JPH03279596A - Excavation method of large section or superlarge section of tunnel - Google Patents
Excavation method of large section or superlarge section of tunnelInfo
- Publication number
- JPH03279596A JPH03279596A JP7685090A JP7685090A JPH03279596A JP H03279596 A JPH03279596 A JP H03279596A JP 7685090 A JP7685090 A JP 7685090A JP 7685090 A JP7685090 A JP 7685090A JP H03279596 A JPH03279596 A JP H03279596A
- Authority
- JP
- Japan
- Prior art keywords
- area
- bolts
- section
- excavated
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
本発明は、導坑を利用して大断面ないし超大断面トンネ
ルを掘削する工法に関するものである。The present invention relates to a construction method for excavating a tunnel with a large cross section or an extremely large cross section using a shaft.
いま、掘削断面積が70〜80イのトンネルを標準トン
フル、100〜120Mのトンネルを大断面トンネル、
140M以上のトンネルを超大断面トンネルと呼ぶこと
とすると、特に超大断面トンネルの場合には、掘削断面
が大きくなるばかりでなく、偏平率(縦長さ/横長さ)
も小さくなるため、地山の安定がとりわけ問題となる。
そのため、従来一般には、第3図(a)ないしくC)に
それぞれ示すように超大断面を■ないし■、さらに■の
順序で小さく分割して掘削する分割掘削工法、または第
4図に示すように側壁導坑を両側に施工後、これらの間
を剛性の高いパイプルーフやフォアパイリング等を用い
て地山に対し支保しながら大きく掘削する側壁導坑先進
工法が採られていた。Currently, tunnels with an excavation cross section of 70 to 80 m are called standard tunnels, and tunnels with an excavation area of 100 to 120 m are called large cross section tunnels.
If a tunnel of 140M or more is called an ultra-large cross-section tunnel, especially in the case of an ultra-large cross-section tunnel, not only the excavation cross section becomes large, but also the aspect ratio (vertical length / horizontal length)
The stability of the ground becomes a particular issue as the size of the ground becomes smaller. For this reason, conventionally, in general, a divided excavation method was used in which an extremely large cross section is divided into smaller sections in the order of ■ to ■, as shown in Figures 3 (a) to C), respectively, and then excavated into smaller pieces, or as shown in Figure 4. The advanced method of construction of side wall shafts was used, in which side wall shafts were constructed on both sides, and the space between these shafts was supported against the ground using a highly rigid pipe roof or fore pile and a large excavation was made.
しかし、従来の分割断面掘削工法及び側壁導坑先進工法
は、超大断面掘削時の支保工が全断面に対する一括した
安定を意図したもので、がなり大規模な支保が必要であ
った。特に、側壁導坑先進工法ではパイプルーフやフォ
アパイリング等の補助工法が必要となり、工費が高くな
る問題があった。
また、従来においても、分割断面掘削空間や導坑から縫
地ボルトを施工する方法はあったが、それは、あくまで
も分割断面掘削空間や導坑自体を安定化するためで、長
さも短くかつ本数も少ないため、本杭の安定を図ること
はできなかった。
さらに、地表からトンネルの天端部までに垂直縫地ボル
トを施工する方法もあったが、適用場所及び施工深度が
制限される問題があった。
本発明はこのような従来の問題点に鑑み、大断面ないし
超大断面トンネルの周辺の地山を容易に安定させること
ができ、しかも本杭の切羽の安定も事前に確保でき、従
って本杭の支保工を小規模にできるとともに、本杭掘削
を安定した状態で能率的にかつ経済的に行える、掘削工
法を提供することを目的とする。However, in the conventional divided cross-section excavation method and advanced sidewall tunnel construction method, the shoring used when excavating an extremely large cross-section was intended to stabilize the entire cross-section at once, and large-scale shoring was required. In particular, the advanced sidewall tunnel construction method requires auxiliary construction methods such as pipe roofing and forepiling, which poses the problem of increased construction costs. In addition, in the past, there was a method of constructing seam bolts from the divided section excavation space or the guide shaft, but this was only for stabilizing the divided section excavation space or the guide shaft itself, and the length was short and the number of bolts was small. Due to the small number of piles, it was not possible to stabilize the pile. Furthermore, there was a method of constructing vertical seam bolts from the ground surface to the top of the tunnel, but this method had the problem of limiting the applicable location and construction depth. In view of these conventional problems, the present invention can easily stabilize the ground around large-section or extra-large-section tunnels, and can also ensure the stability of the face of the pile in advance. The purpose of the present invention is to provide an excavation method that can reduce the size of the shoring and perform the main pile excavation efficiently and economically in a stable condition.
本発明では、大断面ないし超大断面トンネルの掘削予定
領域内またはその周辺に複数の導坑を設け、各導坑から
大断面ないし超大断面トンネルのための本坑用縫地ボル
トを上記掘削予定領域外へまた切羽安定用ボルトを掘削
予定領域内に貫入した後、該切羽安定用ボルトを撒去し
ながら掘削予定領域内を掘削する。In the present invention, a plurality of guide shafts are provided in or around the area where a large-section or extra-large-section tunnel is scheduled to be excavated, and a seam bolt for the main shaft for the large-section or extra-large cross-section tunnel is inserted from each guide shaft into the area scheduled to be excavated. After penetrating the face stabilizing bolt outward into the area to be excavated, the area to be excavated is excavated while the face stabilizing bolt is scattered.
複数の導坑から貫入した本杭用縫地ボルトによって、周
辺地山の剪断力を増加させ、本杭掘削時のゆるみ等を極
力抑え、また縦断的には本杭切羽前方に切羽安定用ボル
トが事前に打たれることになり、切羽の安定も確保でき
る。The seam bolts for the main pile that penetrate through multiple guide shafts increase the shearing force of the surrounding ground and minimize loosening during excavation of the main pile, and longitudinally, bolts for stabilizing the main pile face are installed in front of the main pile face. is struck in advance, ensuring the stability of the face.
以下、本発明の一実施例を図面に基づき説明する。
第1図に示すように、最終的に施工しようとする超大断
面トンネル(本杭)の掘削予定領域1の頂部に小断面(
例えば直径4.Om程度)の頂設導坑2を掘削し、吹付
はコンクリート及び支保工を施工し、該頂設導坑2から
掘削予定領域1外へ複数本の本杭用縫地ボルト3、掘削
予定領域1内に複数本の切羽安定用ボルト4を貫入する
。また、掘削予定領域1の左右両側下部に、その内外に
わたる小断面(上記と同じ程度)の側壁導坑5を掘削し
、それぞれの側壁導坑5において吹付はコンクリート及
び支保工を施工し、掘削予定領域1の外方へ複数本の本
坑用縫地ボルト6、掘削予定領域1内に複数本の切羽安
定用ボルト7を貫入し、さらに側壁コンクリート8を打
設して予め支保底壁を確保しておく。
なお、本杭用縫地ボルト3.6のうち後述のように本杭
の施工完了後も残すものは、例えば6.0〜10.0m
程度の鋼棒とするが、本杭掘削時に撒去する一部の縫地
ボルト及び切羽安定用ボルト47は4,0〜6.0m程
度のFRP棒とするのが好ましい。
次に、第2図に示すように切羽安定用ボルト4゜7及び
掘削予定領域1内の一部の本杭用縫地ボルト3を撒去し
ながら掘削予定領域1内を全断面または分割断面で掘削
する。この場合、掘削予定領域1の周辺地山は本杭用縫
地ボルト3.6により事前に補強されているため、支保
工を小規模にできるとともに、改めて縫地ボルトを施工
する手間が省ける。また、掘削予定領域1内には切羽安
定用ボルト4.7が施工されているため、事前に切羽の
安定も確保できる。
次いで、左右の側壁コンクリート8間にわたって吹付は
コンクリート及び支保工を施工し、さらに必要に応じ本
杭用縫地ボルトを打設した後、アーチ形に覆工9を施工
し、またインバートコンクリ−目0を打設して超大断面
トンフルを完成させる。
なお、上記実施例では超大断面トンネルを例にしたが、
本発明は大断面トンネルに対しても適用できるこという
までもない。Hereinafter, one embodiment of the present invention will be described based on the drawings. As shown in Figure 1, a small cross-section (
For example, diameter 4. Excavate a top shaft 2 (approximately 1000 ft), spray concrete and shoring, and from the top shaft 2, install multiple bolts 3 for main piles outside the planned excavation area 1, and install concrete and shoring. 1, a plurality of bolts 4 for stabilizing the face are inserted thereinto. In addition, side wall guide shafts 5 with a small cross section (same as above) are excavated in the lower left and right sides of the planned excavation area 1, extending inside and outside the area, and sprayed concrete and shoring are constructed in each side wall guide shaft 5. A plurality of seam bolts 6 for the main shaft are penetrated to the outside of the planned excavation area 1, and a plurality of face stabilization bolts 7 are penetrated into the planned excavation area 1, and side wall concrete 8 is poured to form a supporting bottom wall in advance. Secure it. In addition, among the seam bolts 3.6 for the main pile, those that will remain after the construction of the main pile is completed, as described later, are, for example, 6.0 to 10.0 m.
However, it is preferable that some seam bolts and face stabilizing bolts 47 that are removed during the actual pile excavation be FRP rods with a length of about 4.0 to 6.0 m. Next, as shown in Fig. 2, while removing the face stabilizing bolts 4゜7 and some of the main pile seam bolts 3 in the planned excavation area 1, the entire cross section or divided cross section of the planned excavation area 1 is removed. excavate with. In this case, since the surrounding ground of the planned excavation area 1 has been reinforced in advance with the seam bolts 3.6 for the main piles, the shoring can be made small-scale and the effort of installing seam bolts again can be saved. Moreover, since the face stabilizing bolts 4.7 are installed in the planned excavation area 1, the stability of the face can be ensured in advance. Next, sprayed concrete and shoring were applied to the left and right sidewalls (8 spaces), and if necessary, bolts for the main piles were driven, and then an arch-shaped lining 9 was installed, and inverted concrete was installed. 0 to complete the super large cross section tunnel. In addition, in the above embodiment, an ultra-large cross-section tunnel was used as an example, but
It goes without saying that the present invention can also be applied to large-section tunnels.
本発明によれば次のような効果がある。
■ 大断面ないし超大断面トンネルの掘削前に、周辺地
山を本杭用としてそのまま残す縫地ボルトによって予め
補強するため、本杭掘削を大断面で行うことができる。
■ 支保工を小規模にでき、経済的である。
■ 本杭掘削前に切羽の安定も図れる。
■ 本杭掘削時に改めて縫地ボルトを施工することが不
要になる。According to the present invention, there are the following effects. ■ Before excavating a tunnel with a large or very large cross section, the surrounding ground is reinforced with seam bolts that are left as is for the main pile, so the main pile can be excavated with a large cross section. ■ Shoring can be made small-scale and economical. ■ The face can be stabilized before the actual pile excavation. ■ There is no need to install seam bolts again when excavating the actual pile.
第1図及び第2図は本発明の一実施例の説明図、第3図
(a)〜(C)はそれぞれ従来の分割掘削工法の概念図
、第4図は従来の側壁導坑先進工法の概念図である。
1・・・・・・掘削予定領域、2・・・・・・頂設導坑
、3,6・・・・・・木杭用縫地ポルト、4.7・・・
・・・切羽安定用ボルト、5・・・・・・側壁導坑、8
・・・・・・側壁コンクリート、9・・・・・・覆工、
10・・・・・・インバートコンクリート。
第
図(0)
第
図(b)
第
図(C)
第
図
第
図
第2図Figures 1 and 2 are explanatory diagrams of one embodiment of the present invention, Figures 3 (a) to (C) are conceptual diagrams of the conventional split excavation method, respectively, and Figure 4 is the conventional advanced side wall tunnel construction method. It is a conceptual diagram. 1... Area to be excavated, 2... Top guide shaft, 3, 6... Sewing port for wooden piles, 4.7...
... Face stabilization bolt, 5 ... Side wall guide shaft, 8
...Side wall concrete, 9... Lining,
10... Invert concrete. Figure (0) Figure (b) Figure (C) Figure Figure 2
Claims (1)
たはその周辺に複数の導坑を設け、各導坑から大断面な
いし超大断面トンネルのための本坑用縫地ボルトを上記
掘削予定領域外へ、また切羽安定用ボルトを掘削予定領
域内に貫入した後、該切羽安定用ボルトを撒去しながら
掘削予定領域内を掘削することを特徴とする大断面ない
し超大断面トンネルの掘削工法。1. Provide multiple guide shafts in or around the area where the large-section or extra-large-section tunnel is scheduled to be excavated, and from each guide shaft move the seam bolts for the main shaft for the large-section or extra-large cross-section tunnel out of the area where the tunnel is planned to be excavated. , and a method for excavating a tunnel with a large cross section or a very large cross section, characterized in that after a bolt for stabilizing the face is penetrated into the region to be excavated, the region to be excavated is excavated while the bolt for stabilizing the face is being scattered.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7685090A JP2932197B2 (en) | 1990-03-28 | 1990-03-28 | Excavation method for large or very large tunnel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7685090A JP2932197B2 (en) | 1990-03-28 | 1990-03-28 | Excavation method for large or very large tunnel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH03279596A true JPH03279596A (en) | 1991-12-10 |
| JP2932197B2 JP2932197B2 (en) | 1999-08-09 |
Family
ID=13617132
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7685090A Expired - Fee Related JP2932197B2 (en) | 1990-03-28 | 1990-03-28 | Excavation method for large or very large tunnel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2932197B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113605901A (en) * | 2021-07-20 | 2021-11-05 | 西南交通大学 | Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction |
| JP2022524893A (en) * | 2019-03-22 | 2022-05-10 | ハイパートンネル アイピー リミティッド | Methods and systems for constructing underground tunnels |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6149473B2 (en) | 2013-04-09 | 2017-06-21 | 沖電気工業株式会社 | Medium binding apparatus and medium arranging apparatus |
-
1990
- 1990-03-28 JP JP7685090A patent/JP2932197B2/en not_active Expired - Fee Related
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2022524893A (en) * | 2019-03-22 | 2022-05-10 | ハイパートンネル アイピー リミティッド | Methods and systems for constructing underground tunnels |
| JP2023113780A (en) * | 2019-03-22 | 2023-08-16 | ハイパートンネル アイピー リミティッド | Method and system for constructing underground tunnels |
| US12378884B2 (en) | 2019-03-22 | 2025-08-05 | Hypertunnel Ip Limited | Method and system of constructing an underground tunnel |
| CN113605901A (en) * | 2021-07-20 | 2021-11-05 | 西南交通大学 | Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2932197B2 (en) | 1999-08-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111472801A (en) | Construction method for passing existing line under shallow-buried underground excavation drainage gallery | |
| JP3677699B2 (en) | Construction method of tunnel junction | |
| CN204960946U (en) | Prevention tunnel subsides supporting construction of deformation | |
| CN107387129A (en) | A kind of rapid constructing method for controlling the deformation of tunnel extrusion pressing type | |
| JP3155471B2 (en) | Tunnel construction method and tunnel support structure | |
| JPH03279596A (en) | Excavation method of large section or superlarge section of tunnel | |
| JP3135188B2 (en) | Construction method of underground cavity | |
| JP2001271365A (en) | Construction method for underground structures | |
| JP2003301454A (en) | Construction method of retaining wall and underground structure | |
| JP2762140B2 (en) | Construction method of underground continuous wall based on underground tunnel | |
| JPH0464697A (en) | Construction of tunneling space | |
| KR101091081B1 (en) | Bidirectional tunnel excavation method and bidirectional tunnel formed by the method | |
| JP2648051B2 (en) | Construction method of arch shell in tunnel precedent | |
| JPH07324586A (en) | Prior reinforcing method for tunnel leg | |
| JP2554507B2 (en) | Underground space construction method | |
| JPH07331997A (en) | Constructing method of rock cavern | |
| CN115522941B (en) | Method for constructing tunnel by shield method | |
| JPH08165899A (en) | Tunnel lining method using timbering concurrently serving as reinforcing bar | |
| JPH0654016B2 (en) | Underground space construction method | |
| JP3071252B2 (en) | Excavation method for soft ground tunnel | |
| JPH05118189A (en) | Large sectional tunnel excavating method | |
| CN117780141A (en) | Underground space expansion method and structure based on pre-cut groove and load underpinning system | |
| JPS6272817A (en) | Construction of retaining wall concurrently serving as sheathing | |
| JP2592901B2 (en) | How to put a long pipe into the groove in sheet pile construction | |
| JP2000136693A (en) | Tunnel receiving method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| LAPS | Cancellation because of no payment of annual fees |