JPH03224962A - Delivery shaft - Google Patents
Delivery shaftInfo
- Publication number
- JPH03224962A JPH03224962A JP2162390A JP2162390A JPH03224962A JP H03224962 A JPH03224962 A JP H03224962A JP 2162390 A JP2162390 A JP 2162390A JP 2162390 A JP2162390 A JP 2162390A JP H03224962 A JPH03224962 A JP H03224962A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- hatch
- opening
- equipment
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 claims description 19
- 238000009434 installation Methods 0.000 claims description 4
- 238000010276 construction Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は、建屋内の設備工事に際して設備資材を各階
に搬入する場合のシャフトであって、特に建屋内の最上
階から最下階まで貫通した搬入用板開口を設けた搬入シ
ャフトに関する。[Detailed Description of the Invention] [Industrial Application Field] This invention relates to a shaft for carrying equipment materials to each floor during facility construction inside a building, and in particular a shaft that penetrates from the top floor to the bottom floor in a building. The present invention relates to a loading shaft provided with a loading plate opening.
従来、複数階からなるコンクリート建屋への内部設備を
行う場合には、建屋本体を建設した後に、各階に据え付
けられる設備器具・装置を搬入し、設備される。このよ
うな資材類をコンクリ−1・建屋の各階に搬入するため
に従来から行われている工法は、各階に設けられたドア
や窓等の恒久設備の開口を利用し、資材・機器の搬入を
行っていた。Conventionally, when installing internal equipment in a concrete building consisting of multiple floors, the building itself is constructed, and then the equipment and devices to be installed on each floor are brought in and installed. The conventional construction method for transporting such materials to each floor of a concrete building is to use openings in permanent equipment such as doors and windows installed on each floor to transport materials and equipment. was going on.
しかし、上記従来の工法にあっては、搬入口より搬入し
た機器を開口横引移動させ、開口上部に設けている揚重
設備にて所定の階へ吊り下し、もしくは吊り上げる。こ
の為、資材・機器の搬入には、多大な時間と工数を必要
とする欠点がある。However, in the above-mentioned conventional construction method, the equipment brought in through the entrance is moved horizontally through the opening, and then suspended or hoisted to a predetermined floor using lifting equipment provided above the opening. For this reason, there is a drawback that it requires a large amount of time and man-hours to bring in materials and equipment.
この発明の目的は、前記従来工法の欠点を解消し、複数
階をもつ建屋の各階への資材・機器の搬入を容易にする
搬入シャフトを提供するにある。SUMMARY OF THE INVENTION An object of the present invention is to provide a loading shaft that eliminates the drawbacks of the conventional construction method and facilitates loading of materials and equipment to each floor of a building having multiple floors.
[課題を解決するだめの手段]
複数階から構成されるコンクリート建屋の建屋内設備据
付工事に際して、資材・製品の搬入を可能に上下階に貫
通した搬入仮開口を設けるとともに、この搬入仮開口に
はハツチをスライド開閉可能に設け、前記ハツチの開閉
により荷受は台として用いることにより搬入口から搬入
された資材を据付階へ容易に搬送可能としたものである
。[Means to solve the problem] When installing equipment in a concrete building consisting of multiple floors, we will provide temporary access openings that pass through the upper and lower floors to allow materials and products to be brought in, and In this system, a hatch is provided so that it can be slid open and closed, and by opening and closing the hatch, the cargo receiver is used as a platform, thereby making it possible to easily transport materials carried in through the entrance to the installation floor.
上記構成によれば、数階から成るコンクリート構造建屋
内に、資材・機器を搬入するに際し、各階での横移動を
少なくする手段として、建屋最上階から最下階まで貫通
した搬入用の板間口を建屋建設時に設け、資材類の搬入
階のスライドハツチを閉じて搬入仮開口を閉鎖し、当該
スライドハツチを荷受は台を用いる。ハツチ上に置かれ
た資機材はハツチのスライド移動により搬入板間口上か
ら引き込まれる。したがって、他の階に対する1#大作
業に支承なく資機材の積み卸しを行うことができる。そ
の後、設備据付工事に対応し、工事完了後に開口部を後
打ちすることにより、建屋設備を所定の設計通りに戻す
ことができるので、建屋構造の変更等の問題も全く生じ
ない。According to the above configuration, when carrying materials and equipment into a concrete structure building consisting of several floors, a board opening is provided that penetrates from the top floor to the bottom floor of the building as a means of reducing lateral movement on each floor. shall be installed during building construction, the sliding hatch on the floor for carrying in materials will be closed, the temporary opening for carrying in materials will be closed, and a platform will be used to receive the goods through the sliding hatch. Materials and equipment placed on the hatch are pulled in from above the entrance of the loading board by the sliding movement of the hatch. Therefore, it is possible to load and unload materials and equipment without having to worry about large-scale work on other floors. Thereafter, the building equipment can be returned to the predetermined design by responding to the equipment installation work and post-casting the openings after the work is completed, so there are no problems such as changes to the building structure.
第1図は本発明に係る搬入シャフトの具体的実施例を示
すコンクリート建屋の断面図である。この図に示される
ように、コンクリートの打設によって構造体としての建
屋10を構築されるが、このコンクリート建屋10の各
階を仕切るスラブ12には屋上階も含め各階毎に、同一
位置にて上下に貫通された搬入仮開口14を予め設けて
いる。FIG. 1 is a cross-sectional view of a concrete building showing a specific embodiment of the carry-in shaft according to the present invention. As shown in this figure, a building 10 as a structure is constructed by pouring concrete, and the slab 12 that partitions each floor of this concrete building 10 has two sections, one above the other, at the same location on each floor, including the roof floor. A temporary carry-in opening 14 is provided in advance.
これは予めスラブ12への打設時に型枠によって搬入仮
開口14に相当する部分を除いてコンクリートの打設を
行うことで容易に実現される。そして、各搬入仮開口1
4にはスライドハツチ16を取り付け、このスライドハ
ツチ16によって前記搬入仮開口14を開閉可能にして
いる。スライドハツチ16は鋼板等により形成し、搬入
仮開口14の縁に設けたガイドレール等εこよって摺動
移動可能としておく。もちろん、スライドハツチ16に
車輪等を付帯して走行させてスライドできるようにして
もよい。またスライドハツチ16は各スラブ12の床面
上に設置するようにして、各階層内に引き込み可能とす
る。This can be easily achieved by placing concrete in advance on the slab 12 by using a formwork to remove the portion corresponding to the temporary opening 14 for carrying in the concrete. And each temporary opening 1
A slide hatch 16 is attached to 4, and the slide hatch 16 enables the temporary carry-in opening 14 to be opened and closed. The slide hatch 16 is formed of a steel plate or the like, and is made slidable by a guide rail or the like provided at the edge of the temporary carry-in opening 14. Of course, the slide hatch 16 may be provided with wheels or the like so that it can run and slide. Further, the slide hatch 16 is installed on the floor surface of each slab 12 so that it can be drawn into each floor.
このように構成された搬入シャフトを用いた資材の搬入
作業はつぎのように行われる。まず、コンクリート建屋
10外の搬入路18の位置まで記載しない運搬手段にて
移動してきた資材20を揚重機22Aまたは22Bにて
荷受後、吊り上げ最上部の搬入仮開口14よりコンクリ
ート建屋10内に搬入し、所定階まで吊り下ろす。The work of carrying in materials using the carrying shaft configured as described above is performed as follows. First, the material 20 that has been moved by a transport means not described to the position of the carry-in path 18 outside the concrete building 10 is received by the lifting machine 22A or 22B, and then lifted and carried into the concrete building 10 through the temporary carry-in opening 14 at the top. and hang it down to the designated floor.
この時、すべての搬入仮開口14には、付属設備として
スライドハツチ16が設けであるので、資材20を搬入
する階以外のスライドハツチ16は開放状態にし、資材
20の搬入に障害とはからず、搬入時以外は、閉止状態
とし、開口部を塞ぐ手段として用いる。At this time, all the temporary loading openings 14 are equipped with slide hatches 16 as accessory equipment, so the slide hatches 16 on floors other than those on which the materials 20 are to be brought in are left open so that they do not become an obstacle to the loading of the materials 20. , it is kept closed except when it is being carried in, and is used as a means to close the opening.
このように必要階へ吊り下された資材20は、搬送を容
易にするために予めスライドハツチ16上に案内された
運搬用台車24上に積載され据付位置まで搬送する。The material 20 suspended to the required floor in this manner is loaded onto a transport trolley 24 guided in advance on the slide hatch 16 in order to facilitate transport, and transported to the installation position.
前記実施例にいおいては、建屋屋上よりの搬入方法につ
いて説明したが、途中階にて建屋内に進入できる搬入路
を設けることができるならば、屋上階の開口部は必要と
せずに、最上階天井部に専用の揚重設備を設けてもよい
。この際はその途中階より上方階のスライドハツチ16
は吊り上げ時には開放しておき、荷受は時に閉じて1最
大板間口14を塞くようにすればよい。In the above embodiment, the method of carrying in from the roof of the building was explained, but if it is possible to provide a carry-in path that allows entry into the building at an intermediate floor, an opening in the roof floor is not necessary. Dedicated lifting equipment may be provided in the ceiling of the top floor. In this case, use the slide hatch 16 on the floor above the middle floor.
may be left open during hoisting, and the cargo receiver may be closed at times to cover one maximum board width 14.
各階への設備資材20の搬入作業が終了した後は、スラ
イドハツチ16を取り外し、搬入仮開口14にコンクリ
ート打設を行って本来のスラブ12構造に戻すようにす
る。After the work of transporting the equipment 20 to each floor is completed, the slide hatch 16 is removed and concrete is poured into the temporary transport opening 14 to restore the original structure of the slab 12.
〔発明の効果]
以上説明したように、本発明によれば、各階に搬入仮開
口を設けて上下揚重作業だけで搬入をなすので、各階で
の横移動が最小となり、搬入効率が向上する。しかも、
搬入仮開口にはスライドハツチを設けてこれを荷受は台
として利用するので、荷受は作業が簡便に行われ、かつ
通常はこれを閉じておくことができるので安全性の高い
ものとなる。[Effects of the Invention] As explained above, according to the present invention, a temporary loading opening is provided on each floor and loading is performed only by lifting up and down, thereby minimizing lateral movement on each floor and improving loading efficiency. . Moreover,
Since a slide hatch is provided in the temporary loading opening and the cargo receiver is used as a platform, the cargo receiver can be easily operated, and since it can normally be kept closed, it is highly safe.
第1図は実施例に係る搬入シャフトを形成したコンクリ
ート建屋での作業状態を示す断面図である。
1
0・・・・・・コンクリート建屋、
4・・・・・・搬入板間
口、
■
6・・・・・・スライ
ドハツチ。FIG. 1 is a sectional view showing a working state in a concrete building in which a carry-in shaft according to an embodiment is formed. 1 0... Concrete building, 4... Loading board frontage, ■ 6... Slide hatch.
Claims (1)
内設備据付工事に際して、資材・製品の搬入を可能に上
下階に貫通した搬入仮開口を設けるとともに、この搬入
仮開口にはハッチをスライド開閉可能に設け、前記ハッ
チの開閉により荷受け台として用いることにより搬入口
から搬入された資材を据付階へ容易に搬送可能としたこ
とを特徴とした搬入シャフト。(1) When installing equipment inside a concrete building consisting of multiple floors, a temporary access opening will be provided that penetrates the upper and lower floors to allow materials and products to be brought in, and a hatch will be opened and closed by sliding in this temporary access opening. 1. A carry-in shaft, characterized in that the hatch is provided so that it can be used as a load receiving platform by opening and closing the hatch, thereby making it possible to easily transport materials carried in from a carry-in entrance to an installation floor.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2162390A JPH03224962A (en) | 1990-01-31 | 1990-01-31 | Delivery shaft |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2162390A JPH03224962A (en) | 1990-01-31 | 1990-01-31 | Delivery shaft |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH03224962A true JPH03224962A (en) | 1991-10-03 |
Family
ID=12060192
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2162390A Pending JPH03224962A (en) | 1990-01-31 | 1990-01-31 | Delivery shaft |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH03224962A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2020200731A (en) * | 2019-06-13 | 2020-12-17 | 大成建設株式会社 | Receiving stage and lifting system |
| JP2021001519A (en) * | 2019-06-25 | 2021-01-07 | 株式会社安藤・間 | Material and equipment transportation method |
-
1990
- 1990-01-31 JP JP2162390A patent/JPH03224962A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2020200731A (en) * | 2019-06-13 | 2020-12-17 | 大成建設株式会社 | Receiving stage and lifting system |
| JP2021001519A (en) * | 2019-06-25 | 2021-01-07 | 株式会社安藤・間 | Material and equipment transportation method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP3867188B1 (en) | Method and arrangement | |
| JPH03224962A (en) | Delivery shaft | |
| JP7701105B1 (en) | Lifting fixture and installation method | |
| CN114096479A (en) | Method and apparatus | |
| JP2859811B2 (en) | Equipment transportation method and elevator with transportation basket | |
| JP2001055833A (en) | How to carry in and out construction materials | |
| JP2851758B2 (en) | Lifting method of construction materials | |
| JPH0437168Y2 (en) | ||
| JP2025094429A (en) | Method for transporting materials at a construction site and system for transporting materials at a construction site | |
| JP3252713B2 (en) | Operating method of overhead crane | |
| JPH03224963A (en) | Delivery shaft method | |
| JP2000309428A (en) | Bucket crane | |
| CN210122466U (en) | Civil engineering is with construction elevating gear | |
| JP2588050Y2 (en) | Large cargo doorway equipment | |
| JPS5912062A (en) | Engine room floor of elevator | |
| JP2025126597A (en) | Transporting method of unnecessary material at construction site, and transporting system of unnecessary material at construction site | |
| JPH0835337A (en) | Curing lid for temporary floor opening | |
| JPS59118965A (en) | Converying of material | |
| JPH09132393A (en) | Floor opening device and carrier | |
| JPH03125760A (en) | Multistoried parking apparatus | |
| JP2596283B2 (en) | Omnidirectional solid gantry | |
| JP2000063066A (en) | Escalator frame loading / unloading method | |
| HK40067762A (en) | Methods and devices for transporting construction materials and equipment inside buildings under construction | |
| JPS6234890A (en) | Ship container cargo handling structure | |
| JPH0823222B2 (en) | Mobile pick-up gantry |