JPH03180692A - Building method for enlarging tunnel part - Google Patents

Building method for enlarging tunnel part

Info

Publication number
JPH03180692A
JPH03180692A JP31914589A JP31914589A JPH03180692A JP H03180692 A JPH03180692 A JP H03180692A JP 31914589 A JP31914589 A JP 31914589A JP 31914589 A JP31914589 A JP 31914589A JP H03180692 A JPH03180692 A JP H03180692A
Authority
JP
Japan
Prior art keywords
lining
pit
tunnel
enlarged
small
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP31914589A
Other languages
Japanese (ja)
Other versions
JPH0765456B2 (en
Inventor
Tsuneo Wakita
脇田 恒夫
Yoshiaki Idota
井戸田 芳昭
Toshio Izawa
伊沢 利夫
Kenichi Matsushima
健一 松島
Taro Kasuya
太郎 粕谷
Shigeru Matsuoka
茂 松岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tobishima Corp
Okumura Corp
Tekken Corp
Original Assignee
Tobishima Corp
Okumura Corp
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tobishima Corp, Okumura Corp, Tekken Corp filed Critical Tobishima Corp
Priority to JP1319145A priority Critical patent/JPH0765456B2/en
Publication of JPH03180692A publication Critical patent/JPH03180692A/en
Publication of JPH0765456B2 publication Critical patent/JPH0765456B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To facilitate execution of a work by building a ditchform pit throughout the overall length of an enlargement scheduled section, causing pushing of a small curved pipe body from the one side of the pit in a manner to make one round of the outer periphery of an existing lining to cause the pipe body to arrive at the other side of the pit, and repeating above works. CONSTITUTION:A pit 4 is built throughout the overall length of the enlargement scheduled section of an existing tunnel 1. A pipe body press-in device 5 comprising a small excavator 13, curved so as to have the same curved surface as that of an enlarging tunnel 2, and a jack 11 is disposed in the pit 4. Excavation is progressed by pushing the excavator 13 by means of the jack 11, curved pipe bodies 14 are orderly coupled to the back of the excavator 13 to make one round of the outer periphery of the tunnel 1, and the excavator 13 is excavated to the other side of the pit 4. Further, a similar work described above is repeated by using the pipe bodies 14 serving as a guide to build an enlarging lining part 18. This method freely sets size and a shape and executes a work through small scale excavation.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はシールド工法によって築造したトンネルの所望
長さ部分に拡大トンネル部を構築する方法に関するもの
である。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method for constructing an enlarged tunnel section at a desired length of a tunnel constructed by a shield method.

〔従来の技術〕[Conventional technology]

一般に、下水道や地下鉄或いは配線坑等のトンネルはシ
ールド工法によって掘削されているが、地下鉄における
退避場所や駅の構築、或いは排水、換気設備の設置場所
や配線の引き込み用空間部を必要とする場合には、該ト
ンネルの所定長さ部分に拡大トンネル部を設ける必要が
ある。
In general, tunnels for sewers, subways, or wiring tunnels are excavated using the shield method, but when building evacuation areas or stations in subways, or when a space for installing drainage and ventilation equipment or a space for wiring is required. In this case, it is necessary to provide an enlarged tunnel portion at a predetermined length of the tunnel.

このような拡大トンネル部は、通常、シールド工法によ
ってトンネルを掘削した後、地上からトンネル拡大予定
位置に立坑を掘削し、この立坑を利用して所望のトンネ
ル拡大部を築造することが行われている。
Such an expanded tunnel section is usually constructed by excavating the tunnel using the shield method, then excavating a vertical shaft from the ground at the planned tunnel expansion location, and using this vertical shaft to construct the desired tunnel expansion section. There is.

しかしながら、市街地などにおいては道路事情の悪化や
環境保全等に鑑みて地上から立坑を掘削することができ
ない場合がある。
However, in urban areas, etc., it may not be possible to excavate a vertical shaft from the ground due to deteriorating road conditions or environmental conservation considerations.

このため、例えば特公昭62−16310号公報に記載
しているように、既設トンネルの拡大予定区域における
所望幅部分のシールドセグメントを該区域全長に亘って
除去し、この除去跡にピットを1屈削したのち、該ピッ
ト内に円周シールド機を設置すると共に拡大予定区域の
両端に円周方向に案内部材を取付け、この案内部材に円
周シールド機の基部を係合させてシールドジヤツキの伸
長により該円周シールド機を案内部材に沿って推進させ
ながら、それに後続して円周シールドセグメントを順次
接続することにより、トンネル拡大部を構築する方法が
開発されている。
For this purpose, for example, as described in Japanese Patent Publication No. 62-16310, a shield segment of a desired width in an area scheduled for expansion of an existing tunnel is removed over the entire length of the area, and a pit is placed in the area where it was removed. After cutting, a circumferential shielding machine is installed in the pit, and guide members are installed in the circumferential direction at both ends of the area to be expanded, and the base of the circumferential shielding machine is engaged with this guide member to open the shield jack. A method has been developed for constructing a tunnel enlargement by sequentially connecting circumferential shield segments while the circumferential shield machine is propelled along a guide member by elongation.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

この工法によれば、立坑を掘削することなくトンネル拡
大部を構築できるが、計画予定区域の全長に亘る長さを
有する円周シールド機を推進させるには大規模な装置を
必要とする上に、その推進に従って土砂を掘削や拡大予
定部のシールドセグメントの除去を行う必要があるため
に、作業が輻較し、能率が低下するという問題点がある
。
According to this construction method, it is possible to construct an expanded tunnel without excavating a vertical shaft, but it requires large-scale equipment to propel a circumferential shield machine that spans the entire length of the planned area. In accordance with the progress, it is necessary to excavate earth and sand and remove shield segments in areas scheduled for expansion, which causes problems in that work is crowded and efficiency is reduced.

さらに、円周シールド機は既設トンネルを支点としてこ
のトンネルの外周を一巡するものであるから、築造され
るトンネル拡大部は既設トンネルと同心円上に形成され
ることになって、既設トンネルの一例部に他側部よりも
広い拡幅部を形成することができないものである。
Furthermore, since the circumferential shield machine uses the existing tunnel as a fulcrum and goes around the outer circumference of this tunnel, the tunnel expansion part to be constructed will be formed concentrically with the existing tunnel, and it will be a part of the existing tunnel. It is not possible to form a widened part wider than the other side part.

又、上記のように、大規模な円周シールド機の推進が困
難であるために、長さが大で、且つ大断面のトンネル拡
大部を構築することが難しい等の問題点があった。
Further, as mentioned above, since it is difficult to propel a large-scale circumferential shield machine, there have been problems such as difficulty in constructing a tunnel expansion section that is long and has a large cross section.

本発明はこのような問題点を解消することを目的とする
拡大トンネル部の構築方法を提供するものである。
The present invention provides a method for constructing an enlarged tunnel section, which aims to solve these problems.

〔課題を解決するための手段〕[Means to solve the problem]

上記目的を達成するために、本発明の拡大トンネル部の
構築方法は、シールド工法によって築造した既設トンネ
ル覆工における拡大予定区域にその区域の全長に亘って
適宜幅と深さを有するピットを設け、このピットの一側
面適所から所望長さ寸法を有する小径の彎曲管体を順次
直列状態に接続しながら前記既設トンネル覆工の外周方
を一巡するように推進させてピットの他側面に到達させ
ることにより一エレメントの拡大覆工部を形成し、この
拡大覆工部を形成した前記小径彎曲管体をガイドとして
該拡大覆工部に隣接する次の小径彎曲管体列よりなる拡
大覆工部をトンネルの長さ方向に形成し、この作業を拡
大予定区域の全長に亘って繰り返し行って該拡大予定区
域部の既設トンネル覆工を覆った拡大覆工を形成し、し
かるのち、拡大予定区域の既設トンネル覆工を除去する
と共に拡大覆工内の土砂を掘削、除去することを特徴と
するものである。
In order to achieve the above object, the method for constructing an expanded tunnel section of the present invention includes providing a pit having an appropriate width and depth over the entire length of the area to be expanded in an existing tunnel lining constructed by the shield method. , Small-diameter curved pipes having a desired length are connected in series from an appropriate position on one side of the pit, and are propelled around the outer periphery of the existing tunnel lining to reach the other side of the pit. By doing so, an enlarged lining part of one element is formed, and the enlarged lining part is made up of the next row of small diameter curved pipe bodies adjacent to the enlarged lining part, using the small diameter curved pipe body forming this enlarged lining part as a guide. is formed in the length direction of the tunnel, and this work is repeated over the entire length of the planned expansion area to form an expanded lining that covers the existing tunnel lining in the planned expansion area. This method is characterized by removing the existing tunnel lining and excavating and removing the earth and sand within the expanded lining.

〔作   用〕[For production]

ピットの一側面適所から所望長さ寸法を有する小径の彎
曲管体を順次直列状態に接続しながら前記既設トンネル
覆工の外周方を一巡するように推進させてピットの他側
面に到達させることにより、まず、拡大予定区域におけ
るトンネル長さ方向の一部分に一エレメントの拡大覆工
部を形成するものであるから、比較的小規模の掘削手段
によって拡大覆工部を築造できると共にその拡大覆工部
の大きさや形状等が比較的自由に設定できて、既設トン
ネルの一側部が他側部よりも広い拡幅部となった拡大覆
工部を得ることができ、次いで、この拡大覆工部をガイ
ドとして次の拡大覆工部をトンネルの長さ方向に形成し
、この作業を繰り返すことによって拡大予定区域の全長
に亘って一連の拡大覆工部による拡大覆工を形成するも
のであるから、比較的長く且つ大断面の拡大覆工を容易
に施工し得る。
By connecting small-diameter curved pipes having a desired length in series from an appropriate position on one side of the pit, the pipes are propelled around the outer periphery of the existing tunnel lining to reach the other side of the pit. First, since an expanded lining of one element is formed in a portion of the tunnel lengthwise in the planned expansion area, the expanded lining can be constructed by relatively small-scale excavation means, and the expanded lining can also be expanded. The size and shape of the existing tunnel can be set relatively freely, and it is possible to obtain an expanded lining section in which one side of the existing tunnel is wider than the other side. The next enlarged lining section is formed in the length direction of the tunnel as a guide, and by repeating this operation, an enlarged lining is formed by a series of enlarged lining sections over the entire length of the area to be expanded. Expanded lining that is relatively long and has a large cross section can be easily constructed.

このようにして拡大覆工を施工したのち、拡大予定区域
の既設トンネル覆工を除去すると共に拡大覆工内の土砂
を掘削、除去するものであるから、既設トンネル覆工の
除去作業と拡大覆工内の土砂の掘削作業とは順次連続的
に行え、拡大トンネル部の築造作業が円滑且つ能率良く
行えるものである。
After constructing the expansion lining in this way, the existing tunnel lining in the area planned for expansion is removed, and the earth and sand within the expansion lining is excavated and removed. The earth and sand excavation work within the construction site can be carried out sequentially and continuously, allowing the construction work of the enlarged tunnel section to be carried out smoothly and efficiently.

なお、上記方法において、拡大覆工部を形成するための
小径彎曲管体を既設トンネル覆工の外周方に沿って推進
させるに際して、上記ピットの一側面適所から内周端を
既設トンネル覆工の内周面に係合させて計画拡大覆工ま
での寸法を規制するガイド部材を順次直列に連結しなが
ら推進させてピットの他側面に達するリング状ガイドを
形成したのち、このリング状ガイドに案内させながら上
記最初の拡大覆工部の小径彎曲管体を推進させれば、拡
大覆工部の築造作業が一層確実に行える。
In addition, in the above method, when the small diameter curved pipe for forming the expanded lining section is propelled along the outer periphery of the existing tunnel lining, the inner periphery end is moved from an appropriate position on one side of the pit to the outer periphery of the existing tunnel lining. After forming a ring-shaped guide that reaches the other side of the pit by connecting the guide members that engage with the inner circumferential surface and regulate the dimensions up to the planned expansion lining in series, the guide members are guided to the ring-shaped guide. If the small-diameter curved pipe body of the first expanded lining section is propelled while moving, the construction work of the expanded lining section can be performed more reliably.

又、拡大予定区域の既設トンネル覆工の適所に予め該ト
ンネル覆工の外周を1巻きするようにしてワイヤを巻装
しておき、上記ピットの形成後に該ピットの一側から推
進させる小径彎曲管体の最先端側に該ワイヤの一端を固
着すると共にピットの他側から該ピット内に引き出した
ワイヤの他端を小径彎曲管体の推進と共に張引すること
によって、或いは、ピットの一側面から拡大覆工部を形
成するこめの小径彎曲管体を推進させるに際して、該小
径彎曲管体の先端部にワイヤを固定すると共にこの小径
彎曲管体の計画推進経路に向かって既設トンネル覆工内
部からガイド部材を計画推進経路に沿って周方向に適宜
間隔毎に突設し、ピット内でワイヤを張引することによ
り小径彎曲管体を上記ガイド部材に沿って推進させるこ
とによって小径彎曲管体の推進方向を正確に制御するこ
とができる。
In addition, a wire is wound in advance at a suitable location on the existing tunnel lining in the planned expansion area so that the outer circumference of the tunnel lining is wrapped once, and after the pit is formed, a small diameter curvature is propelled from one side of the pit. By fixing one end of the wire to the most extreme side of the pipe body and pulling the other end of the wire into the pit from the other side of the pit as the small diameter curved pipe body is propelled, or by pulling the other end of the wire into the pit from one side of the pit. When propelling the small-diameter curved pipe of the temple that forms the enlarged lining section, a wire is fixed to the tip of the small-diameter curved pipe and the inside of the existing tunnel lining is moved toward the planned propulsion route of the small-diameter curved pipe. Guide members are protruded at appropriate intervals in the circumferential direction along the planned propulsion route, and the small diameter curved pipe body is propelled along the guide member by tensioning a wire in the pit. The direction of propulsion can be precisely controlled.

〔実 施 例] 本発明の実−施例を図面について説明すると、第1図に
おいて、(1)はシールド工法によって築造された既設
のトンネルであり、(2)は該既設のトンネル(1)の
所望個所に築造すべき計画拡大トンネル部である。
[Embodiment] To explain the embodiment of the present invention with reference to the drawings, in Fig. 1, (1) is an existing tunnel constructed by the shield method, and (2) is the existing tunnel (1). This is the planned expansion tunnel section to be constructed at the desired location.

まず、この計画拡大トンネル部(2)における既設トン
ネル(1)の−次覆エセグメント(3)の下周部を計画
拡大トンネル部(2)の全長に亘って掘り下げて適宜幅
のピット(4)を形成する(第1図乃至第3図参照)。
First, the lower periphery of the secondary cover segment (3) of the existing tunnel (1) in this planned expansion tunnel section (2) is dug down over the entire length of the planned expansion tunnel section (2), and a pit (4 ) (see Figures 1 to 3).

このピット(4)の形成は、核部の一次覆エセグメンI
−(3)を取り外したのち、適宜な掘削手段によって行
ってもよいが、トンネル構築時において、そのピット形
成予定部分に拡幅用のセグメン) (3a)を組み立て
ておき、このセグメント(3a)を上周部のセグメント
(3)に反力をとって押し下げながら掘進させることに
よって所望深さのピット(4)を形成することもできる
。
The formation of this pit (4) is due to the primary covering segment I of the core.
- After removing (3), this may be done by appropriate excavation means, but when constructing the tunnel, a widening segment (3a) is assembled in the area where the pit is planned to be formed, and this segment (3a) is It is also possible to form a pit (4) of a desired depth by using the reaction force of the segment (3) on the upper periphery to push down and dig.

こうしてピット(4)の形成後、該ピット(4)内に第
8図に示すような管体圧入装置(5)を設置する。
After the pit (4) is thus formed, a tube press-fitting device (5) as shown in FIG. 8 is installed in the pit (4).

この管体圧入装置(5)は、トンネル長さ方向に移動自
在な台枠(5a)上に上面が計画拡大トンネル部(2)
の覆工(2)の曲面に略等しい凹弧面に形成されている
架台(6)を固定すると共に台枠(5a)の−側部に管
体挿通口(7)と上下ガイドローラ(8a) (8b)
を設けている側板(9)を一体に設け、さらに、台枠(
5a)の他側端に反力壁00)を立設すると共に該反力
壁0ωの内面にジヤツキ(11)を取付け、このジヤツ
キ00のロンド先端に前記架台(6)上を移動する押枠
(121を取付けてなるものである。
This tube press-fitting device (5) is mounted on an underframe (5a) that is movable in the tunnel length direction, and the upper surface is located at the planned enlarged tunnel section (2).
A frame (6) formed in a concave arc surface approximately equal to the curved surface of the lining (2) is fixed, and a tube insertion opening (7) and upper and lower guide rollers (8a ) (8b)
A side plate (9) is provided integrally with the underframe (9).
5a) A reaction wall 00) is erected at the other end, and a jack (11) is attached to the inner surface of the reaction wall 0ω, and a push frame that moves on the frame (6) is attached to the rond tip of the jack 00. (121 is attached.

この管体圧入装置(5)をその側板(9)がピット(4
)の適所の一側面に当接状態となるように設置したのち
、架台(6)上に計画拡大トンネル部(2)の覆工(2
)の曲面と略等しい彎曲度で長さ方向に彎曲している小
径掘削機03)を載置し、ジヤツキ(11)を伸長させ
ることによって押枠02)を介し、該小径掘削機0つを
側Fi(9)の挿通口(7)から既設トンネル(1)の
覆工セグメント(3)の外周方に押じ出し、土砂を掘削
しながら推進させる。
The side plate (9) of this tube press-fitting device (5) is connected to the pit (4).
), and then install the lining (2) of the planned expansion tunnel section (2) on the pedestal (6).
) is placed, and by extending the jack (11), the small diameter excavators 03), which are curved in the length direction with approximately the same degree of curvature as the curved surface of It is pushed out from the insertion port (7) of the side Fi (9) toward the outer periphery of the lining segment (3) of the existing tunnel (1), and is propelled while excavating the earth and sand.

この小径掘削機03)が側板(9)から完全に地中に推
進させたのち、ジヤツキ01)を収縮させて架台(6)
上に該小径掘削機03)と略同径で且つ、同−彎曲度で
長さ方向に彎曲している一定寸法の小径彎曲管体04)
をこの小径掘削機03)の背面に当接状態で連結、後続
させ、この小径彎曲管体0巾をジヤツキ(11)で押進
すると共に小径掘削機θ3)により前方の地盤を掘削し
ながら該小径彎曲管体Q4)を地中に押し込む。
After this small-diameter excavator 03) is completely propelled underground from the side plate (9), the jack 01) is contracted and the mount (6) is
Above is a small-diameter curved pipe body 04) of a constant size, which has approximately the same diameter as the small-diameter excavator 03) and is curved in the length direction with the same degree of curvature.
is connected to and follows the back of this small-diameter excavator 03), and this small-diameter curved pipe body 0 width is pushed forward with a jack (11), and the ground in front is excavated by the small-diameter excavator θ3). Push the small diameter curved pipe Q4) into the ground.

小径彎曲管体Oaには、トンネル長さ方向に面した両側
面部に第9図に示すように係合ガイド溝05)とこの係
合ガイド溝05)に係合可能な係止突片0ωとを夫々長
さ方向に突設しである。
As shown in FIG. 9, the small diameter curved tube body Oa has an engagement guide groove 05) and a locking protrusion 0ω that can be engaged with the engagement guide groove 05) on both side faces facing the tunnel length direction. are provided protruding in the length direction.

小径掘削機03)によって掘削された土砂は、この小径
彎曲管体04)の空間内部を通してピンI−(4)内に
排出される。なお、ジヤツキ(11)による管体押し込
み反力が反力壁00)に伝達されて管体圧入装置(5)
が後退しようとするので、反力壁00)とピット(4)
の他側面間に適宜な反力受0′7)を介在させておく。
The earth and sand excavated by the small diameter excavator 03) is discharged into the pin I-(4) through the space inside the small diameter curved pipe body 04). Note that the reaction force for pushing the tube by the jack (11) is transmitted to the reaction wall 00), and the tube press-fitting device (5)
tries to retreat, so the reaction wall 00) and the pit (4)
An appropriate reaction force receiver 0'7) is interposed between the other sides.

小径掘削機03)に後続して一本の小径彎曲管体0(1
)を地中に圧入したのちは、該小径彎曲管体04)に次
の同形状の小径彎曲管体側を継ぎ足して上記同様に圧入
し、以下、先行する小径彎曲管体0巾に後続して複数本
の小径彎曲管体Q4)を順次直列状態に連結させながら
第5図に示すように、既設トンネル(1)の覆工セグメ
ント(3)の外周地盤中に周方向に推進させる。
Following the small diameter excavator 03), a small diameter curved pipe body 0 (1
) is press-fitted into the ground, the next small-diameter curved pipe body side of the same shape is added to the small-diameter curved pipe body 04) and press-fitted in the same manner as above, and hereafter, the small-diameter curved pipe body 0 width is followed by the preceding small-diameter curved pipe body 0 width. A plurality of small diameter curved pipes Q4) are successively connected in series and propelled into the ground around the outer periphery of the lining segment (3) of the existing tunnel (1) as shown in FIG. 5.

この時、小径掘削機03)の彎曲並びに小径彎曲管体側
によって既設トンネル(1)の覆工セグメント(3)の
外周を該外周面から適宜間隔を存した状態で取り巻く方
向に方向制御しながら推進され、先端の小径掘削機03
)がトンネル外周を一巡してピット(4)の他側面に到
達する。
At this time, the curved and small diameter curved pipe body side of the small diameter excavator 03) is propelled while controlling the direction to surround the outer circumference of the lining segment (3) of the existing tunnel (1) with an appropriate distance from the outer circumferential surface. The tip of the small diameter excavator 03
) goes around the outer circumference of the tunnel and reaches the other side of the pit (4).

こうして、複数本の小径彎曲管体04)の連なりによっ
て既設トンネル(1)の覆工セグメント(3)の外周方
に一エレメント分の拡大覆工部0印を形成し、ピット(
4)に達した小径掘削機aつの撤去後、ピット(4)の
両側に臨んでいる小径彎曲管体側04)間を該小径彎曲
管体04)と同一形状で且つ上記係合ガイド溝05)や
係止突片00を設けていない彎曲管体09)によって接
続する(第6図参照)。
In this way, an enlarged lining part 0 mark corresponding to one element is formed on the outer periphery of the lining segment (3) of the existing tunnel (1) by a series of plural small diameter curved pipe bodies 04), and the pit (
After removing the small diameter excavator A which has reached 4), the small diameter curved pipe body side 04) facing both sides of the pit (4) is spaced between the small diameter curved pipe body sides 04) with the same shape as the small diameter curved pipe body 04) and the engagement guide groove 05) mentioned above. (See FIG. 6).

次に、上記管体圧入装置(5)を拡大覆工部04)の厚
み間隔だけトンネル方向に移動させたのち、この管体圧
入装置(5)により拡大覆工部08)に隣接して上記小
径掘削機03)を架台(6)の挿通口(7)から圧入し
たのち、該小径掘削機03)に後続して小径彎曲管体0
・υを圧入する。この際、既に埋設されている上記拡大
覆工部側の最後部、即ち、架台(6)の側板(9)側の
ピット(4)内に臨んでいる小径彎曲管体0褐の係合ガ
イド溝05)に圧入すべき小径彎曲管体04)の係止突
片06)を係合させ、この状態で圧入すると、拡大覆工
部側を形成した複数本の小径彎曲管体(14)がその係
合ガイド溝θ9を一連のリング状に連通させているので
、これらの係合ガイド溝05)に係止突片0ωを摺接さ
せながら一定方向に推進、圧入することができる。
Next, after moving the tube press-fitting device (5) in the tunnel direction by the thickness interval of the enlarged lining section 04), the tube press-fitting device (5) moves the tube adjacent to the enlarged lining section 08). After the small-diameter excavator 03) is press-fitted through the insertion port (7) of the mount (6), the small-diameter curved pipe body 0 is inserted following the small-diameter excavator 03).
・Press in υ. At this time, the engagement guide of the small-diameter curved pipe body 0 facing the rearmost part of the enlarged lining part that has already been buried, that is, the pit (4) on the side plate (9) side of the pedestal (6). When the locking protrusion 06) of the small diameter curved pipe body 04) to be press-fitted into the groove 05) is engaged and press-fitted in this state, the plurality of small diameter curved pipe bodies (14) forming the enlarged lining part side are Since the engagement guide grooves θ9 are connected in a series of ring shapes, the locking projections 0ω can be pushed and press-fitted in a certain direction while slidingly in contact with these engagement guide grooves 05).

こうして、小径彎曲管体側を管体圧入装置(5)によっ
て一連に連続させながら順次圧入して、既に埋設した拡
大覆工部08)に隣接する拡大覆工部08)を形成する
。
In this way, the small-diameter curved pipe body side is successively press-fitted by the pipe press-fitting device (5) in a continuous manner to form an enlarged lining part 08) adjacent to the already buried enlarged lining part 08).

この作業を既設トンネル(1)の長さ方向に順次行って
、第10図に示すように、計画拡大トンネル部(2)の
全長に亘って、隣接する拡大覆工部08)同士が互いに
係合ガイド講05)と係止突片0ωを介して接した一連
の並列拡大覆工部08)側・・・08)による拡大覆工
12rjが得られる。
By performing this work sequentially in the length direction of the existing tunnel (1), as shown in Figure 10, the adjacent expanded lining sections 08) are connected to each other over the entire length of the planned expanded tunnel section (2). An enlarged lining 12rj is obtained by a series of parallel enlarged lining parts 08) side...08) that are in contact with the guide section 05) via the locking protrusion 0ω.

なお、小径掘削機0つ及び小径彎曲管体04)の彎曲度
とその圧入方向を適宜設定することによって、拡大覆工
12(Ilの断面形状の大きさを決めることができると
共に、既設トンネル(1)に対して偏心した拡大覆工Q
(D、即ち、既設トンネルの両側に対してトンネル外周
から拡大覆工C!Φはその一例部が他側部よりも大きく
離間した拡幅部となるように施工することができる。
In addition, by appropriately setting the degree of curvature of the small-diameter excavator 0 and the small-diameter curved pipe body 04) and its press-in direction, the size of the cross-sectional shape of the enlarged lining 12 (Il) can be determined, and the size of the cross-sectional shape of the expanded lining 12 (Il) can be determined. Enlarged lining Q eccentric to 1)
(D) In other words, the expanded lining C!Φ can be constructed on both sides of the existing tunnel from the outer periphery of the tunnel so that one part of the lining becomes a widened part that is further apart from the other side part.

こうして、既設トンネル(1)の拡大予定区域に拡大覆
工QOを施したのち、該区域部のトンネル(1)の覆工
セグメント(3)を取り外し、しかるのち、或いは該覆
工セグメント(3)の除去と並行して拡大覆工QIIl
により囲まれた土砂を適宜な掘削手段により掘削、排除
して拡大トンネル部(2)を形成するものである。
In this way, after applying the expansion lining QO to the area scheduled for expansion of the existing tunnel (1), the lining segment (3) of the tunnel (1) in the area is removed, or the lining segment (3) In parallel with the removal of
The expanded tunnel section (2) is formed by excavating and removing the earth and sand surrounded by the excavation means using an appropriate excavation means.

なお、各拡大覆工部08)は、ピット(4)内において
彎曲管体09)により最前部の小径彎曲管体04)と最
後部の小径彎曲管体0褐とを連結されており、この彎曲
管体09)の下周部とピット(4)の内底面間の空間部
にコンクリート(21)を打設する(第7図)。
In addition, in each enlarged lining section 08), the small diameter curved pipe body 04) at the frontmost part and the small diameter curved pipe body 0 brown at the rearmost part are connected by a curved pipe body 09) in the pit (4). Concrete (21) is placed in the space between the lower circumference of the curved pipe body 09) and the inner bottom surface of the pit (4) (Fig. 7).

次に、上記実施例において、最初に施工する拡大覆工部
08)の形威は、小径掘削機03)とそれに後続する小
径彎曲管体04)の彎曲度によって所定の軌跡を招くよ
うに推進させることにより行っているが、この拡大覆工
部側は、次に述べるような方向制御手段を介して行うこ
とが好ましい。
Next, in the above embodiment, the shape of the expanded lining section 08) to be constructed first is determined by the degree of curvature of the small-diameter excavator 03) and the small-diameter curved pipe body 04) that follows it, so that it is propelled to a predetermined trajectory. However, it is preferable that the enlarged lining section side is controlled via a direction control means as described below.

即ち、第11図及び第12図に示すように、拡大予定区
域における既設トンネル(1)の覆工セグメント(3)
の適所に全周に亘ってガイド部材(22)の挿通係止間
隔部(23)を設け、この係止間隔部(23)にピット
(4)の−側部から、第13図及び第14図に示すよう
な、内端に既設トンネル(1)の覆工セグメント内面に
係止する係止ローラ(24)を回転自在に軸支し、且つ
外端部両面に保合ガイド溝(15a)と係止突片(16
a)を夫々突設した適宜高さを有する扇形板状ガイド部
材(22)を順次直列に連結しながらジヤツキ(25)
で推進させてピット(4)の他側面に達するリング状ガ
イド(A)を形成したのち、このリング状ガイド(A)
の一連に連通した係合ガイド溝(15a)と係止突片(
16a)に小径掘削機03)に後続する小径彎曲管体0
4)の係止突片06)又は係合ガイド溝05)を係合さ
せながら管体圧入装置(5)により上記同様にして小径
彎曲管体04)を順次圧入していくものである。
That is, as shown in FIGS. 11 and 12, the lining segment (3) of the existing tunnel (1) in the planned expansion area
A locking interval part (23) is provided at a proper position along the entire circumference of the guide member (22), and a guide member (22) is inserted into the locking interval part (23) from the negative side of the pit (4) as shown in FIGS. 13 and 14. As shown in the figure, a locking roller (24) that locks on the inner surface of the lining segment of the existing tunnel (1) is rotatably supported at the inner end, and retaining guide grooves (15a) are provided on both sides of the outer end. and locking protrusion (16
The fan-shaped plate-shaped guide members (22) having appropriate heights, each of which is protruded from a), are successively connected in series and jacked (25).
After forming a ring-shaped guide (A) that reaches the other side of the pit (4), this ring-shaped guide (A)
The engagement guide groove (15a) and the locking protrusion (15a) communicate with each other in a series.
In 16a), a small diameter curved pipe body 0 following the small diameter excavator 03)
While engaging the locking projections 06) or the engagement guide grooves 05) of 4), the small diameter curved tubes 04) are sequentially press-fitted using the tube press-fitting device (5) in the same manner as described above.

上記ガイド部材(22)を挿通させる係止間隔部(23
)は、トンネル(1)の築造時に、その部分の覆工セグ
メント間に撤去可能なリング状部材を介在させておくこ
とによって形威し得る。
The locking interval portion (23) through which the guide member (22) is inserted
) can be effected by interposing a removable ring-shaped member between the lining segments of the tunnel (1) during construction.

又、ガイド部材(22)がこの係止間隔部(23)に既
設トンネル(1)の内面側から挿通係止可能な場合には
、上記したようなジヤツキ(25)によることなくリン
グ状ガイド(A)を形成することができる。
In addition, if the guide member (22) can be inserted and locked into the locking interval (23) from the inner surface of the existing tunnel (1), the ring-shaped guide ( A) can be formed.

さらに、このガイド部材(22)として第15図に示す
ように、先端に上記小径彎曲管体04)と同一形状の彎
曲管体部(14a)を一体に設けたものをピット(4)
内から上記と同様にして管体圧入装置(5)により小径
掘削機03)に後続、連結して順次圧入し、リング状ガ
イドを形成してもよい。この場合、彎曲管体部(14a
)の両面に突設した係合ガイド溝(15b)と係止突片
(16b)が小径彎曲管体(ロ)の係止突片06)と係
合ガイド溝05)の係合ガイドとなるものである。
Furthermore, as shown in FIG. 15, this guide member (22) is provided with a curved tube part (14a) having the same shape as the small diameter curved tube body 04) at the tip thereof.
Similarly to the above, the tubular body press-fitting device (5) may be connected to the small-diameter excavator 03) and sequentially press-fitted from the inside to form a ring-shaped guide. In this case, the curved pipe body part (14a
The engagement guide groove (15b) and locking protrusion (16b) protruding from both sides of ) serve as engagement guides for the locking protrusion 06) and engagement guide groove 05) of the small diameter curved tube body (b). It is something.

拡大覆工部0■の大きさ並びに形状は、既設トンネル(
1)の覆工セグメント(3)の係止部からリング状ガイ
ド(A)の周方向に連続した保合ガイド溝と係止突片ま
での距離及びこの一連の保合ガイド溝又は係合突片の形
状によって設定でき、ガイド部材(22)を順次その高
さ(内端からガイド溝や係合突片までの寸法)を連続的
に変化させることによって既設トンネル(1)の覆工セ
グメント(3)の周囲に空間広さの異なった拡大覆工を
築造することができる。
The size and shape of the expanded lining section 0■ are similar to the existing tunnel (
The distance from the locking part of the lining segment (3) in 1) to the circumferentially continuous retaining guide groove and locking protrusion of the ring-shaped guide (A), and the series of retaining guide grooves or engaging protrusions. The lining segment of the existing tunnel (1) can be set by changing the height (dimension from the inner end to the guide groove or engagement protrusion) of the guide member (22) sequentially. 3) It is possible to construct expanded linings with different spatial widths around the area.

第16図は別な方向制御手段を示すもので、拡大予定区
域における既設トンネル(1)の覆工セグメント(3)
の適所に、該トンネル構築時に予め覆工セグメント(3
)の外周を1巻きするようにしてワイヤ(26)を巻装
しておき、上記ピット(4)の形成後に、該ピット(4
)の−側からジヤツキ(27)によって地中に推進され
る小径掘削機03)の先端部に該ワイヤ(26)の一端
を固着すると共にピット(4)の他側から該ピット(4
)内に引き出したワイヤ(26)の他端を小径掘削機0
3)に後続して順次圧入される小径彎曲管体側の推進に
従ってピット(4)内に設置したウィンチ(28)によ
り張引することによって一連の小径彎曲管体04)を既
設トンネル(1)の覆工セグメント(3)の外周方で所
望の軌跡を閘くようにその推進方向を制御し、最初の一
エレメントの拡大覆工部08)を形成するものである。
Figure 16 shows another directional control means, in which the lining segment (3) of the existing tunnel (1) in the area planned for expansion is shown.
When constructing the tunnel, lining segments (3
) The wire (26) is wound around the outer circumference of the pit (4) once, and after forming the pit (4),
) One end of the wire (26) is fixed to the tip of a small-diameter excavator 03) that is propelled into the ground by a jack (27) from the - side of the pit (4), and from the other side of the pit (4)
) into the small diameter excavator 0.
3), a series of small diameter curved pipes 04) are pulled into the existing tunnel (1) by being pulled by a winch (28) installed in the pit (4) as the small diameter curved pipes are pushed in sequentially. The direction of propulsion is controlled so as to follow a desired trajectory on the outer circumference of the lining segment (3), thereby forming an enlarged lining portion 08) of the first element.

この拡大覆工部(18)をガイドとして、上記実施例と
同様に管体圧入装置(5)を使用して順次拡大覆工部0
8)を施工し、所望の拡大覆工C1)を築造するもので
あり、築造後はその拡大予定区域部のトンネル(1)の
覆工セグメント(3)を取り外すと共に拡大覆工i2G
により囲まれた土砂を掘削、排除して拡大トンネル部(
2)を形成するものである。
Using this enlarged lining part (18) as a guide, the pipe body press-fitting device (5) is used as in the above embodiment to sequentially enlarge the lining part 0.
8) and build the desired expanded lining C1). After construction, the lining segment (3) of the tunnel (1) in the area planned for expansion is removed and the expanded lining i2G is constructed.
Excavate and remove the earth and sand surrounded by the enlarged tunnel section (
2).

第17図は更に別な方向制御手段を示すもので、ピット
(4)の−側面から最初の拡大覆工部08)を形成する
ための小径彎曲管体側を推進させるに際して、該小径彎
曲管体04)の先端に連結している小径掘削機0つの先
端部にワイヤ(26)を固定する一方、この小径彎曲管
体07I)の計画推進経路に向かって既設トンネル覆工
セグメント(3)の内方から上記実施例で述べた挿通係
止間隔部(23)を通じて先端にガイドローラ(28)
を回転自在に軸支している所望長さのガイド棒(29)
を計画推進経路に沿って周方向に適宜間隔毎に突出させ
、ワイヤ(26)をガイド捧(29)のローラ(28)
に案内させながらピント(4)内で該ワイヤ(26)を
ウィンチ(30)により張引して一連の小径彎曲管体0
4)を上記ガイド部材に沿ってtfi進させるように制
御するものである。
FIG. 17 shows still another direction control means, in which the small diameter curved pipe body side is propelled from the -side of the pit (4) to form the first enlarged lining section 08). While fixing a wire (26) to the tip of the small diameter excavator 0 connected to the tip of the small diameter excavator 04), the inside of the existing tunnel lining segment (3) is The guide roller (28) is inserted from the front end through the insertion locking interval part (23) described in the above embodiment.
A guide rod (29) of desired length that rotatably supports the
are projected at appropriate intervals in the circumferential direction along the planned propulsion route, and the wire (26) is connected to the roller (28) of the guide shaft (29).
The wire (26) is pulled by the winch (30) in the pinto (4) while being guided by a series of small diameter curved tubes.
4) is controlled so as to advance by tfi along the guide member.

この場合、ワイヤ(26)は上記方向制御手段で述べた
ように、覆工セグメント(3)の外周を1巻きさせてピ
ット(4)の他側から引っ張ってもよい。
In this case, the wire (26) may be wound once around the outer periphery of the lining segment (3) and pulled from the other side of the pit (4), as described in the above direction control means.

〔発明の効果) 以上のように本発明の拡大トンネル部の構築方法によれ
ば、シールド工法によって築造した既設トンネル覆工に
おける拡大予定区域にその区域の全長に亘って適宜幅と
深さを有するピットを設け、このピットの一側面適所か
ら所望長さ寸法を有する小径の彎曲管体を順次直列状態
に接続しながら前記既設トンネル覆工の外周方を一巡す
るように推進させてピットの他側面に到達させることに
より、まず、拡大予定区域におけるトンネル長さ方向の
一部分に一エレメントの拡大覆工部を形成するものであ
るから、比較的小規模の掘削手段によって該拡大覆工部
を形成することができると共にその拡大覆工部の大きさ
や形状等が自由に設定できて、既設トンネルに対してそ
の一側方が他側方よりも広い拡幅部となった拡大覆工部
を形成することができるものである。
[Effects of the Invention] As described above, according to the method for constructing an expanded tunnel section of the present invention, the area to be expanded in the existing tunnel lining constructed by the shield method has an appropriate width and depth over the entire length of the area. A pit is provided, and small-diameter curved pipes having a desired length are connected in series from an appropriate position on one side of the pit, and are propelled around the outer periphery of the existing tunnel lining to open the other side of the pit. By reaching this point, an expanded lining of one element is first formed in a portion of the tunnel lengthwise in the area to be expanded, so the expanded lining is formed by relatively small-scale excavation means. In addition to being able to freely set the size and shape of the expanded lining, it is possible to form an expanded lining in which one side of the existing tunnel is wider than the other side. It is something that can be done.

さらに、この拡大覆工部をガイドとして次の拡大覆工部
をトンネルの長さ方向に形成し、この作業を繰り返すこ
とによって拡大予定区域の全長に亘って一連の拡大覆工
部による拡大覆工を形成するものであるから、所望長さ
の且つ大断面の拡大覆工を容易に施工し得る。
Furthermore, using this expanded lining section as a guide, the next expanded lining section is formed in the length direction of the tunnel, and by repeating this operation, an expanded lining section is formed by a series of expanded lining sections over the entire length of the area to be expanded. Therefore, an enlarged lining with a desired length and large cross section can be easily constructed.

又、このようにして拡大覆工を施工したのち、拡大予定
区域の既設トンネル覆工を除去すると共に拡大覆工内の
土砂を掘削、除去するものであるから、既設トンネル覆
工の除去作業と拡大覆工内の土砂の掘削作業とはj噴次
連続的に行え、拡大l・ンネル部の築造作業が円滑且つ
能率良く行えるものである。
In addition, after constructing the expanded lining in this way, the existing tunnel lining in the area scheduled for expansion is removed, and the earth and sand within the expanded lining is excavated and removed, so it is not the same as the removal work of the existing tunnel lining. The work of excavating earth and sand in the expanded lining can be carried out continuously, and the construction work of the expanded tunnel can be carried out smoothly and efficiently.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の実施例を示すもので、第1図:よ拡大予
定区域部のトンネルの横断平面図、第2図は縦断正面図
、第3図はピントを形成した状態の縦断正面図、第4図
乃至第7図は拡大覆工部の施工工程を示す縦断正面図、
第8図は管体圧入装置の縦断正面図、第9図は隣接する
小径彎曲管体の接続状態を示す断面図、第10図は拡大
覆工を築造したトンネル部分の横断平面図、第1I図は
方向制御手段を配設した状態の横断平面図、第12図は
その方向制御手段の施工状態を示す簡略縦断正面図、第
13図はガイド部材の正面図、第14図はその側面図、
第15図はガイド部材の変形例を示す側面図、第16図
及び第17図は別な方向制御手段を示す簡略縦断正面図
である。 (1)・・・既設トンネル、(2)・・・計画拡大トン
ネル部、(3)・・・覆工セグメント、(4)・・・ピ
ント、(5)・・・管体圧入装置、 0つ・・・小径掘削機、 04・・・小径彎曲管体、 08)・・・ 拡大覆工部、 QO・・・拡大覆工。 ネベ 注へ 2べ 序込 a大 テ 層へ 1う λべ め 7/1 ノジて 3 戻へ 、ダ 2氷 ヅ 庄) ≧六 6 層き ネX ノア 側へ
The drawings show an embodiment of the present invention; Fig. 1 is a cross-sectional plan view of the tunnel in the area to be expanded, Fig. 2 is a longitudinal sectional front view, and Fig. 3 is a longitudinal sectional front view with a focused state. Figures 4 to 7 are longitudinal sectional front views showing the construction process of the enlarged lining section;
Fig. 8 is a longitudinal sectional front view of the pipe press-fitting device, Fig. 9 is a cross-sectional view showing the connection state of adjacent small diameter curved pipes, Fig. 10 is a cross-sectional plan view of the tunnel section where the enlarged lining has been constructed, and Fig. 1I The figure is a cross-sectional plan view of the direction control means installed, FIG. 12 is a simplified vertical cross-sectional front view showing the installation state of the direction control means, FIG. 13 is a front view of the guide member, and FIG. 14 is its side view. ,
FIG. 15 is a side view showing a modified example of the guide member, and FIGS. 16 and 17 are simplified longitudinal sectional front views showing other direction control means. (1) Existing tunnel, (2) Planned expansion tunnel section, (3) Lining segment, (4) Pinto, (5) Pipe press-in device, 0 1...Small diameter excavator, 04...Small diameter curved pipe body, 08)...Expanded lining section, QO...Expanded lining section. To Nebe Note 2 Be Introduction A to Ote Layer 1 λ Beme 7/1 Nojite 3 Go back, Da 2 Ice Zusho) ≧66 Layer Kine X To Noah side

Claims (4)

【特許請求の範囲】[Claims] (1)、シールド工法によって築造した既設トンネル覆
工における拡大予定区域にその区域の全長に亘って適宜
幅と深さを有するピットを設け、このピットの一側面適
所から所望長さ寸法を有する小径の彎曲管体を順次直列
状態に接続しながら前記既設トンネル覆工の外周方を一
巡するように推進させてピットの他側面に到達させるこ
とにより一エレメントの拡大覆工部を形成し、この拡大
覆工部を形成した前記小径彎曲管体をガイドとして該拡
大覆工部に隣接する次の小径彎曲管体列よりなる拡大覆
工部をトンネルの長さ方向に形成し、この作業を拡大予
定区域の全長に亘って繰り返し行って該拡大予定区域部
の既設トンネル覆工を覆った拡大覆工を形成し、しかる
のち、拡大予定区域の既設トンネル覆工を除去すると共
に拡大覆工内の土砂を掘削、除去することを特徴とする
拡大トンネル部の構築方法。
(1) A pit with an appropriate width and depth is provided over the entire length of the area scheduled for expansion in the existing tunnel lining constructed using the shield method, and a small diameter pit with the desired length is installed from an appropriate location on one side of the pit. The curved pipe bodies of the above are connected in series in sequence and are propelled around the outer periphery of the existing tunnel lining to reach the other side of the pit, thereby forming an enlarged lining part of one element. This work is planned to be expanded by forming an enlarged lining section consisting of the next row of small diameter curved pipe bodies adjacent to the enlarged lining section in the length direction of the tunnel using the small diameter curved pipe body that formed the lining section as a guide. This is repeated over the entire length of the area to form an expanded lining that covers the existing tunnel lining in the area planned for expansion, and then the existing tunnel lining in the area scheduled for expansion is removed and the earth and sand in the expanded lining is removed. A method of constructing an enlarged tunnel section characterized by excavating and removing.
(2)、拡大覆工部を形成するための小径彎曲管体を既
設トンネル覆工の外周方に沿って推進させるに際して、
上記ピットの一側面適所から内周端を既設トンネル覆工
の内周面に係合させて計画拡大覆工までの寸法を規制す
るガイド部材を順次直列に連結しながら推進させてピッ
トの他側面に達するリング状ガイドを形成したのち、こ
のリング状ガイドに案内させながら上記最初の拡大覆工
部の小径彎曲管体を推進させることを特徴とする請求項
(1)記載の拡大トンネル部の構築方法。
(2) When propelling the small diameter curved pipe body for forming the expanded lining section along the outer periphery of the existing tunnel lining,
A guide member whose inner peripheral end engages with the inner peripheral surface of the existing tunnel lining to regulate the dimensions of the planned expanded tunnel lining is moved from a suitable position on one side of the pit to the other side of the pit while being successively connected in series. Construction of an enlarged tunnel section according to claim (1), characterized in that after forming a ring-shaped guide that reaches , the small-diameter curved tube of the first enlarged lining section is propelled while being guided by this ring-shaped guide. Method.
(3)、拡大予定区域の既設トンネル覆工の適所に予め
該トンネル覆工の外周を1巻きするようにしてワイヤを
巻装しておき、上記ピットの形成後に該ピットの一側か
ら推進させる小径彎曲管体の先端側に該ワイヤの一端を
固着すると共にピットの他側から該ピット内に引き出し
たワイヤの他端を小径彎曲管体の推進と共に張引するこ
とによって小径彎曲管体の推進方向を制御することを特
徴とする請求項(1)記載の拡大トンネル部の構築方法
。
(3) A wire is wound in advance at a suitable location on the existing tunnel lining in the planned expansion area so that the outer circumference of the tunnel lining is wrapped once, and after the above-mentioned pit is formed, the wire is propelled from one side of the pit. The small diameter curved tube is propelled by fixing one end of the wire to the tip side of the small diameter curved tube and pulling the other end of the wire drawn into the pit from the other side of the pit as the small diameter curved tube is propelled. The method for constructing an enlarged tunnel portion according to claim 1, characterized in that the direction is controlled.
(4)、ピットの一側面から拡大覆工部を形成するため
の小径彎曲管体を推進させるに際して、該小径彎曲管体
の先端部にワイヤを固定すると共にこの小径彎曲管体の
計画推進経路に向かって既設トンネル覆工内部からガイ
ド部材を計画推進経路に沿って周方向に適宜間隔毎に突
設し、ピット内でワイヤを張引することにより小径彎曲
管体を上記ガイド部材に沿って推進させるように制御す
ることを特徴とする拡大トンネル部の構築方法。
(4) When propelling a small-diameter curved pipe for forming an enlarged lining section from one side of the pit, a wire is fixed to the tip of the small-diameter curved pipe, and the planned propulsion path of this small-diameter curved pipe Guide members are protruded from inside the existing tunnel lining at appropriate intervals in the circumferential direction along the planned propulsion route, and by tensioning the wire in the pit, the small diameter curved pipe body is guided along the guide members. A method of constructing an enlarged tunnel section, characterized by controlling the enlarged tunnel section so as to propel it.
JP1319145A 1989-12-09 1989-12-09 How to build an expanded tunnel section Expired - Lifetime JPH0765456B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1319145A JPH0765456B2 (en) 1989-12-09 1989-12-09 How to build an expanded tunnel section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1319145A JPH0765456B2 (en) 1989-12-09 1989-12-09 How to build an expanded tunnel section

Publications (2)

Publication Number Publication Date
JPH03180692A true JPH03180692A (en) 1991-08-06
JPH0765456B2 JPH0765456B2 (en) 1995-07-19

Family

ID=18106945

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1319145A Expired - Lifetime JPH0765456B2 (en) 1989-12-09 1989-12-09 How to build an expanded tunnel section

Country Status (1)

Country Link
JP (1) JPH0765456B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017218878A (en) * 2016-06-11 2017-12-14 株式会社大林組 Starting area construction method of small-diameter shield

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6216310A (en) * 1985-07-13 1987-01-24 中村 欽哉 Manufacture of pack
JPS6229596A (en) * 1985-07-31 1987-02-07 サノフイ Peptide amino-alcohol derivative controlling rennin and acidprotease and containing 4-substituted carbon atom, obtainingprocess and therapeutical use

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6216310A (en) * 1985-07-13 1987-01-24 中村 欽哉 Manufacture of pack
JPS6229596A (en) * 1985-07-31 1987-02-07 サノフイ Peptide amino-alcohol derivative controlling rennin and acidprotease and containing 4-substituted carbon atom, obtainingprocess and therapeutical use

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017218878A (en) * 2016-06-11 2017-12-14 株式会社大林組 Starting area construction method of small-diameter shield

Also Published As

Publication number Publication date
JPH0765456B2 (en) 1995-07-19

Similar Documents

Publication Publication Date Title
KR101737628B1 (en) Construction method of underground structures using the repeating process of the protective tube-attraction and the structure-propulion
JP5024228B2 (en) Widening method of shield tunnel
CN109026035B (en) Tunnel annular variable cross section expanding excavation method
JP2005036435A (en) Tunnel structure and construction method
JP7357517B2 (en) Pipe construction method using propulsion method
JP7185667B2 (en) Press bar for open shield method
JPH0765456B2 (en) How to build an expanded tunnel section
JPH0489992A (en) Existing pipe duct enlarging method and shield excavation device used with the method
CN119572285B (en) Mobile supporting device for tunnel construction and tunnel construction method
JP3253854B2 (en) Inner formwork for concrete lining of tunnel walls
JP7625743B1 (en) Box roof and its construction method
JP4705467B2 (en) Construction method of underground structure
JPS5820898A (en) Method and apparatus for constructing small inner diameter pipe in ground
CN112780298B (en) Tunnel construction method using fabricated tunnel shallow buried section shed tunnel structure
KR101620787B1 (en) underground excavation construction method
JP6019689B2 (en) Tunnel widening method
JP5158631B2 (en) Construction method of tunnel junction
KR100558260B1 (en) Method shield rig and method shield method
JPH076345B2 (en) Enlarged tunnel lining method
JP2597874B2 (en) Widening culvert and its construction method
JPH11336048A (en) Construction method of impermeable wall for gutter pipe
JPS6145037B2 (en)
JPH07208065A (en) Tunnel construction method
JP2003206697A (en) Construction method for underground structures
JPH02296993A (en) Tunnel part spread shield method and device thereof and guide segment piece related thereto

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080719

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080719

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090719

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090719

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100719

Year of fee payment: 15

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100719

Year of fee payment: 15