JPH0348285B2 - - Google Patents
Info
- Publication number
- JPH0348285B2 JPH0348285B2 JP59049792A JP4979284A JPH0348285B2 JP H0348285 B2 JPH0348285 B2 JP H0348285B2 JP 59049792 A JP59049792 A JP 59049792A JP 4979284 A JP4979284 A JP 4979284A JP H0348285 B2 JPH0348285 B2 JP H0348285B2
- Authority
- JP
- Japan
- Prior art keywords
- projections
- position slightly
- concrete
- shaped steel
- steel plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】
本発明は、形鋼とコンクリートからなる合成床
版橋に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a composite deck bridge made of section steel and concrete.
従来、例えば道路橋等における合成床版橋は、
例えば第1図に示す如く、上部フランジ1aの上
面に突起1bを有するT形鋼1を所要等間隔に並
列配置し、この各突起付T形鋼1の下端面間にわ
たつて底鋼板2を溶接し、各突起付T形鋼1の上
部フランジ1aよりも若干上部位置に、各突起付
T形鋼1と直交して上配力鉄筋3を配設し、前記
底鋼板2の上面から上配力鉄筋3の若干上方位置
までのいわゆる開断面鋼箱桁内にコンクリート4
を打設して構築されている。 Conventionally, for example, synthetic deck bridges such as road bridges,
For example, as shown in FIG. 1, T-beams 1 having protrusions 1b on the upper surface of the upper flange 1a are arranged in parallel at required regular intervals, and a bottom steel plate 2 is placed between the lower end surfaces of each T-beam 1 with protrusions. Welded, an upper force distribution reinforcing bar 3 is disposed at a position slightly above the upper flange 1a of each T-shaped steel 1 with projections, perpendicular to each T-shaped steel 1 with projections. Concrete 4 is placed inside the so-called open section steel box girder up to a position slightly above the distribution reinforcing bars 3.
It is constructed by pouring.
このようにしてなる合成床版橋は、その版高比
(支間に対する床版高さの比)を1/30以下と低く
抑えることができるため、支間長26m以下の橋梁
に採用されている。 Composite slab bridges made in this way can keep the slab height ratio (ratio of slab height to span) as low as 1/30 or less, so they are used for bridges with span lengths of 26 m or less.
しかしながら、この従来の合成床版橋にあつて
は、開断面鋼箱桁内にコンクリートを全充填して
いるため、支間が長くなるに従い、床版高さが大
きくなり、それに伴つて単位面積当りのコンクリ
ート重量が増加し、第2図に示す如く、コンクリ
ート重量を支える鋼桁重量も増加する。 However, in this conventional composite deck bridge, the open cross-section steel box girder is completely filled with concrete, so as the span becomes longer, the deck height increases, and as a result, the As shown in Figure 2, the weight of the steel girder supporting the concrete weight also increases.
支間長が20mを越えると、鋼桁の単位面積当り
の重量が急激に増大し、経済性を著しく損い、ま
た支間長が26m以上の橋梁を、コンクリート全充
填式の合成床版橋によつて構築することは、経済
的にも力学的にも困難となる。 When the span length exceeds 20 m, the weight per unit area of the steel girder increases rapidly, which significantly impairs economic efficiency.In addition, bridges with span lengths of 26 m or more cannot be constructed using composite slab bridges that are fully filled with concrete. It would be economically and mechanically difficult to construct such a system.
本発明は、かくの如き従来の合成床板橋の問題
を解決すべくなしたものであつて、その実施例を
以下に説明する。 The present invention has been made to solve the problems of conventional synthetic deck bridges, and examples thereof will be described below.
第3図乃至第5図に示すものは、本発明の第1
実施例であつて、上部フランジ1aの上面に突起
1bを有するT形鋼1を所要等間隔に並列配置
し、この各突起付T形鋼1の下端面間にわたつて
底鋼板2を溶接し、各突起付T形鋼1の上部フラ
ンジ1aよりも若干上部位置に、各突起付T形鋼
1と直交して上配力鉄筋3を配設する。 What is shown in FIGS. 3 to 5 is the first embodiment of the present invention.
In this embodiment, T-shaped steels 1 having projections 1b on the upper surface of the upper flange 1a are arranged in parallel at required regular intervals, and a bottom steel plate 2 is welded between the lower end surfaces of each of the T-shaped steels 1 with projections. , an upper force distribution reinforcing bar 3 is disposed at a position slightly above the upper flange 1a of each T-shaped steel 1 with projections and perpendicular to each T-shaped steel 1 with projections.
前記各突起付T形鋼1のウエブ部1cには、そ
の高さのほぼ1/2部位の長手方向所定間隔をもつ
て孔1dが穿たれており、各突起付T形鋼1のウ
エブ部1cのこの孔1d間にわたつて下配力鉄筋
5を貫通配設し、前記底鋼板2の上面から下配力
鉄筋5の若干下方位置までに、比重が0.06以下の
非常に軽い発泡樹脂板6を充填し、この発泡樹脂
板6の上面から前記上配力鉄筋3の若干上方位置
まで膨張コンクリート7を打設して、合成床版橋
を構築する。 Holes 1d are bored in the web portion 1c of each T-shaped steel 1 with projections at predetermined intervals in the longitudinal direction at approximately 1/2 the height of the web portion 1c of each T-shaped steel 1 with projections. A lower distribution reinforcing bar 5 is provided through the holes 1d of 1c, and a very light foamed resin plate with a specific gravity of 0.06 or less is installed from the upper surface of the bottom steel plate 2 to a position slightly below the lower distribution reinforcing bar 5. 6 and pour expanded concrete 7 from the upper surface of the foamed resin board 6 to a position slightly above the upper load distribution reinforcing bars 3 to construct a composite deck bridge.
第6図に示すものは、本発明の第2実施例であ
つて、前記下配力鉄筋5の若干下方位置なる各突
起付T形鋼1のウエブ部1c間に、支持金具8を
介して、生め殺し型枠としての波形鋼板9を配設
し、この波形鋼板9の上面から前記上配力鉄筋3
の若干上方位置まで膨張コンクリート7を打設
し、前記底鋼板2の上面と、波形鋼板9の下面と
の間を空間部10となして、合成床版橋を構築す
る。 What is shown in FIG. 6 is a second embodiment of the present invention, in which a support metal fitting 8 is provided between the web portions 1c of the T-beams 1 with projections located slightly below the lower distribution reinforcing bars 5. , a corrugated steel plate 9 as a half-filling formwork is arranged, and the upper distribution reinforcing bar 3 is inserted from the upper surface of this corrugated steel plate 9.
Expanded concrete 7 is poured to a position slightly above the bottom steel plate 2, and a space 10 is formed between the upper surface of the bottom steel plate 2 and the lower surface of the corrugated steel plate 9, thereby constructing a composite deck bridge.
なお、前記下配力鉄筋5の直径としては13mm以
上必要であると共に、下配力鉄筋5の相互間隔は
最大300mmである。 The diameter of the lower reinforcing bars 5 must be 13 mm or more, and the distance between the lower reinforcing bars 5 is at most 300 mm.
また打設するコンクリートとしては、材令28日
で圧縮強度が270Kg/cm2以上の普通コンクリー
トでもよいが、コンクリートの乾燥収縮に伴うひ
び割れ発生を防止する目的から、上記普通コンク
リートの配合に、膨張性セメント混和材を30Kg/
m3添加した膨張コンクリートの使用が好ましい。 The concrete to be poured may be ordinary concrete with a compressive strength of 270 kg/cm 2 or more at 28 days old, but in order to prevent cracks from occurring due to drying shrinkage of concrete, expansion is added to the above ordinary concrete mix. 30Kg of cement admixture
Preference is given to using expanded concrete with the addition of m 3 .
さらに、骨材としての砂および砂利に、単位容
積重量2トン/m3以下の人工軽量骨材を用いるこ
とにより、一層コンクリート重量の軽量化を図る
ことができる。 Furthermore, by using artificial lightweight aggregate with a unit volume weight of 2 tons/m 3 or less as the sand and gravel as the aggregate, it is possible to further reduce the weight of the concrete.
本発明は、上述の如く、上部フランジの上面に
突起を有するT形鋼を所要等間隔に並列配置し、
この各突起付T形鋼のウエブ部の下端面間にわた
つて底鋼板を溶接し、変突起付T形鋼の上部フラ
ンジの上面よりも若干上部位置に、各突起付T形
鋼と直交して上配力鉄筋を配設し、かつ各突起付
T形鋼のウエブ部の高さのほぼ1/2部位に直交貫
通して下配力鉄筋を配設し、この下配力鉄筋の若
干下方位置から前記上配力鉄筋の若干上方位置ま
でコンクリートを打設して合成床版橋を構成した
ので、各突起付T形鋼のウエブ部の下端面間にわ
たつて底鋼板を溶接により一体構造としており、
底鋼板が連続していることから、あたかもI形鋼
を連続並列したようになり、大きな外力に対する
抵抗力を有する。 As described above, the present invention arranges T-beams having protrusions on the upper surface of the upper flange in parallel at required equal intervals,
A bottom steel plate is welded between the lower end surfaces of the web parts of each T-shaped steel with projections, and a bottom steel plate is welded to a position slightly above the upper surface of the upper flange of the T-shaped steel with modified projections, and is perpendicular to each T-shaped steel with projections. An upper force distribution reinforcing bar is installed, and a lower force distribution reinforcing bar is installed perpendicularly through approximately 1/2 the height of the web portion of each T-beam with a projection. Since a composite slab bridge was constructed by pouring concrete from the lower position to a position slightly above the upper distribution reinforcing bars, the bottom steel plate was integrated by welding between the lower end surfaces of the web parts of each T-shaped steel with protrusions. The structure is
Since the bottom steel plate is continuous, it looks like I-beams are lined up in series, and has resistance to large external forces.
また、横方向の正曲げモーメント(下縁側引張
応力)に対しては、中立軸に対し下方において底
鋼板が引張力を受け持ち、上方の圧縮力はコンク
リートが受け持つて抵抗する。 In addition, with respect to a positive bending moment in the lateral direction (lower edge side tensile stress), the bottom steel plate takes charge of the tensile force below the neutral axis, and the concrete takes charge of the compressive force above the neutral axis.
すなわち、中立軸よりも下方にコンクリートが
充填されていても、床版橋の強度には寄与しな
い。 In other words, even if concrete is filled below the neutral axis, it does not contribute to the strength of the slab bridge.
このようなことから、本発明の合成床版橋によ
れば、第1図に示す従来の合成床版橋のように、
底鋼板の上面から上配力鉄筋の若干上方位置まで
のいわゆる開断面鋼箱桁内にコンクリートを全充
填することなく、ウエブ部の高さのほぼ1/2部位
に直交貫通して下配力鉄筋を配設し、この下配力
鉄筋の若干下方位置から上方のみにコンクリート
を打設するので、単位面積当りのコンクリート重
量および鋼桁重量を低減することができ、従つて
合成床版橋の適用支間の範囲を40mまで拡張する
ことができる。 For this reason, according to the synthetic deck bridge of the present invention, like the conventional synthetic deck bridge shown in FIG.
Without completely filling the so-called open section steel box girder from the top surface of the bottom steel plate to a position slightly above the upper load distribution reinforcing bar, the lower distribution force is passed orthogonally to approximately 1/2 of the height of the web section. Since reinforcing bars are placed and concrete is placed only above and slightly below the lower reinforcing bars, the weight of concrete and steel girder per unit area can be reduced, and the weight of the steel girder can be reduced. The applicable span range can be extended to 40m.
第1図は従来の合成床版橋の横断面図、第2図
は単位面積当りの鋼桁重量と支間長との関係を示
すグラフ、第3図は本発明の第1実施例を示す合
成床版橋の横断面図、第4図は、第3図A−A線
における断面図、第5図は、第3図B−B線にお
ける断面図、第6図は本発明の第2実施例を示す
合成床版橋の横断面図である。
Fig. 1 is a cross-sectional view of a conventional composite deck bridge, Fig. 2 is a graph showing the relationship between the steel girder weight per unit area and span length, and Fig. 3 is a composite showing the first embodiment of the present invention. A cross-sectional view of the deck bridge; FIG. 4 is a cross-sectional view taken along the line A-A in FIG. 3; FIG. 5 is a cross-sectional view taken along the line B-B in FIG. 3; FIG. It is a cross-sectional view of a synthetic deck bridge showing an example.
Claims (1)
所要等間隔に並列配置し、この各突起付T形鋼の
ウエブ部の下端面間にわたつて底鋼板を溶接し、
各突起付T形鋼の上部フランジの上面よりも若干
上部位置に、各突起付T形鋼と直交して上配力鉄
筋を配設し、かつ各突起付T形鋼のウエブ部の高
さのほぼ1/2部位に直交貫通して下配力鉄筋を配
設し、この下配力鉄筋の若干下方位置から前記上
配力鉄筋の若干上方位置までコンクリートを打設
して成る合成床版橋。1 T-beams having protrusions on the upper surface of the upper flange are arranged in parallel at the required equal intervals, and a bottom steel plate is welded between the lower end surfaces of the web portions of the T-beams with protrusions,
An upper force distribution reinforcing bar is arranged at a position slightly above the upper surface of the upper flange of each T-shaped steel with projections, perpendicular to each T-shaped steel with projections, and the height of the web portion of each T-shaped steel with projections is A composite floor slab is made by placing lower distribution reinforcing bars perpendicularly through approximately 1/2 of the area, and pouring concrete from a position slightly below the lower distribution reinforcement bars to a position slightly above the upper distribution reinforcement bars. bridge.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4979284A JPS60195205A (en) | 1984-03-14 | 1984-03-14 | Construction of plywood floor panel bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4979284A JPS60195205A (en) | 1984-03-14 | 1984-03-14 | Construction of plywood floor panel bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60195205A JPS60195205A (en) | 1985-10-03 |
| JPH0348285B2 true JPH0348285B2 (en) | 1991-07-24 |
Family
ID=12840998
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4979284A Granted JPS60195205A (en) | 1984-03-14 | 1984-03-14 | Construction of plywood floor panel bridge |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60195205A (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3465836B2 (en) * | 1995-10-09 | 2003-11-10 | 株式会社 ソーシン | Buffer support structure in coupler |
| JP2007023714A (en) * | 2005-07-21 | 2007-02-01 | Jfe Engineering Kk | Synthetic floor slab using synthetic steel, composite floor slab bridge or composite girder bridge, and construction method thereof |
| JP5200825B2 (en) * | 2008-09-29 | 2013-06-05 | Jfeエンジニアリング株式会社 | Construction method of arch rib of concrete arch bridge |
| CN108130852A (en) * | 2016-12-01 | 2018-06-08 | 上海浦东建筑设计研究院有限公司 | A kind of steel reinforced concrete combined board structure of Short/Medium Span Bridge |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5030837U (en) * | 1973-06-29 | 1975-04-05 | ||
| JPS5833611A (en) * | 1981-08-25 | 1983-02-26 | 川崎製鉄株式会社 | Constructing of reinforced concrete beam |
-
1984
- 1984-03-14 JP JP4979284A patent/JPS60195205A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS60195205A (en) | 1985-10-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4604841A (en) | Continuous, precast, prestressed concrete bridge deck panel forms, precast parapets, and method of construction | |
| US5471694A (en) | Prefabricated bridge with prestressed elements | |
| KR100483083B1 (en) | Composite Deck having Frame and Concrete | |
| KR20020086506A (en) | Composite structural framing system | |
| US5152112A (en) | Composite girder construction and method of making same | |
| JP3611510B2 (en) | Half precast floor slab | |
| JPH04228710A (en) | Road slab for bridge | |
| KR100634344B1 (en) | Composite bottom plate and its connection structure | |
| JPH0348285B2 (en) | ||
| JP4293696B2 (en) | Construction method of composite floor slab bridge | |
| JPS6282147A (en) | Novel prestressed synthetic beam and its construction | |
| JP3579167B2 (en) | Deck for road surface and its laying method | |
| KR100650411B1 (en) | Lower cavity concrete slab | |
| JP2963879B2 (en) | Bridge girder | |
| JPS6361443B2 (en) | ||
| JPH0521522Y2 (en) | ||
| JP2002275833A (en) | Continuous girder method and girder structure for existing bridges | |
| CN116591037A (en) | A prefabricated anti-collision guardrail, construction method and bridge | |
| GB2256881A (en) | Load supporting structure | |
| JPS62146342A (en) | reinforced steel beam | |
| JP4492422B2 (en) | Structure near the intermediate support of a continuous I-girder bridge | |
| KR101998394B1 (en) | Precast concrete girder composed of upper structure and bridge containing girder and method for constructing this bridge | |
| JP2010281040A (en) | Steel concrete composite floor slab, panel for constructing the steel concrete composite floor slab, and construction method for steel concrete composite floor slab | |
| JPH06173379A (en) | Concrete floor construction method | |
| KR100197760B1 (en) | Concrete columns of buildings and joining structures for joining steel beams |