JPH03260221A - Slope-reinforcing vegetating work - Google Patents
Slope-reinforcing vegetating workInfo
- Publication number
- JPH03260221A JPH03260221A JP5710990A JP5710990A JPH03260221A JP H03260221 A JPH03260221 A JP H03260221A JP 5710990 A JP5710990 A JP 5710990A JP 5710990 A JP5710990 A JP 5710990A JP H03260221 A JPH03260221 A JP H03260221A
- Authority
- JP
- Japan
- Prior art keywords
- slope
- vegetation mat
- ground
- perforated
- vegetation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 16
- 239000000463 material Substances 0.000 claims abstract description 7
- 238000000034 method Methods 0.000 claims abstract description 7
- 230000002787 reinforcement Effects 0.000 claims description 13
- 238000010276 construction Methods 0.000 claims description 7
- 238000009412 basement excavation Methods 0.000 abstract description 5
- 239000002184 metal Substances 0.000 abstract description 2
- 229910052751 metal Inorganic materials 0.000 abstract description 2
- 150000002739 metals Chemical class 0.000 abstract 1
- 239000012779 reinforcing material Substances 0.000 description 8
- 230000000694 effects Effects 0.000 description 6
- 239000002689 soil Substances 0.000 description 5
- 238000005507 spraying Methods 0.000 description 5
- 239000003292 glue Substances 0.000 description 4
- 230000000087 stabilizing effect Effects 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000009434 installation Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003337 fertilizer Substances 0.000 description 1
- 238000009432 framing Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000005416 organic matter Substances 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明はのり面補強緑化工法に係り、特に通常斜面の安
定勾配より急勾配となる切土斜面の補強及び緑化に好適
な工法に関する6
〔従来の技術〕
のり面保護工は、原則として安定勾配で施工したのり面
を対象とし、表層変状等の小規模なのり面変状を防止す
ることを目的に実施されている。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a slope reinforcement and greening method, and particularly relates to a method suitable for reinforcing and greening a cut slope that is steeper than the stable slope of a normal slope. [Conventional technology] Slope protection works are, in principle, performed on slopes constructed with stable slopes, with the aim of preventing small-scale slope deformations such as surface deformations.
工種を大別すると、緑化工と構築物による保護工とに分
けられる。緑化工には、植物の種子と、土壌、有機質、
肥料、土壌改良材、水等とを適宜混合したものを吹付機
械を用いて吹き付ける植生工がある。また、構築物によ
る保護工には、コンクリート吹付工、コンクリートブロ
ック積工、現場打コンクリート枠工、鉄筋類挿入による
補強土工法、のり面アンカー工法等がある。上記の対象
と目的に対しては植生工で十分対応できる場合が多い。Broadly speaking, the types of work can be divided into greening work and protection work using structures. Greening involves plant seeds, soil, organic matter,
There is a method of revegetation in which a suitable mixture of fertilizer, soil improvement material, water, etc. is sprayed using a spraying machine. In addition, structural protection works include concrete spraying, concrete block masonry, cast-in-place concrete framing, reinforced earthwork by inserting reinforcing bars, and slope anchoring. In many cases, vegetation works are sufficient for the above targets and purposes.
しかし、最近は現地状況により制約、用地の有効利用等
の理由で、安定勾配よりも急な勾配で施工する場合が増
えてきている。その際用いられる構築物による保護工に
は、上記目的以外に、ある程度の土圧に対抗することが
要求される。そのため、のり表面の緑化は大きな制約を
受けることとなり、景観上好ましくないものとなってい
る。However, recently, due to constraints due to local conditions, efficient use of land, etc., construction is increasingly being carried out on steeper slopes than stable slopes. In addition to the above-mentioned purpose, the protective structures used in this case are required to withstand a certain degree of earth pressure. Therefore, the greening of the surface of the glue is subject to significant restrictions, making it undesirable from a landscape perspective.
構築物による保護工として鉄筋類挿入による補強土工法
を用いた場合、のり表面の保護工には、通常コンクリー
ト吹付工が施工されることが多い。When reinforcing earthworks by inserting reinforcing bars is used to protect structures, concrete spraying is often used to protect the surface of the structure.
その理由は、のり表面の保護工に補強材では拘束しきれ
ないのり面の土塊を安定化させる作用をも期待するため
である。The reason for this is that the protection work for the slope surface is expected to have the effect of stabilizing the soil clods on the slope surface that cannot be restrained by the reinforcing material.
しかしながら、現在実施されているコンクリート吹付け
には、以下に示すような問題点があった。However, the currently practiced concrete spraying has the following problems.
(1)吹付はコンクリートへの植生が困難なため、いつ
までもコンクリート地肌が露出していて美観を損なう。(1) Since it is difficult to plant vegetation on the concrete during spraying, the concrete surface remains exposed forever, impairing its aesthetic appearance.
(2)地山から出る水の処理が難かしく5コンクリ一ト
面が浮き上がったり、コンクリートと地山の間に空洞が
出来る6
(3)地山の変形に対して追随できず、ひび割れが生じ
る。(2) It is difficult to treat the water coming out of the ground, causing the surface of the concrete to rise, and cavities to form between the concrete and the ground.6 (3) It is not possible to follow the deformation of the ground, resulting in cracks. .
本発明の目的は上記問題点を解消するためになされたも
ので、切土のり面を安定化させる保護工に、積極的に緑
化工の採用を可能ならしめるのり面補強緑化工法を提供
することである。The purpose of the present invention was to solve the above-mentioned problems, and to provide a slope reinforcement greening method that makes it possible to proactively adopt greening work as a protection work for stabilizing cut slopes. It is.
上記の目的は、地山を掘削して形成されたのり面あるい
は既設ののり面に植生マットを敷設し。The above purpose is to lay a vegetation mat on a slope created by excavating the ground or on an existing slope.
その後該植生マットの上から該のり面を網状体で被覆し
、次いでこれらの上から該のり面に有孔補強管を水平も
しくはやや上向きに打設し、該有孔補強管と該植生マッ
ト及び該網状体とを一体的に連結して該のり面に固定す
るのり面補強緑化工法によって達成することができる。Thereafter, the slope surface is covered with a net-like material from above the vegetation mat, and then a perforated reinforcement pipe is driven horizontally or slightly upwardly onto the slope surface from above, and the perforated reinforcement pipe and the vegetation mat and This can be achieved by a slope surface reinforcement greening method in which the net-like body is integrally connected and fixed to the slope surface.
また、有孔補強管を植生マットより先に施工することも
できるし、場合によっては網状体を省略することもでき
る。更に、植生マットに代えて最後に植生工を施工して
もよい。Further, the perforated reinforcing pipe can be installed before the vegetation mat, and depending on the case, the mesh can be omitted. Furthermore, instead of the vegetation mat, a vegetation work may be constructed at the end.
上記構成によれば、網状体は補強材では拘束しきれない
のり面の土塊を安定させる作用があり、ある程度の地山
の変形に追随することが可能で、局部的に発生した力を
周辺に分散させることができるため1局所的な破壊を防
ぐのに効果的である。According to the above configuration, the net-like body has the effect of stabilizing the soil mass on the slope that cannot be restrained by the reinforcing material, and is able to follow the deformation of the ground to a certain extent, and can transfer locally generated forces to the surrounding area. Since it can be dispersed, it is effective in preventing localized destruction.
植生マットは、植生効果とともに地山と網状体とのクツ
ション材にもなり、両者の間隙を埋める役割も果す。施
工後は、植物の生育とともに両者はより緊密な状態にな
り、のり表面はより安定化していく。In addition to providing a vegetation effect, the vegetation mat also serves as a cushioning material between the ground mass and the net-like body, and also plays the role of filling the gap between the two. After installation, as the plants grow, the two will become closer together and the glue surface will become more stable.
有孔管を用いた補強材は、地山深部の地下水あるいは浸
透水をのり表面に補給して、水分の不足しがちな急勾配
斜面での植生を助ける。また、地山から水を抜くことは
斜面の安定に大きく寄与し、補強効果を高めることにも
つながる。Reinforcement materials using perforated pipes replenish the surface of the slope with groundwater or seepage water from deep within the ground, helping to support vegetation on steep slopes that tend to lack moisture. In addition, draining water from the ground greatly contributes to the stability of the slope and increases the reinforcement effect.
そのため、切土斜面を、美観に優れ、安定化したものに
することができる。Therefore, the cut slope can be made aesthetically pleasing and stable.
以下、本発明のいくつかの実施例を図面を参考に説明す
る。Hereinafter, some embodiments of the present invention will be described with reference to the drawings.
地山の状態と斜面勾配により、2通りの施工方法が考え
られる。一つは、比較的不安定な地盤状態における施工
で、掘削に従かい逐次のり面保護工を実施するものであ
る。もう−っは、やや安定な地盤状態における施工で、
有孔補強管の打設を伴う全掘削終了後にまとめて表面保
護工を実施するものである。There are two possible construction methods depending on the condition of the ground and slope slope. One is construction work in relatively unstable ground conditions, in which slope protection work is carried out sequentially as excavation is carried out. The other is construction in a somewhat stable ground condition.
Surface protection work will be carried out at once after all excavation, including the installation of perforated reinforcing pipes, is completed.
前者の例を第1の実施例として説明する。第1図及び第
2図に示すように、地山2にまず1.0〜2.Omの高
さの掘削を行ない。のり表面4に植生マツトロとジオグ
リッド8Aを敷設する。その上から補強材として有孔補
強管10を水平方向に1.0〜2.0mピッチで打設し
、連結プレート12および止め金具14を用いて表面保
護工と連結する。その後、更に掘削を進め、前段階に敷
設したジオグリッド8Aと、後に敷設したジオグリッド
8Bとを接続部16でゆるみがないように接続する。こ
のようにすることによって、第2図に示した補強材では
拘束しきれない土塊20も安定化する。上記一連の作業
を繰り返し施工して安定した切土斜面を形成する。The former example will be described as a first embodiment. As shown in FIGS. 1 and 2, the ground mass 2 is first filled with 1.0 to 2. Excavation was carried out to a height of Om. Lay the vegetation Matsutoro and geogrid 8A on the glue surface 4. Perforated reinforcing pipes 10 are cast thereon as reinforcing materials at a pitch of 1.0 to 2.0 m in the horizontal direction, and connected to the surface protection work using connecting plates 12 and fasteners 14. After that, the excavation is further progressed, and the geogrid 8A laid in the previous stage and the geogrid 8B laid later are connected at the connection part 16 so that there is no loosening. By doing this, the earth clod 20 that cannot be restrained by the reinforcing material shown in FIG. 2 is also stabilized. Repeat the above series of operations to form a stable cut slope.
本実施例によれば、比較的不安定な、また、高さの高い
切土斜面を順次切下げて施工するのに好適である。According to this embodiment, it is suitable for constructing a relatively unstable or high cut slope by successively cutting down the slope.
次に、後者の例を第2の実施例として上記図面を参考に
して説明する。第1の実施例と同じ要領で掘削と補強材
10の打設を全斜面に実施した後に、植生マツトロおよ
びジオグリッド8を全面に敷設し、補強材頭と植生マッ
ト及びジオグリッドとを連結するものである。本実施例
によれば、やや安定した切土斜面を一度で施工すること
ができる。Next, the latter example will be described as a second embodiment with reference to the above drawings. After excavating and placing the reinforcing material 10 on the entire slope in the same manner as in the first embodiment, the vegetation mats and geogrid 8 are laid on the entire surface, and the reinforcing material head is connected to the vegetation mat and the geogrid. It is something. According to this embodiment, a somewhat stable cutting slope can be constructed in one go.
他の実施例として、補強材打設とジオグリッド敷設を行
った後、植生マットの代わりに吹付による植生工を施工
してもよい。As another example, after the reinforcing material is placed and the geogrid is laid, sprayed vegetation may be applied instead of the vegetation mat.
これらの実施例において、第3図に示すように、補強材
10 (Q=3.0〜5.0m、φ=40−100mm
)は水抜きパイプとしての機能を果すために、5度〜1
0度上向きに打設する。また。In these examples, as shown in FIG.
) is 5 degrees to 1 degree in order to function as a drain pipe.
Pour at 0 degrees upward. Also.
ジオグリッド8と補強材10との連結部は、できるだけ
応力の集中を避けるために、連結プレート12に突起1
8を設けると効果的である。The connecting portion between the geogrid 8 and the reinforcing material 10 is provided with projections 1 on the connecting plate 12 in order to avoid concentration of stress as much as possible.
It is effective to provide 8.
また、斜面が比較的緩勾配の場合には、ジオグリッドを
使用しなくても植生マットの網状部の強度のみで、有孔
補強管では拘束しきれないのり面の土塊を安定させうる
場合もある。In addition, if the slope is relatively gentle, the strength of the network of the vegetation mat alone may be sufficient to stabilize the soil mass on the slope that cannot be restrained by perforated reinforcing pipes, even without using a geogrid. be.
上述のとおり本発明によれば、切土斜面を安定化させる
保護工に、積極的に緑化工を採用することができ、美観
に優れ、安定した切土のり面を施工することができる。As described above, according to the present invention, greening work can be actively employed as a protection work for stabilizing a cut slope, and a stable cut slope with excellent aesthetic appearance can be constructed.
第1図ないし第3図は本発明の一実施例を説明するもの
で、第1図は正面図、第2図は断面図、第3図は詳細図
である。
2・・・地山、4・・・のり表面、
8.8A、8B・・・ジオグリッド、
10・・・有孔補強管、12・・連結プレート、14・
・・止め金具、16・・・接続部、18・・・突起。
第
図
2尾函1 to 3 illustrate one embodiment of the present invention, in which FIG. 1 is a front view, FIG. 2 is a sectional view, and FIG. 3 is a detailed view. 2... Earth, 4... Glue surface, 8.8A, 8B... Geogrid, 10... Perforated reinforcement pipe, 12... Connecting plate, 14...
...Fixing metal fitting, 16...Connection part, 18...Protrusion. Figure 2 Tail box
Claims (1)
り面に植生マットを敷設し、その後該植生マットの上か
ら該のり面を網状体で被覆し、次いでこれらの上から該
のり面に有孔補強管を水平もしくはやや上向きに打設し
、該有孔補強管と該植生マット及び該網状体とを一体的
に連結して該のり面に固定する、のり面補強緑化工法。 2、地山を掘削して形成されたのり面に、有孔補強管を
水平もしくはやや上向きに打設し、その後該のり面に植
生マットを敷設し、次いで該植生マットの上から該のり
面を網状体で被覆し、該有孔補強管と該植生マット及び
該網状体とを一体的に連結して該のり面に固定する、の
り面補強緑化工法。 3、地山を掘削して形成されたのり面に、有孔補強管を
水平もしくはやや上向きに打設する施工と、該のり面を
網状体で被覆する施工とを行い、該有孔補強管と該網状
体とを連結して該のり面に固定した後、該のり面に植生
工を施工する、のり面補強緑化工法。 4、地山を掘削して形成されたのり面に植生マットを敷
設し、該植生マットの上から該のり面に有孔補強管を水
平もしくはやや上向きに打設し、該有孔補強管と該植生
マットとを一体的に連結して該のり面に固定する、のり
面補強緑化工法。[Claims] 1. A vegetation mat is laid on a slope formed by excavating the ground or an existing slope, and then the slope is covered with a net-like material from above the vegetation mat, and then these A perforated reinforcing pipe is driven horizontally or slightly upwardly onto the slope from above, and the perforated reinforcing pipe, the vegetation mat, and the net-like body are integrally connected and fixed to the slope. Surface reinforcement greening method. 2. A perforated reinforcing pipe is installed horizontally or slightly upwardly on the slope formed by excavating the ground, then a vegetation mat is laid on the slope, and then the slope is placed over the vegetation mat. A slope surface reinforcing greening construction method in which the perforated reinforcing pipe, the vegetation mat, and the net structure are integrally connected and fixed to the slope surface. 3. The perforated reinforcement pipe is installed horizontally or slightly upwardly on the slope formed by excavating the ground, and the slope is covered with a net-like material. A slope surface reinforcement greening construction method, which comprises connecting and fixing the net-like body to the slope surface, and then constructing vegetation on the slope surface. 4. Lay a vegetation mat on the slope formed by excavating the ground, and drive a perforated reinforcement pipe horizontally or slightly upwards from above the vegetation mat onto the slope. A slope surface reinforcement greening construction method in which the vegetation mat is integrally connected and fixed to the slope surface.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2057109A JP2619297B2 (en) | 1990-03-08 | 1990-03-08 | Slope reinforcement greening method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2057109A JP2619297B2 (en) | 1990-03-08 | 1990-03-08 | Slope reinforcement greening method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH03260221A true JPH03260221A (en) | 1991-11-20 |
| JP2619297B2 JP2619297B2 (en) | 1997-06-11 |
Family
ID=13046353
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2057109A Expired - Lifetime JP2619297B2 (en) | 1990-03-08 | 1990-03-08 | Slope reinforcement greening method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2619297B2 (en) |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5744026A (en) * | 1980-08-28 | 1982-03-12 | Tadashi Miyamoto | Tree-planting method for slope |
| JPS645942U (en) * | 1987-07-01 | 1989-01-13 |
-
1990
- 1990-03-08 JP JP2057109A patent/JP2619297B2/en not_active Expired - Lifetime
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5744026A (en) * | 1980-08-28 | 1982-03-12 | Tadashi Miyamoto | Tree-planting method for slope |
| JPS645942U (en) * | 1987-07-01 | 1989-01-13 |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2619297B2 (en) | 1997-06-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3053071B2 (en) | Natural ecological self-restoration type slope construction method and slope structure | |
| JP3083250B2 (en) | Slope reinforcement and greening | |
| JP3472708B2 (en) | Slope and seawall retaining wall structures and their construction methods | |
| KR100603141B1 (en) | reinforced earth wall for planting and construction/reconstruction method of it | |
| JPH03260221A (en) | Slope-reinforcing vegetating work | |
| KR19990046526A (en) | A structure for establing a slope and execution method using it | |
| JP2000248553A (en) | Landscaping landscape revegetation method | |
| JP3244324B2 (en) | Mountain retaining method | |
| KR100992076B1 (en) | Structure of raising the ground level and excecution method thereof | |
| JPS63284321A (en) | Sheathing for inclined surface of filling | |
| JP2001323472A (en) | Greening method of special precast method | |
| JP4698437B2 (en) | Masonry retaining wall using retaining wall unit and its construction method | |
| JP2001182064A (en) | Protective planting structure of slope face, wall surface and bank surface | |
| JPH09209371A (en) | Method for constructing foundation | |
| KR102892092B1 (en) | the slope reinforcement unit and the vegetation reinforced construction method using the same | |
| JP2500358B2 (en) | Seawall block and seawall structure | |
| KR102892093B1 (en) | the slope reinforcement frame unit and the vegetation reinforced construction method using the same | |
| JP2001348881A (en) | Slope frame structure, slope frame construction method and frame inside greening method | |
| JP3117066B2 (en) | Slope reinforcement and greening method and its fabric sheet | |
| JP3099040B2 (en) | Embankment culvert | |
| JPH0978590A (en) | Frame material, and protection work, vegetation work, widening work vertical earth retaining wall for slope face with frame material | |
| JPH0359222A (en) | Steep slope banking | |
| JP2002070024A (en) | Earth retaining frame and earth retaining method of slope or the like | |
| KR200159771Y1 (en) | Lattic type wire mesh frame for protection net applying surface of earth cut | |
| JPH09144007A (en) | Earth retaining structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090311 Year of fee payment: 12 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100311 Year of fee payment: 13 |
|
| EXPY | Cancellation because of completion of term |