268489A/en
Pending legal-status Critical Current

Links

Landscapes

  • Furnace Details (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明はスクラップ予熱における脱臭装置の制御方法に
関する。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a method for controlling a deodorizing device during scrap preheating.

金属材料の溶解にアーク炉が広く利用されているが、該
アーク炉からは、金属材料をアーク熱により溶解する性
質上、膨大な顕熱を有する高温の排ガスが発生する。該
排ガスは、最終的には集塵装置で処理された後に大気中
へ放出されるが、該排ガスの膨大な顕熱を特に有効利用
することなく大気中へ放出したのでは熱エネルギの著し
い無駄である。
Arc furnaces are widely used for melting metal materials, but because the metal materials are melted by arc heat, arc furnaces generate high-temperature exhaust gas having a huge amount of sensible heat. The exhaust gas is finally released into the atmosphere after being treated with a dust collector, but if the enormous amount of sensible heat in the exhaust gas is released into the atmosphere without being particularly effectively utilized, it would be a significant waste of thermal energy. It is.

そこで、アーク炉から発生する排ガスの顕熱を原料スク
ラップの予熱に利用することが行なわれるのであるが、
該スクラップが例えばダライ粉やシュレッダ等の低級ス
クラップであると特に、スクラップ予熱後の排ガス中に
、該低級スクラップの油分や塗料等に起因する悪臭成分
、例えば硫化水素やアセトアルデヒド更にはスチレン等
が多量に含まれてくる。かかる悪臭成分は、これをその
まま集塵装置へ供すると、該集塵装置へ悪影響を及ぼす
だけでなく、重大な二次公害を引き起こすことにもなる
Therefore, the sensible heat of the exhaust gas generated from the arc furnace is used to preheat raw material scrap.
In particular, if the scrap is low-grade scrap such as milling powder or shredder, the exhaust gas after preheating the scrap will contain a large amount of foul-smelling components such as hydrogen sulfide, acetaldehyde, and even styrene caused by the oil and paint of the low-grade scrap. It is included in If such malodorous components are directly supplied to a dust collector, they will not only have an adverse effect on the dust collector, but also cause serious secondary pollution.

このため、スクラップ予熱においては一般に、スクラッ
プ予熱機構の下流側に脱臭装置を連結し、該脱臭装置で
スクラップ予熱後の排ガスを燃料供給下に燃焼させて脱
臭することが行なわれるのであるが、この際いうまでも
なく、スクラップ予熱がアーク炉から発生する排ガスの
顕熱を有効利用しようとする観点に立つものであるから
、該観点に逆行することのないよう、できるだけ省エネ
ルキ化された条件下に脱臭装置を制御することが要請さ
れる。
For this reason, when preheating scrap, a deodorizing device is generally connected downstream of the scrap preheating mechanism, and the exhaust gas after preheating the scrap is combusted in the deodorizing device while being supplied with fuel to deodorize it. Needless to say, scrap preheating is aimed at making effective use of the sensible heat of the exhaust gas generated from the arc furnace, so it should be done under conditions that save as much energy as possible so as not to go against this perspective. It is required to control the deodorizing equipment.

本発明は上記要請に応える脱臭装置の制御方法に関する
ものである。
The present invention relates to a method for controlling a deodorizing device that meets the above requirements.

〈従来の技術、その課題〉 従来、スクラップ予熱における脱臭装置の運転は、該脱
臭装置への燃料供給量を常時一定且つ最大に維持した状
態で行なわれている。スクラップ予熱後の排ガス中に含
まれてくる悪臭成分は、原料スクラップの等級が同じで
あっても、該スクラップ予熱に利用するアーク炉からの
排ガスの温度によって大きな影響を受け、該排ガスの温
度が変動することによって上記悪臭成分の濃度が大きく
変動するのであるが、スクラップ予熱中において脱臭装
置への燃料供給量を常時−・定に維持する従来法では、
該燃料供給量を悪臭成分の最大濃度時に合わせてこれを
燃焼するに必要な量すなわち最大量にしておかないと、
悪臭成分の燃焼が不充分となって、結局は悪臭成分の−
・部が集塵装置へと供給され、更には大気中へと放出さ
れてしまうからである。
<Prior Art and its Problems> Conventionally, a deodorizing device for scrap preheating is operated while the amount of fuel supplied to the deodorizing device is always maintained at a constant and maximum level. The malodorous components contained in the exhaust gas after preheating the scrap are greatly affected by the temperature of the exhaust gas from the arc furnace used for preheating the scrap, even if the raw material scrap is of the same grade. The concentration of the above-mentioned malodorous components fluctuates greatly due to fluctuations in the concentration of malodorous components, but in the conventional method of constantly maintaining the amount of fuel supplied to the deodorizing equipment during scrap preheating,
If the amount of fuel supplied is not adjusted to the maximum concentration of malodorous components to the amount necessary for combustion, that is, the maximum amount,
The combustion of the malodorous components becomes insufficient, and eventually the malodorous components -
This is because part of the dust is supplied to the dust collector and then released into the atmosphere.

しかし、このような従来法には、スクラップ予熱後の排
ガス中に含まれてくる悪臭成分の濃度が低いときでも、
脱臭装置へ不必要に過剰の燃料を供給することになるた
め、その分だけ熱エネルギの無駄になるという問題があ
る。
However, such conventional methods do not have the ability to produce
Since excess fuel is unnecessarily supplied to the deodorizing device, there is a problem in that thermal energy is wasted accordingly.

実情は、もともとスクラップ予熱がアーク炉から発生す
る排ガスの顕熱を有効利用しようとする観点に立つもの
であることを考え併せると、スクラップ予熱後の排カス
を脱臭装置で燃料供給下に燃焼させて脱臭するに際して
は、該脱臭装置への燃料供給量を悪臭成分の濃度に応じ
より実際的に制御する方法の出現が要請されているので
ある。
In reality, considering that scrap preheating is originally intended to effectively utilize the sensible heat of the exhaust gas generated from the arc furnace, it is possible to burn the waste residue after scrap preheating using a deodorizing device while supplying fuel. There is a need for a method for more practically controlling the amount of fuel supplied to the deodorizing device according to the concentration of malodorous components.

〈発明が解決しようとする課題、その解決手段〉本発明
は、メクラ−2ブ予熱における叙−Lの如き従来の問題
を解決して、実情の要請に応える、脱臭装置の制御方法
を提供するものである。
<Problems to be Solved by the Invention and Means for Solving the Problems> The present invention provides a method for controlling a deodorizing device that solves the conventional problems such as the problem in preheating a double-blade and meets the needs of the actual situation. It is something.

しかして本発明は、 アーク炉からの胡ガスを利用してスクラップ予熱を行な
い、該スクラップ予熱後の排ガスを脱臭装置で燃料供給
下に燃焼させることによって脱臭するに際し、脱臭装置
への燃料供給量を、アーク炉の炉蓋の開閉信号に同期さ
せて制御することを骨子とする脱臭装置の制御方法に係
る。
Therefore, in the present invention, when preheating the scrap using gas from an arc furnace and deodorizing the exhaust gas after preheating the scrap by burning it in a deodorizing device while supplying fuel, the amount of fuel supplied to the deodorizing device is reduced. The present invention relates to a method for controlling a deodorizing device, the gist of which is to control the following in synchronization with the opening/closing signal of the lid of an arc furnace.

本発明において肝要な点は、スクラップ予熱機構の下流
側に連結される脱臭装置への燃料供給量を、該スクラッ
プ予熱機構へ送入される排ガスの発生源であるアーク炉
の炉蓋の開閉信号に同期させて制御し、よって全体とし
ての脱臭装置への燃料供給量を減少させる処にある。
An important point in the present invention is that the amount of fuel supplied to the deodorizing device connected downstream of the scrap preheating mechanism is controlled by the opening/closing signal of the lid of the arc furnace, which is the source of the exhaust gas sent to the scrap preheating mechanism. The deodorizing device is controlled in synchronization with the deodorizing device, thereby reducing the overall amount of fuel supplied to the deodorizing device.

以下、図面に基いて本発明の構成を更に詳細に説明する
Hereinafter, the configuration of the present invention will be explained in more detail based on the drawings.

〈実施例〉 第1図は本発明の一実施手順を略示する系統図である。<Example> FIG. 1 is a system diagram schematically showing one implementation procedure of the present invention.

アーク炉11からの排ガスが燃焼塔21で自己燃焼によ
り後燃焼され、バルブ31.32で分岐された後、その
一部又は全部がスクラップ予熱機構41へと送入されて
、該スクラップ予熱機構41で所定通リスクラップを予
熱した後の排ガスが脱臭装置151へと送入されている
。脱臭装置51には制御バルブ61を介装する燃料供給
系62が配管されており、制御バルブ61にはアーク炉
11の炉蓋12の開閉信号に同期して制御バルブ61の
開度を調節するタイマ内蔵の制御装置63が接続されて
いる。例えば、炉蓋12が開から閉になった信号を受け
て制御装M63が制御バルブ61を全開にし、タイマの
作用で10〜15分後に制御装置63が制御バルブ61
を1/3開にして、かかる制御バルブ61の開度調節に
よりそれに応じて燃料供給系62を介し燃料が最大量又
は1/3量、脱臭装置51へと供給されるのである。か
くして制御された燃料供給の下に脱臭装置51で燃焼さ
れて脱臭された排ガスは、前記バルブ31で分岐された
排ガスと合流し、クーラ71及び吸引ファン81を介し
て、最終的に集塵装置91で処理されてから大気中へと
放出されている。
After the exhaust gas from the arc furnace 11 is post-combusted by self-combustion in the combustion tower 21 and branched off at valves 31 and 32, part or all of it is fed into the scrap preheating mechanism 41. The exhaust gas after preheating the scrap through a predetermined passage is sent to the deodorizing device 151. A fuel supply system 62 with a control valve 61 is piped to the deodorizing device 51, and the opening degree of the control valve 61 is adjusted in synchronization with the opening/closing signal of the furnace cover 12 of the arc furnace 11. A control device 63 with a built-in timer is connected. For example, upon receiving a signal indicating that the furnace lid 12 has changed from open to closed, the control device M63 fully opens the control valve 61, and after 10 to 15 minutes due to the action of a timer, the control device 63 opens the control valve 61 fully.
By opening the control valve 61 to 1/3, the maximum amount or 1/3 of the fuel is supplied to the deodorizing device 51 via the fuel supply system 62 accordingly. The exhaust gas, which has been combusted and deodorized in the deodorizing device 51 under the controlled fuel supply, joins the exhaust gas branched at the valve 31, passes through the cooler 71 and the suction fan 81, and is finally sent to the dust collector. 91 and then released into the atmosphere.

第2図は本発明の実施結果を例示するグラフである。こ
の場合、第1図について前述したー実施手順にしたがっ
て脱臭装置への燃料供給量を制御しており、図中、縦軸
は排ガス中の全炭化水素濃度(HC1x102ppm)
、横軸は時間(分)であって、破線は脱臭装置の入口に
おける場合、実線は脱臭装置の出口における場合を示し
ている。
FIG. 2 is a graph illustrating the results of implementing the present invention. In this case, the amount of fuel supplied to the deodorizing device is controlled according to the implementation procedure described above with reference to Figure 1, and in the figure, the vertical axis represents the total hydrocarbon concentration in the exhaust gas (HC1 x 102 ppm).
, the horizontal axis is time (minutes), the broken line indicates the case at the inlet of the deodorizing device, and the solid line indicates the case at the outlet of the deodorizing device.

すなわち、時間Oの段階で炉蓋を開、時間12の段階で
炉蓋を閉、そしてこの間にアーク炉へのスクラップ初装
を行なっており、その一方でスクラップ予熱機構には予
め低級スクラップが装填されているのであるが、時間1
2の段階で炉蓋を閉にした直後、脱臭装置の入口におけ
るスクラップ予熱後の排ガス中の全炭化水素濃度が急激
に上昇している。これは、炉蓋が開の状態において比較
的低温の排ガスがスクラップ予熱機構へ送入され、した
がって蒸発直前の凝縮状態におかれていた上記低級スク
ラップの油分や塗料が、炉蓋が閉になって高温の排ガス
がスクラップ予熱機構へ送入された結果、−度に蒸発す
るためと考えられる。同様の傾向は、時間30の段階で
炉蓋な開、時間35の段階で炉蓋を閉、そしてこの間に
アーク炉へのスクラップ追装を行なったときの炉蓋を閉
にした直後にも生じている。
That is, the furnace lid is opened at time O, closed at time 12, and during this period the initial loading of scrap into the arc furnace is carried out. At the same time, the scrap preheating mechanism is loaded with low grade scrap in advance. However, time 1
Immediately after closing the furnace lid in step 2, the total hydrocarbon concentration in the exhaust gas after preheating the scrap at the inlet of the deodorizing device increases rapidly. This is because relatively low-temperature exhaust gas is sent to the scrap preheating mechanism when the furnace lid is open, and therefore the oil and paint from the low-grade scrap that was in a condensed state just before evaporation is removed when the furnace lid is closed. It is thought that this is because high-temperature exhaust gas is fed into the scrap preheating mechanism and evaporated to -degrees. A similar tendency occurred when the furnace lid was opened at time 30, closed at time 35, and immediately after the furnace lid was closed when additional scrap was loaded into the arc furnace during this period. ing.

図面の場合、時間12〜22の時間帯における10分間
及び時間35〜50の時間帯における15分間、炉蓋を
閉にした信号を受けてタイマ内蔵の制御装置により制御
バルブを全開状態にし、その他の定常の時間帯は制御バ
ルブを1/3開の状態に制御している。
In the case of the drawing, the control valve is fully opened by the control device with a built-in timer in response to the signal that the furnace lid is closed for 10 minutes in the time period from 12 to 22 and for 15 minutes in the time period from 35 to 50. During the steady time period, the control valve is controlled to be 1/3 open.

スクラップ予熱においては、アーク炉の炉蓋を開から閉
にすると、その直後に、脱臭装置の入口におけるスクラ
ップ予熱後の排ガス中の全炭化水素濃度が急激に高くな
り、かかる高濃度の状態が次第に低下しながら所定時間
続く一方で、他の定常の時間帯では該全炭化水素濃度が
比較的安定して低くなるという知見を得、かかる全炭化
水素濃度の変動に事前に対応して、アーク炉の炉蓋が開
から閉になった直後から所定の時間は、脱臭装置へ高濃
度の全炭化水素(悪臭成分)を燃焼させるために必要且
つ充分な燃料供給すなわち最大の燃料供給を行ない、そ
の一方で他の定常の時間帯では、脱臭装置へ比較的低濃
度の全炭化水素(悪臭成分)を燃焼させるために必要且
つ充分な燃料供給すなわち上記最大時の1/3の燃料供
給を行なっているのである。
During scrap preheating, when the furnace lid of the arc furnace is opened and then closed, the total hydrocarbon concentration in the exhaust gas after scrap preheating at the inlet of the deodorizing equipment increases rapidly, and this high concentration state gradually increases. We obtained the knowledge that while the total hydrocarbon concentration continues to decrease for a predetermined period of time, during other steady periods the total hydrocarbon concentration remains relatively stable and low. Immediately after the furnace lid changes from opening to closing, for a predetermined period of time, the necessary and sufficient fuel is supplied to the deodorizing equipment to burn all the high-concentration hydrocarbons (malodorous components), that is, the maximum fuel supply is carried out. On the other hand, during other regular periods, the deodorizer is supplied with the necessary and sufficient fuel to burn all the hydrocarbons (malodorous components) at a relatively low concentration, that is, 1/3 of the maximum fuel supply mentioned above. There is.

このように脱臭装置への燃料供給量を制御すると、その
結果、スクラップ予熱における全体としての該燃料供給
量を、常時一定且つ最大に維持する従来法に比べて、約
半分以下に削減することができ、その上で、いうまでも
ないが、図中の実線で示すように、脱臭装置の出口にお
ける全炭化水素濃度を充分に減少させ、したがって悪臭
成分を充分に燃焼させて、スクラップ予熱後の排ガスを
脱臭することができるのである。
By controlling the amount of fuel supplied to the deodorizing equipment in this way, the overall amount of fuel supplied during scrap preheating can be reduced to about half or more compared to the conventional method, which maintains a constant and maximum amount at all times. Needless to say, as shown by the solid line in the figure, the total hydrocarbon concentration at the outlet of the deodorizing device can be sufficiently reduced, and the malodorous components can be sufficiently combusted, resulting in the scrap being preheated. It can deodorize exhaust gas.

〈発明の効果〉 以上説明した通りであるから、本発明には、スクラップ
予熱における脱臭装置への燃料供給量を著しく減少させ
、したがってそれだけ省エネルギ化を図ることができる
という効果がある。
<Effects of the Invention> As explained above, the present invention has the effect that the amount of fuel supplied to the deodorizing device during scrap preheating can be significantly reduced, and therefore energy saving can be achieved accordingly.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施手順を略示する系統図であり、
また第2図はその実施結果を例示するグラフである。 11・・・・アーク炉、12・・・・炉蓋21・・・・
燃焼塔、31.32・・・・バルブ41・・・・スクラ
ップ予熱機構、51・・・・脱臭装置61・・・・制御
バルブ、82・・・・燃料供給系63・・・・制御装置
、71・・・・ターラ81・・・・吸引ファン、81・
・・・集塵装置特許出願人 大同特殊鋼株式会社 代理人 弁理士 入 山 宏 正
FIG. 1 is a system diagram schematically showing one implementation procedure of the present invention,
Moreover, FIG. 2 is a graph illustrating the implementation results. 11... Arc furnace, 12... Furnace lid 21...
Combustion tower, 31.32... Valve 41... Scrap preheating mechanism, 51... Deodorizing device 61... Control valve, 82... Fuel supply system 63... Control device , 71... Tara 81... Suction fan, 81...
...Dust collector patent applicant Daido Steel Co., Ltd. Agent Patent attorney Hiroshi Iriyama

Claims (1)

【特許請求の範囲】 1、アーク炉からの排ガスを利用してスクラップ予熱を
行ない、該スクラップ予熱後の排ガスを脱臭装置で燃料
供給下に燃焼させることによって脱臭するに際し、脱臭
装置への燃料供給量を、アーク炉の炉蓋の開閉信号に同
期させて制御することを特徴とする脱臭装置の制御方法
。 2、脱臭装置への燃料供給量を、アーク炉の炉蓋の開か
ら閉への信号によって最大とし、次いでタイマによる所
定時間後に減少させる請求項1記載の脱臭装置の制御方
法。
[Scope of Claims] 1. When preheating scrap using exhaust gas from an arc furnace and deodorizing the exhaust gas after preheating the scrap by burning it in a deodorizing device while supplying fuel, supplying fuel to the deodorizing device. A method for controlling a deodorizing device, characterized in that the amount is controlled in synchronization with an opening/closing signal of a furnace lid of an arc furnace. 2. The method of controlling a deodorizing device according to claim 1, wherein the amount of fuel supplied to the deodorizing device is maximized by a signal from opening to closing of the furnace lid of the arc furnace, and then reduced after a predetermined time by a timer.
JP22078388A 1988-09-02 1988-09-02 Control method for deodorizing device in pre-heating scrap Pending JPH0268489A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22078388A JPH0268489A (en) 1988-09-02 1988-09-02 Control method for deodorizing device in pre-heating scrap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22078388A JPH0268489A (en) 1988-09-02 1988-09-02 Control method for deodorizing device in pre-heating scrap

Publications (1)

Publication Number Publication Date
JPH0268489A true JPH0268489A (en) 1990-03-07

Family

ID=16756504

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22078388A Pending JPH0268489A (en) 1988-09-02 1988-09-02 Control method for deodorizing device in pre-heating scrap

Country Status (1)

Country Link
JP (1) JPH0268489A (en)

Similar Documents

Publication Publication Date Title
JP2001227714A (en) Waste incineration method
JP3092083B2 (en) Preheating apparatus and preheating method for iron scrap
JP2003042429A (en) Gasification melting plasma ash melting furnace equipment and start-up method thereof
JPH0268490A (en) Control method for deodorizing device in pre-heating scrap
JP2000005538A (en) Exhaust gas treatment equipment for arc furnace
JPS6249988A (en) Melting treatment for waste
JPH0331966B2 (en)
JPH02606B2 (en)
JPH11248371A (en) Waste heat recovery equipment for electric furnaces for steelmaking
CN108266734B (en) A kind of high-moisture rubbish cracking apparatus and method
JP2743531B2 (en) Control method of deodorization tower in scrap preheating
JPS5864483A (en) Method of preheating scrap
JPH0241459Y2 (en)
JPH01155195A (en) Deodorizing method in preheating of scrap
JPS633207B2 (en)
JPH10287884A (en) Apparatus and method for treating metal-containing organic waste
JP3722069B2 (en) Hot air drying furnace operation method
JPS55152584A (en) Combustion/melt treatment of solud waste and equipment therefor
JPS5926870B2 (en) Electric furnace scrap preheating device
JP3759791B2 (en) Operation method of combustion melting furnace in waste treatment equipment
JPS6354969B2 (en)
JPH0894031A (en) Waste gasification and melting furnace
JPS6149597B2 (en)
JPS6143070Y2 (en)
JPS6242207B2 (en)