JPH0326741B2 - - Google Patents

Info

Publication number
JPH0326741B2
JPH0326741B2 JP15387184A JP15387184A JPH0326741B2 JP H0326741 B2 JPH0326741 B2 JP H0326741B2 JP 15387184 A JP15387184 A JP 15387184A JP 15387184 A JP15387184 A JP 15387184A JP H0326741 B2 JPH0326741 B2 JP H0326741B2
Authority
JP
Japan
Prior art keywords
concrete
water
underwater
foundation
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP15387184A
Other languages
Japanese (ja)
Other versions
JPS6131530A (en
Inventor
Eisaku Kobayashi
Masatoshi Furuoku
Tetsuo Suwa
Takeshi Nishimura
Juzo Kimura
Tadanori Ootomo
Masakazu Koga
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP15387184A priority Critical patent/JPS6131530A/en
Publication of JPS6131530A publication Critical patent/JPS6131530A/en
Publication of JPH0326741B2 publication Critical patent/JPH0326741B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 本発明は、本体構造物の基礎を作る場合に、そ
の基礎の位置が地下水位より低い位置であつたり
河川や海中であつたりするさいに、止水用の仮設
コンクリートを打設することなく、直接的にこれ
を構築する水中基礎工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention provides a method for using temporary concrete to stop water when building a foundation for a main structure, when the foundation is located at a location lower than the groundwater level, or located in a river or the sea. This article relates to an underwater foundation construction method that directly constructs a foundation without pouring it.

従来、地下水位が高くて透水係数が大きく、水
換えが困難な箇所での地盤中に本体構造物の基礎
を作る場合には、例えば、第1〜2図に示すよう
に止水用の仮設コンクリート1を打設してドライ
アツプしていた(同図において、2は地下水位、
3は土留鋼矢板を示している)。すなわち、まず
第1図のように、土留鋼矢板3で囲われた掘削空
間を作り、この掘削空間内の湧水4の存在下で仮
設コンクリート1を底部に打設する。通常、この
仮設コンクリート1は、止水を目的とするもので
あるから、配筋は特に必要としない。次いでこの
コンクリート1が硬化して止水機能を持つように
なつてから水4をドライアツプし、第2図に示す
ように、配筋した基礎構造物5および6をドライ
アツプ下で構築する。
Conventionally, when building the foundation of the main structure in the ground in places where the groundwater level is high and the hydraulic conductivity is large, making it difficult to change the water, temporary construction to stop water was used, for example, as shown in Figures 1 and 2. Concrete 1 was placed and dry-up (in the figure, 2 is the groundwater level,
3 shows the earth retaining steel sheet pile). That is, first, as shown in FIG. 1, an excavation space surrounded by earth retaining steel sheet piles 3 is created, and temporary concrete 1 is placed at the bottom in the presence of spring water 4 within this excavation space. Normally, the purpose of this temporary concrete 1 is to stop water, so reinforcement is not particularly required. Next, after this concrete 1 has hardened and has a water-stopping function, water 4 is dry-upped, and as shown in FIG. 2, substructures 5 and 6 with reinforced reinforcement are constructed under dry-up.

しかし、このような従来の仮設コンクリート1
を設けて止水する工法では、このコンクリートの
下にかかる揚水圧に対抗するために多量のコンク
リートを必要とし、また、そのために掘削深さが
深くなる。従つて、掘削量が多くなると共に大面
積の土留鋼矢板3を必要とするほか、この仮設コ
ンクリート打設のためにそのぶん工期が長くなり
工費も増大する結果となつていた。
However, such conventional temporary concrete 1
The construction method of installing a water stop requires a large amount of concrete to counteract the pumping pressure that is applied under the concrete, and the excavation depth is therefore deep. Therefore, not only does the amount of excavation increase, but also a large area of earth-retaining steel sheet piles 3 is required, the construction period and construction cost also increase due to the temporary concrete pouring.

本発明は、このような従来の水中基礎工法の問
題の解決を目的としたもので、コンクリート打設
位置が水面下である箇所での基礎構築にさいし、
水面上において基礎構築用の鉄筋を組み立て、こ
の組み立てた鉄筋構造物を水中に吊り降ろしてコ
ンクリート打設位置にセツトし、次いで、水中で
の材料分離を抑制する粘稠剤を配合した未だ固ま
らないコンクリートを該水中の打設位置に水中打
設することを特徴とする水中基礎工法を提供する
ものである。
The purpose of the present invention is to solve the problems of the conventional underwater foundation construction method.
Reinforcing bars for foundation construction are assembled above the water surface, and the assembled rebar structure is lowered into the water and set at the concrete placement position.Then, a thickening agent is added to suppress material separation underwater, so that it does not harden yet. The present invention provides an underwater foundation construction method characterized by pouring concrete into the underwater pouring position.

以下に、図面に従つて本発明工法を具体的に説
明する。
The construction method of the present invention will be specifically explained below with reference to the drawings.

第3図〜第10図は、これから構築しようとす
る本体構築物の基礎を地下水位が高い地盤中に築
く場合を例として、本発明工法の工程を順を追つ
て示したものである。
Figures 3 to 10 show the steps of the construction method of the present invention in order, taking as an example the case where the foundation of the main structure to be constructed is to be built in the ground with a high groundwater level.

(1) 支持杭および仮設杭打設工程…第3図。(1) Support pile and temporary pile driving process...Figure 3.

ドライアツプ時の躯体に働く浮力に対して躯
体の重量が不足する場合、地盤の支持力が将来
の躯体の重量に対して不足する場合、または将
来沈下が生じて支障がでる恐れがある場合、等
においては、支持杭10を打設する。また、工
事に必要であれば仮設杭を打設する。仮設杭は
支持杭で代用できる。2は地下水位を示す。
If the weight of the building structure is insufficient to compensate for the buoyancy that acts on the building structure during dry-up, if the supporting capacity of the ground is insufficient for the future weight of the building structure, or if there is a risk of future subsidence causing problems, etc. In this step, the support pile 10 is driven. In addition, temporary piles will be driven if necessary for the construction work. Temporary piles can be replaced with support piles. 2 indicates the groundwater level.

(2) 掘削工程…第4図。(2) Excavation process...Figure 4.

躯体を構築するのに必要な量だけ掘削する。
すなわち、従来のように止水用仮設コンクリー
トの分の掘削は行わず、躯体構築分だけ掘削す
る。この場合、排水を行つても水位を低下でき
ない場合は、水4が存在したままで掘削する。
11は掘削機械を示す。
Excavate only the amount necessary to construct the frame.
In other words, unlike in the past, excavation is not carried out for the temporary concrete for waterproofing, but only for the construction of the frame. In this case, if the water level cannot be lowered even after drainage, excavation is carried out with water 4 still present.
11 indicates an excavating machine.

(3) 鋼矢板打設、掘削面均し、および鉄筋組み立
ての工程…第5図。
(3) Process of driving steel sheet piles, leveling the excavated surface, and assembling reinforcing bars...Figure 5.

(ア) 鋼矢板打設工程 鋼矢板12は、地表面から打設可能であれ
ば、前記の掘削工程の前に地表より打設して
もよい。この場合には土留壁として機能す
る。地中に転石その他の障害物があつて地表
より打設できない場合には第5図のように障
害物を掘削してから鋼矢板12を打ち込む。
(A) Steel sheet pile driving process If the steel sheet pile 12 can be driven from the ground surface, it may be driven from the ground surface before the above-mentioned excavation process. In this case, it functions as a retaining wall. If the steel sheet pile 12 cannot be driven from the ground surface because of boulders or other obstacles underground, the obstruction is excavated as shown in FIG. 5 before the steel sheet pile 12 is driven.

この鋼矢板12は、ドライアツプ時の止水
壁となり、またコンクリートの型枠となる。
従つて、相互に隙間が生じないような面体に
構成する。しかし、この鋼矢板12はコンク
リートの側圧とドライアツプ時の水圧を受け
るのに十分な強度を有するだけでよく、ま
た、ボイリングやヒービングの恐れが少ない
ので、通常の締切りに比較して小さな根入れ
長さでよい。
This steel sheet pile 12 serves as a water-stop wall during dry-up and also serves as a formwork for concrete.
Therefore, the face pieces are constructed so that no gaps are formed between them. However, this steel sheet pile 12 only needs to have sufficient strength to receive the lateral pressure of concrete and the water pressure during dry-up, and there is little risk of boiling or heaving, so the penetration length is smaller than that of a normal cofferdam. It's good.

(ロ) 掘削面均し工程 栗石または砕石13を掘削底面に投入し、
その表面を均らす。
(b) Excavation surface leveling process: Put chestnut stone or crushed stone 13 on the bottom of the excavation,
Level the surface.

(ハ) 鉄筋組み立て工程 構築しようとする躯体の実質的に直上であ
つて且つ水面上の空中において吊り材のもと
で鉄筋を組み立てる。より具体的には、PC
鋼棒のような吊り材14によつて仮説梁15
を介して鉄骨16を水面上に吊りわたし、こ
の鉄骨16を作業台として鉄筋17を組み立
てる。鉄骨16は、スパンが大きい場合には
トラス構造とする。この鉄骨16は鉄筋組み
立て用の空中作業台として使用されるが、後
には、鉄筋17と共にコンクリート中に埋め
込まれる。従つて、その形状によつては水を
コンクリート中に取り込む場合も有り得るの
で、特に臨海地帯での地下水や海水での施工
を対象とする場合には、鉄筋や鉄骨の腐食の
原因となるコンクリート中への取込み水を少
なくするために、この鉄骨には強度上許され
る範囲で、できるだけ穴をあけておくのがよ
い。
(c) Reinforcing bar assembly process Reinforcing bars are assembled under hanging materials substantially directly above the frame to be constructed and in the air above the water surface. More specifically, the PC
A hypothetical beam 15 is formed by a hanging member 14 such as a steel rod.
A steel frame 16 is suspended above the water surface via the steel frame 16, and reinforcing bars 17 are assembled using the steel frame 16 as a workbench. The steel frame 16 has a truss structure when the span is large. This steel frame 16 is used as an aerial platform for assembling reinforcing bars, but will later be embedded in concrete together with reinforcing bars 17. Therefore, depending on the shape of the concrete, water may be introduced into the concrete, which can cause corrosion of reinforcing bars and steel frames, especially when construction is being carried out using groundwater or seawater in coastal areas. In order to reduce the amount of water taken into the steel frame, it is a good idea to make as many holes as possible in this steel frame as long as its strength allows.

このようにして、水面上において基礎構築
用の鉄筋構造物を組み立てるから、水中で組
み立てる場合に比べて能率が良く且つ精度も
良くすることができる。この場合、支持杭1
0もこの組み立て作業を安定して行うための
横揺れ防止材あるいは仮設梁15の受け材と
して利用することができる。吊り材14には
センターホールジヤツキ18を介装させてお
き、これによつて作業位置の調整と組み立て
た鉄筋構造物の下降操作を自由にできるよう
にしておく。
In this way, since the reinforcing steel structure for foundation construction is assembled on the water surface, efficiency and precision can be improved compared to when assembling it underwater. In this case, support pile 1
0 can also be used as a rolling prevention material or a receiving material for the temporary beam 15 in order to perform this assembly work stably. A center hole jack 18 is interposed on the hanging member 14 so that the working position can be adjusted and the assembled reinforcing steel structure can be lowered freely.

(4) 鉄筋構造物の据付工程…第6図。(4) Installation process of reinforced structures...Figure 6.

水面上で組み立てた鉄筋構造物(鉄筋組み立
て用作業台として使用した鉄骨16に鉄筋17
を結束してなる一体的な構造物)を水中に吊り
降ろしてコンクリート打設位置にセツトする。
これは先述の吊り材14に介装させたセンター
ホールジヤツキ18の操作によつて行う。な
お、立ち上がり壁等にも配筋する場合に、同様
にして、水中にこの部分の鉄筋をセツトしても
よい。
Reinforced structure assembled on the water surface (reinforced steel 17 on steel frame 16 used as a workbench for assembling rebar)
(an integral structure made up of bundles of concrete) is lowered into the water and set at the concrete pouring position.
This is done by operating the center hole jack 18 interposed on the hanging material 14 mentioned above. Note that when reinforcing a standing wall or the like, the reinforcing bars for this part may be set underwater in the same way.

(5) 杭頭切断、水中コンクリート打設の工程…第
7図。
(5) Process of cutting pile heads and placing concrete underwater...Figure 7.

第7図に示すように、杭10の不要部分(躯
体を支持するのに不要な上方の部分)を除去す
る。これは、杭10の地盤からの突出部分を切
り取る作業であり水中で機械切断する。次い
で、ポンプ車20によつてコンクリート打設す
るが、その前に、汚泥などがコンクリート打設
位置に沈降している場合にはこれをサンドポン
プによつて吸い上げる。打設するコンクリート
は、水中での材料分離を抑制する粘稠剤を配合
し、また流動性を高めるように調整したいわゆ
る水中コンクリート(例えばハイドロクリー
ト)を使用する。この水中コンクリートを使用
する場合には、トレミー管などの吐出口を打設
コンクリート中に浸漬して打ち上げるような処
方によらずとも、図示のようにホース21を使
用し、大気中での打設法と変わらない処方(打
設位置にその上方から流し込む方法)で簡便に
打ち込むことができる。この場合、鋼矢板12
は側部の型枠となる。現場が臨海地帯であり、
水位が潮汐などの影響を受けて変動する場合に
は、鋼矢板12の一部に貫通穴を設けておき、
鋼矢板12の内側空間と外側空間との間の水位
差がないようにしておくのがよい。これは、水
中コンクリートが未だ固まらないときに、過剰
な水圧がかかつて水みちを作り将来漏水するの
を未然に防止するためである。
As shown in FIG. 7, the unnecessary part of the pile 10 (the upper part unnecessary for supporting the frame) is removed. This is a work to cut out the protruding portion of the pile 10 from the ground, and is mechanically cut underwater. Next, concrete is placed by the pump truck 20, but before that, if sludge or the like has settled at the concrete placement position, it is sucked up by a sand pump. The concrete to be poured is so-called underwater concrete (for example, hydrocrete), which is mixed with a thickening agent to suppress material separation in water and is adjusted to increase fluidity. When using this underwater concrete, it is not necessary to immerse the discharge port of a tremie pipe into the concrete and cast it in the concrete. It can be easily cast using the same recipe (pouring into the casting position from above). In this case, steel sheet pile 12
will be the side formwork. The site is a coastal area,
If the water level fluctuates due to the influence of tides, etc., a through hole is provided in a part of the steel sheet pile 12,
It is preferable that there be no difference in water level between the inner space and the outer space of the steel sheet pile 12. This is to prevent future water leakage from occurring when the underwater concrete has not yet hardened and excessive water pressure creates a water path.

(6) ドライアツプ工程…第8図。(6) Dry-up process...Figure 8.

前工程で打設した水中コンクリート22は、
水中において十分に養生し、その強度が所要の
強度に達したら、鋼矢板12で締め切られた内
部空間の水を排出する。もちろん鋼矢板12に
穴をあけておいた場合にはこれを閉鎖する。こ
れによつて、コンクリート層22と鋼矢板12
で仕切られたドライ空間が形成される。
The underwater concrete 22 placed in the previous process is
After sufficient curing in water and its strength reaching the required strength, the water in the internal space closed off by the steel sheet piles 12 is discharged. Of course, if a hole has been made in the steel sheet pile 12, this is closed. As a result, the concrete layer 22 and the steel sheet pile 12
A dry space partitioned by

(7) 普通コンクリートの打設工程…第9図。(7) Ordinary concrete pouring process...Figure 9.

前工程で形成されたドライ空間内で、壁23
等の必要な躯体構造を普通コンクリート打設で
形成する。
In the dry space formed in the previous process, the wall 23
The necessary frame structure is formed by pouring ordinary concrete.

(8) 矢板引抜きおよび埋戻し工程…第10図。(8) Sheet pile pulling and backfilling process...Figure 10.

鋼矢板12を引抜き、壁23の背後を埋戻し
て基礎構造物の工事が完了する。
The steel sheet pile 12 is pulled out and the area behind the wall 23 is backfilled to complete the construction of the foundation structure.

このようにして、本発明によると、地下水位が
高く透水性が高い地盤であつても止水用の仮設コ
ンクリート層を設けることなく大型の基礎を構築
することができ、掘削量とコンクリート量の低減
を図りながら短い工期と低い工費のもとで強固な
基礎を構築できる。また河川や海水中においても
同様にして基礎構造物を構築することができる。
In this way, according to the present invention, it is possible to construct a large foundation without providing a temporary concrete layer to stop water even in ground with a high groundwater level and high permeability, and the amount of excavation and amount of concrete can be reduced. It is possible to build a strong foundation with a short construction period and low construction costs while reducing construction costs. Furthermore, foundation structures can be constructed in the same manner in rivers and seawater.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第2図は従来の地下水位下での基礎工
法を説明するための略断面図であり、第1図は止
水用仮設コンクリート層を形成する段階を示す
図、第2図は止水用仮設コンクリートの上に躯体
を形成する段階を示す図である。また、第3図〜
第10図は、いずれも本発明の水中基礎工法の一
連の工程を説明するための略断面図であり、第3
図は杭打ちの工程、第4図は掘削の工程、第5図
は鉄筋組み立ての工程、第6図は鉄筋降下据付の
工程、第7図は水中コンクリートの打設工程、第
8図はドライアツプの工程、第9図は普通コンク
リートの打設工程、第10図は埋戻しの工程をそ
れぞれ示す図である。 1……止水用仮設コンクリート、2……地下水
位、10……支持杭、11……掘削機械、12…
…鋼矢板、13……栗石、14……吊り材、15
……仮設梁、16……作業台となる鉄骨、17…
…鉄筋、18……センターホールジヤツキ、20
……ポンプ車、21……ホース、22……水中コ
ンクリート、23……普通コンクリート。
Figures 1 and 2 are schematic cross-sectional views for explaining the conventional foundation construction method below the groundwater level. Figure 1 is a diagram showing the stage of forming a temporary concrete layer for waterproofing, and Figure 2 is It is a figure which shows the stage of forming a frame on temporary concrete for waterproofing. Also, Figure 3~
FIG. 10 is a schematic sectional view for explaining a series of steps of the underwater foundation construction method of the present invention.
The figure shows the pile driving process, Figure 4 shows the excavation process, Figure 5 shows the reinforcing bar assembly process, Figure 6 shows the reinforcing bar lowering installation process, Figure 7 shows the underwater concrete placement process, and Figure 8 shows the dry-up process. Fig. 9 shows the ordinary concrete casting process, and Fig. 10 shows the backfilling process. 1... Temporary water stop concrete, 2... Groundwater level, 10... Support pile, 11... Excavation machine, 12...
...Steel sheet pile, 13...Chestnut stone, 14...Hanging material, 15
...Temporary beam, 16...Steel frame that will serve as a workbench, 17...
...Reinforcing bar, 18...Center hole jack, 20
...Pump truck, 21...Hose, 22...Underwater concrete, 23...Ordinary concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 コンクリート打設位置が水面下である箇所で
の基礎構築にさいし、水面上において基礎構築用
の鉄筋を組み立て、この組み立てた鉄筋構造物を
水中に吊り降ろしてコンクリート打設位置にセツ
トし、次いで、水中での材料分離を抑制する粘稠
剤を配合した未だ固まらないコンクリートを該水
中の打設位置に水中打設することを特徴とする水
中基礎工法。
1. When constructing a foundation in a place where the concrete placement position is below the water surface, the reinforcing bars for the foundation construction are assembled above the water surface, the assembled reinforcing steel structure is lowered into the water and set at the concrete placement position, and then An underwater foundation construction method characterized by pouring unhardened concrete containing a thickening agent that suppresses material separation underwater at the underwater placement position.
JP15387184A 1984-07-24 1984-07-24 Method of constructing underwater foundation Granted JPS6131530A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15387184A JPS6131530A (en) 1984-07-24 1984-07-24 Method of constructing underwater foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15387184A JPS6131530A (en) 1984-07-24 1984-07-24 Method of constructing underwater foundation

Publications (2)

Publication Number Publication Date
JPS6131530A JPS6131530A (en) 1986-02-14
JPH0326741B2 true JPH0326741B2 (en) 1991-04-11

Family

ID=15571928

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15387184A Granted JPS6131530A (en) 1984-07-24 1984-07-24 Method of constructing underwater foundation

Country Status (1)

Country Link
JP (1) JPS6131530A (en)

Also Published As

Publication number Publication date
JPS6131530A (en) 1986-02-14

Similar Documents

Publication Publication Date Title
KR100722665B1 (en) Steel guide wall for underground continuous wall construction and underground continuous wall construction method
EP0810327B1 (en) Method and device for laying underground continuous walls
EP0136355A1 (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP3967473B2 (en) Construction method of underground structure
JP2726611B2 (en) How to set up an open caisson
JP4011209B2 (en) Construction method of shaft
JPH07197473A (en) Open caisson structure
JPH07268878A (en) Method for immersing caisson and structure of cutting face of caisson
JPH0326741B2 (en)
KR200224758Y1 (en) Structure of caisson soil protection four concret caisson
JP2874906B2 (en) Shaft construction method
JP3614587B2 (en) How to install a shaft in the groundwater under pressure
JP2784314B2 (en) How to set up an open caisson
JPH116164A (en) Underground structure construction method
JP2581602B2 (en) Waste treatment method
JP2003074076A (en) Construction method of building with underground part
JPH09177068A (en) Method for excavating trench for underground structure and construction method for underground structure
JP2001323485A (en) Method of constructing underground structure
JP2933546B2 (en) Basement construction method and lower frame material used in the construction method
JPH01121414A (en) Excavation work of ground
CN119640812A (en) Building construction foundation pit supporting structure and supporting method thereof
CN118997128A (en) District sinking type elevator shaft reconstructed under sand geology and construction method thereof
JP2022108444A (en) Reinforcement method for existing bank
KR20220140660A (en) Installing method of steel shear material inside of steel pile underwater
JPH11152988A (en) Construction method for underground structures