JPH03115656A - Compaction method for concrete structure - Google Patents

Compaction method for concrete structure

Info

Publication number
JPH03115656A
JPH03115656A JP25102489A JP25102489A JPH03115656A JP H03115656 A JPH03115656 A JP H03115656A JP 25102489 A JP25102489 A JP 25102489A JP 25102489 A JP25102489 A JP 25102489A JP H03115656 A JPH03115656 A JP H03115656A
Authority
JP
Japan
Prior art keywords
concrete
concrete structure
plate
jack
top end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP25102489A
Other languages
Japanese (ja)
Inventor
Noboru Sakata
昇 坂田
Masatoshi Yasaka
雅利 八坂
Mutsuki Tanaka
田中 睦規
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP25102489A priority Critical patent/JPH03115656A/en
Publication of JPH03115656A publication Critical patent/JPH03115656A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PURPOSE:To homogenize the unit strength of a concrete structure by vertically pressurizing the top end of the concrete structure in which concrete placing is completed up to the top end by a plate or the like to dehydrate the upper layer followed by compaction. CONSTITUTION:In compaction method using a jack, a plate 1 corresponding to the thickness or sectional width of a concrete structure S such as a pile prepared in field is placed on the top end of the concrete C of the concrete structure S. A frame 3 is laid between anchors 2, 2, buried on both sides of the structure S, and a jack 4 is placed between the plate 1 and the frame 3. Then, the rod 4a of the jack 4 is extended to closely press the upper layer part of the structure S with the plate 1. The magnitude of the pressurizing force is about 20-50 t/m<2>. Hence, the vertical heterogeneous state of the concrete structure S can be solved to homogenize the unit strength.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は地下連続壁や現場造成杭等のコンクリート構
造体を鉛直方向に均質化する、コンクリート構造体の締
め固め方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for compacting concrete structures, such as underground continuous walls and on-site piles, to homogenize them in the vertical direction.

(発明が解決しようとする課題) 例えば泥水置換工法等により施工される地下連続壁や現
場造成杭は、削孔内にコンクリートをトレミー管を通じ
て打設し、その後コンクリートが自重により自然に締め
固まることによって構築されるものであるが、深度の大
きさによって上方から加わる、それより上部のコンクリ
ート重量が異なるため締め固めの程度は深さ方向に相違
することになる。
(Problem to be solved by the invention) For example, in underground continuous walls and on-site constructed piles constructed using the muddy water displacement method, concrete is poured into an excavated hole through a tremie pipe, and then the concrete compacts naturally under its own weight. However, since the weight of concrete applied from above differs depending on the depth, the degree of compaction differs in the depth direction.

すなわち上載荷重の大きく働く下層部では十分な締め固
めと脱水が期待できるが、この効果は主に下層部に留ま
り、上層部に行くほど載荷効果が薄れるため完成したコ
ンクリート構造体の圧縮強度は鉛直方向に不均質となる
In other words, sufficient compaction and dewatering can be expected in the lower layer, where the overload is large, but this effect mainly remains in the lower layer, and the loading effect weakens as you move toward the upper layer, so the compressive strength of the completed concrete structure is It becomes heterogeneous in the direction.

この発明はこの現場打ちコンクリート構造体の抱える問
題に着目してなされたもので、鉛直方向の不均質状態を
解消し、品質を高める方法を提案しようとするものであ
る。
This invention was made by paying attention to the problems faced by cast-in-place concrete structures, and aims to propose a method for eliminating vertical non-uniformity and improving quality.

(課題を解決するための手段) 本発明では天端までコンクリートの打設が完了したコン
クリート構造体天端面にほぼ全面に亘って、その天端面
から鉛直下向きに荷重を加えることによりコンクリート
構造体の上層部分に下層部分と同程度の載荷効果を与え
、コンクリート構造体の上層部分をその硬化前に強制的
に圧密すると同時に、その部分を脱水してコンクリート
構造体を鉛直方向に均質化し、その圧縮強度を高める。
(Means for Solving the Problems) In the present invention, a load is applied vertically downward from the top surface of the concrete structure, covering almost the entire surface of the top surface of the concrete structure for which concrete has been poured up to the top. Applying the same loading effect to the upper layer as the lower layer, forcibly consolidating the upper layer of the concrete structure before it hardens, and at the same time dewatering that area to homogenize the concrete structure vertically and compressing it. Increase strength.

(実施例) 以下本発明を一実施例を示す図面に基づいて説明する。(Example) The present invention will be explained below based on the drawings showing one embodiment.

この発明は第1図に示すように地下連続壁や現場造成杭
等のコンクリート構造体Sの、打設が完了したコンクリ
ートcの天端より鉛直下向きに力を加え、コンクリート
Cを鉛直方向に圧密すると同時に、脱水してコンクリー
ト構造体Sの品質を向上させる方法である。
As shown in Fig. 1, this invention applies vertically downward force from the top of the concrete c that has been completely placed in a concrete structure S such as an underground continuous wall or on-site pile to consolidate the concrete C in the vertical direction. At the same time, this method improves the quality of the concrete structure S by dewatering it.

加力の大きさは20〜50t/n?程度が目安であり、
この荷重は第1図に示すようにコンクリート構造体Sの
ほぼ全面に亘って均等に、コンクリートCの打設完了直
後、コンクリートCの硬化前に加えられる。
Is the amount of applied force 20 to 50t/n? The degree is a guideline;
As shown in FIG. 1, this load is applied evenly over almost the entire surface of the concrete structure S immediately after the concrete C is placed and before the concrete C hardens.

また圧密されたコンクリートCより浮上する水の、載荷
面回りから排出を促し、圧密効果を上げるために図示す
るように載荷面積をコンクリート構造体S断面より僅か
に小さくすることが好ましい。
Further, in order to encourage the discharge of water floating from the consolidated concrete C from around the loading surface and to improve the consolidation effect, it is preferable to make the loading area slightly smaller than the cross section of the concrete structure S, as shown in the figure.

コンクリート構造体Sが連続壁の場合を示す第2図以下
の図面により本発明の具体的方法を説明する。
A specific method of the present invention will be explained with reference to the following drawings in FIG. 2 showing a case where the concrete structure S is a continuous wall.

第2図−■に示す実施例はコンクリ−)cの天端上にコ
ンクリート構造体Sの厚さ または断面に相当する幅を
有する、適当な長さのプレート1を載せ、コンクリート
構造体S両側の地盤に埋設されたアンカー2,2間にフ
レーム3を架設し、このフレーム3とプレート1間にジ
ヤツキ4を設置し、アンカー2,2で反力を取りながら
ジヤツキ4のロンド4aを伸長させることによりプレー
ト1を押し下げて載荷する方法である。
In the embodiment shown in Fig. 2-■, a plate 1 of an appropriate length having a width corresponding to the thickness or cross section of the concrete structure S is placed on the top of the concrete structure S. A frame 3 is erected between the anchors 2 and 2 buried in the ground, a jack 4 is installed between the frame 3 and the plate 1, and the rond 4a of the jack 4 is extended while taking the reaction force with the anchors 2, 2. In this method, the plate 1 is pushed down and loaded.

第2図−■はコンクリートc中に配筋された鉄筋すが天
端から露出する場合であるが、ジヤツキ4はプレートl
にあけられた鉄筋す挿通用の挿通孔1aの間に設置され
、上記の要領でプレート1に力がかけられる。
Figure 2-■ shows the case where the reinforcing bars placed in the concrete c are exposed from the top, but the jack 4 is the plate l.
The plate 1 is installed between the insertion holes 1a drilled in the plate 1 for insertion of reinforcing bars, and a force is applied to the plate 1 in the manner described above.

この場合はプレート1回りからの排水に加え、挿通孔1
aからの脱水が促される利点がある。
In this case, in addition to draining water from around the plate 1,
This has the advantage of promoting dehydration from a.

第3図の実施例は第2図の実施例と同様にアンカー2,
2によりコンクリートCの天端上に固定された、プレー
ト1と同程度の面積を持つ拘束板5と天端間にエアバッ
グ6を設置し、中に空気を送り込み、これを膨張させる
ことにより天端面に荷重を加える載荷方法である。
The embodiment of FIG. 3 is similar to the embodiment of FIG.
An airbag 6 is installed between the top and the restraining plate 5, which is fixed on the top of the concrete C according to 2 and has an area similar to that of the plate 1, and air is pumped into the top of the concrete C to inflate it. This is a loading method that applies a load to the end face.

以上の第2図、または第3図に示す載荷方法によりコン
クリートCの圧密か行われる。
Consolidation of the concrete C is performed by the loading method shown in FIG. 2 or FIG. 3 above.

第4図の実施例はプレート1に全面に亘って孔1bをあ
け、第1図、または第2図の、ジヤツキ4やエアバッグ
6を用いる方法により上方から力を加えた際にプレート
l全面からの脱水効果を図る方法である。
In the embodiment shown in FIG. 4, holes 1b are drilled over the entire surface of the plate 1, and when force is applied from above by the method using the jack 4 or the air bag 6 shown in FIG. This is a method to improve the dehydration effect from water.

第5図の実施例はプレート1の背面側に不織布等の溌水
材7を張り付け、天端まで浮上した水をプレート1の周
辺まで逃がして回り込ませることにより脱水を促進させ
る方法である。
The embodiment shown in FIG. 5 is a method of promoting dehydration by attaching a water repellent material 7 such as a non-woven fabric to the back side of the plate 1 and allowing water that has floated to the top to escape to the periphery of the plate 1 and circulate around it.

第6図の実施例は載荷時にコンクリートcウニパイブレ
ーク8を差し込み、これでコンクリートcに振動を与え
ることによってコンクリートcの圧密と脱水の効果を上
げる方法である。
The embodiment shown in FIG. 6 is a method in which a concrete c sea urchin pie break 8 is inserted during loading and vibration is applied to the concrete c, thereby increasing the effect of compaction and dewatering of the concrete c.

(発明の効果) この発明は以上の通りであり、コンクリートの打設完了
後、その硬化前に天端から全面に亘って均等に荷重を加
え、自重のみでは圧密に不足する上層部を強制的に圧密
し、脱水するものであるためコンクリート構造体の強度
は深さ方向に均質化され、その品質を向上させることが
できる。
(Effects of the Invention) This invention is as described above, and after concrete is poured and before it hardens, a load is applied evenly over the entire surface from the top, and the upper layer, which cannot be consolidated by its own weight alone, is forcibly Since the concrete is consolidated and dehydrated, the strength of the concrete structure is made uniform in the depth direction, and its quality can be improved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の要領を示した斜視図、第2図−1,■
はジヤツキを用いる方法を示した斜視図、第3図はエア
バッグを用いる方法を示した斜視図、第4図〜第6図は
他の実施例を示した斜視図である。 S・・・・・・コンクリート構造体、C・・・・・・コ
ンクリート、b・・・・・・鉄筋、■・・・・・・プレ
ート、1a・・・・・・挿通孔、1b・・・・・・孔、
2・・・・・・アンカー 3・・・・・・フレーム、4
・・・・・・ジヤツキ、4a・・・・・・口・ンド、5
・・・・・・拘束板、6・・・・・・エアバ・ング、7
・・・・・・撥水材、8・・・・・・パイブレーク。 第 3 図 第 図 第 図 第 図
Figure 1 is a perspective view showing the gist of the present invention, Figure 2-1, ■
3 is a perspective view showing a method using a jack, FIG. 3 is a perspective view showing a method using an air bag, and FIGS. 4 to 6 are perspective views showing other embodiments. S...Concrete structure, C...Concrete, b...Reinforcement, ■...Plate, 1a...Through hole, 1b. ...hole,
2...Anchor 3...Frame, 4
・・・・・・Jyatsuki, 4a・・・mouth・do, 5
...Restraint plate, 6... Air bar ng, 7
...Water repellent material, 8...Pie break. Figure 3 Figure 3 Figure 3

Claims (1)

【特許請求の範囲】[Claims] (1)天端までコンクリートの打設が完了したコンクリ
ート構造体の天端面に、ほぼ全面に亘って鉛直下向きに
荷重を加え、コンクリート構造体の上層部分をその硬化
前に圧密するとともに、その部分を脱水するコンクリー
ト構造体の締め固め方法。
(1) A load is applied vertically downward over almost the entire surface of the top surface of the concrete structure for which concrete has been poured up to the top, to consolidate the upper layer of the concrete structure before it hardens, and to A compaction method for concrete structures that dewaters.
JP25102489A 1989-09-27 1989-09-27 Compaction method for concrete structure Pending JPH03115656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25102489A JPH03115656A (en) 1989-09-27 1989-09-27 Compaction method for concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25102489A JPH03115656A (en) 1989-09-27 1989-09-27 Compaction method for concrete structure

Publications (1)

Publication Number Publication Date
JPH03115656A true JPH03115656A (en) 1991-05-16

Family

ID=17216490

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25102489A Pending JPH03115656A (en) 1989-09-27 1989-09-27 Compaction method for concrete structure

Country Status (1)

Country Link
JP (1) JPH03115656A (en)

Similar Documents

Publication Publication Date Title
US6354768B1 (en) Soil reinforcement method and apparatus
DE19518830B4 (en) Method of stabilising underground below roads and buildings - involves column excavation replaced by geo-textile load-bearing casing for dewatering and compacting in-situ with resultant ground load absorption
CN214089820U (en) Building foundation construction reinforcing apparatus
JPH05302318A (en) Method and apparatus for stabilizing friction soiland adjacent cohesion soil layers
JPH03115656A (en) Compaction method for concrete structure
JPH0144852B2 (en)
JP2730705B2 (en) Improvement method for soft ground
JP3458174B2 (en) Construction method of reinforced soil retaining wall
JP2622312B2 (en) Construction method of double cofferdam
JP2002138487A (en) Support structure of building structure
JP3177723B2 (en) Embankment method
JP2005163271A (en) Restrained soil structure and its construction method
JPH0441209B2 (en)
JP2553648B2 (en) Reinforcing cage for cast-in-place concrete pile and construction method using it
JPS6347418A (en) Reinforcing structure of banking ground
CN214005697U (en) Steel wire grid net protection structure for broken rock mass of rock slope
KR890004540B1 (en) Soft Ground Underground Structure
JPH04336116A (en) Executing method for cast-in-place concrete pile
KR960003748B1 (en) Working method of concrete pile or sand pile for a soft-soil foundation
JP2927612B2 (en) Foundation method
JPH0739666B2 (en) Permeable temporary earth retaining material, permeable frame structure and concrete wall construction method
CN115928820A (en) Strengthening Method of Silt Foundation and Ground Pile
JPS59199919A (en) Pile foundation
JPH0547683B2 (en)
JP2005163268A (en) Restrained soil structure and its construction method