JPH035592A - Shielding method - Google Patents
Shielding methodInfo
- Publication number
- JPH035592A JPH035592A JP13903089A JP13903089A JPH035592A JP H035592 A JPH035592 A JP H035592A JP 13903089 A JP13903089 A JP 13903089A JP 13903089 A JP13903089 A JP 13903089A JP H035592 A JPH035592 A JP H035592A
- Authority
- JP
- Japan
- Prior art keywords
- pressure
- earth
- sand
- chamber
- liquid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
本発明は、掘削した土砂を利用して他山圧力に対抗させ
ながら掘進するシールド工法に関するものである。The present invention relates to a shield construction method in which excavated earth and sand are used to excavate while counteracting the pressure of other mountains.
従来の一般的なシールド工法としては、泥水加圧シール
ド工法と泥土加圧シールド工法とがあり、それぞれ次の
ような問題点があった。
■ 泥水加圧シールド工法
(a)泥水加圧シールド工法の切羽原理は、シールド掘
進機のチャンバ内に泥水(液体)を充満させた泥水圧力
(液圧)により他山に対抗させるもので、第3図に示す
ように他山圧力の分布Paとチャンバ内の泥水圧力の分
布pbに差異が生ずる。
偽)掘削土砂は、チャンバより泥水に土砂を混入させた
液体として排出されるため、掘削体積の6〜10倍の泥
水が必要である。
(C) 切羽圧力は送水用ポンプの加圧で、流量の調
整は排出用ポンプにより制御するため、複数のバルブが
必要である。
(d) 掘削土砂は液体として搬出されるため、搬山
稜に土砂を水から分離することが必要である。
■ 泥土圧シールド工法
(a) 泥土圧シールド工法は、カッタにより切削し
た土砂に添加材を加えてチャンバ内で混練りすることに
より、土砂を塑性流動化させ、シールドジヤツキの掘進
により発生した泥土圧により切羽の安定を図るもので、
第4図に示すように地山圧力の分布Paに対して泥土圧
力の分布Pcは上部が小さく、下部が大きくなる。
Φ) チャンバからの土砂の排出はスクリューコンベア
により行われているため、これにはチャンバ内の圧力の
遮断能力はない。
(C) チャンバ内の圧力制御はスクリューコンベア
の回転の増減により行われ、スクリューコンヘアで圧力
を保持するのは、土砂とスクリュー切羽の摩擦抵抗であ
り、土砂に一定の物性範囲の塑性が必要で、厳密な流動
調整を要する。Conventional general shield construction methods include the mud pressure shield construction method and the mud pressure shield construction method, each of which has the following problems. ■ Mud water pressurized shield construction method (a) The face principle of the mud water pressurized shield construction method is to counteract other piles with mud water pressure (liquid pressure) filled with mud water (liquid) in the chamber of the shield excavator. As shown in FIG. 3, a difference occurs between the distribution Pa of the other mountain pressure and the distribution Pb of the mud pressure inside the chamber. False) The excavated earth and sand is discharged from the chamber as a liquid containing muddy water and earth and sand, so muddy water of 6 to 10 times the excavation volume is required. (C) The face pressure is increased by the water pump, and the flow rate is controlled by the discharge pump, so multiple valves are required. (d) Since excavated soil is transported as a liquid, it is necessary to separate the soil from water at the ridge of the transport pile. ■ Mud and earth pressure shield method (a) The mud and earth pressure shield method adds additives to the earth and sand cut by a cutter and mixes them in a chamber to plastically fluidize the earth and remove the mud generated by the excavation of the shield jack. It uses pressure to stabilize the face.
As shown in FIG. 4, the distribution Pc of mud pressure is small in the upper part and large in the lower part with respect to the distribution Pa of the rock pressure. Φ) Since the discharge of earth and sand from the chamber is carried out by a screw conveyor, this does not have the ability to shut off the pressure inside the chamber. (C) Pressure inside the chamber is controlled by increasing or decreasing the rotation of the screw conveyor, and pressure is maintained in the screw conveyor by the frictional resistance between the earth and sand and the screw face, and the earth and sand must have plasticity within a certain range of physical properties. Therefore, strict flow adjustment is required.
本発明の課題は、(1)地山圧力分布に対するチャンバ
内圧力分布、(2)掘削土砂の排出、(3)チャンバ内
圧力及び排出量の制御の3点について、次のように従来
の問題点を解決することにある。
(1)地山圧力分布に対するチャンバ内圧力分布従来の
泥水加圧シールド工法では、切羽上部が過大圧力となっ
て噴発の恐れがあった。また泥土加圧シールド工法では
、上部が過小土圧、下部が過大となり、切羽崩壊を防ぐ
ために上部圧力を地山圧力と同じとすれば、チャンバ内
総圧力が過大となり、大きなシールド掘進力が必要であ
った。
本発明の工法では、切削された土砂に水または添加材を
加えて液状化してチャンバ内土砂の比重を調整し、地山
圧力分布と同じチャンバ圧力分布を行う。
(2)掘削土砂の排出
従来の泥水加圧シールド工法では、掘削土砂を泥水と混
合した液体として渦巻ポンプで排出していた。ところが
、渦巻ポンプは構造上液体の遮断機能が無いため、パイ
プラインに複数のバルブが必要であった。また泥土圧シ
ールド工法では、掘削土砂に加泥材を添加して塑性体と
してスクリューコンベアにより排出していたが、スクリ
ューコンベアも構造上液体の遮断機能が無いため、地下
水の噴出を防止できなかった。
本発明の工法では、掘削土砂を液状化土砂とし、これを
ロークリポンプ、スクリューポンプ。
ピストンポンプ等の構造上液体の遮断機能を有した密閉
型ポンプにより排出するため、チャンバ内の圧力を確実
に保持できる。
(3)チャンバ内圧力及び排出量の制御従来の泥水加圧
シールド工法では、送水ポンプにより圧力を、排出ポン
プにより排出流量を調整し、流体の流れを停止させるた
めには複数のバルブが必要で、その制御には複雑な制御
装置を必要とした。また泥土圧シールド工法では、圧力
、排出量をスクリューコンベアにより制御しているため
、土砂の塑性化状態により圧力の保持能力、排出量が大
幅に変化し、適切な制御が困難であった。
本発明の工法では、上記のように液状化した土砂を液体
の遮断機能を存した密閉型ポンプにより排出するため、
圧力及び排出量を的確に制御できる。The problems of the present invention are as follows: (1) chamber pressure distribution relative to rock pressure distribution, (2) discharge of excavated soil, and (3) control of chamber pressure and discharge amount. The point is to solve the problem. (1) Pressure distribution in the chamber relative to the ground pressure distribution In the conventional mud water pressurization shield construction method, there was a risk of an eruption due to excessive pressure at the upper part of the face. In addition, in the mud pressurized shield method, the earth pressure is too low at the top and too high at the bottom.If the top pressure is set to be the same as the ground pressure to prevent face collapse, the total pressure inside the chamber will be too high, and a large shield excavation force will be required. Met. In the construction method of the present invention, water or an additive is added to the cut earth and sand to liquefy it, adjust the specific gravity of the earth and sand in the chamber, and achieve the same chamber pressure distribution as the rock pressure distribution. (2) Discharge of excavated earth and sand In the conventional mud water pressure shield construction method, excavated earth and sand are discharged as a liquid mixed with mud water using a centrifugal pump. However, because the centrifugal pump does not have a liquid shutoff function due to its structure, multiple valves were required in the pipeline. In addition, in the mud pressure shield method, a muddy material was added to the excavated soil and the plastic material was discharged by a screw conveyor, but the screw conveyor did not have a liquid-blocking function due to its structure, so it was not possible to prevent groundwater from gushing out. . In the construction method of the present invention, the excavated soil is liquefied soil, and this is used as a liquefaction pump or a screw pump. Since the chamber is discharged using a closed-type pump such as a piston pump, which has a liquid-blocking function due to its structure, the pressure inside the chamber can be maintained reliably. (3) Control of chamber pressure and discharge volume In the conventional mud water pressurization shield construction method, multiple valves are required to adjust the pressure with a water pump and the discharge flow rate with a discharge pump, and to stop the flow of fluid. , which required a complex control device. In addition, in the mud pressure shield method, the pressure and discharge amount are controlled by a screw conveyor, so the pressure holding capacity and discharge amount change significantly depending on the plasticity state of the soil, making it difficult to control it appropriately. In the construction method of the present invention, the liquefied earth and sand is discharged as described above using a closed pump that has a liquid blocking function.
Pressure and discharge volume can be precisely controlled.
すなわち、本発明が採用した手段は次の通りである。
■ シールド掘進機のカッタにより切削された土砂に、
シールド掘進機のチャンバ内で添加材を混合して液状化
させる。すなわち、土の含水比の違いからその性質を固
態、半固態、プラスチックな状態、液態の4段階に分類
する土のコンステンシー(緊硬度)でいえば、本発明は
掘削した土砂を液態とする。
なお、従来の泥土圧シールド工法における泥土は半固態
ないしプラスチックな状態の範晴に入り、泥水加圧シー
ルド工法における泥水は4分類の何れの範晴からも外れ
た液体である。
■ チャンバ内の液状土砂の圧力により地山圧力に対抗
させながら、チャンバ内の圧力を複数の圧力センサによ
り検出してその圧力勾配を求める。この圧力勾配と推定
した他山圧力勾配との差に従って添加材の添加率を調整
して地山圧力勾配とチャンバ内圧力勾配を同じにする。
■ チャンバ内圧力と推定した地山圧力との差に従って
排出量を調整しかつ掘進に同調させて、液体の遮断機能
を有した密閉型ポンプによりチャンバ内の液状土砂を排
出する。That is, the means adopted by the present invention are as follows. ■ Earth and sand cut by the cutter of the shield excavator,
The additives are mixed and liquefied in the chamber of the shield tunneling machine. In other words, in terms of soil consistency (hardness), which classifies soil properties into four stages: solid, semi-solid, plastic, and liquid based on differences in soil moisture content, the present invention treats excavated soil as liquid. . In addition, the mud in the conventional mud pressure shield construction method falls into the category of semi-solid or plastic state, and the mud in the mud water pressure shield construction method is a liquid that does not fit into any of the four classifications. (2) While the pressure of the liquid earth and sand in the chamber is used to counteract the rock pressure, the pressure in the chamber is detected by a plurality of pressure sensors and its pressure gradient is determined. The addition rate of the additive is adjusted according to the difference between this pressure gradient and the estimated pressure gradient of other mountains to make the pressure gradient of the ground and the pressure gradient in the chamber the same. ■ Adjust the discharge amount according to the difference between the chamber internal pressure and the estimated ground pressure, and synchronize with the excavation, and discharge the liquid earth and sand in the chamber using a closed pump with a liquid cutoff function.
チャンバ内の液状化した土砂の圧力が他山圧力に対抗し
、しかもその圧力分布が他山圧力分布と同じであり、か
つ液状土砂が液体の遮断機能を有した密閉型ポンプによ
り、排出量を調整しつつかつ掘進に同調させて排出され
るため、大断面シールドでも常に的確な切羽安定が保持
される。The pressure of the liquefied earth and sand in the chamber opposes the pressure of other mountains, and the pressure distribution is the same as the pressure distribution of other mountains. Since it is adjusted and discharged in synchronization with the excavation, precise face stability is always maintained even in large-section shields.
以下、本発明の一実施例を図面を参照して詳細に説明す
る。
第1図は本発明のシールド工法のシステム構成図である
。シールド掘進機1は、カッタ2を回転させて地山3を
切削しながらシールドジヤツキ4により掘進させる。掘
削された土砂は、シールド掘進機1のチャンバ5内で地
上から後述の如く送給される添加材と混合されて液状土
砂とされ、−定容積のチャンバ5内に充満する。本発明
はこの充満させた液状土砂をもって他山圧力に対抗させ
、切羽の崩壊を防止する。ここで使用する添加材は土砂
を液状化できるものであればよく、例えば泥漿材、高分
子材、気泡、水等が考えられる。添加材は後述のような
バイブラインを介してシールド掘進機1へ送給され、該
シールド掘進機1側に備えられている添加材注入ポンプ
6により注入ロアからチャンバ5中に注入され、カッタ
2の回転により土砂と混合され、さらにアジテータ8に
より撹拌される。添加材注入ポンプ6としては、ローク
リポンプ、スクリューポンプ、ピストンポンプ等の構造
上液体の遮断機能を有した密閉型ポンプを使用する。
チャンバ5内の液状土砂の圧力は一定の間隔をおいて配
設された複数の圧力センナ(または土圧計)9で検出さ
れ、その検出圧力からCPUを含む制御装置10におい
てチャンバ内液状土砂の圧力勾配が求められる。同時に
また、シールドジヤツキ4に備えられたストローク計1
1により掘進速度が検知される。そして、これら圧力勾
配と掘進速度とから制御装置10において添加材注入量
が演算され、この添加材注入量から添加材注入ポンプ6
の回転数が制御され、必要量の添加材がチャンバ5中に
注入される。
垂迦山Jソd1λ乳堅
添加材は、(a)第2図に示すように他山の圧力勾配P
aとチャンバ内圧力勾配Pdとを同じにするために、チ
ャンバ5内の土砂の比重調整を行うこと、(b)土砂を
液態として流動化させる注入が必要であること、の2点
を考慮して注入量を調整する。
土質により(a)、(b)の調整度合は異なるが以下の
ようにして調整できる。
(a)に関し、地山圧力勾配は、地下水や地盤条件によ
り求めることができるので、これからチャンバ内圧力に
必要な土砂の比重は推定できる。
(b)に関し、切削土砂を液態として流動化させるため
の含水比は地山の土質試験により求めることができる。
(a)に基づく調整量をA、(b)に基づく調整量をB
とする゛と、A>Bの場合にはチャンバ内への注水によ
ってチャンバ内土砂の比重を調整する。
逆にA<Bの場合は、高分子系添加材などの特殊な添加
材により流動化を促進させ、見掛けの液状化含水比を低
下させてA>Bの関係とし、比重は注入量により調整す
る。
具体的には、(a)に関しては、地質調査により地山圧
力(地下水圧+土圧)を求め、チャンバ内流動化土砂の
必要な比重を推定する。(ト))に関しては、土質試験
により液性限界と添加材に必要な物性を求め、これによ
り単位地山体積に対する添加材注入率を求める。
実際の添加材の注入は、ストローク計11により検出し
たシールドジヤツキ4のストロークから制御装置10に
おいて地山掘削量を演算し、上記添加材注入率より単位
時間当たりの注入量を演算して添加材注入ポンプ6を制
御して注入を行う。同時に、土圧センサ9によりチャン
バ内液状土砂の比重を検出し、比重の大小により注入率
を制御装置10で演算して修正し、チャンバ5内の液状
土砂の比重を一定に保つ。なお、添加材注入ポンプ6に
よって注入される添加材の流量、圧力、比重は流量・圧
力・比重計12によって検出される。
切羽圧 の制御と 削土 の 出
一定容積のチャンバ5内はそれへの添加材の注入とシー
ルド掘進機1の旧道により圧力が上昇するので、切羽安
定のためにチャンバ5内を他山圧力と同等の圧力に保持
する必要がある。そこで、切羽圧力の制御は、チャンバ
5内の土砂を排土ポンプ13により排出することによっ
て行う。この排土ポンプ13としては、添加材注入ポン
プ6と同様にロータリポンプ、スクリューポンプ、ピス
トンポンプ等の構造上液体の遮断機能を有した密閉型ポ
ンプを使用する。
基本的には、制御装置110にチャンバ目標圧力を予め
設定し、土圧センサ9によりチャンバ内圧力を監視し、
目標圧力より高い場合には排土ポンプ13の回転を速く
して排出土砂量を増加させ、目標圧力より低い場合には
排土ポンプ13の回転を遅くして排出土砂量を減少させ
、チャンバ5内の圧力を一定に保つように制御する。制
御後の一定圧力の維持は、添加材注入バイブロ及び排土
ポンプ13が停止してそれ自体が密閉構造になることに
よって行える。なお、排土ポンプ13によって排出され
る土砂の流量、圧力、比重は流量・圧力・比重計14に
よって検出される。
掘111痕列1次
排土ポンプ13からの土砂はパイプライン15を介して
後方の中継ポンプ16へ送り、さらにこの中継ポンプ1
6によりパイプライン17で圧送して坑外(地上)へ搬
出する。圧送距離が長いときは中継ポンプ16を複数台
使用する。なお、中継ポンプ16とパイプライン17に
よる圧送に代えてズリトロによる搬出も可能である。
朋狙上髪立宣立
切羽安定が正しく行われたか否かの判断には掘削土砂の
管理が必要である。この実施例では、添加材の注入量を
流量・圧力・比重計12で、チャンバ内土砂の排出量を
流量・圧力・比重計14で、シールド掘進量をストロー
ク計11でそれぞれ検出し、これらを総計解析すること
により掘削土量の適否を判定する。
土砂p処理
掘削土砂は液状化されて排出されるため、土砂と水の分
離が必要である。
この実施例では、上記のように中継ポンプ16がらパイ
プライン17を介して搬出される液状土砂をいったん上
水混合機18内に入れ、ここで必要により循環水バイブ
19からの土砂分離用循環水と混合し、振動篩機20に
よって検分を除去する。そして、検分はベルトコンベア
21によってホッパ等へ搬送し、検分以外の液状土砂は
土砂タンク22に一時貯溜し、土砂ポンプ23によって
遠心分離@24へ送り、水と土砂とを分離する0分離し
た土砂はベルトコンベア25によってホッパ等へ搬送し
、水は循環水タンク26に一時貯溜し、その一部は循環
水ポンプ27により上記のように循環水パイプ19を通
じて土砂分離に利用し、余剰水は調整水ポンプ28によ
り調整水タンク29へ送入する。
一方、添加材プラント30から必要に応じ高分子材等を
調整水タンク29内の水に加えて物性を調整し、その水
を添加材ポンプ31によりパイプライン32を通じて中
継タンク33へ送り、該中継タンク33から添加材注入
ポンプ6により前述のように添加材としてチャンバ5内
に注入する。
なお、排出液状土砂を水と土砂に分離して処理する例を
示したが、パイプライン17を通じて搬出される土砂に
固化材等を加えて固化処理することも可能である。Hereinafter, one embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a system configuration diagram of the shield construction method of the present invention. The shield excavator 1 excavates with the shield jack 4 while rotating the cutter 2 and cutting the earth 3. The excavated earth and sand is mixed with an additive material fed from the ground as described below in the chamber 5 of the shield excavator 1 to form liquid earth and sand, and the liquid earth and sand is filled in the chamber 5 having a constant volume. The present invention prevents the face from collapsing by using the filled liquid earth and sand to counter the pressure from other mountains. The additive used here may be any material as long as it can liquefy the earth and sand, such as slurry, polymer, air bubbles, water, etc. The additive material is fed to the shield excavator 1 via a vibrator line as described below, and is injected into the chamber 5 from the injection lower by an additive injection pump 6 provided on the shield excavator 1 side, and then is injected into the chamber 5 through the cutter 2. It is mixed with earth and sand by the rotation of the , and further stirred by the agitator 8 . As the additive injection pump 6, a hermetic pump such as a rotary pump, a screw pump, a piston pump, etc., which has a liquid-blocking function due to its structure, is used. The pressure of the liquid earth and sand in the chamber 5 is detected by a plurality of pressure sensors (or earth pressure gauges) 9 arranged at regular intervals, and based on the detected pressure, the pressure of the liquid earth and sand in the chamber is determined by the control device 10 including the CPU. The slope is found. At the same time, the stroke meter 1 provided on the shield jack 4
1, the digging speed is detected. Then, based on these pressure gradients and excavation speeds, the control device 10 calculates the additive injection amount, and from this additive injection amount, the additive injection pump 6
The rotational speed of the chamber 5 is controlled, and the required amount of additive material is injected into the chamber 5. (a) The pressure gradient P of other mountains is as shown in Fig. 2.
In order to make a and the pressure gradient Pd in the chamber the same, the specific gravity of the earth and sand in the chamber 5 must be adjusted, and (b) it is necessary to inject the earth and sand to fluidize it as a liquid. Adjust the injection volume. The degree of adjustment of (a) and (b) differs depending on the soil quality, but it can be adjusted as follows. Regarding (a), since the ground pressure gradient can be determined from groundwater and ground conditions, the specific gravity of the earth and sand required for the chamber internal pressure can be estimated from this. Regarding (b), the water content ratio for fluidizing the cut earth and sand as a liquid can be determined by a soil test of the ground. The adjustment amount based on (a) is A, and the adjustment amount based on (b) is B.
If A>B, the specific gravity of the earth and sand in the chamber is adjusted by injecting water into the chamber. Conversely, if A<B, fluidization is promoted using special additives such as polymeric additives, and the apparent liquefaction water content ratio is lowered to create a relationship of A>B, and the specific gravity is adjusted by the injection amount. do. Specifically, regarding (a), the rock pressure (groundwater pressure + earth pressure) is determined through a geological survey, and the necessary specific gravity of the fluidized soil in the chamber is estimated. Regarding (g)), determine the liquid limit and physical properties required for the additive through soil tests, and from this determine the additive injection rate per unit volume of the ground. The actual injection of the additive is performed by calculating the amount of earth excavation in the control device 10 from the stroke of the shield jack 4 detected by the stroke meter 11, and calculating the injection amount per unit time from the above additive injection rate. Injection is performed by controlling the material injection pump 6. At the same time, the specific gravity of the liquid earth and sand in the chamber is detected by the earth pressure sensor 9, and the injection rate is calculated and corrected by the control device 10 depending on the magnitude of the specific gravity, so that the specific gravity of the liquid earth and sand in the chamber 5 is kept constant. Note that the flow rate, pressure, and specific gravity of the additive injected by the additive injection pump 6 are detected by a flow rate/pressure/density meter 12. Control of face pressure and excavation As the pressure inside chamber 5, which has a constant volume, increases due to the injection of additives into it and the old path of shield excavator 1, the pressure inside chamber 5 is increased by other pressure in order to stabilize the face. It is necessary to maintain the same pressure. Therefore, the face pressure is controlled by discharging the earth and sand in the chamber 5 using the soil discharge pump 13. As this soil discharge pump 13, similarly to the additive material injection pump 6, a closed type pump having a structurally liquid blocking function, such as a rotary pump, a screw pump, or a piston pump, is used. Basically, a chamber target pressure is set in advance in the control device 110, and the chamber internal pressure is monitored by the earth pressure sensor 9.
When the pressure is higher than the target pressure, the rotation of the soil discharge pump 13 is increased to increase the amount of discharged soil, and when the pressure is lower than the target pressure, the rotation of the soil discharge pump 13 is slowed down to decrease the amount of discharged soil. control to keep the pressure inside constant. The constant pressure after control can be maintained by stopping the additive injection vibro and the soil removal pump 13 and making the system itself a sealed structure. Note that the flow rate, pressure, and specific gravity of the earth and sand discharged by the earth discharge pump 13 are detected by a flow rate/pressure/density meter 14. The earth and sand from the excavation 111 trace row primary earth removal pump 13 is sent to the rear relay pump 16 via the pipeline 15, and then this relay pump 1
6, the oil is pumped through a pipeline 17 and transported outside the mine (above ground). When the pumping distance is long, a plurality of relay pumps 16 are used. In addition, instead of the pressure feeding using the relay pump 16 and the pipeline 17, it is also possible to carry out the transfer using a slider. Management of the excavated soil is necessary to determine whether or not stabilization of the standing face was carried out correctly. In this embodiment, the amount of additive material injected is detected by the flow rate/pressure/density meter 12, the amount of discharged earth and sand in the chamber is detected by the flow rate, pressure, and specific gravity meter 14, and the amount of shield excavation is detected by the stroke meter 11. The suitability of the amount of excavated soil is determined by total analysis. Sediment p treatment Since excavated soil is liquefied and discharged, it is necessary to separate the earth and sand from water. In this embodiment, as described above, the liquid earth and sand carried out from the relay pump 16 through the pipeline 17 is once put into the clean water mixer 18, and here, if necessary, the circulating water for earth and sand separation is supplied from the circulating water vibrator 19. The sample is removed by a vibrating sieve 20. Then, the liquid soil for inspection is transported to a hopper etc. by a belt conveyor 21, and the liquid soil other than the one for inspection is temporarily stored in a soil tank 22, and sent to a centrifugal separator @24 by a soil pump 23, where water and soil are separated. The water is conveyed to a hopper etc. by a belt conveyor 25, the water is temporarily stored in a circulating water tank 26, a part of which is used for soil separation by a circulating water pump 27 through a circulating water pipe 19 as described above, and surplus water is regulated. The water pump 28 sends the water to the adjustment water tank 29 . On the other hand, if necessary, a polymeric material or the like is added to the water in the adjustment water tank 29 from the additive plant 30 to adjust the physical properties, and the water is sent to the relay tank 33 via the pipeline 32 by the additive pump 31, and then The additive material is injected into the chamber 5 from the tank 33 by the additive material injection pump 6 as described above. Although an example has been shown in which the discharged liquid earth and sand is separated into water and earth and sand for treatment, it is also possible to add a solidifying agent or the like to the earth and sand carried out through the pipeline 17 for solidification treatment.
本発明のシールド工法によれば次のような効果がある。
■ 切羽圧力分布が地山圧力分布と近似するため、大断
面シールドで有効な山留効果が得られる。
■ 切羽の圧力制御に密閉型ポンプを使用するため、1
0kg以上の高水圧下での圧力保持も確実である。
■ 液状土砂にして搬出するため、その輸送用パイプは
、泥土圧シールドのポンプ圧送に比較して圧送抵抗が小
さくなるので長距離圧送でき、また泥水加圧シールドと
比較して循環泥水量が173〜1/4となるため小規模
でよく、土砂輸送コストが低減できる。
■ 切羽圧力制御、土砂輸送制御などの制御対象が少な
いので、システムが単純化される。
■ 排出土砂の処理に関し、泥水加圧シールドと比較し
て土砂処理量が少ないので、ランニングコストが低減で
きる。
■ 大深度地下でも効率よく工事できる。The shield construction method of the present invention has the following effects. ■ Since the face pressure distribution approximates the ground pressure distribution, an effective mountain retaining effect can be obtained with a large cross-section shield. ■ Since a hermetic pump is used to control the pressure at the face, 1
It also ensures pressure retention under high water pressure of 0 kg or more. ■ Because it is transported as liquid soil, the transportation pipe has less pumping resistance than the pump of the mud pressure shield, so it can be pumped over long distances, and the volume of circulating mud is 173% compared to the mud pressure shield. Since the size is 1/4, it can be small-scale and the earth and sand transportation cost can be reduced. ■ The system is simplified because there are fewer control targets such as face pressure control and sediment transport control. ■ Concerning the treatment of discharged sediment, running costs can be reduced because the amount of sediment processed is smaller compared to muddy water pressure shields. ■ Efficient construction work is possible even at great depths underground.
第1図は本発明のシールド工法の一例のシステム構成図
、第2図はそれにおける地山圧力分布とチャンバ内圧力
分布の関係を示す説明図である。
第3図は従来の泥水加圧シールド工法における地山圧力
分布とチャンバ内圧力分布の関係を示す説明図、第4図
は従来の泥土圧シールド工法における同様の説明図であ
る。
1・・・・・・シールド掘進機、2・・・・・・カッタ
、3・・・・・・地山、4・・・・・・シールドジヤツ
キ、5・・・・・・チャンバ、6・・・・・・添加材注
入ポンプ、9・・・・・・圧力センサ、11・・・・・
・ストローク計、13・・・・・・排土ポンプ。
建設省土木研究所長
株式会社大本組
株式会社小松製作所
佐騒工業株式会社
鉄建建設株式会社
東洋建設株式会社
戸田建設株式会社
飛島建設株式会社
西松建設株式会社
日本国土開発株式会社
株式会社間組
日立建機株式会社
フジタ工業株式会社
不動建設株式会社
前田建設工業株式会社FIG. 1 is a system configuration diagram of an example of the shield construction method of the present invention, and FIG. 2 is an explanatory diagram showing the relationship between the rock pressure distribution and the chamber internal pressure distribution therein. FIG. 3 is an explanatory diagram showing the relationship between the rock pressure distribution and the chamber pressure distribution in the conventional mud pressure shield construction method, and FIG. 4 is a similar explanatory diagram in the conventional mud pressure shield construction method. 1... Shield excavator, 2... Cutter, 3... Ground rock, 4... Shield jack, 5... Chamber, 6... Additive injection pump, 9... Pressure sensor, 11...
・Stroke meter, 13...Earth removal pump. Director of Civil Engineering Research Institute, Ministry of Construction Omotogumi Co., Ltd. Komatsu Ltd. Sanai Kogyo Co., Ltd. Tekken Construction Co., Ltd. Toyo Construction Co., Ltd. Toda Construction Co., Ltd. Tobishima Construction Co., Ltd. Nishimatsu Construction Co., Ltd. Japan Land Development Co., Ltd. Magumi Co., Ltd. Hitachi Construction Machinery Co., Ltd. Fujita Kogyo Co., Ltd. Fudo Construction Co., Ltd. Maeda Construction Co., Ltd.
Claims (1)
シールド掘進機のチャンバ内で添加材を混合して液状化
させ、その液状土砂の圧力により地山圧力に対抗させな
がら、上記チャンバ内の圧力を複数の圧力センサにより
検出してその圧力勾配を求め、この圧力勾配と推定した
地山圧力勾配との差に従って上記添加材の添加率を調整
し、またチャンバ内の液状土砂を、チャンバ内圧力と推
定した地山圧力との差に従って排出量を調整しかつ掘進
に同調させて、液体の遮断機能を有した密閉型ポンプに
より排出することを特徴とするシールド工法。1. In the earth and sand cut by the cutter of the shield excavator,
Additives are mixed and liquefied in the chamber of the shield excavator, and the pressure of the liquefied earth and sand is used to counteract the ground pressure, while the pressure in the chamber is detected by multiple pressure sensors to determine the pressure gradient. , the addition rate of the additive is adjusted according to the difference between this pressure gradient and the estimated rock pressure gradient, and the amount of liquid earth and sand discharged from the chamber is adjusted according to the difference between the chamber internal pressure and the estimated rock pressure. This shield construction method is characterized by discharging liquid in synchronization with the excavation using a closed pump with a liquid blocking function.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13903089A JP2700411B2 (en) | 1989-06-02 | 1989-06-02 | Shield method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13903089A JP2700411B2 (en) | 1989-06-02 | 1989-06-02 | Shield method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH035592A true JPH035592A (en) | 1991-01-11 |
| JP2700411B2 JP2700411B2 (en) | 1998-01-21 |
Family
ID=15235829
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13903089A Expired - Lifetime JP2700411B2 (en) | 1989-06-02 | 1989-06-02 | Shield method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2700411B2 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003097180A (en) * | 2001-09-20 | 2003-04-03 | Komatsu Ltd | Shield machine |
| JP2006348731A (en) * | 2005-05-16 | 2006-12-28 | Taisei Corp | Excavation sediment treatment method and excavation sediment disposal apparatus |
| JP2023013173A (en) * | 2021-07-15 | 2023-01-26 | 大成建設株式会社 | Chamber Pressure Control System and Chamber Pressure Control Method for Mud Pressure Shield Machine |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4617909B2 (en) * | 2005-02-04 | 2011-01-26 | 株式会社大林組 | Injection method of additives in shield method |
-
1989
- 1989-06-02 JP JP13903089A patent/JP2700411B2/en not_active Expired - Lifetime
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003097180A (en) * | 2001-09-20 | 2003-04-03 | Komatsu Ltd | Shield machine |
| JP2006348731A (en) * | 2005-05-16 | 2006-12-28 | Taisei Corp | Excavation sediment treatment method and excavation sediment disposal apparatus |
| JP2023013173A (en) * | 2021-07-15 | 2023-01-26 | 大成建設株式会社 | Chamber Pressure Control System and Chamber Pressure Control Method for Mud Pressure Shield Machine |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2700411B2 (en) | 1998-01-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Anagnostou et al. | Face stability conditions with earth-pressure-balanced shields | |
| Liu et al. | Analytical study and field investigation on the effects of clogging in slurry shield tunneling | |
| CN110966010B (en) | Dual-mode shield machine with adjustable density, mud, water and earth pressure | |
| JPH035592A (en) | Shielding method | |
| JP2000274184A (en) | Laying method for inground buried pipeline | |
| JP7085505B2 (en) | Shield excavator and shield method | |
| US5180252A (en) | Earth pressure system shield process | |
| JPS6122114B2 (en) | ||
| KR101796929B1 (en) | The shield tunnel excavator and it's tunnel excavation method with reverse injection of underground water | |
| JPH0828200A (en) | Filling of space part | |
| CN111119914A (en) | Working mode conversion method of shield machine with adjustable density | |
| JP4332080B2 (en) | Excavation soil treatment equipment in shield excavator | |
| Ikonnikov et al. | The structure of reclaiming warehouse of minerals at open-cut mines with the use combined transport | |
| JPH10317878A (en) | Mud shield method | |
| RU2785720C1 (en) | Dredge | |
| JPS58207492A (en) | Method of controlling stability of coal face of shield excavator | |
| JPH085134Y2 (en) | Sediment carry-out device | |
| JPH0258697A (en) | Hydraulic balance type forced earth removal shield method and shield excavation machine | |
| RU2091583C1 (en) | Method of mining of mineral upper horizons | |
| RU2010953C1 (en) | Method of determination of cracks spreading height in basic zone of working | |
| Andras et al. | Overview Of The Unwanted Effects Of Unmineable Rock Formations On The Mining System Of Bucket Wheel Excavator During The Excavation Process | |
| CN115182740B (en) | Double-mode shield cooperation construction method for round gravel-mudstone composite stratum | |
| JPS6218715B2 (en) | ||
| Duhme | Urban tunneling in settlement risk areas | |
| JPS6128699A (en) | Shield drilling method using muddy water having clogging material for sand and gravel foundation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081003 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081003 Year of fee payment: 11 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081003 Year of fee payment: 11 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081003 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091003 Year of fee payment: 12 |
|
| EXPY | Cancellation because of completion of term | ||
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091003 Year of fee payment: 12 |