JPH03279596A - Excavation method of large section or superlarge section of tunnel - Google Patents

Excavation method of large section or superlarge section of tunnel

Info

Publication number
JPH03279596A
JPH03279596A JP7685090A JP7685090A JPH03279596A JP H03279596 A JPH03279596 A JP H03279596A JP 7685090 A JP7685090 A JP 7685090A JP 7685090 A JP7685090 A JP 7685090A JP H03279596 A JPH03279596 A JP H03279596A
Authority
JP
Japan
Prior art keywords
area
bolts
section
excavated
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7685090A
Other languages
Japanese (ja)
Other versions
JP2932197B2 (en
Inventor
Shin Terauchi
伸 寺内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP7685090A priority Critical patent/JP2932197B2/en
Publication of JPH03279596A publication Critical patent/JPH03279596A/en
Application granted granted Critical
Publication of JP2932197B2 publication Critical patent/JP2932197B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To improve the efficiency of construction by providing plural headings inside or at the periphery of a scheduled excavation area, driving in soil-sewing bolts for main pit from each heading to the outside ot the area, and bolts for stabilizing facings into the area respectively, and excavating the inside of the area. CONSTITUTION:A top heading 2 is excavated on the top of a scheduled excavating area 1, a sticking concrete and a timbering are applied, and plural soil- sewing bolts 3 for main pit are driven in to the outside of the area 1, while plural bolts 7 for stabilizing facings are driven in to the area 1 respectively. Then, side wall headings 5 extending along the inside and the outside of the area 1 are excavated at both lower sides of the area 1, a spraying concreating and a timbering are applied, and plural soil-sewing bolts 6 for main pit and plural bolts 7 for stablizing facings are driven in, outside the area 1 and inside the area 1 respectively. And side wall concretes 8 are placed to secure the bottom wall of timbering. Then, the area 1 is excavated while removing the bolts 4 and 7, and a part of bolts 3 in the area 1. Consequently, the cost of construction can be reduced.

Description

【発明の詳細な説明】[Detailed description of the invention] 【産業上の利用分野】[Industrial application field]

本発明は、導坑を利用して大断面ないし超大断面トンネ
ルを掘削する工法に関するものである。
The present invention relates to a construction method for excavating a tunnel with a large cross section or an extremely large cross section using a shaft.

【従来の技術】[Conventional technology]

いま、掘削断面積が70〜80イのトンネルを標準トン
フル、100〜120Mのトンネルを大断面トンネル、
140M以上のトンネルを超大断面トンネルと呼ぶこと
とすると、特に超大断面トンネルの場合には、掘削断面
が大きくなるばかりでなく、偏平率(縦長さ/横長さ)
も小さくなるため、地山の安定がとりわけ問題となる。 そのため、従来一般には、第3図(a)ないしくC)に
それぞれ示すように超大断面を■ないし■、さらに■の
順序で小さく分割して掘削する分割掘削工法、または第
4図に示すように側壁導坑を両側に施工後、これらの間
を剛性の高いパイプルーフやフォアパイリング等を用い
て地山に対し支保しながら大きく掘削する側壁導坑先進
工法が採られていた。
Currently, tunnels with an excavation cross section of 70 to 80 m are called standard tunnels, and tunnels with an excavation area of 100 to 120 m are called large cross section tunnels.
If a tunnel of 140M or more is called an ultra-large cross-section tunnel, especially in the case of an ultra-large cross-section tunnel, not only the excavation cross section becomes large, but also the aspect ratio (vertical length / horizontal length)
The stability of the ground becomes a particular issue as the size of the ground becomes smaller. For this reason, conventionally, in general, a divided excavation method was used in which an extremely large cross section is divided into smaller sections in the order of ■ to ■, as shown in Figures 3 (a) to C), respectively, and then excavated into smaller pieces, or as shown in Figure 4. The advanced method of construction of side wall shafts was used, in which side wall shafts were constructed on both sides, and the space between these shafts was supported against the ground using a highly rigid pipe roof or fore pile and a large excavation was made.

【発明が解決しようする課題】[Problem to be solved by the invention]

しかし、従来の分割断面掘削工法及び側壁導坑先進工法
は、超大断面掘削時の支保工が全断面に対する一括した
安定を意図したもので、がなり大規模な支保が必要であ
った。特に、側壁導坑先進工法ではパイプルーフやフォ
アパイリング等の補助工法が必要となり、工費が高くな
る問題があった。 また、従来においても、分割断面掘削空間や導坑から縫
地ボルトを施工する方法はあったが、それは、あくまで
も分割断面掘削空間や導坑自体を安定化するためで、長
さも短くかつ本数も少ないため、本杭の安定を図ること
はできなかった。 さらに、地表からトンネルの天端部までに垂直縫地ボル
トを施工する方法もあったが、適用場所及び施工深度が
制限される問題があった。 本発明はこのような従来の問題点に鑑み、大断面ないし
超大断面トンネルの周辺の地山を容易に安定させること
ができ、しかも本杭の切羽の安定も事前に確保でき、従
って本杭の支保工を小規模にできるとともに、本杭掘削
を安定した状態で能率的にかつ経済的に行える、掘削工
法を提供することを目的とする。
However, in the conventional divided cross-section excavation method and advanced sidewall tunnel construction method, the shoring used when excavating an extremely large cross-section was intended to stabilize the entire cross-section at once, and large-scale shoring was required. In particular, the advanced sidewall tunnel construction method requires auxiliary construction methods such as pipe roofing and forepiling, which poses the problem of increased construction costs. In addition, in the past, there was a method of constructing seam bolts from the divided section excavation space or the guide shaft, but this was only for stabilizing the divided section excavation space or the guide shaft itself, and the length was short and the number of bolts was small. Due to the small number of piles, it was not possible to stabilize the pile. Furthermore, there was a method of constructing vertical seam bolts from the ground surface to the top of the tunnel, but this method had the problem of limiting the applicable location and construction depth. In view of these conventional problems, the present invention can easily stabilize the ground around large-section or extra-large-section tunnels, and can also ensure the stability of the face of the pile in advance. The purpose of the present invention is to provide an excavation method that can reduce the size of the shoring and perform the main pile excavation efficiently and economically in a stable condition.

【課題を解決するための手段】[Means to solve the problem]

本発明では、大断面ないし超大断面トンネルの掘削予定
領域内またはその周辺に複数の導坑を設け、各導坑から
大断面ないし超大断面トンネルのための本坑用縫地ボル
トを上記掘削予定領域外へまた切羽安定用ボルトを掘削
予定領域内に貫入した後、該切羽安定用ボルトを撒去し
ながら掘削予定領域内を掘削する。
In the present invention, a plurality of guide shafts are provided in or around the area where a large-section or extra-large-section tunnel is scheduled to be excavated, and a seam bolt for the main shaft for the large-section or extra-large cross-section tunnel is inserted from each guide shaft into the area scheduled to be excavated. After penetrating the face stabilizing bolt outward into the area to be excavated, the area to be excavated is excavated while the face stabilizing bolt is scattered.

【作  用】[For production]

複数の導坑から貫入した本杭用縫地ボルトによって、周
辺地山の剪断力を増加させ、本杭掘削時のゆるみ等を極
力抑え、また縦断的には本杭切羽前方に切羽安定用ボル
トが事前に打たれることになり、切羽の安定も確保でき
る。
The seam bolts for the main pile that penetrate through multiple guide shafts increase the shearing force of the surrounding ground and minimize loosening during excavation of the main pile, and longitudinally, bolts for stabilizing the main pile face are installed in front of the main pile face. is struck in advance, ensuring the stability of the face.

【実 施 例】【Example】

以下、本発明の一実施例を図面に基づき説明する。 第1図に示すように、最終的に施工しようとする超大断
面トンネル(本杭)の掘削予定領域1の頂部に小断面(
例えば直径4.Om程度)の頂設導坑2を掘削し、吹付
はコンクリート及び支保工を施工し、該頂設導坑2から
掘削予定領域1外へ複数本の本杭用縫地ボルト3、掘削
予定領域1内に複数本の切羽安定用ボルト4を貫入する
。また、掘削予定領域1の左右両側下部に、その内外に
わたる小断面(上記と同じ程度)の側壁導坑5を掘削し
、それぞれの側壁導坑5において吹付はコンクリート及
び支保工を施工し、掘削予定領域1の外方へ複数本の本
坑用縫地ボルト6、掘削予定領域1内に複数本の切羽安
定用ボルト7を貫入し、さらに側壁コンクリート8を打
設して予め支保底壁を確保しておく。 なお、本杭用縫地ボルト3.6のうち後述のように本杭
の施工完了後も残すものは、例えば6.0〜10.0m
程度の鋼棒とするが、本杭掘削時に撒去する一部の縫地
ボルト及び切羽安定用ボルト47は4,0〜6.0m程
度のFRP棒とするのが好ましい。 次に、第2図に示すように切羽安定用ボルト4゜7及び
掘削予定領域1内の一部の本杭用縫地ボルト3を撒去し
ながら掘削予定領域1内を全断面または分割断面で掘削
する。この場合、掘削予定領域1の周辺地山は本杭用縫
地ボルト3.6により事前に補強されているため、支保
工を小規模にできるとともに、改めて縫地ボルトを施工
する手間が省ける。また、掘削予定領域1内には切羽安
定用ボルト4.7が施工されているため、事前に切羽の
安定も確保できる。 次いで、左右の側壁コンクリート8間にわたって吹付は
コンクリート及び支保工を施工し、さらに必要に応じ本
杭用縫地ボルトを打設した後、アーチ形に覆工9を施工
し、またインバートコンクリ−目0を打設して超大断面
トンフルを完成させる。 なお、上記実施例では超大断面トンネルを例にしたが、
本発明は大断面トンネルに対しても適用できるこという
までもない。
Hereinafter, one embodiment of the present invention will be described based on the drawings. As shown in Figure 1, a small cross-section (
For example, diameter 4. Excavate a top shaft 2 (approximately 1000 ft), spray concrete and shoring, and from the top shaft 2, install multiple bolts 3 for main piles outside the planned excavation area 1, and install concrete and shoring. 1, a plurality of bolts 4 for stabilizing the face are inserted thereinto. In addition, side wall guide shafts 5 with a small cross section (same as above) are excavated in the lower left and right sides of the planned excavation area 1, extending inside and outside the area, and sprayed concrete and shoring are constructed in each side wall guide shaft 5. A plurality of seam bolts 6 for the main shaft are penetrated to the outside of the planned excavation area 1, and a plurality of face stabilization bolts 7 are penetrated into the planned excavation area 1, and side wall concrete 8 is poured to form a supporting bottom wall in advance. Secure it. In addition, among the seam bolts 3.6 for the main pile, those that will remain after the construction of the main pile is completed, as described later, are, for example, 6.0 to 10.0 m.
However, it is preferable that some seam bolts and face stabilizing bolts 47 that are removed during the actual pile excavation be FRP rods with a length of about 4.0 to 6.0 m. Next, as shown in Fig. 2, while removing the face stabilizing bolts 4゜7 and some of the main pile seam bolts 3 in the planned excavation area 1, the entire cross section or divided cross section of the planned excavation area 1 is removed. excavate with. In this case, since the surrounding ground of the planned excavation area 1 has been reinforced in advance with the seam bolts 3.6 for the main piles, the shoring can be made small-scale and the effort of installing seam bolts again can be saved. Moreover, since the face stabilizing bolts 4.7 are installed in the planned excavation area 1, the stability of the face can be ensured in advance. Next, sprayed concrete and shoring were applied to the left and right sidewalls (8 spaces), and if necessary, bolts for the main piles were driven, and then an arch-shaped lining 9 was installed, and inverted concrete was installed. 0 to complete the super large cross section tunnel. In addition, in the above embodiment, an ultra-large cross-section tunnel was used as an example, but
It goes without saying that the present invention can also be applied to large-section tunnels.

【発明の効果】【Effect of the invention】

本発明によれば次のような効果がある。 ■ 大断面ないし超大断面トンネルの掘削前に、周辺地
山を本杭用としてそのまま残す縫地ボルトによって予め
補強するため、本杭掘削を大断面で行うことができる。 ■ 支保工を小規模にでき、経済的である。 ■ 本杭掘削前に切羽の安定も図れる。 ■ 本杭掘削時に改めて縫地ボルトを施工することが不
要になる。
According to the present invention, there are the following effects. ■ Before excavating a tunnel with a large or very large cross section, the surrounding ground is reinforced with seam bolts that are left as is for the main pile, so the main pile can be excavated with a large cross section. ■ Shoring can be made small-scale and economical. ■ The face can be stabilized before the actual pile excavation. ■ There is no need to install seam bolts again when excavating the actual pile.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は本発明の一実施例の説明図、第3図
(a)〜(C)はそれぞれ従来の分割掘削工法の概念図
、第4図は従来の側壁導坑先進工法の概念図である。 1・・・・・・掘削予定領域、2・・・・・・頂設導坑
、3,6・・・・・・木杭用縫地ポルト、4.7・・・
・・・切羽安定用ボルト、5・・・・・・側壁導坑、8
・・・・・・側壁コンクリート、9・・・・・・覆工、
10・・・・・・インバートコンクリート。 第 図(0) 第 図(b) 第 図(C) 第 図 第 図 第2図
Figures 1 and 2 are explanatory diagrams of one embodiment of the present invention, Figures 3 (a) to (C) are conceptual diagrams of the conventional split excavation method, respectively, and Figure 4 is the conventional advanced side wall tunnel construction method. It is a conceptual diagram. 1... Area to be excavated, 2... Top guide shaft, 3, 6... Sewing port for wooden piles, 4.7...
... Face stabilization bolt, 5 ... Side wall guide shaft, 8
...Side wall concrete, 9... Lining,
10... Invert concrete. Figure (0) Figure (b) Figure (C) Figure Figure 2

Claims (1)

【特許請求の範囲】[Claims] 1、大断面ないし超大断面トンネルの掘削予定領域内ま
たはその周辺に複数の導坑を設け、各導坑から大断面な
いし超大断面トンネルのための本坑用縫地ボルトを上記
掘削予定領域外へ、また切羽安定用ボルトを掘削予定領
域内に貫入した後、該切羽安定用ボルトを撒去しながら
掘削予定領域内を掘削することを特徴とする大断面ない
し超大断面トンネルの掘削工法。
1. Provide multiple guide shafts in or around the area where the large-section or extra-large-section tunnel is scheduled to be excavated, and from each guide shaft move the seam bolts for the main shaft for the large-section or extra-large cross-section tunnel out of the area where the tunnel is planned to be excavated. , and a method for excavating a tunnel with a large cross section or a very large cross section, characterized in that after a bolt for stabilizing the face is penetrated into the region to be excavated, the region to be excavated is excavated while the bolt for stabilizing the face is being scattered.
JP7685090A 1990-03-28 1990-03-28 Excavation method for large or very large tunnel Expired - Fee Related JP2932197B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7685090A JP2932197B2 (en) 1990-03-28 1990-03-28 Excavation method for large or very large tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7685090A JP2932197B2 (en) 1990-03-28 1990-03-28 Excavation method for large or very large tunnel

Publications (2)

Publication Number Publication Date
JPH03279596A true JPH03279596A (en) 1991-12-10
JP2932197B2 JP2932197B2 (en) 1999-08-09

Family

ID=13617132

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7685090A Expired - Fee Related JP2932197B2 (en) 1990-03-28 1990-03-28 Excavation method for large or very large tunnel

Country Status (1)

Country Link
JP (1) JP2932197B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605901A (en) * 2021-07-20 2021-11-05 西南交通大学 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction
JP2022524893A (en) * 2019-03-22 2022-05-10 ハイパートンネル アイピー リミティッド Methods and systems for constructing underground tunnels

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6149473B2 (en) 2013-04-09 2017-06-21 沖電気工業株式会社 Medium binding apparatus and medium arranging apparatus

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022524893A (en) * 2019-03-22 2022-05-10 ハイパートンネル アイピー リミティッド Methods and systems for constructing underground tunnels
JP2023113780A (en) * 2019-03-22 2023-08-16 ハイパートンネル アイピー リミティッド Method and system for constructing underground tunnels
US12378884B2 (en) 2019-03-22 2025-08-05 Hypertunnel Ip Limited Method and system of constructing an underground tunnel
CN113605901A (en) * 2021-07-20 2021-11-05 西南交通大学 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction

Also Published As

Publication number Publication date
JP2932197B2 (en) 1999-08-09

Similar Documents

Publication Publication Date Title
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
JP3677699B2 (en) Construction method of tunnel junction
CN204960946U (en) Prevention tunnel subsides supporting construction of deformation
CN107387129A (en) A kind of rapid constructing method for controlling the deformation of tunnel extrusion pressing type
JP3155471B2 (en) Tunnel construction method and tunnel support structure
JPH03279596A (en) Excavation method of large section or superlarge section of tunnel
JP3135188B2 (en) Construction method of underground cavity
JP2001271365A (en) Construction method for underground structures
JP2003301454A (en) Construction method of retaining wall and underground structure
JP2762140B2 (en) Construction method of underground continuous wall based on underground tunnel
JPH0464697A (en) Construction of tunneling space
KR101091081B1 (en) Bidirectional tunnel excavation method and bidirectional tunnel formed by the method
JP2648051B2 (en) Construction method of arch shell in tunnel precedent
JPH07324586A (en) Prior reinforcing method for tunnel leg
JP2554507B2 (en) Underground space construction method
JPH07331997A (en) Constructing method of rock cavern
CN115522941B (en) Method for constructing tunnel by shield method
JPH08165899A (en) Tunnel lining method using timbering concurrently serving as reinforcing bar
JPH0654016B2 (en) Underground space construction method
JP3071252B2 (en) Excavation method for soft ground tunnel
JPH05118189A (en) Large sectional tunnel excavating method
CN117780141A (en) Underground space expansion method and structure based on pre-cut groove and load underpinning system
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JP2592901B2 (en) How to put a long pipe into the groove in sheet pile construction
JP2000136693A (en) Tunnel receiving method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees