JPH0351845B2 - - Google Patents

Info

Publication number
JPH0351845B2
JPH0351845B2 JP9461186A JP9461186A JPH0351845B2 JP H0351845 B2 JPH0351845 B2 JP H0351845B2 JP 9461186 A JP9461186 A JP 9461186A JP 9461186 A JP9461186 A JP 9461186A JP H0351845 B2 JPH0351845 B2 JP H0351845B2
Authority
JP
Japan
Prior art keywords
embankment
anchor
concrete
hole
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9461186A
Other languages
Japanese (ja)
Other versions
JPS62253819A (en
Inventor
Masami Fukuoka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP9461186A priority Critical patent/JPS62253819A/en
Publication of JPS62253819A publication Critical patent/JPS62253819A/en
Publication of JPH0351845B2 publication Critical patent/JPH0351845B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は盛土内にアンカーを埋設することに
より、その安定化を図る盛土の安定化工法に関す
る。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to an embankment stabilization method for stabilizing the embankment by burying anchors within the embankment.

(従来の技術) 一般に盛土は第1,2図に示すように、土砂等
の盛土材料2を層状に積上げて構築され、その際
各層の上部にアンカー棒3とアンカー体4とから
なるアンカーを設置し、これを盛土1中に埋設し
ている。第1図は盛土1を構築して擁壁としたも
のであつて、前面に壁板5およびこれを支持する
支柱6を設置し、アンカー棒3は壁板5を貫通し
て支柱に固定されている。第2図は盛土1を路盤
としたものである。
(Prior Art) Generally, embankments are constructed by stacking embankment materials 2 such as earth and sand in layers, as shown in Figs. This is installed and buried in embankment 1. Fig. 1 shows a retaining wall made by constructing an embankment 1, in which a wall plate 5 and supporting columns 6 are installed in the front, and an anchor rod 3 is fixed to the column by penetrating the wall plate 5. ing. Figure 2 shows embankment 1 as the roadbed.

従来、前記のような盛土に埋設されるアンカー
のアンカー体4としては、鉄板やコンクリート板
が使用されているが、いずれの場合も次のような
問題点がある。
Conventionally, a steel plate or a concrete plate has been used as the anchor body 4 of the anchor buried in the embankment as described above, but both cases have the following problems.

(発明が解決しようとする問題点) 鉄板を使用する場合は、これにアンカー棒3挿
通用の穴をあけてアンカー棒を挿通し、両者を溶
接またはナツト等により固定しなければならな
い。この場合、溶接という特殊技術やナツトを必
要とし、またナツトを螺着するためのねじをアン
カー棒に形成するので、加工が面倒であつて費用
が高価になる。
(Problems to be Solved by the Invention) When using an iron plate, it is necessary to make a hole for the insertion of the anchor rod 3 in it, insert the anchor rod, and fix the two by welding or nuts. In this case, a special technique called welding and a nut are required, and a thread for screwing the nut is formed on the anchor rod, so the processing is troublesome and the cost is high.

コンクリート板を使用する場合は、アンカー棒
挿通用の穴を有するコンクリート板をあらかじめ
形成し、これにアンカー棒を挿通して両者をナツ
トにより固定しなければならない。この場合、前
記と同様にナツトを必要とし、またナツトを螺着
するためのねじをアンカー棒に形成するので、加
工が面倒であつて費用が高価になる。
When using a concrete plate, it is necessary to form a concrete plate with a hole for inserting the anchor rod in advance, insert the anchor rod into the concrete plate, and fix both with nuts. In this case, a nut is required in the same manner as described above, and a thread for screwing the nut is formed on the anchor rod, which is cumbersome to process and expensive.

そして鉄板、コンクリート板いずれの場合も既
製のものとして製作されるため、現場までの運搬
費用がかかるだけでなく、必要以上の引抜き強度
に設計され、無駄が多い。すなわちアンカーの引
抜き強度はアンカー体の大きさ、供給される土の
性質、その締固めの強さ等によつて決まるが、工
事現場には各種の土が搬入され、締固めの強さも
現場でどのような締固め方法が採用されるかによ
つて異なつてくるので、設計の段階では未確定の
要素が多い。したがつて安全を見込んでアンカ
ー、特にそのアンカー体を設計しておくことは、
余りにも過大な設計となり、それだけ高価にな
る。
In the case of both steel plates and concrete plates, they are manufactured as ready-made items, which not only incurs transportation costs to the site, but also is designed to have a higher pull-out strength than necessary, resulting in a lot of waste. In other words, the pull-out strength of an anchor is determined by the size of the anchor body, the nature of the supplied soil, the strength of its compaction, etc. However, various types of soil are brought to the construction site, and the strength of compaction also varies at the site. This will depend on the type of compaction method used, so there are many undetermined factors at the design stage. Therefore, it is important to design the anchor, especially the anchor body, with safety in mind.
This results in an excessively large design, which increases the cost accordingly.

この発明は上記のような従来の問題点に鑑みて
なされたものであつて、特にアンカー体を現場打
ちコンクリートによつて製作することを前提と
し、その製作工程を盛土の構築工程に組み入れ、
それにより所要の引抜き強度をもつたアンカーを
安価に製作し、工事費用の低減を図ることができ
る工法を提供することを目的とする。
This invention was made in view of the conventional problems as described above, and is based on the premise that the anchor body is manufactured from cast-in-place concrete, and incorporates the manufacturing process into the embankment construction process.
The object of the present invention is to provide a construction method that can inexpensively manufacture an anchor with a required pull-out strength and reduce construction costs.

(問題点を解決するための手段) 上記目的を達成するためのこの発明は、盛土材
料を層状に積上げて盛土を構築するに際し、各層
の盛土材料を積上げるごとに、その上部に穴をあ
けるとともに、各層の上面にアンカー棒を横たえ
てその一部を穴上に配置し、次いで穴の周囲に盛
土材料を適宜高さまで積み上げてその内部にアン
カー棒を埋没させ、穴内にコンクリートを充填し
てアンカー棒と一体化させることを特徴とする盛
土の安定化工法にある。
(Means for Solving the Problems) This invention to achieve the above object is to create a hole in the upper part of each layer of embankment material when building an embankment by piling up embankment materials in layers. At the same time, anchor rods are placed on the top of each layer and a portion of the rods are placed over the holes, then embankment materials are piled up to an appropriate height around the holes, the anchor rods are buried inside, and the holes are filled with concrete. This is an embankment stabilization method that is characterized by being integrated with anchor rods.

(作用) 上記工法によれば、アンカー体を現場打ちコン
クリートによつて盛土の構築にともなつて形成す
るので、供給される盛土材料の種類、その締固め
程度を勘案してその都度アンカー体の大きさを所
要のものに設定することができる。穴に充填され
たコンクリートは時間とともに強度を増すが、盛
土の立上がり速度はそれ程速くないので、コンク
リートの初期の強度はそれ程大きくなつている必
要はない。
(Function) According to the above method, the anchor body is formed with cast-in-place concrete as the embankment is constructed. You can set the size to whatever you want. The concrete filled in the hole increases its strength over time, but the rising speed of the embankment is not that fast, so the initial strength of the concrete does not need to be that high.

(実施例) 第3A〜3D図はこの発明工法の手順を示す。(Example) Figures 3A to 3D show the steps of this invention method.

第3A図に示すように、盛土材料2を層状に積
上げ、この層の上部に所要大きさの穴7をあけ、
この層の上面には鉄筋等からなるアンカー棒3を
横たえ、フツク3aが形成されたその端部を穴7
上に位置させる。
As shown in Fig. 3A, the embankment material 2 is piled up in layers, a hole 7 of the required size is made in the upper part of this layer,
An anchor rod 3 made of reinforcing steel or the like is laid down on the top surface of this layer, and the end where the hook 3a is formed is inserted into the hole 7.
position it above.

次に第3B図に示すように、穴7の中に型枠8
を配置する。型枠8は第4,5図に示すように、
各1対ずつの側板8a,8bを具えた角筒状のも
のからなり、アンカー棒3と交差する側板8aに
は長溝9が形成されていて、型枠8の配置時にア
ンカー棒3はこの長溝9に受け入れられる。
Next, as shown in FIG. 3B, formwork 8 is inserted into hole 7.
Place. As shown in Figs. 4 and 5, the formwork 8 is
It is made of a rectangular tube shape with a pair of side plates 8a and 8b, and a long groove 9 is formed in the side plate 8a that intersects with the anchor rod 3. When the formwork 8 is placed, the anchor rod 3 is inserted into the long groove. Accepted by 9.

次に第3C図に示すように、盛土材料2を型枠
8の高さまで積上げ締固めたら、第3D図に示す
ように型枠8を引抜き、土で囲まれた穴の中にコ
ンクリートを充填して硬化させ、アンカー棒3と
一体となつたアンカー体4を形成する。以後、盛
土材料を層状に積上げるごとに、前記のような工
程を繰返し、第1図あるいは第2図に示すような
盛土を構築する。アンカー体4上への盛土材料の
積上げは、コンクリートが完全に硬化しないうち
に行つてもよい。
Next, as shown in Fig. 3C, after the embankment material 2 is piled up to the height of the formwork 8 and compacted, the formwork 8 is pulled out as shown in Fig. 3D, and concrete is filled into the hole surrounded by soil. The anchor body 4 is formed integrally with the anchor rod 3 by hardening. Thereafter, each time the embankment materials are piled up in layers, the above steps are repeated to construct an embankment as shown in FIG. 1 or FIG. 2. The embankment material may be piled up on the anchor body 4 before the concrete has completely hardened.

第2図に示すようにアンカー棒を長く連結する
必要のある場合、第6図に示すようにアンカー棒
3の端部どうしを針金10等で繋ぎ合わせ、この
繋ぎ合わせ端部においてコンクリートを打設する
とよい。このようにすることによりアンカー棒ど
うしの溶接が不要になる。この場合型枠8には対
向する1対の側板8aに長溝9をそれぞれ形成す
ることになる。
When it is necessary to connect long anchor rods as shown in Fig. 2, the ends of the anchor rods 3 are connected with wire 10, etc., as shown in Fig. 6, and concrete is poured at the connected ends. It's good to do that. This eliminates the need to weld the anchor rods together. In this case, long grooves 9 are formed in a pair of opposing side plates 8a of the formwork 8, respectively.

第7図はこの発明工法にともなつて形成される
アンカーのコンクリート打設6日後の引抜試験の
結果を示す。アンカー体の大きさは第8図におい
て、寸法a×b×cが20cm×20cm×60cmのもの
と、40cm×40cm×60cmのものの2種とした。
FIG. 7 shows the results of a pull-out test of an anchor formed according to the construction method of this invention 6 days after concrete placement. As shown in FIG. 8, there are two types of anchor bodies with dimensions a x b x c of 20 cm x 20 cm x 60 cm and 40 cm x 40 cm x 60 cm.

(発明の効果) 以上のようにこの発明によれば、アンカー体を
盛土の構築にともなつて現場打ちコンクリートに
よつて形成するので、盛土材料の種類、その締固
め程度等諸要素を勘案してその都度アンカー体の
大きさを所要のものに設定することができ、した
がつてアンカー体の強度が必要以上に大きなもの
とならず、施工費用の低減化を図ることができ
る。また従来のように、溶接作業やナツト取付の
ためのねじ加工が一切不要となり、加工手間を大
幅に省略することができる。
(Effects of the Invention) As described above, according to the present invention, the anchor body is formed from cast-in-place concrete during the construction of the embankment, so various factors such as the type of embankment material and the degree of compaction are taken into consideration. Therefore, the size of the anchor body can be set to a required size each time, so the strength of the anchor body does not become larger than necessary, and construction costs can be reduced. Further, there is no need for any welding work or thread processing for nut attachment, which is required in the past, and processing time can be significantly reduced.

コンクリートは盛土の構築にともなつて形成す
る穴内に充填されるので、コンクリート打設のた
めの型枠は不要であり、また充填されたコンクリ
ート中の余剰水分は盛土材料内に滲出することに
なり、早期に高強度のコンクリート塊を得ること
ができる。
Since the concrete is filled into the holes formed during the construction of the embankment, there is no need for formwork for concrete pouring, and excess water in the filled concrete will seep into the embankment material. , high strength concrete mass can be obtained at an early stage.

【図面の簡単な説明】[Brief explanation of drawings]

第1,2図は一般的な盛土を示す断面図、第3
A〜3D図はこの発明工法の手順を示す断面図、
第4図は同上に使用する型枠を示す平面図、第5
図は第4図の線A−Aに沿つた側面図、第6図は
アンカー棒どうしの繋ぎ合わせを示す平面図、第
7図はアンカーの引抜試験の結果を示すグラフ、
第8図は同上の試験に使用したアンカーの寸法を
示す斜視図。 1……盛土、2……盛土材料、3……アンカー
棒、4……アンカー体、7……穴、8……型枠。
Figures 1 and 2 are cross-sectional views showing general embankments, Figure 3
Figures A to 3D are cross-sectional views showing the steps of this invention method;
Figure 4 is a plan view showing the formwork used for the same as above, Figure 5
The figure is a side view taken along the line A-A in Fig. 4, Fig. 6 is a plan view showing how the anchor rods are connected together, Fig. 7 is a graph showing the results of the anchor pullout test,
FIG. 8 is a perspective view showing the dimensions of the anchor used in the above test. 1... Embankment, 2... Embankment material, 3... Anchor rod, 4... Anchor body, 7... Hole, 8... Formwork.

Claims (1)

【特許請求の範囲】[Claims] 1 盛土材料を層状に積上げて盛土を構築するに
際し、各層の盛土材料を積上げるごとに、その上
部に穴をあけるとともに、各層の上面にアンカー
棒を横たえてその一部を穴上に配置し、次いで穴
の周囲に盛土材料を適宜高さまで積み上げてその
内部にアンカー棒を埋没させ、穴内にコンクリー
トを充填してアンカー棒と一体化させることを特
徴とする盛土の安定化工法。
1. When constructing an embankment by stacking embankment materials in layers, drill a hole in the top of each layer of embankment material, place an anchor rod on top of each layer, and place a part of it over the hole. Then, the embankment stabilization method is characterized in that embankment materials are piled up to an appropriate height around the hole, anchor rods are buried therein, and concrete is filled in the hole and integrated with the anchor rods.
JP9461186A 1986-04-25 1986-04-25 Stabilization work of banking Granted JPS62253819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9461186A JPS62253819A (en) 1986-04-25 1986-04-25 Stabilization work of banking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9461186A JPS62253819A (en) 1986-04-25 1986-04-25 Stabilization work of banking

Publications (2)

Publication Number Publication Date
JPS62253819A JPS62253819A (en) 1987-11-05
JPH0351845B2 true JPH0351845B2 (en) 1991-08-08

Family

ID=14115042

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9461186A Granted JPS62253819A (en) 1986-04-25 1986-04-25 Stabilization work of banking

Country Status (1)

Country Link
JP (1) JPS62253819A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291707A (en) * 2006-04-25 2007-11-08 Nishi Nippon Spc Kk Embankment structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291707A (en) * 2006-04-25 2007-11-08 Nishi Nippon Spc Kk Embankment structure and construction method thereof

Also Published As

Publication number Publication date
JPS62253819A (en) 1987-11-05

Similar Documents

Publication Publication Date Title
US4163621A (en) Method for forming a continuous footing with prefabricated footing blocks
JPS615125A (en) Foundation of building
JPH0351845B2 (en)
JPH0379486B2 (en)
JP2544159Y2 (en) Temporary retaining wall
JPS6290445A (en) Block for foundation and its manufacture
JPH04102630A (en) Construction method for block piled retaining wall
JPS6015776B2 (en) How to build a concrete wall
JPH0156213B2 (en)
JPH0352822Y2 (en)
JPH05306523A (en) Banking work
JPS6043495B2 (en) How to build a retaining wall
JPH0813405A (en) Widening construction of road
JPH0352257Y2 (en)
JPH03144014A (en) Geotextile integral with fixing part and steep slope banking using thereof
JPH0739666B2 (en) Permeable temporary earth retaining material, permeable frame structure and concrete wall construction method
JP2506978Y2 (en) Synthetic retaining wall
JPH11210004A (en) Reinforcing retaining wall construction method for slope
JPH0522009B2 (en)
JP2818845B2 (en) Comb-type continuous wall and its construction method
JPH09209370A (en) Method for constructing foundation of building
JPH03260223A (en) Positioning plate for base construction of housing
JPH0671538U (en) Block for retaining wall and retaining wall structure
JPH10147929A (en) Lateral flow countermeasure structure
JPS6029496Y2 (en) Cutting formwork