JPH0325103A - Joint work for pc pillar and pc cap beam - Google Patents
Joint work for pc pillar and pc cap beamInfo
- Publication number
- JPH0325103A JPH0325103A JP16043889A JP16043889A JPH0325103A JP H0325103 A JPH0325103 A JP H0325103A JP 16043889 A JP16043889 A JP 16043889A JP 16043889 A JP16043889 A JP 16043889A JP H0325103 A JPH0325103 A JP H0325103A
- Authority
- JP
- Japan
- Prior art keywords
- pillar
- plate
- concrete
- column
- cavity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
この発明は、鉄道,道路などの高架橘におけるPC柱と
PC枕梁の接合工法,特にパイルベント方式の接合工法
に関するものである.「従来の技術,発明か解決せんと
する問題点」従来、地盤に打込んだPCパイルを基礎と
槌脚を兼ねた柱材とし、この柱材の上部に枕梁を結合一
・体化し、この枕梁上に桁と床版を布設することにより
高架橘を構築するようにしたパイルベントカ式が知られ
ている。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for joining PC columns and PC pillows in elevated structures such as railways and roads, particularly a pile bent method. ``Prior art, problems to be solved by invention'' Conventionally, a PC pile driven into the ground was used as a column material that served as a foundation and a hammer foot, and a pillow beam was connected and integrated on the top of this column material. The pile bentoka method is known, in which an elevated bridge is constructed by laying girders and floor slabs on top of the pillow beams.
そして、従来のパイルベント方式においては柱材として
ブレストレストコンクリート杭を用い、枕梁は現場打ち
コンクリートにより施工するのかー・般的であった.
そのため、従来工法では枕梁川の型枠及び鉄筋の鍬女工
及びコンクリート打設工を行うことから工数が多く、工
期も長くなると共に、型枠及び鉄筋の組立の技能者を要
し、しかもコンクリートの品質が安定したものか得られ
ない等の問題かあった。In the conventional pile bent method, breast-stressed concrete piles were used as pillar materials, and the pillow beams were constructed using cast-in-place concrete. For this reason, the conventional construction method requires a large number of man-hours and a long construction period because it involves howing the formwork and reinforcing bars and pouring concrete. There were problems such as stable quality or not being able to obtain it.
「問題点を解決するための手段」
この発明は前記従来の課題を解決するために枕梁lをプ
レキャストコンクリートにより成形し、その上部に箱抜
き空胴2を設け,その底面と枕梁1の下面に連通して杵
挿大のための挿入開口3を設け、この箱抜き空胴2内に
はPC枕梁lの内部の配筋と連続一体に鉄筋4を配節し
、更に挿入開口3の下端開口周縁には接合プレート6を
固定し、また中空のPC柱7の上端部下方の外周に環状
鋼板8を取付け、その外周に水平に張出した鋼製の梁受
プレート9を固定しておき,環状鋼板8の上方における
PC柱7の上端部を破砕して内部の補強鉄筋lOを露出
させ、このPC柱7の環状鋼板部をPC枕梁lの挿入開
口の下方から挿入して補強鉄筋10を箱抜き空胴2内に
突設し、梁受プレート9上に接合プレート6を載置して
溶接し、この状態で箱抜き空胴2内にコンクリート1l
を打設することにより、PC柱7とPC枕梁lを接合一
体化するようにした接合工法を提案するものてある.
「実施例」
以下この発明を図面に示す実施例について説IJjする
と、PC枕梁1は第1.2図に示すように、その上部に
所要数の箱抜き空胴2か設けられ,その底面と枕梁下面
に連通して柱挿入のための神大開口3が設けられており
、箱抜き空胴2内にはPC枕梁lの内部の配筋と連続一
体に鉄筋4が配筋されており、挿入開口3の内周面には
鋼板5が固定され、また挿入開口3の下端開口周縁には
鋼板5と一体に接合プレート6が固定されている.
PC柱7は第3図に示すようにコンクリートパイルから
なり、その上端部下方の外周に環状鋼板8か取付けられ
,この環状鋼板8の外周には水平に張出した鋼製の梁受
プレート9が固定されている.
上記PC枕梁lとPC柱7の接合施工に際しては7JJ
n!!に示すように、先ず環状鋼板8の上方におけるP
C柱7の上端部のコンクリートなハツリ破砕して内部の
補強鉄筋10を露出させこのPC柱7の上端部をPC枕
梁lのf方から挿入開口3に挿入し、その梁受プレート
9LにPC枕梁lの接合プレート6を載せて両者を溶接
により固定し、PC柱7上に枕梁iを仮支持する.
この状態において、PC柱7の環状鋼板8の部分は挿入
開口3内に嵌合され、露出した補強鉄筋10は箱抜き空
胴2内に突出されており、この箱抜き空胴2内にコンク
リート11を打設することにより、PC枕梁1とPC柱
7は一体に接合される。"Means for Solving the Problems" In order to solve the above-mentioned conventional problems, the present invention forms the pillow beam l using precast concrete, provides a boxed cavity 2 in the upper part, and connects the bottom surface of the pillow beam 1 to the pillow beam 1. An insertion opening 3 for inserting a punch is provided in communication with the lower surface, and reinforcing bars 4 are arranged in this box-opening cavity 2 so as to be continuous and integral with the reinforcement inside the PC pillow beam l. A joining plate 6 is fixed to the periphery of the opening at the lower end, and an annular steel plate 8 is attached to the outer periphery below the upper end of the hollow PC column 7, and a steel beam support plate 9 extending horizontally is fixed to the outer periphery. Then, the upper end of the PC column 7 above the annular steel plate 8 is crushed to expose the internal reinforcing reinforcing bar lO, and the annular steel plate part of the PC column 7 is inserted from below the insertion opening of the PC pillow l to reinforce it. A reinforcing bar 10 is installed protruding into the box cavity 2, a joint plate 6 is placed on the beam support plate 9 and welded, and in this state, 1 liter of concrete is placed inside the box cavity 2.
This paper proposes a joining method in which the PC column 7 and the PC pillar support l are joined and integrated by pouring. ``Embodiment'' The embodiment of this invention shown in the drawings will be described below. As shown in FIG. A large opening 3 for inserting a column is provided in communication with the lower surface of the PC pillow beam, and reinforcing bars 4 are arranged in the box-cut cavity 2 in a continuous manner with the reinforcement inside the PC pillow beam l. A steel plate 5 is fixed to the inner circumferential surface of the insertion opening 3, and a joining plate 6 is fixed integrally with the steel plate 5 to the periphery of the lower end of the insertion opening 3. As shown in Fig. 3, the PC pillar 7 is made of a concrete pile, and a ring-shaped steel plate 8 is attached to the outer periphery of the lower part of the upper end. It is fixed. 7JJ when connecting the above PC pillar support l and PC column 7.
n! ! As shown in FIG.
The concrete of the upper end of the C column 7 is chipped to expose the internal reinforcing steel bar 10, and the upper end of the PC column 7 is inserted into the insertion opening 3 from the f side of the PC pillow beam l, and inserted into the beam support plate 9L. The joining plate 6 of the PC pillow beam l is placed on it, and both are fixed by welding, and the pillow beam i is temporarily supported on the PC column 7. In this state, the annular steel plate 8 part of the PC column 7 is fitted into the insertion opening 3, the exposed reinforcing reinforcing bar 10 is projected into the box cavity 2, and the concrete is inserted into the box cavity 2. 11, the PC pillar support 1 and the PC column 7 are joined together.
このコンクリート打設の際には、PC柱7の中空部は適
当な封鎖板で封鎖しておく。During this concrete pouring, the hollow part of the PC column 7 is sealed with a suitable sealing plate.
なお、補強鉄ft55ioのみでは鉄筋縫として不足す
る場合等、必要に応じて環状鋼板8に補助鉄筋を溶接す
ることかできる.
「発明の効果」
以上の通りこの発明によれば、枕梁かプレキャストコン
クリート製であるので、現場での型枠や鉄筋の組立が不
要で、施工工数及び工期を低減させることができ、また
コンクリートの品質も安定化したものが得られると共に
、箱抜き空胴が設けられているので、全体的に軽量化さ
れ、運搬等の取扱か容易である.
また,PC柱の上端部下方の外周に取付けた環状鋼板の
外周に固定してなる鋼製の梁受プレート上にPC枕梁の
挿入開口の下端開口周縁の接合プレートを載置して溶接
するので、PC枕梁なPC柱上に簡単に仮支持し、この
状態で箱抜き空胴内にコンクリートを打設して両者を容
易に接合一体化することかでき,短時間で能率的に接合
施工を行うことができる.In addition, if the reinforcing iron FT55io alone is insufficient for sewing reinforcing bars, auxiliary reinforcing bars can be welded to the annular steel plate 8 as necessary. ``Effects of the Invention'' As described above, according to this invention, since the pillow beams are made of precast concrete, there is no need to assemble formwork or reinforcing bars on site, reducing the number of construction steps and construction period. The quality of the product is also stabilized, and since a box-cutting cavity is provided, the overall weight is reduced, making transportation and other handling easier. In addition, the joining plate around the lower end opening of the insertion opening of the PC pillow beam is placed and welded onto the steel beam support plate fixed to the outer periphery of the annular steel plate attached to the outer periphery of the lower end of the upper end of the PC column. Therefore, it is possible to easily temporarily support the PC pillars on the PC pillars, and in this state, pour concrete into the box cavity to easily join and integrate the two, allowing for efficient joining in a short time. Construction can be carried out.
第1図はこの発明に係るPC枕梁の平面図、第2図は同
縦断正面図、第3図はこの発明に係るPC柱の半断面正
面図、第4図はこの発明による接合状態を示す縦断正面
図,第5図はこの発明により構築した高架橋の正面図,
第6図は同側面図である.
l・・PC枕梁、2・・箱抜き空胴、
3・・神入開口、4・・鉄筋,5・・鋼板、6・・接合
プレート,7・・PC柱、FIG. 1 is a plan view of a PC pillar according to the present invention, FIG. 2 is a longitudinal front view of the same, FIG. 3 is a half-sectional front view of a PC column according to the present invention, and FIG. 4 shows a joined state according to the present invention. Figure 5 is a front view of the viaduct constructed according to the present invention.
Figure 6 is a side view of the same. l...PC pillow beam, 2...box-cutting cavity, 3...Kamiiri opening, 4...reinforcing bar, 5...steel plate, 6...joint plate, 7...PC column,
Claims (1)
板の外周に、水平に張出した鋼製の梁受プレートを固定
し、前記環状鋼板の上方におけるPC柱の上端部を破砕
して内部の補強鉄筋を露出させ、PC枕梁の上部に設け
た箱抜き空胴の底面と下面に連通して設けた挿入開口の
下方から、前記PC柱の環状鋼板部を挿入して前記補強
鉄筋を前記箱抜き空胴内に突設し、前記梁受プレート上
に前記挿入開口の開口周縁に固定した鋼製の接合プレー
トを載置して溶接し、前記箱抜き空胴内にコンクリート
を打設することを特徴とするPC柱とPC枕梁の接合工
法。1) A horizontally protruding steel beam support plate is fixed to the outer periphery of an annular steel plate attached to the outer periphery below the upper end of a hollow PC column, and the upper end of the PC column above the annular steel plate is crushed. The internal reinforcing bars are exposed, and the annular steel plate part of the PC pillar is inserted from below the insertion opening provided in communication with the bottom and lower surfaces of the box-cut cavity provided at the upper part of the PC pillar. protruding into the box-cut cavity, a steel joint plate fixed to the opening periphery of the insertion opening is placed and welded onto the beam receiving plate, and concrete is poured into the box-cut cavity. A method for joining PC columns and PC pillow beams.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16043889A JPH0325103A (en) | 1989-06-22 | 1989-06-22 | Joint work for pc pillar and pc cap beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16043889A JPH0325103A (en) | 1989-06-22 | 1989-06-22 | Joint work for pc pillar and pc cap beam |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0325103A true JPH0325103A (en) | 1991-02-01 |
Family
ID=15714939
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16043889A Pending JPH0325103A (en) | 1989-06-22 | 1989-06-22 | Joint work for pc pillar and pc cap beam |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0325103A (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20010097524A (en) * | 2000-04-24 | 2001-11-08 | 배종렬 | Hybrid precast concrete structure and the method of the same |
| JP2003027418A (en) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | Concrete structure and construction method |
| JP2007077575A (en) * | 2005-09-09 | 2007-03-29 | Naikai Aakit:Kk | Precast concrete girder |
| JP2007197975A (en) * | 2006-01-25 | 2007-08-09 | Taisei Corp | Connection structure between pile head and precast girder and connection method thereof |
| KR101388135B1 (en) * | 2012-08-27 | 2014-04-23 | 삼성물산 주식회사 | Precast Concrete Pier Cap Structure In The Bridge And Manufacturing Method Of Pretension Precast Concrete Pier Cap |
| CN108677685A (en) * | 2018-05-31 | 2018-10-19 | 湖南大学 | A kind of ultra-high performance concrete-part girder steel combination bent cap and its construction method |
| CN114164748A (en) * | 2022-01-07 | 2022-03-11 | 广西交科集团有限公司 | A new type of prefabricated cover beam and its construction method |
-
1989
- 1989-06-22 JP JP16043889A patent/JPH0325103A/en active Pending
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20010097524A (en) * | 2000-04-24 | 2001-11-08 | 배종렬 | Hybrid precast concrete structure and the method of the same |
| JP2003027418A (en) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | Concrete structure and construction method |
| JP2007077575A (en) * | 2005-09-09 | 2007-03-29 | Naikai Aakit:Kk | Precast concrete girder |
| JP2007197975A (en) * | 2006-01-25 | 2007-08-09 | Taisei Corp | Connection structure between pile head and precast girder and connection method thereof |
| KR101388135B1 (en) * | 2012-08-27 | 2014-04-23 | 삼성물산 주식회사 | Precast Concrete Pier Cap Structure In The Bridge And Manufacturing Method Of Pretension Precast Concrete Pier Cap |
| CN108677685A (en) * | 2018-05-31 | 2018-10-19 | 湖南大学 | A kind of ultra-high performance concrete-part girder steel combination bent cap and its construction method |
| CN108677685B (en) * | 2018-05-31 | 2024-01-16 | 湖南大学 | Ultra-high-performance concrete-part steel beam combined bent cap and construction method thereof |
| CN114164748A (en) * | 2022-01-07 | 2022-03-11 | 广西交科集团有限公司 | A new type of prefabricated cover beam and its construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0393923A (en) | Connection method of steel pillar of cast-in-place pile and connection structure | |
| JPH0325103A (en) | Joint work for pc pillar and pc cap beam | |
| JPH0790933A (en) | Construction method of structure | |
| JP2002030672A (en) | Joint structure between foundation pile and column base and its construction method | |
| JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
| JP3849234B2 (en) | Reinforced concrete underground outer wall construction method | |
| JP2616207B2 (en) | Building construction method using reinforced concrete columns and steel beams | |
| JPH079921Y2 (en) | Joint structure between reinforced concrete column and steel beam | |
| JPH1150538A (en) | Building and its construction method | |
| JPH041325A (en) | Box-like slope frame and its construction | |
| JPH07324376A (en) | Method for constructing reinforced concrete structure | |
| JPH0452815B2 (en) | ||
| JP2635872B2 (en) | How to build a composite structure | |
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JPH0123614B2 (en) | ||
| JP2713139B2 (en) | Floor method using steel assembly as beam form | |
| JPH0746652Y2 (en) | Precast Steel Reinforced Concrete Beam | |
| JPH01146035A (en) | Connection section structure of filling steel pipe concrete post | |
| JPH0688342A (en) | Constructing method of post | |
| JPH05179700A (en) | Jointing method of precast girder to precast beam | |
| JPH11343665A (en) | Hollow precast concrete column and its construction method | |
| JPH0531622B2 (en) | ||
| JPH07229203A (en) | Joint section of precast reinforced concrete | |
| JP2001059346A (en) | Pillar relocation method | |
| JPH07279245A (en) | Construction method of a frame composed of reinforced concrete columns and steel beams |